"Re: SCH# 20061221106; Springhill Suites - GPA 05-05/ZC 05-02/LCPA 05-02/RP 05-03/SDP 05-
04/CDP 05-14
The Califomia Public Utilities Commission (Commission) has jurisdiction over the safety of highway-rail
crossings (crossings) in Califomia. The Califomia Public Utilities Code requires Commission approval
for the constmction or alteration of crossings and grants the Commission exclusive power on the design,
alteration, and closure of crossings. Commission staff is concemed that the new development near
Carlsbad Boulevard and Oak Avenue (lat=33.156846, long=-l 17.344842) may increase traffic volumes
not only on streets and at intersections, but also at at-grade highway-rail crossings:
1. Grand Avenue (DOT 026820X)
2. Carlsbad Village Drive (DOT 026821E)
3. Tamarack Avenue (DOT 026822L)
Mitigation measures to consider include, but are not limited to, grade separation of major thoroughfares,
safety knprovements to existing at-grade highway-rail crossings due to an increase in traffic volumes and
appropriate fencing to limit the access of trespassers to railroad right-of-way.
The Commission did not receive a copy ofthe Negative Declaration from the State Clearinghouse.
Please provide us with a copy for review. The City of Carlsbad shoxild arrange a meeting with the
Commission's Rail Crossings Engineering Section and North County Transit District (NCTD) to discuss
relevant safety issues and, if necessary, file a G088-B request for authority to modify an at-grade
crossing.
Please advise us on the status of the project. If you have any questions in this matter, please contact me at
(213) 576-7078 or at rxm(gcpuc.ca.gov.
lOZ, PJ
Utilities Engineer
Rail Crossings Engineering Section
Consumer Protection & Safety Division
C: Richard Walker, NCTD
December 13, 2006
TO: Cliff Jones, Assistant Planner
Van Lynch, Senior Planner
Michele Masterson, Management Analyst
Michelle Gregory, Senior Office Specialist
FROM: Michael Elliott, City of Carlsbad's Contract Landscape Architect
RE: Landscape Architectural Review - Conceptual Review - 3*^^ Review
DKN Hotel - SpringhiU Suites - Marriott - RP05-03 - CDP05-14 - SDP05-04
- ZC05-02
3136 Carlsbad Blvd.
PELA file: 116 - DKN Hotel - Springhill Suites - Marriott - RP05-03 - Con3
Landscape Architect: Wilkinson Design Group, (760) 434-2152
Plans have previously been through two (2) reviews and a meeting was held with the applicant
on November 28 to review issues. Previous landscape design comments number 2 and 5 were
deleted based on direction from the City at the November 28 meeting. Based on the third
landscape submittal, the following conditions of approval are recommended:
1. Existing turf parkways along Carlsbad Boulevard shall be repaired if damaged and shall
be provided with a complete automatic irrigation system all as approved by the Planning
Director. Turf, shmb and ground cover plantings within the parkway shall be maintained
by the project owner.
2. The parkway turf plantings located at the southwest comer of the project on the east side
of the Carlsbad Boulevard sidewalk shall be revised to appropriate shmbs and ground
covers as approved by the Planning Director.
3. Plans shall be revised to provide woody shmbs planted over herbaceous ground covers to
cover a minimum 60% of the ground cover area at maturity along Lincoln Street as
approved by the Planning Director.
CITY OF CARLSBAD
ENGINEERING DEPARTMENT
LAND USE REVIEW
December 11, 2006
TO: Cliff Jones - Housing and Redevelopment
FROM: David Rick - Engineering Department
COMPLETENESS REVIEW
PROJECT ID: RP 04-04(A)/CT 06-18 ROOSEVELT GARDENS CONDOMIMIUM
The Engineering Department has completed its review of the above referenced project for
compliance with the previously determined issues. The project appears to comply with City
engineering standards and all issues have been addressed. Please add the following conditions
of approval to the approving resolution or letter:
ENGINEERING CONDITIONS
/VOTE: Unless specifically stated in the condition, all of the following conditions, upon the
approval of this proposed tentative map, must be met prior to approval of a building or grading
permit whichever occurs first.
Genera/
1. Prior to hauling dirt or construction materials to or from any proposed construction site
within this project, Developer shall apply for and obtain approval from the City Engineer
for the proposed haul route.
2. The area designated for vehicular back up shall be clearly delineated with signage
and/or pavement graphics to preclude unauthorized parking.
3. Developer shall submit to the City Engineer, a reproducible 24" x 36", mylar copy of the
tentative map and a digital copy of said map (in AutoCAD format, latest version)
reflecting the conditions approved by the final decision making body. The reproducible
shall be submitted to the City engineer, reviewed and, if acceptable, signed by the City's
project engineer and project planner prior to submittal of the building plans, final map,
improvement or grading plans, whichever occurs first. The digital file copy shall be
submitted in a format as approved by the City Engineer.
4. Developer shall and does hereby agree to indemnify, protect, defend and hold harmless
the City of Carlsbad, its Council members, agents, officers, and representatives, from
and against any and all liabilities, losses, damages, demands, claim and costs, including
court costs and attorney's fees incurred by the City arising, directly or indirectly, from (a)
City's approval and issuance of this tentative parcel map, (b) City's approval or issuance
of any permit or action, whether discretionary or non-discretionary, in connection with
the use contemplated herein, including an action filed within the time period specified in
H:\LIBRARY\ENG\WPDATA\MISC\COMPREV
Government Code Section 66499.37 and (c) Developer's installation and operation of
the facility permitted hereby, including without limitation, any and all liabilities arising
from the emission by the facility of electromagnetic fields or other energy waves or
emissions.
5. Developer shall provide to the City Engineer, an acceptable means, CC&Rs and/or other
recorded document, for maintaining the private easements within the subdivision and all
the private improvements: streets, sidewalks, street lights, and storm drain facilities
located therein and to distribute the costs of such maintenance in an equitable manner
among the owners of the properties within the subdivision.
6. Subject to the City Engineer's approvai, the property owner shall enter into an
encroachment agreement with the City for the proposed enhanced pavement
shown within the driveway. Application processing and criteria for said
encroachment agreement is subject to the requirements established by the City
Engineer.
Fees/Agreemente
7. Prior to approval of any grading or building permits for this project. Developer shall
cause Owner to give written consent to the City Engineer to the annexation of the area
shown within the boundaries of the site into the existing City of Carlsbad Street Lighting
and Landscaping District No. 1 and/or to the formation or annexation into an
additionai Street Lighting and Landscaping District. Said written consent shali be
on a form provided by the City Engineer.
Grading
8. Based upon a review of the proposed grading and the grading quantities shown on the
site plan, a grading permit for this project is required. Developer shall apply for and
obtain a grading permit from the city engineer prior to issuance of a building permit for
the project.
Dedications/Improvements
9. Developer shall comply with the City's requirements of the National Pollutant Discharge
Elimination System (NPDES) permit. Developer shall provide improvements constructed
pursuant to best management practices as referenced in the "California Storm Water
Best Management Practices Handbook" to reduce surface pollutants to an acceptable
level prior to discharge to sensitive areas. Plans for such improvements shall be
submitted to and subject to the approval of the City Engineer. Said plans shall include
but not be limited to notifying prospective owners and tenants of the following:
A. All owners and tenants shall coordinate efforts to establish or work with
established disposal programs to remove and properly dispose of toxic and
hazardous waste products.
B. Toxic chemicals or hydrocarbon compounds such as gasoline, motor oil,
antifreeze, solvents, paints, paint thinners, wood preservatives, and other such
fluids shall not be discharged into any street, public or private, or into storm drain
H:\LIBRARY\ENG\WPDATA\MISC\COMPREV
or storm water conveyance systems. Use and disposal of pesticides, fungicides,
herbicides, insecticides, fertilizers and other such chemical treatments shall meet
Federal, State, County and City requirements as prescribed in their respective
containers.
C. Best Management Practices shall be used to eliminate or reduce surface
pollutants when planning any changes to the landscaping and surface
improvements.
10. Prior to the issuance of grading permit or building permit, whichever occurs first,
Developer shall submit for City approval a "Storm Water Management Plan (SWMP)."
The SWMP shall demonstrate compliance with the City of Carlsbad Standard Urban
Stormwater Mitigation Plan (SUSMP), Order 2001-01 issued bythe San Diego Region
of the California Regional Water Quality Control Board and City of Carlsbad Municipal
Code. The SWMP shall address measures to avoid contact or filter said pollutants from
storm water, to the maximum extent practicable, for the post-construction stage of the
project. At a minimum, the SWMP shall:
a. identify existing and post-development on-site pollutants-of-concern;
b. identify the hydrologic unit this project contributes to and impaired water bodies that
could be impacted by this project;
c. recommend source controls and treatment controls that will be implemented with this
project to avoid contact or filter said pollutants from storm water to the maximum
extent practicable before discharging to City right-of-way;
d. establish specific procedures for handling spills and routine clean up. Special
considerations and effort shall be applied to resident education on the proper
procedures for handling clean up and disposal of pollutants;
e. ensure long-term maintenance of all post construct BMPs in perpetuity; and
f. identify how post-development runoff rates and velocities from the site will not
exceed the pre-development runoff rates and velocities to the maximum extent
practicable.
11. Prior to building permit or grading permit issuance, whichever occurs first, developer
shall design, apply for and obtain approval of the City Engineer, for the structural section
for the access aisles with a traffic index of 5.0 in accordance with City Standards due to
truck access through the parking area and/or aisles with an ADT greater than 500. The
structural pavement design of the aisle ways shall be submitted together with required
R-value soil test information and approved by the City Engineer as part of the building or
grading plan review whichever occurs first.
12. Developer shall cause Owner to make an offer of dedication to the City and/or other
appropriate entities for all public streets and other easements shown on the tentative
map. The offer shall be made by a certificate on the final map. All land so offered shall
be offered free and clear of all liens and encumbrances and without cost. Streets that
already public are not required to be rededicated.
13. Developer shall execute and record a City standard Subdivision Improvement
Agreement to install and secure with appropriate security as provided by law, public
improvements shown on the tentative map and the following improvements including,
but not limited to installation of sewer and water mains and related appurtenances to
H:\LIBRARY\ENG\WPDATA\MISC\COMPREV
City Standards to the satisfaction of the City Engineer. The improvements are:
a) All sewer and water facilities located within the public right-of-way
and proposed on-site public utility and public utility access
easement.
b) Curb outlet and driveway approach within the public right-of-way
and the "easement for public sidewalk and incidental purposes", as
shown on the tentative map.
A list of the above shall be placed on an additional map sheet on the Final Map per the
provisions of Sections 66434.2 of the Subdivision Map Act. Improvements listed above
shall be constructed within 18 months of approval of the subdivision or development
improvement agreement or such other time as provided in said agreement.
Final Map Notes
14. Developer shall show on Final Map the net developable acres for each parcel.
15. Note(s) to the following effect(s) shall be placed on the map as non-mapping data
A. All improvements are privately owned and are to be privately maintained with the
exception of the following:
1. All sewer and water facilities located within the public right-of-way and
proposed on-site public utility and public utility access easement
2. Curb outlet and driveway approach within the public right-of-way and the
"easement for public sidewalk and incidental purposes", as shown on
the tentative map.
B. Building permits will not be issued for development of the subject property unless
the appropriate agency determines that sewer and water facilities are available.
Carlsbad Municipal Water District
16. Prior to issuance of building permits. Developer shall pay all fees, deposits, and charges
for connection to public facilities. Developer shall pay the San Diego County Water
Authority capacity charge(s) prior to issuance of Building Permits.
17. The Developer shall install (potable water and/or recycled water services) and meters at
a location approved by the District Engineer. The locations of said services shall be
reflected on public improvement plans.
18. The Developer shall install sewer laterals and clean-outs at a location approved by the
District Engineer. The locations of sewer laterals shall be reflected on public
improvement plans.
19. This project is approved upon the express condition that building permits will not be
issued for the development of the subject property, unless the District Engineer has
determined that adequate water and sewer facilities are available at the time of
occupancy. A note to this effect shall be placed on the Final Map, as non-mapping data.
