HomeMy WebLinkAboutPIP 89-06; Bassi Court; Planned Industrial Permit (PIP) (8)Citv of Carlsbad
April 12. 1989
Plant and Cook, Inc.
2385 Camino Vida Roble, #lo7
Carlsbad, CA 92009
RE: PIP 89-6 - BASSI COURT
(LOT 4 OF MINOR SUBDIVISION NO. 7831 -
ENGINEERING DEPT. COMPLETENESS REVIEW AND ISSUES
The Engineering Department has completed its review of the subject
project for application completeness. The application and plans
submitted for this project are incomplete and unsuitable for further
review due to the following reasons:
1.
2.
3.
4.
5.
6.
You will need to submit a preliminary 'title report and show
all easements.
Show existing curbs, gutters, sidewalks, etc., for Camino
Vida Roble. Also show proposed improvements for your private
cul-de-sac,
Show typical street sections for Camino Vida Roble and your
private cul-de-sac.
spot elevations. Also show existing and proposed drainage
You will need to show existing and proposed contousand provide
facilitieslflow lines.
Show existing utilities; water, sewer mains and storm drains.
Also show your proposed laterals.
You need to dimension your parking lot aisles and driveway.
of the project for Engineering issues. (See attached initial review
In addition, the Engineering Department made a preliminary review
and assessment checklist.) Major engineering issues which will
as follows:
need to be resolved or adequately addressed for this project are
2075 Las Palrnas Drive - Carlsbad. California 92009-4859 (619) 438-1 161
Plant and Cook, Inc.
RE: PIP 89-6
April 12, 1989 Page 2
1. You will need to provide on-site circulation (show) 407E Caltrans
truck turning radii (42 ft.) to and from your trash enclosure
and your truck loading area. You also need to provide and
show either rear loading or side loading (8 ft. x 40 ft. area).
Site loading area and circulation will - not work as shown.
-
Also please find the included check print no. "1" for your use.
Please return the check print with your resubmittal to assist us
in our continued review.
JIM MURRAY
Associate Civil Engineer
JM:jb
C: Chris Griffin (Project Planner)