Dear Chris:
The following is a list of the items discussed in our Friday meeting, which need to
be addressed concerning the above referenced Amended P.I.P. We are currently
addressing the items and intend to respond with comments by Wednesday, February
1st. Gary Moss and I are scheduled to meet with you at the City Hall, Wednesday
at 8:OO a.m. At which time, we will go to the jobsite to review the spotted the
daylight line per the approved subdivision and place balloons at the four corners
of the building to help visualize the impact of the building along the south and
west approach on Palamar Airport Road. Based on the assumption that we will be
able to resolve the items noted, it is our understanding that the 2:30 p.m.
Wednesday meeting scheduled with Mike Holezmiller will expedite the
administrative procedure for final approval of this Amended P.I.P. and we can
anticipate issuance of Site Grading Permit by Friday, February 3rd. It is
understood that issuance of this permit is contingent on approval of the Haul
Route and the issue concerning stockpiled materials from Phase I.
Items to be Addressed:
1. Surveyor to plot building corners and Daylight Line for Wednesday meeting.
2) Provide copy of the letter from City of Carlsbad addressing the setback
requirement along Daylight Line (allowing average 15'-0" setback).
3) Provide cross section of retaining wall along the side of the building
showing the relationship with the Daylight Line. (Top of wall to be flush with Daylight Line).
4) Re-confirm building square footage for building and verify if adequate on-
site parking is provided (City calculations indicate we are short required
parking by 3).
5) Parking stalls located in southwest corner of parking lot do not have
adequate space for backing (minimum required is 5'-0" per stall). Option of
either increasing stall depth or converting it to compact stalls.
6) Request that parking along south side of parking lot be set a minimum 15'- 0" back from Daylight Line versus the 15'-0" average as currently shown.
(Opus to study feasibility).
OPUS SOUTHWEST AND INDEPENDENT AFFILIATES IN PHOENIX MINNEAPOLIS CHICAGO MILWAUKEE TAMPA PENSACOLA
4742 NORTH 24TH STREET SUITE 270 PHOENIX, AZ 85016 (602) 468-7000
City of Carlsbad - Amended P.I.P. # 86-6
Page 2
7) Study options for garbage enclosure
8) Confirm that the turning radius of truck is correct. City’s template
indicated that radius as shown is incorrect.
9) Request that berming be provided along the south side parking adjacent to
the Daylight Line.
10) Verify we do not exceed maximum 25% compact parking stalls.
11) Recommend specimen landscaping be provided along west side of building
to help screen the building (Chris will review/recommend landscaping with
input from the City’s Designer, Mzrk Steyaertj.
12) Study options of moving building back from Daylight Line. (Both south
and west side).
13) Chris will contact the utilities and maintenance, fire department and
building department prior to the Wednesday meeting and advise Opus
Southwest Corporation of any comments prior to the meeting.
14) In reference to the Haul Permit approval, Opus Southwest Corporation needs
to provide confirmation that the Owner has a permit to receive the soil on
the designated lot. . I.
In addition to the above items yet to be resolved the following item were addressed
and resolved:
1) Lunch Area for the building will not be required considering the building is
located 1,000 feet from an established park and the property to the west of
the building has been set aside for non-commercial development and
potential future park development.
The Haul Permit/Site Grading Permit currently is in a Catch-22 situation as
a result of the stockpiled material from Phase I. Engineering is of the
opinion that it will not issue a haul permit unless the existing stockpiled
material from Phase I is removed from this site. Considering the property
lacks an original stockpile permit, the catch with removal is that no haul
permit was issued under Phase I. Opus understands that if we agree to haul
the material prior to issuance of site grading permit, a letter will be issued
by engineering advising that the official site grading permit will follow
within five (5) days of removal of fill. The Phase I1 haul permit will need
to include the subject stockpile to avoid violation of haul permit
requirements.
3) Compact parking adjacent to the north side of the parking was discussed. it
is understood the City discourages to end compact parking, however, due to
limited area along the compact row addition of standard stalls would impact
entire parking count. Issue was dropped during our discussions.
OPUS SOUTHWEST CORPORATION
"-
City of Carlsbad - Amended P.I.P. # 86-6 Page 3
We trust that you are in agreement with this letter's content. Please advise me of
any additional information you might need prior to our meeting.
Sincerely,
OPUS SOUTHWEST CORPORATION
\?-&"a Dennis . Cornelius, AIA
Senior Project Manager
D WC! jme
cc: Mike Holezmiller
OPUS SOUTHWEST CORPORATION
8 0
b
1
0
L
\
i I\,
f'
c
1- I
,59' @**
I
OPUS SOUTHWEST
DESIGNERS - BUlLDERS * DEVELOPERS
4742 North 24th Sm. Suits 270. phasnix. Anzona 85016 Irn) 4"7m
c
1
PALOMAR AIRPORT ROAD
I
162.00' FS
160.00' FS
ROOF 196.00'
3RD FL. 183.66'
2ND FL. 171.33' -
1ST FL. 159.00'
GARAGE
0 a
% OPUS SOUTHWEST CORPORATION
DESIGNERS - BUILDERS - DEVELOPERS
1 4742 North 24th Street, Suite 270. Phoenix. Arizona 85016
IW21 468-7000
0
1-31 -09
OPUS SOUTHWEST CORPORATION
DESIGNERS BUILDERS * DEVELOPERS
0
4742 North 24th Street. Suite 270. Phoenix, Arizona 85016
16021 468-7"