H:\LIBRARY\ENG\WPDATA\MISC\COMPREV
20. Prior to approval of improvement plans or final map. Developer shall meet with the Fire
Marshal to determine if fire protection measures (fire flows, fire hydrant locations,
building sprinklers) are required to serve the project. Fire hydrants, if proposed, shall be
considered public improvements and shall be served by public water mains to the
satisfaction of the District Engineer.
21. The Developer shall design and construct public water, sewer, and recycled water
facilities substantially as shown on the (Tentative Map/Site Plan) to the satisfaction of
the District Engineer. Proposed public facilities shall be reflected on public improvement
plans.
22. The Developer shall provide separate potable water meters for each separately owned
unit.
23. Sewer cleanouts shall be provided for each sewer lateral per City Standards.
24. The proposed water service pipe for the fire sprinkler system shall be a minimum
6 inches in diameter for that portion installed within the public right-of-way.
Code Reminder
The project is subject to all applicable provisions of local ordinances, including but not limited to
the following:
A. The tentative map shall expire twenty-four (24) months from the date this tentative map
approval becomes flnal.
B. Developer shall exercise special care during the construction phase of this project to
prevent offsite siltation. Planting and erosion control shall be provided in accordance
with Carlsbad Municipal Code Chapter 15.16 (the Grading Ordinance) to the saflsfacflon
of the City Engineer.
If you or the applicant has any questions regarding the above, please either see or call me at
extension 2781.
David Rick
Assistant Engineer - Development Services Division
H:\LIBRARY\ENG\WPDATA\MISC\COMPREV
PLANNING
SYSTEMS
LAND USE/COASTAL PLANNING
LANDSCAPE ARCHITECTURE • LA,3900
POLICY AND PROCESSING
ENVIRONMENTAL MITIGATION
October 30, 2006
Mr. Cliff Jones
CITY OF CARLSBAD
Housing & Redevelopment Department
2965 Roosevelt St. Ste B
Carisbad, CA 92008
RE: RP 05-03/SDP 05-04/DEV 05-19/LCPA 05-02/ZC 05-02/GPA 05-05 -
DKN Springhill Suites
Dear Cliff:
Per your letter dated August 30,2006 identifying Staff items and issues w^ith the submittal of the
above-referenced project, the project applicant has commissioned modifications to the project
design and the provision of the additional information requested. To this end, attached vv^ith this
cover letter please find a re-submittal package including:
• Five (5) sets of revised plans
• Landscape redlines
• Materials and color board
With regard to the specific items and issues identified in the August 30 letter, the following is a
discussion of the method in which the redesigned project addresses the general issues, followed
by a specific response to each item/issue identified by City Staff, in the order presented in your
draft letter.
Issues of Concem
Housing & Redevelopment and Planning:
1. As mentioned in previous correspondence, staff has concern regarding the look of the roof of the
proposed building. Any modifications to the roof to make it appear more like a true roof
(consistent with fhe architectural design chosen) would benefit the project. The dormers could be
integrated into the roofiine rather than just "planted on" and the roofiine could also benefit from
the use of larger/lengthier exposed eaves. Additionally, the mansard roof could be broken up more
as viewed from the north and south.
Response: Pursuant to the conclusions of our meeting on October 5, we have
prepared computer/artist renderings (Sheets A-15 & A-16) which have been included
into the plan package. These renderings better depict that the eaves will project only 24"
from the facade, with dormers extending only up to 36" from the fagade. The mansard
roof line steps in and out with the relief in the fagade. We are very pleased with the
architectural design and roofiine as shovm on these computer-based renderings. We are
hopeful that these provide an understandable visual simulation of the roofiine and
architecture of the project.
1530 FARADAY AVENUE • SUITE 100 • CARLSBAD, CA 92008 • (760) 931-0780 • FAX (760) 931-5744 • info@planningsystems.net
2. Staff is concemed with the elevation depicted as Elevation B on Sheet A-7. The roofiine at the
northeast corner ends nine feet from the property line. Staff is concerned how this will look.
Additional articulation should be incorporated at this location or the applicant should consider
planted landscaping that grows tall to improve the look ofthis corner. Additionally, no detail is
provided regarding the look ofthe east side ofthe building that projects above the existing 7-11
shopping center. Please provide detail on how this elevation will look and provide articulation as
necessary.
Response: Elevation B-1 was added for clarity as requested at the October 5
meeting. The stairwell is defined by a higher parapet and wood brace detailing.
Additional detailing was added to the north elevation as shown in the elevation.
3. Staff suggests the southwest elevation ofthe building that has no windows could use more
building articulation in line with the architectural theme already chose for the project.
Response: This 12-0" wide portion of the elevation contains relief at the ground
level in the form of a covered patio, and is capped by a mansard roof and roof terrace.
The blank wall portion in-between provides a nice canvas for the hotel identification
signage as seen on elevation F/A-8.
4. The elevator necessary to access the roof deck at the south elevation could benefit from
architectural screening.
Response: The elevator override parapet massing is set back 9' from the face of
the stair gable end roofiine. This can be seen in the 3-D shadow studies on sheet A-11
and View 1 3-D sketch on sheet A-15. The line weights on the elevations have been
adjusted to better depict the reUef.
5. On Sheet A-14 please correct "BuiJding Section X" illustration to refiect a residential building
not hotel suites.
Response: The notation has been corrected. The sections now appear on Sheet A-
13.
6. On Sheet A-14 please indicate the building setbacks for "Building Section" illustration.
Response: The setbacks have been indicated and can be seen on Sheet A-13.
7. Please provide an updated color and materials board.
Response: An updated color and materials board has been included with this re-
submittal, as requested.
8. Once the final design is acceptable to staff, the applicant should consider providing artist
renderings or photo simulation in order to better demonstrate to the public what the final building
will look like.
Response: Two artist renderings have been included in the plan sets on Sheet A-16
for staff review. Colored renderings mounted on boards will be provided prior to public
hearing or at Staff's request.
PLANNING
SYSTEMS D
Landscape:
1. Plans are too conceptual to allow for an appropriate review. There is one symbol used for several
trees/palms. In several cases the list of possible trees/palms has plants that are drastically
different. One symbol is used for all shrubs where the list of shrubs is very different in character.
Please provide one symbol for each tree and palm unless they have the same character (i.e.
evergreen of same height and width and character) and provide one symbol for each type of shrub
(i.e. large evergreen screen shrub; medium evergreen shrub; small fiowering accent shrub; etc.).
Final comments are reserved pending more complete plans.
Response: The plant legend has been revised and now shows all symbols used on
the landscape plan.
2. Please identify all symbols used on the plans. Check all symbols.
Response: All symbols have now been shown on the legend.
3. Please address planting of all landscape areas.
Response: All planting areas have been illustrated to define their treatments.
4. Provide detailed information as to the expected ultimate size ofthe plants that are to be grown in
the containers.
Response: Size data has been added to the legend.
5. There appear to be windows with views out to the 6' masonry wall along the southeast side ofthe
building. Please provide landscaping along this wall and enhance views.
Response: Vines have been added to the inside face of the masonry wall along the
southeast side of the building.
6. Please show and label all property lines and easements on the landscape plans.
Response: All property lines have been shown on the landscape plan.
7. Provide a plant palette list indicating the following:
a. Tree types and quantities
b. Shrub types and quantities (approximate)
c. Proposed plant sizes (either by number or % of total quantity)
Response: The plant legend has been updated to include the requested
information.
8. All planting areas shall be outlined as one of the four planting zones below and described in
Appendix A:
Zone One Lush
Zone Two Refined
Zone Three Naturalizing/Transitional
Zone Four Native
Response: The landscape plan has no Zone 3 or Zone 4. Zone 1 is identified and all
other areas are Zone 2. A note has been added to the plan indicating the Zone
breakdovm.
PLANNING
SYSTEMS a
9. Indicate the percentage ofthe landscaped area (as defined in Appendix G) of each planting zone as
described in Section A.5-3 and Appendix A.
Response: A note on planting zones has been added to the landscape plan.
10. Show and label any bio-swales/detention basins or underground drainage collection systems (in or
under planting areas that could impact the planting) and work these facilities into the design.
Response: AU drainage collection systems proposed as part of the project have been
labeled on the landscape plan.
11. 50% ofthe shrubs (except on slopes 3:1 or steeper) shall be a minimum 5 gallon size. Please
insure this requirement is met.
Response: At least 50% of the shrubs proposed for this project shall be a minimum 5
gallon size.
12. All utilities are to be screened. Landscape construction drawings will be required to show and
label all utilities and provide appropriate screening. Please also locate all light poles on the
landscape plans and insure that there are rw confiicts with trees.
Response: Existing utiUties have been labeled. There are no street lights within the
public right-of-way.
13. Plans shall include but not be limited to:
a. Extent of Planting Zone 1 (Lush) - Indicate percentage of Zone 1 planting (per Appendix A) of
the total landscaped area (as defined in Appendix G). Provide justification for the appropriateness
of where Zone 1 plantings are used in terms of water conservation. (For example, are Zone 1
plantings in areas of shade where they will use less water and/or has the soil been suitably
amended so as to retain relatively greater moisture?)
b. Proposed turf areas, (see limitations in IV.C.3-4.2) Give percentage of turf of the total
landscaped area.
Response: The plan proposed no turf other than the existing turf located in the
public right-of-way,
14. Plan notes indicate that other than the turf, there are no zone 1 plantings. Plans califor Cyperus
which is zone 1. Please revise notes as appropriate. Include all zone 1 plantings in the percentage
calculations per comment numbers 10 and 14 above.
Response: The notes and percentage calculations have been revised.
15. Per the water conservation section ofthe manual (C.3-4.6), woody shrubs must be planted over
herbaceous groundcover to cover 60% ofthe groundcover area at maturity. Please insure that this
requirement is met.
Response: A section titled "Herbaceous Groundcover" has been added to the
legend and the landscape plan now meets this standard.
16. Please reduce the percentage of turf to meet requirements ofthe landscape manual section IV, C.3-
4.2-1.
PLANNING
SYSTEMS a
Response: The plan proposed no turf other than the existing turf located in the
public right-of-way.
17. Please clearly indicate and label the precise location ofthe Red Fescue planting on the plans.
Response: The Red Fescue has been labeled on the landscape plan.
18. It is recommended that landscaping be included along the southwest side ofthe pool to soften and
enhance this wall. Please address.
Response: Vines have been added to the area along the southwest side of the pool.
19. Retum redlines and provide 2 copies of all plans (concept and water conservation) on the next
submittal.
Response: The redlined plans have been retumed along with 2 copies of the revised
landscape plan.
Thank you for your continued assistance with the planning of this project. With these minor
revisions, we are hopeful that the project design is now acceptable for docketing for Design
Review Board/Planning Commission hearing.
Sincerely,
PSUIJ. Klukas J
Director of Planning
cc: Neil Patel
Attachments
PLANNING
SYSTEMS a
Citv of Carlsbad
Housing & Redevelopment Department
August 30, 2006
DKN HOTELS
540 GOLDEN CIRCLE DRIVE #214
SANTA ANA, CA 92705
SUBJECT: DKN - Marriott (RP 05-03, SDP 05-04, CDP 05-14. LCPA 05-02, ZC 05-02, GPA
05-05)
APN: 203-250-08 & 203-250-26
The purpose of this letter Is to address issues of concern raised by City staff following a
review of the revised plans. The issues of concern are attached for your review. These
issues must be addressed prior to staff making a formal recommendation on the project.
Please contact my office at (760) 434-2813, if you have any questions or wish to set up a
meeting to discuss the application.
Sincerely,
CLIFF JONES
Assistant Planner
c: Kenny Booth, Planning Systems
Van Lynch, Planning
File
2965 Roosevelt St., Ste. 8 • Carlsbad, CA 92008-2389 • (760) 434-2810/2811 • FAX (760) 720-2037 @
DKN Marriott
08/30/2006
Page 2 of 4
ISSUES OF CONCERN
No. RP 05-03, SDP 05-04. CDP 05-14. LCPA 05-02, ZC 05-02. GPA 05-05
Staff has completed a review of the subject project for issues of ooncern. The following items
need to be resolved or adequately addressed prior to staff making a final determination on the
proposed project: (Please note, the issues are listed under the department which identified
them as an area of concern.)
