HomeMy WebLinkAboutPIP 98-01; Palomar Crest Corporate Center; Planned Industrial Permit (PIP) (3).-
.¶
Planning Department
City of Carlsbad
2075 Las Palmas Drive
Carlsbad, California 92009
TO:
FROM: CMWD NOL%- a\
SUBJECT:
The District is responding to your request for conditions . In response to your inquiry of
District has reviewed the subject project. Based on our review of the proje'ct, we have
the following conditions regarding potable water, recycled water and sewer systems:
I.
2.
9':"
4.
The Developer shall be responsible for all fees, deposits and charges which will
be collected before and/or at the time of issuance of the building permit. The
San Diego County Water Authority capacity charge will be collected at issuance
of application for any meter installation.
The Developer shall provide detailed information to the District Engineer
regarding water demand, irrigation demand, fire flow demand in gallons per
minute, and projected sewer flow in million gallons per day.
The entire potable water system, recycled water system and sewer system shall
be evaluated in detail by Developer and District Engineer to insure that adequate
capacity, pressure and flow demands can be met.
All District pipelines, pump stations, pressure reducing stations and
appurtenances required for this project by the District shall be within public right-
of-way or within easements granted to the District or the City of Carlsbad
L P
Page two
Planning Department
D5te:
5. Sequentially, the Developer's Engineer shall do the following:
A. Meet with the City Fire Marshal and establish the fire protection
requirements.
8. Prepare and submit a colored recycled water use area map and submit
this map to the Planning Department for processing and approval by the
District Engineer.
C. Prior to the preparation of sewer, water and recycled water improvement
plans, the Developer shall submit preliminary system layouts to the District
Engineer for review, comment and approval.
6. The following note shall be placed on the final map. "This project is approved
upon the expressed condition that building permits will not be issued for
development of the subject property unless the District serving the development
has adequate water and sewer capacity available at the time development is to
occur, and that such water and sewer capacity will continue to be available until
time of occupancy."
7. All potable water and recycled water meters shall be placed within public right of
way.
8. The following items shall apply if checked:
0 No more than 19 homes shall be served on a single potable water distribution
pipeline. For those locations with more than 19 homes, a looped potable water
A public fire flow system shall be required for this industrial or commercial
line system shall be designed.
ent, and it shall be constructed-as a looped pipeline system.
9. -
If you have any questions, please contact
&I+-
Erlgineering Technician
RG:sjs
the undersigned.