HomeMy WebLinkAboutPIP 89-13; Mercotac; Planned Industrial Permit (PIP) (4)November 27, 1989
Gary Seward
Plant & Cook
2385 Camino Vida Roble, Suite 107
Carlsbad, CA 92009
This is to inform you that the items previously requested to make your Planned Industrial
Permit, application no. PIP 89-13, complete have been received and reviewed by the
Planning Department. It has been determined that the application is now complete for
processing. Although the initial processing of your application may have already begun,
the technical acceptance date is acknowledged by the date of this communication.
Please note that although the application is now considered complete, there may be issues
that could be discovered during project review and/or environmental review. Any issues
should be resolved prior to scheduling the project for public hearing. In addition, the City
may request, in the course of processing the application, that you clarify7 amplify, correct,
or otherwise supplement the information required for this application. Attached is a list
of issues identified by the Planning and Engineering Departments.
The Planning Department will begin processing your application, as of the date of this
communication. Please contact Eric Munoz, at (619) 438-1161 extension 4325, if you have
questions or wish additional information.
Sincerely,
MICHAEL J. HOLZMILLER
Planning Director
MJH:ENM:af
c: Gary Wayne
Crystal/Angelina
Erin Letsch
Bob Wojcik
Data Entry
Chris DeCerbo
Sherri Howard
2075 Las Palmas Drive - Carlsbad. California 92009-4859 (619) 438-1 161
ISSUES OF CONCERN
PIP 89-13
PLANNING:
1. Maintain a 10 foot minimum building setback from the top of slope.
2. The employee eating area is acceptable on a conceptual basis, however, it should
be more fully developed to meet the spatial and area requirements established by
Administrative Policy No. 19. Second floor balcony area may be used as employee
eating area but only if it is in excess of the overall area required.
ENGINEERING:
1. Drainage:
a) hbel line, inlet, and outlet to street for line shown at western border on
b) Label drainage line shown under driveway (Corte Del Cedro). Use a grated
c) Label & lines proposed or existing.
d) Include proposed elevations. Show more proposed elevations around slope.
Corte De La Pina. Use grated inlet, not a bench inlet.
inlet or a curb inlet.
2. Title report call out Pacific Telephone easement (Item #3). Submit site plan to
them and include their approval of building location prior to approval of Planned
Industrial Permit.
3. Include contours of slope or spot elevations at top of slope and bottom of slope.
Clarify what is existing and what is proposed over entire site.
4. Section to be free of any obstructions greater than 30 inches is inappropriate to call
out since slope is greater than 30". No signs can be placed there.