Housing & Redevelopment & Planning:
1. As mentioned in previous correspondence, staff has concern regarding the look of the roof
of the proposed building. Any modifications to the roof to make it appear more like a true
roof (consistent with the architectural design chosen) would benefit the project. The
dormers could be integrated into the roof line rather than just "planted on" and the roof line
could also benefit from the use of larger/lengthier exposed eaves. Additionally, the
mansard roof could be broken up more as viewed from the north and south.
2. Staff is concerned with the elevation depicted as Elevation B on Sheet A-7. The roofiine at
the northeast corner ends nine feet from the property line. Staff is concerned how this will
look. Additional articulation should be incorporated at this location or the applicant should
consider planted landscaping that grows tall to improve the look of this corner. Additionally,
no detail is provided regarding the look of the east side of the building that projects above
the existing 7-11 shopping center. Please provide detail on how this elevation will look and
provide articulation as necessary.
3. Staff suggests the southwesf elevation of the building that has no windows could use more
building articulation in line with the architectural theme already chosen for the project.
4. The elevator necessary to access the roof deck at the south elevation could benefit from
architectural screening.
5. On Sheet A-14 please correct "Building Section X" illustration to reflect a residential building
not hotel suites.
6. On Sheet A-14 please indicate the building setbacks for "Building Section" illustration.
7. Please provide an updated color & materials board.
8. Once the final design is acceptable to staff, the applicant should consider providing artist
renderings or photo simulation in order to better demonstrate to the publk: what the final
building will look like.
For questions regarding Housing & Redevelopment Department and Planning comnnents,
please contact Cliff Jones at 760-434-2813.
Landscape:
1. Plans are too conceptual to allow an appropriate review. There is one symbol used for
several trees/palms. In several cases the list of possible trees/palms has plants that are
drastically different. One symbol is used for all shrubs where the list of shrubs is very
different in character. Please provide one symbol for each tree and palm unless they have
DKN Marriott
08/30/2006
Page 3 of 4
the same character (i.e. evergreen of same height and width and character) and provide
one symbol for each type of shrub (i.e. large evergreen screen shrub; medium evergreen
shrub; small flowering accent shrub; etc.). Final comments are reserved pending more
complete plans.
2. Please identify all symbols used on the plans. Check all symbols.
3. Please address planting of all landscape areas.
4. Provide detailed information as to the expected ultimate size of the plants that are to be
grown in the containers.
5. There appear to be windows with views out to the 6' masonry wall along the southeast side
of the building. Please provide landscaping along this wall to soften and enhance views.
6. Please show and label all property lines and easements on the landscape plans.
7. Provide a plant palette list indicating the following:
a. Tree types and quantities
b. Shrub types and quantities (approximate)
c. Proposed plant sizes (either by number or % of total quantity)
8. All planting areas shall be outlined as one of the four planting zones below and described in
Appendix A:
Zone One Lush
Zone Two Refined
Zone Three Naturalizing/Transitional
Zone Four Native
9. Indicate the percentage of the landscaped area (as defined in Appendix G) of each planting
zone as described in Section A.5-3 and Appendix A.
10. Show and label any bio-swales/detention basins or underground drainage collection
systems (in or under planting areas that could impact the planting) and work these facilities
into the design.
11. 50% of the shrubs (except on slopes 3:1 or steeper) shall be a minimum 5 gallon size.
Please insure this requirement is met.
12. All utilities are to be screened. Landscape construction drawings will be required to show
and label all utilifies and provide appropriate screening. Please also locate all light poles on
the landscape plans and insure that there are no conflicts with trees.
13. Plans shall include but not be limited to:
a. Extent of Planting Zone 1 (Lush) - Indicate percentage of Zone 1 planting (per
Appendix A) of the total landscaped area (as defined in Appendix G). Provide
justification for the appropriateness of where Zone 1 plantings are used in terms
of water conservation. (For example, are Zone 1 plantings in areas of shade
where they will use less water and/or has the soil been suitably amended so as
to retain relatively greater moisture?)
b. Proposed turf areas. (See limitations in IV.C.3-4.2) Give percentage of turf of
the total landscaped area.
14. Plan notes indicate that other than the turf, there are no zone 1 plantings. Plans call for
Cyperus which is zone 1. Please revise notes as appropriate. Include all zone 1 planfings
in the percentage calculations per comment numbers 10 and 14 above.
15. Per the water conservation section of the manual (C.3-4.6), woody shrubs must be planted
over herbaceous groundcover to cover 60% of the groundcover area at maturity. Please
insure that this requirement is met.
16. Please reduce the percentage of turf to meet requirements of the landscape manual
section IV, C.3-4.2-1.
17. Please clearly Indicate and label the precise location of the Red Fescue planting on the
plans.
DKN Marriott
08/30/2006
Page 4 of 4
18. It is recommended that landscaping be included along the southwest side of the pool to
soften and enhance this wall. Please address.
19. RETURN REDLINES and provide 2 copies of all plans (concept and water
conservation) on the next submittal.
For quesfions regarding Landscape Consultant comments, please contact Michael Elliott at
760-944-1620.
August 1, 2006
TO: Cliff Jones, Assistant Plamier
Van Lynch, Senior Planner
Michele Masterson, Management Analyst
FROM: Michael Elliott, City of Carisbad's Contract Landscape Architect
RE: Landscape Architectural Review - Conceptual Review - 1^ Review
DKN Hotel - Springhill Suites - Marriott - RP05-03 - CDP05-14 - SDP05-04
- ZC05-02
3136 Carlsbad Blvd.
PELA file. 116 DKN Hotel ~ Sprin^ill Suites - Marriott RP05-03 - Conl
Landscape Architect: Wilkinson Design Group, (760) 434-2152
Please advise the applicant to make the following corrections to the plans so that they will meet
the requirements of the City of Carlsbad's Landscape Manual.
Numbers below are referenced on the red line plans where appropriate for ease in locating the
area of the comment concem.
1. Plans are too conceptual to allow an appropriate review. There is one symbol used for
several trees/palms. In several cases the list of possible trees/palms has plants that are
drastically different. One symbol is used for all shmbs where the list of shmbs is very
different in character. Please provide one symbol for each tree and palm unless they have
the same character (i.e. evergreen of same height and width and character) and provide
one symbol for each type of shmb (i.e. large evergreen screen shmb; medium evergreen
shmb; small flowering accent shmb; etc.). Final comments are reserved pending more
complete plans.
2. Proposed landscape is minimal and out of scale with the overall project. In an effort to
better balance the project without major re-design, it is recommended that the two patio
areas (one at the southwest and one at the northwest comers of the project) along
Carlsbad Boulevard be reduced in size by approximately 50% and used as landscape area.
Groupings of large scale trees should be incorporated in these locations to soften and
enhance the architecture.
3. Please identify all symbols used on the plans. Check all symbols.
4. Please address planting of all landscape areas.
5. Landscaping is minimal and insufficient along the southeast and northwest sides of the
building leaving elevations exposed and un-softened. Plantings that are proposed are in
containers (due to a parking stmcture below) which will limit the ultimate size of the
plants. Additional landscaping is needed to both soften and enhance these elevations.
Please provide additional plantings to better scale with the architectural mass. Provide
detailed information as to the expected ultimate size of the plants that are to be grown in
the containers.
6. There appear to be windows with views out to the 6' masonry wall along the southeast
side of the building. Please provide landscaping along this wall to soften and enhance
views.
7. Please show and label all property lines and easements on the landscape plans.
DKN Hotel - Springhill Suites - Marriott - RP05-03 - CDP05-14 August 1, 2006
Conceptual Plan Review Page 2
8. Provide a plant palette list indicating the following:
a. Tree types and quantities
b. Shmb types and quantities (approximate)
c. Proposed plant sizes (either by number or % of total quantity)
9. All planting areas shall be outlined as one of the four planting zones below and described
in Appendix A:
Zone One Lush
Zone Two Refmed
Zone Three Naturalizing/Transitional
Zone Four Native
10. Indicate the percentage of the landscaped area (as defined in Appendix G) of each
planting zone as described in Section A.5-3 and Appendix A.
11. Show and label any bio-swales/detention basins or underground drainage collection
systems (in or under planting areas that could impact the planting) and work these
facilities into the design.
12. 50% of the shmbs (except on slopes 3:1 or steeper) shall be a minimum 5 gallon size.
Please insure this requirement is met.
13 . All utilities are to be screened. Landscape constmction drawings will be required to
show and label all utilities and provide appropriate screening. Please also locate all light
poles on the landscape plans and insure that there are no conflicts with trees.
14. Plans shall include but not be Hmited to:
a. Extent of Planting Zone 1 (Lush) - Indicate percentage of Zone 1 planting (per
Appendix A) of the total landscaped area (as defined in Appendix G). Provide
justification for the appropriateness of where Zone 1 plantings are used in terms
of water conservation. (For example, are Zone 1 plantings in areas of shade
where they will use less water and/or has the soil been suitably amended so as to
retain relatively greater moisture?)
b. Proposed turf areas. (See limitations in IV.C.3-4.2) Give percentage of turf of the
total landscaped area.
15. Plan notes indicate that other than the turf, there are no zone 1 plantings. Plans call for
Cypems which is zone 1. Please revise notes as appropriate. Include all zone 1 plantings
in the percentage calculations per comment numbers 10 and 14 above.
16. Per the water conservation section of the manual (C.3-4.6), woody shmbs must be
planted over herbaceous groundcover to cover 60% of the groundcover area at maturity.
Please insure that this requirement is met.
17. Please reduce the percentage of turf to meet requirements of the landscape manual
section IV, C.3-4.2-1.
18. Please clearly indicate and label the precise location of the Red Fescue planting on the
plans.
19. It is recommended that landscaping be included along the southwest side of the pool to
soften and enhance this wall. Please address.
20 RETURN REDLINES and provide 2 copies of all plans (concept and water
conservation) on the next submittal.
(5 itv of Carlsbad
Public Works/Parks Division
July 26, 2005
Mr. Kenny Booth
1530 Faraday Avenue, Suite 100
Carlsbad CA 92008
Dear Mr. Booth,
I wish to tiiank you for your letter to Mr. Kyle Lancaster, dated July 20, 2005, regarding
the removal and relocation of the three Washington robusta pakns. Although, these
palms will be planted in our right-of-way they are not in our Street Tree Inventory.
Therefore, the City does not maintain tiiese trees. I will be forwarding your letter to the
City's Housing and Redevelopment office for their review.
Again, thank you for notifying us as to your future landscape plans and all the best to you
and staff regarding this project.
Sincerely,
Michael E. Bliss
Tree Supervisor
760/434-2985
1200 Carlsbad Village Drive • Carlsbad, CA 92008 • (760) 434-2825 • FAX (760) 434-7185
PLANNING
SYSTEMS •
LAND USE/COASTAL PLANNING
LANDSCAPE ARCHITECTURE • LA3900
POLICY AND PROCESSING
ENVIRONMENTAL MITIGATION
RECEIVED
JUL 2 0 2005
July 20,2005
Kyle Lancaster
CITY OF CARLSBAD
General Services Division
3096 Harding Street
Carlsbad, CA 92008
RE: RP 05-03/SDP 05-04/DEV 05-19/LCPA 05-02/ZC 05-02/GPA 05-05 -
DKN Hampton Inn
Dear Mr. Lancaster: / ^
We have recently submitted an application to the City of Carlsbad Housing & Redevelopment
Department for a Redevelopment Permit, Site Development Plan, Local Coastal Program
Amendment, Zone Change and General Plan Amendment for the development of a Hampton Inn
Suites on the property located at 3136 Carlsbad Boulevard.
The proposed development will impact three (3) Washingtonia Robusta trees located in the public
right-of-way. The trees will be removed to make room for a new driveway that will give access
to the project. The current proposal is for the trees to be relocated within the public right-of-way.
Please fmd attached a copy of the conceptual project plans. Included in the plans is the
Preliminary Landscape Plan, which shows the current location of the trees and the proposed
relocation sites.
Please accept this letter as a formal application for the removal and relocation of these trees.
Sincerely,
Kenny Booth
Planner
cc: Paul Klukas
Neil Patel
Attachment
1530 FARADAY AVENUE • SUITE 100 • CARLSBAD, CA 92008 • (760) 931-0780 • FAX (760) 931-5744 • info@planmngsystems.net
PLANNING
SYSTEMS D LAND USE/COASTAL PLANNING
LANDSCAPE ARCHITECTURE • LA3900
POLICY AND PROCESSING
ENVIRONMENTAL MITIGATION RECEiVED
JUL 1 ^ 2006
CIW OF CARLSBAD HOUSING & REDEVELOPMENT
DEPARTMENT
July 14,2006
Cliff Jones
CITY OF CARLSBAD
Housing & Redevelopment Department
2965 Roosevelt St. Ste B
Carlsbad, CA 92008
RE: RP 05-03/SDP 05-04/DEV 05-19/LCPA 05-02/ZC 05-02/GPA 05-05 -
DBCN Springhill Suites
Dear CHff:
Per your letter dated March 1,2006 identifying Staff items and issues with the subnuttai
of the above-referenced project, the project applicant has commissioned modifications to
the project design and the provision of the additional information requested regarding
the project. To this end, attached with this cover letter please find a re-submittal
package including:
Five (5) sets of revised plans
Height Analysis
CDP fee of $3,817.80
Variance Findings
Pool Area Detail Exhibit
With regard to the specific items and issues identified in the March 1 letter, the
following is a discussion of the method in which the redesigned project addresses the
general issues, followed by a specific response to each item/issue identified by City
Staff, in the order presented in your draft letter.
Issues of Concern
Housing & Redevelopment and Planning:
1. Please replace tiie DEV 05-19 # witii tiie Coastal Development Pennit # (CDP 05-
14) on the front cover sheet of the plans.
Response: DEV 05-19 has been replaced by CDP 05-14 on all plan sheets.
2. Please correct the spelling error on the front cover sheet under Developer to read
"DKN Hotels".
Response: The spelling error on the Cover Sheet (CS) has been revised. It
now reads "DKN Hotels".
1530 FARADAY AVENUE • SUITE 100 • CARLSBAD, CA 92008 • (760) 931-0780 • FAX (7160) 931-5744 • iiifo@planningsystems.net
3. Staff recently noticed that a fee was not collected for CDP 05-14. A fee for the
CDP will need to be coUected. The fee wiU need to be broken down by zoning. Staff
will need to coUect $560 for the VR zoning and $835.00 -i- .10 per square foot for the area
outside the VR zoning. Please contact staff for more information.
Response: A check for $3,817.80 is included with this re-submittal.
Breakdown as foUows:
36,954 sq. ft. x .10 = $3,695.40 + $835.00 + $560 (-25% discount) = $3,817.80
4. Staff coimts a total of 105 rooms. Each room that has a door and direct access to
the main haU way should be calculated in the room coimt. This has an effect on the
parking calculation. Please revise the plans accordingly.
Response: After redesign of the hotel, the room coimt now stands at 104. AU
rooms that have a door and direct access to the main haUway have been included
in this count. Correspondingly, the parking calculations have been revised to
properly match the room count.
5. Architectural features may only encroach two feet in required yards. Please
make sure that aU overhangs and coltmms are at least 3 feet back from the front property
line.
Response: The plans have been revised to show that aU oveihangs and
columns encroach no more than 2 feet into all required yards, including the front
property line. ThiscanbeseenontheRoof Plan (Sheet A-9).
6. Please provide section detail and elevations of the proposed property line waUs
so staff can evaluate design.
Response: Elevations and section details of the proposed property line waUs
have been provided. These can be seen on Sheet A-15.
7. Staff does not have enough information to evaluate the proposed signage.
Signage wiU require a separate pemiit; therefore it may be best to ehminate the signage
plan Sheet A-11 for now. The signage can be approved as part of a sign pemiit separate
from the major redevelopment pennit. We apologize for the confusion.
Response: The signage plan (Sheet A-11) has been eliminated from the plans
as requested. An application for a sign pemiit wiU be initiated after the hearings
and approval of the project.
8. Staff assumes the building height displayed on the elevation sheets is displayed
from the most restrictive point (of existing or finished grade). Is that correct?
Response: Building height has been calculated from existing grade to the top
of the parapet. This is the most restrictive point since there wiU be 1-2 feet of fiU
soil which has been included in the height calculation. This information can be
seen on Sheet A-10.
PLANNING
SYSTEMS
9. Staff has not received the necessary variance findings to support the northem
portion of the building to abut the adjacent 7-11 use. Please provide the support for the
variance findings required imder 21.35.130 of the Carlsbad Mimicipal Code.
Response: Included with this re-suhmittal are draft variance findings to
support the northem portion of the building abutting the adjacent 7-11 property.
The findings have been made as required under 21.35.130 of the Carlsbad
Municipal Code.
Engineering:
1. Label private drainage easement as shown on redlines.
Response: The Engineering plans have been revised and the private drainage
easement has been properly labeled.
Fire:
1. The breakfast room measures greater than 750 square feet, thus it requires two
exits equal to one-half of the rooms diagonal measurement.
Response: Two separate exits from the breakfast room have been provided.
This can be seen on the First Floor Plan (Sheet A-2).
2. Provide a walkway from the meeting room westward to the pubHc way
(Carlsbad Blvd) joining the outdoor dining or patio area.
Response: A walkway has been added from the meeting rooms westward
toward Carlsbad Boulevard. The walkway wiU give patrons exiting the meeting
rooms access to both the outdoor dining/patio area and Carlsbad Boulevard.
This can be seen on Sheet A-2.
3. The "rated" corridor shall not be intermpted by intervening room(s). Refer to
CBC 1004.2.2 "Interveni ng Rooms".
Response: A pair of doors with magnetic hold-open devices has been
added to separate the 1-hour corridor from the pubHc space intervening room.
The corridor has a direct exit to the south elevation. This information can be seen
on Sheet A-2.
4. Provide a detail of the pool area and enclosure and gates including proposed
hardware. Note: all gates shaU be provided with panic hardware.
Response: As requested, an 8 ¥2" xll" exhibit has been included that
provides a detaU of the pool area and gates.
PLANNING
SYSTEMS
Additional City Comments:
1. Include a shade/shadow study for the proposed portion of the hotel nearest the
neighboring property to the south as well as for a potential residential project on the
existing R-3 portion of the property.
Response: A shade/shadow comparative analysis for a potential hotel use
and residential use (on the existing R-3 portion of the property) has been
included with this re-suhmittal. This analysis can be seen on Sheets A-12
through A-14.
2. Please provide a height analysis of the proposed project in relation to
neighboring properties.
Response: A height analysis of the subject project in relation to neighboring
properties has been included as part of this re-submittal. The analysis shows the
existing building heights in the vicinity of the proposed project.
3. Include colored elevations.
Response: Colored elevations for the proposed hotel have been included as
part of this re-submittal package.
4. Consider lowering the roof pitch along Lincohi Avenue and the side of the hotel.
Try to make it look more like a tme roof Hne. In doing so, this may also lower the
overaU height of the project along Lincoln Avenue.
Response: We have conducted a detailed analysis of the option of lowering
the roof pitch in this area. It is our conclusion that a lower roof pitch is not
physicaUy and stmcturaUy compatible with the gable projections and roofiine of
the remainder of the project. The eave has been lowered to sit on top of the top
plate, resulting in a larger roof area. The height along Lincoln Avenue (as
measured from existing grade) is now 34' 6".
Thank you for your continued assistance with the plarming of this project. With these
minor revisions, we are hopeful that the project design is now acceptable. We look
forward now to docketing for Design Review Board/Plaiming Commission hearing.
Paul J. Klukas
Director of Planning
cc: Neil Patel
Attachments
PLANNING
SYSTEMS
FINDINGS OF APPROVAL - VARIANCE
1. Because of special circumstances applicable to the subject property, including size,
shape, topography, location or surroundings, the strict application of the zone regulation
deprives such property of privileges enjoyed by other property in the vicinity and under
identical zoning classification.
Finding: The subject lot contains unusual circumstances which deprive the
property ovmer from privileges that other properties in the area enjoy. The
subject parcel is oddly shaped, due to the alignment of Carlsbad Blvd., with a
small triangular shaped wedge jutting north along this Carlsbad Blvd. frontage.
Traditional setback standards would render this portion of the property virtually
useless. Additionally, the parcel sits at a diagonal along Carlsbad Boulevard
making that portion of the property more restrictive to the setback standards.
2. The variance shall not constitute a grant of special privileges inconsistent with the
limitations upon other properties in the vicinity and zone in which the subject property is
located and is subject to any conditions necessary to assure compliance with this finding.
Finding: The applicant is being denied property rights that other property owners
in the vicinity of the project have been given. The adjacent 7-11 building
possesses a zero setback along the shared northem property line. The six unit
apartment complex to the south of the proposed hotel has been built to only a 3
foot side yard setback where a 7.5 foot setback would typically be required within
the R-3 zone. Additional residential units immediately south of the proposed
hotel have 1 foot setbacks on the shared property line with the subject parcel.
These projects are legally non-conforming to present day zoning standards.
The proposed hotel proposes all setbacks in accordance with both the VR and CT
zones with the exception of the northem property line adjacent to the west side of
the existing 7-11 building. Along that property line, a zero setback is proposed
due to the irregular shape of that portion of the subject property, and the fact that
the adjacent project also possesses a zero setback. A standard setback would not
allow for use of the triangular shaped piece of the lot. This is only along a small
fraction of the site.
3. The variance does not authorize a use or activity which is not otherwise expressly
authorized by the zone regulation goveming the subject property.
Finding: The VR zone does allow for variances for decreased setbacks.
Variances shall be granted according to the regulations set forth in Section
21.35.130 of the Carlsbad Municipal Code. The proposed use is consistent with
the allowed uses in the zone.
PLANNING
SYSTEMS a
4. The variance is consistent with the general purpose and intent of the general plan,
Carlsbad village area redevelopment plan, and the Carlsbad village redevelopment master
plan and design manual.
Finding: The variance is consistent with the general purpose and intent of the
General Plan in as much as the General Plan indicates that the Village is
designated as a redevelopment area and is regulated by the Carlsbad Village Area
Redevelopment Plan and the Village Design Guidelines Manual. The General
Plan also identifies specific goals for the Village that includes encouraging new
economic development in the Village and near transportation corridors to attract
additional tourist-oriented uses. The proposed hotel directly fulfills this goal and
the setback variance will allow for full intensification of the site particularly along
Carlsbad Boulevard.
The variance is consistent with the Carlsbad Village Redevelopment Master Plan
and Design Manual. The Design Manual states: ''Variances shall be granted
according to the regulations set forth in Section 21.35.130 of the Carlsbad
Municipal Code."
5. In addition, in the coastal zone, that the variance is consistent with and implements the
requirements of the certified local coastal program and that the variance does not reduce
or in any manner adversely affect the protection of coastal resources as specific in the
zones included in this title, and that the variance implements the purposes of zones
adopted to implement the local coastal program land use plan.
Finding: The variance is consistent with the Local Coastal Program (LCP) in as
much as the LCP calls for tourist serving uses on the site. The variance will allow
for full use of the property and allow for a reasonable maximum number of tourist
serving uses.
PLANNING
SYSTEMS
4-1 -S
_ O (0
in vj) 3
E: O
TO
IP
s_
sz
O
in
£
ti_ .—
O SI Ll O «5 — a_ CL
in vn 3
Legend
I 1 Building Height < 15'
I iRiiiifiing Height 15-29'
•••Building Height 30'-34'
•••Building Height 35'+
CZZZ3 Proposed DKN Hotel
DKN Surf Motel-Vicinity Heights Analysis
Existing Conditions
Carlsbad, Caiifomia
July 13,2006 PS#041030
0' 75' 150' 300'
Scale: 1" = ISO-
PLANNING
SYSTEMS
Memorandum
TO: Cliff Jones - Assistant Planner
FROM: David Rick - Assistant Engineer
DATE: July 5, 2005
RP 05-03/DEV 05-19/ZC 05-02/GPA 05-05/LCPA 05-02/SDP 05-04/EIA 05-02 - DKN
HAMPTON INN
COMPLETNESS AND ISSUES REVIEW
Engineering Department staff has completed a review of the above-referenced project for completeness
and engineering issues of concern. All items needed for engineering review are provided for determining
the application as complete. Engineering issues which need to be resolved or adequately addressed prior
to staff making a determination on the proposed project are as follows:
1. Determine the size of the existing water services and meters. Will several of the existing services
be utilized or will one service line (i.e. 2" pipe and meter) be used for the entire potable water
supply? Will the existing fire sprinkler service line with back flow preventor located at the
southerly corner of the lot on Carlsbad Boulevard be abandoned since a new 6-inch pipe with
Double Detector Check Valve is proposed on Lincoln Street? In addition, the meter located in the
main entrance driveway must be located outside the driveway, so either label as "to be
abandoned" or show area of relocation.
2. Provide scaled centeriine longitudinal profile of driveway with BVC and EVC at top and bottom of
driveway.
3. In your letter, you stated that Parcels 1-4 are legal parcels. Provide proof that Parcels 1-4 are
separate legal parcels. A chain of title search may be required. If each parcel was established by
deed prior to June 1, 1956, then each parcel will be considered legal parcels. Although the
adjustment plat would legalize the parcels, there is no assurance that parcels beyond the
boundary of the adjustment plat was illegally subdivided.
4. Plot the raised median in the Carlsbad Boulevard cross-section and dimension the sidewalk.
5. Provide proof that application for permitting removal of the three trees within the public right-of-
way has been submitted to the General Services Division.
6. Although details of the underground parking drainage are not provided, filtering of the
hydrocarbons, heavy metals, etc. must be addressed on the plan and through the SWMP.
7. Revise the hydrology report per the redlined comments.
8. It appears that a new 55-foot contour line is shown on Parcel 28 to the south. Is off site grading
proposed to redirect drainage away from the subject property? If so, then temporary off-site
construction easements will ultimately be required. In the mean time, provide a letter from the
property owner giving preliminary permission to grade. An option to grading off-site would be to
allow drainage to continue to flow onto the subject property. The objective is to prevent any new
flooding or ponding on the neighbor's property do to this development
9. The D-25 drain outlet manhole cannot be placed in the sidewalk. Place the manhole behind the
sidewalk. Propose a public drainage easement over the manhole.
10. Revise the attached Water System and Sewer System Analysis Plans per redlined comments.
Submit two copies of corrected plans with next submittal.
11. The grading quantities indicate that 2,047 cubic yards of soil will be excavated and according to
your response letter, this amount includes excavation for the garage. However, given that the
lower level garage is 28,251 square feet and approximately 20 feet deep, rough calculations for
the excavation come out to at least 21,000 cubic yards of soil. Please recalculate the quantities.
12. Provide an addendum to the soils report or letter from the soils engineer determining the potential
impacts, if any, that the saturated soil from the retention basin could have on the adjacent street
improvements and building. On the site plan, provide the ADT generated from the existing use
that will be demolished.
13. The letter mentioned with your recent submittal from Flores Lund Consultants explaining the
recommended construction techniques for shoring was not included in the submittal package.
Please provide this information.
14. Revise the traffic report per redlined comments and submit two copies of corrected report with
your next submittal.
15. Revise the redlined Storm Water Management Plan and submit two copies of the revised plan
with your next submittal.
Please have applicant return all attached redlined plans and documents with their next submittal.
If you or the applicant has any questions, please either see or contact me at 602-2781.
DAVID RICK
Assistant Engineer
Engineering Development Services Division
Attachment: Redlined Storm Water Management Plan
Redlined Traffic Impact Analysis
Redlined Water and Sewer System Analysis
Redlined Preliminary Hydrology Report
Redlined Grading and Drainage Plan
C: Deputy City Engineer, Development Services Division
Memorandum
TO: Cliff Jones, Assistant Planner
FROM: David Rick, Assistant Engineer
DATE: April 6, 2005
RP 05-03/DEV 05-19/ZC 05-02/GPA 05-05/LCPA 05-02/SDP 05-04/EIA
05-02/CDP 05-14: DKN - HAMPTON INN COMPLETENESS & ISSUES
REVIEW
Engineering Department staff has completed a review of the above-referenced project
for application completeness. The application and plans submitted for this proposed
project are currently incomplete and unsuitable for further review due to the
following incomplete items:
1. A Storm Water Management Plan completed, sealed and signed by a registered
civil engineer.
The following issues need to be resolved prior to resubmittal:
2. On the preliminary grading and drainage plan:
a. Plot or identify with note the location of the nearest fire hydrant and
distance from building to said hydrant.
b. Screen existing facilities and darken proposed facilities to make more
distinguishable.
c. Add potable and peak potable water and fire flow demand in gpm.
d. Add sewer generation rate in million gallons per day.
e. Under "Construction Legend for Surface Improvements" note No. 4,
change "Private" to "Public".
f. Identify the street signs along the property frontage, including the "Begin
Park Parallel" and "End Parking to the Corner" signs.
g. Identify Bus Stop on Carlsbad Blvd.
h. Specify that the water line in Carlsbad Blvd. is ACP and show connecting
line in Oak.
i. Show southerly continuation of sewer main in Carlsbad Blvd.
j. Add water meter symbols on Lincoln Street and irrigation BFP symbol on
Carlsbad Blvd. The notes have leaders pointing at nothing. Also, plot all
water service lines.
k. Provide cross sections at the northerly and southerly boundary of Parcel
three.
I. Plot the water main in Lincoln Street and show all service lines to the
subject property.
m. Determine if the wood fence along the Lincoln Street frontage will remain
or be removed.
n. Add Top of Wall/Bottom of Wall elevations to those retaining walls that do
not provide this information.
3. Plot intersection site distance for a vehicle exiting the driveway onto Carisbad
Blvd. and a trash truck backing onto Lincoln Street from the Service Entrance.
Also, will the service entrance primarily be used for deliveries?
4. On Carlsbad Blvd., show sidewalk as existing and plot transition with abutting
frontages. On Lincoln Street, plot existing sidewalk fronting the 7-Eleven
Shopping Center.
5. Provide a cross sectional profile ofthe driveway ramp and include BVC and EVC
at the base of the driveway. Also, plot percent grade of the parking lot ramps
and add vertical curves as needed.
6. The trash receptacles are placed on the north side of the Service Entrance on
Sheet C-1 and on the south side on Sheet A-1. Since the driveway approach
complies with City standards for separation from property line on Sheet C-1, this
design should prevail.
7. Are Parcels 1-4, as described in the titie report, separate legal parcels? If so, an
adjustment plat may be necessary to consolidate the parcels into one. Provide
documentation to support status.
8. Correct the street sections plotted on Sheet C-1. Identify east and west side of
the cross section and show sidewalk on the east side of Carlsbad Blvd. as non-
contiguous. Also, extend base an additional 6 inches beyond curb.
9. Plot the location of all tree trunks within the public right-of-way. Determine
whether the trees wili remain or be removed. Permission from the General
Services Division of the City Parks and Recreation Department must be granted
for any trees to be removed within the public right-of-way.
10. Clearly plot the proposed sidewalk as contiguous with the proposed curb and
gutter on Lincoln Street. It appears that the sidewalk is proposed as non-
contiguous with the sidewalk. Clearly show that the sidewalk will end at the
southern boundary of the Lincoln Street project frontage and that sidewalk does
not exist along the southerly abutting property. Plot edge of pavement and flow
line and/or spot elevations within this area to illustrate adequate drainage and
pavement transition. Add detail if needed.
11. Show drain inlet and dual alternating pumps for the ramp leading to the garage.
How will the underground garage drain? Will rain/irrigation water reach this area?
How will water from periodic cleaning of garage be extracted? Provide
explanation on plans.
12. Plot all existing and proposed sewer laterals and water service lines. Provide
pipe material and size. Include water line and DDC valve for fire sprinkler
system. If any of the existing water services and meters is not going to be used,
identify as abandoned. Meters shall be placed in the public right-of-way. Check
valves shall be placed on private property.
13. Correct the attached redlined hydrology report and submit two copies of
corrected plan with your next submittal.
14. Drainage on Parcel 28 appears to flow northerly toward the subject property. A
retaining wall is proposed at the property line. This wall will block drainage as
designed. Provide a means to prevent ponding in this area.
15. Place D-25 manhole within the public right-of-way so that City may access for
cleaning outiet.
16. Per the Storm Drain Legend, the "V" designation indicates that the minimum size
of the proposed yard drain is 12". This size seems excessive. It appears that a
lesser size would be adequate. Please reevaluate.
17. Provide a detail of the proposed wall on the north side of the driveway ramp.
Given the depth of excavation, height of the wall to support the underground
parking, the location at the property line and close proximity to the 7/11 Store,
there are concerns about potential effects the excavation and wall could have on
the neighboring property. In addition, it does not appear that enough space exists
between the proposed wall and property line to accommodate an underground
drainpipe. A cross section would help illustrate the proposed design.
18. Include the excavation quantities for the garage.
19. Address the issues/comments redlined in the soils report.
20. On Sheet CS, the owner's name should be the same as the name of the owner
in title report. However, sheet CS states that the owner is DNK Hotels. The title
report states that the estate is vested in "Dahya Bhai L. Patel and Shantaben
Patel, husband and wife as joint tenants, as to Parcels 1, 2 and 3 and Dahya
Patel, a married man as his sole and separate property, as to Parcel 4. Please
clarify. Correct property owner needs to be placed on Sheet CS.
21. Correct the ADT on Sheet CS to read 8/unit = 808 ADT. Also, subtract existing
ADT to establish net increase.
22. Indicate on cover sheet that fire sprinklers will be installed.
23. Some of the bearings and distances vary several feet or minutes from record
information. Please correct accordingly.
24. Add a note to the plans stating that the overhead utilities along Lincoln Street
frontage will be placed underground.
25. On Sheet A-10 (Building Sections), show adjacent buildings such as 7-Eleven.
Also, plot ground water table and identify lateral loads from excavation for
underground garage based on 1:1 inclination.
26. Are any doors, meters or other routinely accessed facilities located behind the 7-
Eleven building? If so, how will access be maintained given that the grade will be
lowered for the driveway ramp?
27. Correct the traffic study per redlined comments.
28. Due to proposed land use changes, provide a water and sewer analysis to
determine ability of existing City infrastructure to accept any additional demand.
Please submit all redlined documents and plans with your next submittaL Three
copies of each corrected document shall be submitted. If you or the applicant has
any questions, please either see or contact me at extension 2781.
DM}Bli\CK
assistant Engineer
Development Services Division
Attachment: Redlined grading and drainage plan
Redlined Hydrology Report
Redlined Soils Report
Redlined Traffic Report
C: Senior Engineer - Development Services Division
Project Planner - Van Lynch
City of Carlsbad
Housing & Redevelopment Department
March 1, 2006
DKN HOTELS
540 GOLDEN CIRCLE DRIVE #214
SANTA ANA, CA 92705
SUBJECT: DKN - Hampton Inn (RP 05-03, SDP 05-04, CDP 05-14, LCPA 05-02, ZC 05-02,
GPA 05-05)
APN: 203-250-08 & 203-250-26
The purpose of this letter is to address issues of concem raised by City staff following a review
of the revised plans. The issues of concern are attached for your review. These issues must
be addressed prior to staff making a formal recommendation on the project.
Please contact my office at (760) 434-2813, if you have any questions or wish to set up a
meeting to discuss the application.
Sincerely,
CLIFF JONES
Assistant Planner
Kenny Booth, Planning Systems
Debbie Fountain, Housing & Redevelopment Director
Greg Ryan, Fire
Van Lynch, Planning
David Rick, Engineering
2965 Roosevelt St., Ste. B • Carlsbad, CA 92008-2389 • (760) 434-2810/2811 • FAX (760) 720-2037 @
DKN Hampton Inn
03/01/2006
Page 2 of3
ISSUES OF CONCERN
No. RP 05-03, SDP 05-04, CDP 05-14, LCPA 05-02, ZC 05-02, GPA 05-05
Staff has completed a review of the subject project for issues of concem. The following items
need to be resolved or adequately addressed prior to staff making a final determination on the
proposed project: (Please note, the issues are listed under the department which identified
them as an area of concern.)
l-lousing & Redevelopment & Planning:
1. Please replace the DEV 05-19 # with the Coastal Development Permit # (CDP 05-14) on
the front cover sheet of the plans.
2. Please correct the spelling error on the front cover sheet under Developer to read "DKN
Hotel".
3. Staff recently noticed that a fee was not collected for CDP 05-14. A fee for the CDP will
need to be collected. The fee will need to be broken down by zoning. Staff will need to
collect $560 for the VR zoning and $835.00 + .10 per square foot for the area outside the
VR zoning. Please contact staff for more information.
4. Staff counts a total of 105 rooms. Each room that has a door and direct access to the main
hall way should be calculated in the room count. This has an effect on the parking
calculation. Please revise the plans accordingly.
5. Architectural features may only encroach two feet into required yards. Please make sure
that all overhangs and columns are at least 3 feet back from the front property line.
6. Please provide section detail and elevations of the proposed property line walls so staff can
evaluate design.
7. Staff does not have enough information to evaluate the proposed signage. Signage will
require a separate permit; therefore it may be best to eliminate the signage plan sheet A-11
for now. The signage can be approved as part of a sign permit separate from the major
redevelopment permit. We apologize for the confusion.
8. Staff assumes the building height displayed on the elevation sheets is displayed from the
most restrictive point (of existing or finished grade). Is that correct?
9. Staff has not received the necessary variance findings to support the northern portion of the
building to abut the adjacent 7-11 use. Please provide the support for the variance findings
required under 21.35.130 ofthe Carlsbad Municipal Code.
For questions regarding Housing & Redevelopment Department and Planning comments,
please contact Cliff Jones at 760-434-2813.
Fire:
1. The breakfast room measures greater than 750 square feet, thus It requires two exits equal
to one-half of the rooms diagonal measurement.
DKN Hampton Inn
03/01/2006
Page 3 of 3
2. Provide a walkway form the meeting room westward to the public way (Carlsbad Boulevard)
joining the outdoor dining or patio area.
3. The "rated" corridor shall not be interrupted by intervening room(s). Refer to CBC 1004.2.2
"Intervening Rooms"
4. Provide a detail of the pool area and enclosure and gates including proposed hardware.
Note: All gates shall be provided with panic hardware.
For questions regarding Fire Department comments, please contact Greg Ryan at 760-602-
4663.
Engineering:
Engineering Department comments are forthcoming and will be sent under a separate cover.
21.35.117
2135.117 Notice of public hearings.
Notice of any public hearing required by this chap-
ter shall be given as provided in Section 21.54.060( 1)
ofthis code. (Ord. NS-330 § 4 (part), 1995)
21 J5.120 Consolidation of other pemiits and
discretionary approvals—^Findings
requirenients.
(a) Whenever a project would require a pennit
or approval underthe provisions of this title, notwith-
standing this chapter, the redeveiopment pennit shall
be deemed to satisfy the requirements for such pennit
or approval; provided, however, that in considering
the redevelopment permit for said project the direc-
tor, design review board and the housing and rede-
velopment commission shali apply the provisions of
this chapter and the provisions of this title otherwise
applicable to such other pennit or approval for the
project
(b) Whenever a project consists only of exemp-
tion determinations and/or administrative pennits or
administrative variances within the authority of either
the director of planning or the director, they shall be
consolidated and considered by the director, subject
to apF>eal to the design review board witb regard to
determinations other than exemptions.
(c) If the project includes pennits or other dis-
cretionary approvals outside the director's adminis-
trative permit or administrative variance authority,
the administrative permit and/or administrative vari-
ance aspects shall be consolidated with the other mat-
ters and submitted to the design review board.
(d) No variance, detennination of exemption or
administrative, minor or major redevelopment permit
shall be granted unless the decisionmaker finds, in
addition to any other findings otherwise required for
the project, that the project as approved, or condi-
tionally approved is consistent with this code, the
general plan, the Carlsbad village area redevelopment
plan and the village master plan and design manual.
(Ord. NS-330 § 4 (part), 1995)
2U5.130 Variances.
(a) The housing and redevelopment commissicm
may grant variances from the limits, restrictions and
controls established by this chapter for major rede-
velopment permits if the commission finds that:
(1) Because of special circumstances applicable
to the subject property, including size, shape, topog-
raphy, location or surroundings, the strict application
of the zone regulation deprives such property of
privileges enjoyed by other property in the vicinit}'
and under identical zoning classification;
(2) The variance shall not constitute a grant of
special privileges inconsistent with the limitations
upon other properties in the vicinity and zone in
which the subject property is located and is subject to
any conditions necessary to assure compliance with
this finding;
(3) The variance does not authorize a use or activ-
ity which is not otherwise e^q^ressly aumorized by the
zone regulation goveming the subject property;
(4) The variance is consistent with die general
purpose and intent of the general plan, Carisbad vil-
lage area redevelopment plan, and the Carlsbad vil-
lage redevelopment master plan and design manual;
(5) In addition, in the coastal zone, tiiat the vari-
ance is consistent with and implements the require-
ments of the certified local coastal program and that
the variance does not reduce or in any manner ad-
versely affect the protection of coastal resources as
specified in the zones included in this titie, and diat
the variance implements the purposes of 2^nes
adopted to implement the local coastal program land
use plan.
(b) An application for a variance shall be proc-
essed in the same manner established by this chapter
for a redevelopment pennit.
(c) The design review board may grant variances
from the limits, restrictions and controls established
by this chapter for minor redevelofmient projects (or
otherwise administrative f»x)jects consolidated or on
appeal fipom a director decision), if the board makes
the variance findings set forth in subsection (a) of
this section.
(d) The director may grant administrative vari-
ances in accordance with Section 21.35.090(e), if the
director makes the findings set forth in subsection (a)
ofthis section. (Ord. NS-675 § 36, 2003: Ord. NS-
330 §4 (part), 1995)
(Cvlstad Supp. No. 7.2-04) 648
February 08, 2006
Van Lynch
1635 Faraday Avenue
Carlsbad, CA. 92008
Re: 3155 Lincoki Street
Carlsbad, CA. 92008
Dear Mr. Lynch:
This letter is in regard to the proposed Marriott Motel expansion at 3155 Lincohi Street,
Carlsbad, CA. 92008. I am the owner/neighbor at 3177 Lincoln Street, Carlsbad, CA.
92008. I purchased this apartment complex with the intent of making my personal
residence in one of the units and have occupied unit F since 1999. My overall Hving
experience here has been one of tranquility and enjoyment. My tenants have been quality
individuals with few exceptions.
In past years we have periodicaUy had complaints conceming noise originating from the
motel-owned properties (tenants), and after notifying poUce numerous times of the
problem, the offending individuds were requested to quiet down without fiirther official
action. If you, personally, have had similar dismptions in the middle of the night, I am
sure you will agree how very annoying the inconvenience can be.
Now my understanding is that a proposed zone change from R3 to multiple units
(commercial) has been under consideration with a pool to be constmcted on the adjacent,
north side of my property. The location of a pool south of the motel has the potential to
create double the noise factor at all hours of the day and night whether svmnming or
socializing around the pool. This dismption would echo not only to the abuttuig property
but to all neighboring properties.
In my opinion this zoning change and proposed building of 100 plus units will drastically
reduce my future property value and monthly income not to mention the threat to my
ability to attract quality tenants who expect a certain level of peace and enjoyment in
their living environment. There is no way to control the noise from that type of density
and the subsequent effect on the surrounding area. The resulting conditions would have a
devastating impact on my property.
Lynch/Kom 02/08/06
Therefore, I am requesting that the zoning on the property at 3155 Lincoki Street not be
changed from the present zoning. My investment would suffer a severe loss and the
current favorable living condtions at 3177 Lincoki Street would greatly deteriorate.
I have discussed this proposal with owners of Pme Street properties adjacent to mine
and they are as concemed as I am about the noise and extreme density.
Thank you for your attention and consideration of this matter.
Sincerely,
WiUiam (Sam) Kom
CC: C. Jones, Assistant Planner
CityofCarlsbad
Sam
760-730-3333
Property owner to the south off Lincoln Street.
Met with him on 2/2/2006 and showed him the plans.
Spoke with him on the phone on 2/6/06.
Concems:
• Wall Height
• Building is large and will shade his property
• Units/acre will be greater as commercial hotel than if residential
PLANNING
SYSTEMS •
LAND USE/COASTAL PLANNING
LANDSCAPE ARCHITECTURE • LA3900
POLICY AND PROCESSING
ENVIRONMENTAL MITIGATION
February 1, 2006
Cliff Jones
CITY OF CARLSBAD
RECEIVED
FEB U i
Housing & Redevelopment Department
2965 Roosevelt St. Ste B
Carlsbad, CA 92008 "OEPARTMEI
^a^cTD UC4. C4. t) cir/OF CARLSBAD 2965 Roosevelt St. Ste B "OUSlNG&REgjQPMENT
RE: RP 05-03/SDP 05-04/DEV 05-19/LCPA 05-02/ZC 05-02/GPA 05-05 -
DKN Springhill Suites
Dear Cliff:
Per your letter dated December 1, 2005 identifying Staff items and issues with the
submittal of the above-referenced project, the project applicant has commissioned
modifications to the project design and the provision of the additional information
requested regarding the project. To this end, attached with this cover letter please find a
resubmittal package including:
• Five (5) sets of revised plans
• Redlined Grading and Drainage Plan
• 2 copies of revised Preliminary Storm Water Management Plan
• Redlined Preliminary Storm Water Management Plan (Sheet 3 only)
• 2 copies of revised Traffic Study
• Redlined Traffic Study (cover sheet only)
• Chain of Title Search
With regard to the specific items and issues identified in the December 1 letter, the
following is a discussion of the method in which the redesigned project addresses the
general issues, followed by a specific response to each item/issue identified by City
Staff, in the order presented in your draft letter.
Issues of Concem
Housing & Redevelopment and Planning:
1. Please complete the Early Public Notification Package. The requirements for the
early pubHc notice package are enclosed.
Response: A project notification sign was posted onsite on 12/15/05 to
satisfy the requirement of the Early Public Notification Package.
2. Overall Staff Hkes the architectural theme for the project. However, planning
staff has concems about the look of the mansard roof as viewed from Lincoln Street.
Please contact staff if additional clarification is needed.
1530 FARADAY AVENUE • SUITE 100 • CARLSBAD, CA 92008^* (760) 931-0780 • FAX (760) 931-5744 • info@planningsystems.net
Response: The roof line at the Lincoln St. elevation has been revised to reflect
a lower level eave line, which has resulted in the creation of a break-up to the
massing and softer roof lines. This can be seen on Sheets A-7 and A-8.
3. Staff suggests plexiglass walls be placed on top of the mansard roof at the
southwest comer of the site in order to top off the roof and balance the comer.
Response: Plexi-glass walls have been added on top of the roof parapet at
the roof deck to an elevation of 5' abov e finish floor. This can be seen on Sheet
A-7.
4. A few building elevations are still relatively flat with little building articulation.
As a suggestion from staff, these elevations could benefit from the addition of the
decorative half timbering already being used. Additional articulation is needed at the
west elevation depicted on Sheet A-8 as Elevation G, the and Elevation C depicted on
Sheet A-7, and the northem portion of Elevation D on sheet A-7.
Response: Additional half timbering has been added to Elevations C, D, and
G. These can be seen on Sheets A-7 and A-8.
5. The east elevation, adjacent to the 7-11, is not depicted in the elevations. Please
include an elevation of that portion of the building with next submittal.
Response: Elevations B and C have been expanded to include the property
line wall. This can be seen on Sheet A-7.
6. Please identify the location of the a/c units and associated equipment.
Response: Vertical, self-contained air conditioners/heaters will be located at
each of the guestrooms. All that will be seen from the exterior is a small fresh-
air louver mounted on the wall. The public spaces will be served by spUt
systems with the condenser units mounted on the roof. The kitchen exhaust and
make-up air equipment will be mounted on the roof. All roof-top equipment
will be screened from public view. The fresh-air louvers can be seen on Sheets
A-7 and A-8.
Building:
1. FuUy accessible rooms were not indicated on the plans. Please ensure that the
project is in compliance with T-24 Accessibility Standards for pubHc accommodations.
Table 11 B-3 requires that a facUity with 103 rooms provide a minimum of Five (5) fuUy
accessible rooms. Please revise plans before next submittal.
Response: The five fully accessible guestrooms are shown and noted on
the building plans. They can be seen on Sheets A-2, A-3, and A-4.
2. The rooftop terrace wUl need two exits therefrom due to the occupant load being
over 10. There is only one stairway shown that has access to the roof. The roof must
also be served by the elevator to make it accessible. The elevator cannot be counted as
an exit since the car retums to the ground floor in an emergency.
PLANNING
SYSTEMS
Response: Two sets of stairs and one public elevator serve the roof patio,
as requested. This can be seen on Sheet A-9.
3. The elevations close to the property line (adjacent to 7-11) wiU have to be
protected with fire resistive construction detaUing. The glazing nearest the property line
in the B Elevation on Sheet A-7 will not be allowed since it isn't perpendicular to the
property line. And the eave on that same elevation will not be allowed either imless it is
combustible.
Response: The property line wall will be of four hour constmction per code.
The window has been removed, and the eav6 cut back to 5 feet from the property
line. This can be seen on Sheet A-7.
Engineering:
1. Add engineer's seal and signature to the cover of the attached traffic report.
Response: Two (2) copies of a revised traffic report have been included with
this submittal. The reports now contain an engineer's seal and signature o n the
cover sheet.
2. Add a grass lined basin instead of concrete at the southwesterly comer of the
property. Although the dewatering pit will aid in reducing pollutants and should
remain, directing runoff through a vegetated swale or strip prior to reaching the
dewatering pit and/or curb outlet will further treat and treat more effectively storm
water pollutants. If silt entering the dewatering pit is a comer, could the entrance to the
pit be raised to allow some settlement of suspended solids to occur prior to water
entering the pit? Revise Sheet C-1 and detaU "Q- Q" accordingly. Also, the landscape
plans shows vegetation proposed within this basin. The basin should primarily be
comprised of vegetation that adequately absorbs pollutants, such as fescue grass.
Response: The concrete lined desilting basin has been replaced by a grass
lined desilting basin. A portion of the pipe drainage system has been replaced
by a grass swale. Additionally, the basin has been planted with fescue grass to
help absorb pollutants. These changes can be seen Sheets C-1 and L-1.
3. Revise the attached page 3 of the SWMP and have owners sign attached
certification of responsibiUty.
Response: Page 3 of the SWMP has been revised and the certification of
responsibiUty sheet has been signed. Both pages have been included in a new
revised SV/MP. Two (2) copies of the SWMP have been included with this
submittal.
4. We caimot located a copy of the chain of title search that was submitted with the
adjustment plat (ADJ 05-09) apphcation as you indicated in your response letter. Please
submit a new copy.
PLANNING
SYSTEMS n
Response: An additional copy of the chain of title search has been included
with this submittal, as requested.
Fire:
1. Laundry room and Employee Break Room are not permitted in the parking
garage, revise the location of said rooms.
Response: The laundry and break rooms have been moved to the third and
second floor, respectively. They can be seen Sheets A-3 and A-4.
2. Are you using Automatic Fire Sprinklers to achieve FR rating? If so, please state.
Response: The below grade garage will be Type I and of concrete
constmction. The above grade hotel will be Type V-l hour and of wood-framed
constmction. Both 'buildings' will be fully sprinklered, as noted on the Cover
Sheet (CS). If required, area separations willbe provided in the hotel.
3. Elevator car interior dimension shall accommodate an ambulance gumey of 84
inches by 24 inches at a height of 36 inches.
Response: The elevators will be able to accommodate a gumey, see general
note 3 on the Cover Sheet (CS).
4. Occupancy groups shown are not for all areas. Please revise Title Sheet to reflect
the declaration of each area and occupancy classification.
Response: The constmction type and occupancy classifications were revised
to reflect the diflerent conditions. This can be seen on the Cover Sheet (CS).
Thank you for your continued assistance with the planning of this project. With these
minor revisions, we are hopeful that the project design is now acceptable. We look
forward now to docketing for Design Review Board/Planning Commission hearing.
Paul J. Klukas
Director of Plarming
cc: Neil Patel
Attachments
PLANNING
SYSTEMS
Citv of Carlsbad
Housing & Redevelopment Department
December 19, 2005
DKN HOTELS
540 GOLDEN CIRCLE DRIVE #214
SANTA ANA, CA 92705
SUBJECT: DKN - Hampton Inn (RP 05-03, SDP 05-04, CDP 05-14, LCPA 05-02, ZC 05-02,
GPA 05-05)
APN: 203-250-08 & 203-250-26
This letter is a follow-up to my previous letter to you, dated December 1, 2005, in which the
issues of concern related to your application for a Major Redevelopment Permit were identified.
In addition to the items listed in my previous letter, Engineering Department and Fire
Department comments on your proposed project are as follows:
Enqineerinq:
Engineering issues which need to be resolved or adequately addressed prior to staff making a
determination on the proposed project are as follows:
1. Add engineer's seal and signature to the cover of the attached traffic report.
2. Add a grass-lined basin instead of concrete at the southwesterly corner of the
property. Although the dewatering pit will aid in reducing pollutants and should
remain, directing runoff through a vegetated swale or strip prior to reaching the
dewatering pit and/or curb outlet will further treat and treat more effectively storm
water pollutants. If silt entering the dewatering pit is a concern, could the
entrance to the pit be raised to allow some settlement of suspended solids to
occur prior to water entering the pit? Revise Sheet C-1 and detail "Q-Q"
accordingly. Also, the landscape plan shows vegetation proposed with this basin.
The basin should primarily be comprised of vegetation that adequately absorbs
pollutants, such as fescue grass.
3. Revise the attached page 3 of the SWMP and have owners sign attached
certification of responsibility.
4. We cannot locate a copy of the chain of title search that was submitted with the
adjustment plat (ADJ 05-09) application as you indicated in your response letter.
Please submit a new copy.
Please return all attached redlined plans and documents with next submittal. To discuss
all Engineering Department related concerns, please contact David Rick at (760) 602-2781.
Fire:
Fire Department issues which need to be resolved or adequately addressed prior to staff
making a determination on the proposed project are as follows:
1. Laundry Room and Employee Break Room are not permitted in parking garage,
revise the location of said rooms.
2965 Roosevelt St., Ste. B • Carlsbad, CA 92008-2389 • (760) 434-2810/2811 • FAX (760) 720-2037 @
DKN Hanpton Inn
12/19/2005
Page 2 of2
2. Are you using Automatic Fire Sprinklers to achieve FR rating? If so, please
state.
3. Elevator car interior dimension shall accommodate an ambulance gurney of 84
inches by 24 inches at a height of 36 inches.
4. Occupancy groups shown are not for all areas. Please revise Title Sheet to
reflect the declaration of each area and occupancy classification.
To discuss all Fire Department related concerns, please contact Greg Ryan at (760) 602-4663.
Please contact my office at (760) 434-2813 if you have any questions regarding the information
contained in this letter.
Sincerely,
CLIFF JONES
Assistant Planner
Kenny Booth, Planning Systems
David Rick, Engineering Department
Greg Ryan, Fire Department
Van Lynch, Planning Department
File
PLANNING
SYSTEMS a November 2, 2005
LAND USE/COASTAL PLANNING
LANDSCAPE ARCHITECTURE • LA3900
POLICY AND PROCESSING
ENVIRONMENTAL MITIGATION
Cliff Jones
CITY OF CARLSBAD
Housing & Redevelopment Department
2965 Rooseveh St. Ste B
Carlsbad, CA 92008
RECEIVED
NOV ^2 2m
_ CITYOFCARLSBAD
RE: RP 05-03/SDP 05-04/DEV 05-19/LCPA 05-02/ZC 05-02/GPA 05-05 -
DKN Hampton Inn
Dear Cliff:
Per your letter dated June 24,2005 identifying Staff items and issues with the submittal
of the above-referenced project, the project applicant has commissioned modifications to
the project design and the provision of the additional information requested regarding
the project. To this end, attached with this cover letter please find a resubmittal package
including:
Five (5) sets of revised plans
Colored Elevations
Redlined Grading and Drainage Plan
2 copies of revised Preliminary Storm Water Management Plan
Redlined Preliminary Storm Water Management Plan
2 copies of revised Preliminary Hydrology Report
Redlined Hydrology Report
2 copies of revised Traffic Study
Redlined Traffic Study
2 copies of Revised Water Analysis
2 copies of Revised Sewer Analysis
Redlined Water Analysis
Redlined Sewer Analysis
Materials and color board
Shoring constmction techniques letter by Flores Limd Consultants
Response letter fiom General Services Division regarding street tree relocation
New Operator Platform. Since the last submittal, the ovmer/appUcant of the proposed
project has withdrawn agreements with Hilton/Hampton and has now entered into an
agreement with Marriott/Springhill Suites. As a result, this redesigned submittal is now
based on the SpringhiU Suites platform, which has subtle differences in design from
HUton.
Specific Staff Comments. With regard to the specific items and issues identified in the
Jime 24 letter, the following is a discussion of the method in which the redesigned
project addresses the general issues, foUowed by a specific response to each item/issue
identified by City Stafl, in the order presented in your draft letter.
1530 FARADAY AVENUE • SUITE 100 • CARLSBAD, CA 92008 j (760) 931-0780 • FAX (760) 931-5744 • info@planningsystems.net
Items Needed to Complete the Application
Planning
1. The side yard setback for the southem side yard off Lincoln shall be 10 feet
(8'11" proposed). Please correct sheet A-l and A-2 civil sheet.
Response: Sheet A-l has been revised to show the correct side yard setback
of 10 feet.
2. Please correct the roof plan and key maps to reflect the most southem wall
elevation (on left as looking from Lincoln Street (see item #1 above)).
Response: The roof plan and key maps have been revised to match the floor
plans.
3. The portion of the property that falls within the V-R zoning requires a minimum
of a 5:12 roof pitch. Please modify the plans accordingly (roof plan).
Response: The plans have been modified accordingly to show the minimum
roof pitch of 5:12 within the V-R zone.
Issues of Concem
Housing & Redevelopment and Planning:
1. The proposed project design and architectural materials do not promote the
VUlage character, design, and scale. The plans are very corporate architecture and very
manufactured in appearance. Staff advices the appUcant to consider more of a
Craftsman Style of Old World design consistent with the design of the Carlsbad Inn
located north of the project site or the Best Westem View Lodge located to the south.
The VUlage Design Guidelines (attached) should be reviewed carefully and greater
attention should be provided to the design of the project. Sample materials provided do
not reflect the desired VUlage character.
Response: The project has been redesigned to promote the VUlage character,
design and scale. The buUding materials, exterior elevation design and
placement of active function spaces are aU designed to create a more active
VUlage plan. The revised elevations can be seen on Sheets A-7 & A-8. As shown,
the project has taken on a more Craftsman Style of Old World design. This is
more consistent with surrounding properties including the Carlsbad Irm and
Best Westem View Lodge.
2. Staff still has concems with the front elevation of the buUding. Staft would like
to see a grand entryway to the project such as the one provided at the Best Westem
View Lodge. Staff suggests enhanced paving, a senu-circle entrance, and possibly a
fountain at the entry way to the hotel.
PLANNING
SYSTEMS a
Response: As discussed in the meeting on July 11,2005, the project applicant
has redesigned the entire front elevation and floor plan of the hotel. The fiont
elevation has been revised to provide a grander entryway. It has been increased
in width and the exterior materials have been enhanced to create a more inviting
entryway. AdditionaUy, the floor plan of the hotel has been redesigned so that
guest common areas now make up the first floor area along Carlsbad Boulevard.
The hotel lobby, lounge area, business Ubrary, breakfast room and outdoor
eating area have replaced the hotel rooms previously located on the first floor.
This significant redesign of the project has given fhe building a greater street
presence and wiU allow aU hotel guests to enjoy the experience of Carlsbad
Boulevard. These changes can be seen on Sheets A-2 and A-7.
3. The building elevations are still relatively flat. Greater building articulation is
necessary along all building elevations particularly off the highly visible front elevation
off of Carlsbad Blvd. A hotel within the ViUage needs to be able to stand alone and have
a imique look.
Response: Building elevations have been enhanced with greater relief and an
improved materials palette. The front elevation has been revised to provide a
grander entryway. The driveway has been widened and a support beam has
been added to separate fhe entry and exit aisles. Additionally, balconies have
been provided to breakup the front elevation. The lobby of the hotel has been
moved to the street front and guest rooms no longer occupy any space on the
first floor along Carlsbad Blvd. Balconies have also been provided along the
other elevations. The revised elevations can be seen on Sheets A-7 & A-8.
4. The northwest portion of the building has a great street presence, which can be
very desirable as recreational space for hotel guests to observe street traffic. This
location would be a great location for creating a small coffee shop or delicatessen for
hotel guests to get a quick snack or drink or just relax and observe street activity.
Response: The northwest portion of the project site has been redesigned and
now functions as an outdoor dining area for guests of the hotel. A-breakfast
room adjacent to the outdoor dining area wiU provide an indoor gathering place
for guests as weU. This revision can be seen on Sheet A-2.
5. Staff encourages the appHcant to make use of the views avaUable at the subject
property. Staft suggests balconies be provided along front and rear elevations. This wiU
help to break up the dullness of the inherently flat buUding faces.
Response: Balconies have been provided along the Carlsbad Blvd and
Lincoln Street elevations. Additionally, a rooftop balcony has been added to the
front elevation along Carlsbad Blvd. This wiU provide guests with a place to
gather to take in the southwesterly views that the property offers. The revised
elevations can be seen on Sheets A-7 & A-8.
PLANNING
SYSTEMS D
6. Staff has concems with the massing of the roof. Please provide more articulation
to the roof.
Response: The roof has been redesigned and now shows more articulation.
Dormers, hips and gables were added to the roofline to break up the long
stretches of gable roof. The patio at the southwest comer wiU break up the
massing of the roof at the street frontage. The roofline will foUow the natural
lines of the stmcture. This can be seen on Sheet A-9.
7. The elevation which faces onto Lincoln Street should have a faux entrance and
architectural relief to break up this rather flat elevation. The elevations should appear as
front elevations for better street presence as opposed to a rear elevation and the "back"
of a building. The other residences on the street have bakonies which give a better
street presentation. The hotel could step back the upper floor and provide decks with
raUings to achieve this look. There is a concem that there will be a large and abmpt
vertical waU surface within the proposed design.
Response: The elevation along Lincoln Street has been redesigned. Upgrades
in the exterior materials, reUef in the walls with hipped roof lines, window
treatments and facade detailing add to this building elevation. This elevation
now appears more like a front elevation with interspersed balconies and
flowerboxes. This can be seen on Sheet A-8.
8. With the new roof pitch, it would be possible to enclose the mechanical in the
ceUing area as opposed to having a/c units at each room. We have other projects in the
City that have done this successfuUy.
Response: A mansard roof has been provided to create a screened roof weU
for guestroom ventilation fans and other hotel operational equipment.
9. Staff suggests that rockwork be provided along the buUding elevations instead of
the cultured stone. The rockwork gives more texture to the building.
Response: Rockwork has now been provided along the buUding elevations in
place of cultured stone. Owens Coming River Rock will be used. A materials
and color board has been provided with further details.
10. Staff noted that the application of random shutters and window types are a bit
too random. Please choose a window type that supports the overall Village Design
theme.
Response: The random window types and shutters have been redesigned.
Treatments and detailing are now more uniformly distributed throughout aU
building elevations. The new design can be seen on Sheet A-7 & A-8.
11. As part of the design review process, the Design Review Board must be satisfied
that the appUcant has made an honest effort to conform to each of the ten basic
principles outlined in the VUlage Design Guidelines. A copy of the design guidelines
PLANNING
SYSTEMS
has been attached for your review. Some suggestions from the design guideUnes area as
foUows:
-Provide for variety and diversity of building forms. An informal building
character and a sense of individually is desired. Each building shall express its
uniqueness of stmcture and not mere copies of generic buUding types, which
might be foimd anywhere. Staff suggests the applicant pay greater attention to
the design of the front entrance of the project and provide a grand entryway to
the buUdings entrance oft of Carlsbad Boulevard.
-Provide a variety of setbacks along any commercial block front. Varied setbacks
provide a desired informality and diversity of appearance and aUow for greater
landscaping.
-Break larger buUding forms into smaUer units through the use of recessed
facades. Facade projecti ons as well as entry way recesses are elements which
add richness to the Village facades through the creation of shadows and the
contrast between sunny and shady surfaces.
-Design visual interest in all sides of the building. Greater articulation should be
incorporated into aU sides of the building and the upper levels should be stepped
back from the lower levels to reduce the overaU mass of the stmcture.
-Utilize applied surface omamentation and other detail elements for visual
interest and scale.
-Emphasize cottage form, scale, and character. The use of gable roofs, varied
roof heights, and dormers help create interesting detail and are encouraged to
enhance the area's Villa ge character.
-Incorporate an abundance of landscaping into the project.
-Incorporate benches and low walls along public pedestrian frontages such as
Carlsbad Boulevard.
Response: The proposed project has made an honest effort to conform to
each of the ten basic principles outlined in the Village Design Guidelines:
1. Development sliall have an overall informal character.
The overaU character of the proposed project wiU remain informal
through the use of a variety of waU plains, rooflines and handcrafted
detailing, architectural accent features and quality materials.
2. Architectural design shall emphasize variety and diversity.
The proposed project has incorporated a variety of architectural design
features through the use of detailing and materials. The rock work on the
lower level provides for a strong visual base for those viewing from a
distance whUe providing a highly-textured warm material for the up
close pedestrian. The finish above the base is stucco, providing for a
lighter mid section. The building is capped by a heavy concrete shake
PLANNING
SYSTEMS a
roofing material with painted wood bracket and fascia detailing. The
windows are surrounded with plaster casement detailing and some with
flowerboxes, others with false balcony metal raUings. The variety and
diversity of materials and detaUing throughout the building add interest
to the building itself and to the neighboring stmctures.
3. Development shall be small in scale.
The proposed project wiU maximize the usage of the site, however the
stmcture will not have any heights over 45 feet and approximately 31.5%
of the site wiU remain in open space.
4. Intensity of development shall be encouraged.
The project site has been designed to its fullest reasonable potential in
accordance with City guideUnes. The proposed hotel will have 103 rooms
on approximately .84 acres.
5. All development shall have a strong relationship to the street.
The project wiU have a front yard setback of 5 feet. This will aUow the
project to have a strong relationship with Carlsbad Boulevard.
Additionally, the first floor along Carlsbad Boulevard will house the hotel
lobby, lounge, meeting areas, breakfast room and outdoor sitting area.
Furthermore, a rooftop balcony has been added to the front elevation
along Carlsbad Blvd. This will provide guests with a place to gather to
take in the southwesterly views that the property offers.
6. A strong emphasis shall be placed on the design of ground floor facades.
The ground floor fagade facing Carl sbad Boulevard wiU be constmcted
with rock.
7. Buildings shall be enriched with architectural features and details.
The proposed project wiU incorporate varied setbacks along Carlsbad
Boulevard. Rock work and different window styles wUl enhance the
visual entrance of the buUding. A wide driveway with a support beam to
separate the entry and exit aisles has been provided. AdditionaUy,
balconies have been provided to breakup the front elevation.
8. Landscaping shall be an important component ofthe architectural design.
The project wiU have approximately 31.5% open space and extensive and
varied landscaping wUl compose the majority of this open space.
9. Parking shall be visually subordinated.
AU parking shaU be placed in an underground garage.
10. Signage shall be appropriate to a village character.
The tasteful prototypical Springhill Suites signage will be integrated into
the building fagade. Al 1 signage wUl meet the requirements of the Sign
Ordinance (21.41). A sign plan has been provided on Sheet A-11.
PLANNING
SYSTEMS a
Engineering:
1. Determine the size of the existing water services and meters. WiU several of the
existing services be utUized or wUl one service line (i.e. 2" pipe and meter) be used for
the entire potable water supply? WiU the existing fire sprinkler service line with back
flow preventor located at the southerly comer of the lot on Carlsbad Blvd be abandoned
since a new 6" pipe with Double Detector Check Valve is proposed on Lincoln Street?
In addition, the meter located in the main entrance driveway must be located outside the
driveway, so either label as "to be abandoned" o r show area of relocation.
Response: Existing and proposed water services have been labeled as
requested. The existing fire sprinkler service line at the southerly comer of the
lot on Carlsbad Blvd will be abandoned. The water meter located in the main
driveway will also be abandoned. All existing and proposed utilities can be seen
on Sheet C-1.
2. Provide scaled centeriine longitudinal profile of driveway with BVC and EVC at
top and bottom of driveway.
Response: A scaled centeriine longitudinal profile of the driveway with BVC
and EVC at the top and bottom has been provided. This can be seen on Sheet C-2.
3. In your letter, you stated that Parcels lA are legal parcels. Provide proof that
Parcels 1-4 are separate legal parcels. A chain of title search may be required. If each
parcel was established by deed prior to June 1,1956, then each parcel will be considered
legal parcels. Although the adjustment plat would legalize the parcels, there is no
assurance that parcels beyond the boimdary of the adjustment plat was iUegally
subdivided.
Response: A chain of title search has been conducted on the subject property.
This information was induded in a resubmittal of the Adjustment Plat
application package (ADJ 05-09) on October 11,2005.
4. Plot the raised median in the Carlsbad Blvd. cross section and dimension fhe
sidewalk.
Response: The raised median in the Carlsbad Blvd. cross section has been
shown. This can be seen on Sheet C-2. AdditionaUy, the sidewalk has been
dimensioned.
5. Provide proof that appUcation for permitting removal of the three trees within
the public right-of-way has been submitted to the General Services Division.
Response: An application (letter) for permitting the relocation of the three
trees within the public right-of-way was submitted to the General Services
Division on July 20, 2005. A response letter from Michael Bliss has been
included with this submittal. It indicates that the three pahn trees selected for
relocation are not in the City of Carlsbad Street Tree Inventory and therefore the
PLANNING
SYSTEMS
City does not maintain fhe trees. A copy of the letter is attached to this cover
letter.
6. Although detaUs of the underground parking drainage area are not provided,
fUtering of the hydrocarbons, heavy metals, etc. must be addressed on the plan and
through the SWMP.
Response: A note has been added to Sheet C-1 stating "AU drainage waters
within the underground garage shaU be collected in a fUtration device and
pumped to the onsite surface drainage system". The SWMP has also been
revised to address the drainage of the underground parking areas.
7. Revise the hydrology report per the redlined comments.
Response: The hydrology report has been revised. AU redlined comments
have been reviewed. However, no changes in the calculations have been made.
Please note that the grass lined desilting basin is now a concrete lined desilting
basin. This design accompUshes two things:
1. It will collect any site generated silt or debris before the storm water leaves the
site.
2. There is no public storm drain system adjacent to the site for cormection of the
onsite system and the onsite drainage system carmot be designed to outlet at the
elevation of Carlsbad Blvd.
Therefore, the desUting basin wUl hold drainage water untU it ponds to a level
that can discharge to the Carlsbad Blvd. gutter.
Please find two (2) copies of the revised report along with the redline report
included with this submittal.
8. It appears that a new 55 foot contour line is shown on Parcel 28 to the south. Is
off site grading proposed to redirect drainage away from the subject property? If so,
then temporary off-site constmction easements wUl ultimately be required. In the mean
time, provide a letter from the property owner giving preliminary pennission to grade.
An option to grading off-site would be to aUow drainage to continue to flow onto the
subject property. The objective is to prevent any new flooding or ponding on the
neighbor's property du e to this development.
Response: The subject contour line is an existing topographic description.
No offsite grading is proposed.
9. The D-25 drain outlet cannot be placed in the sidewalk. Place the manhole
behind the sidewalk. Propose a pubUc drainage easement over the manhole.
Response: The manhole for the "D-25" outlets has been removed. This is
aUowed by the Regional Standards for a non-pipe connection. This can be seen
on Sheet C-1.
10. Revise the attached Water System and Sewer System Analysis per redlined
comments. Submit 2 copies of corrected plans with next submittal.
PLANNING
SYSTEMS
Response: The Water System Analysis and Sewer System Analysis have been
revised. Please find two (2) copies of each revised report along with the redline
reports included with this submittaL
11. The grading quantities indicate that 2,047 cubic yards of soil wUl be excavated
and according to your response letter, this amount includes excavation for the garage.
However, given that the lower level garage is 28,251 sq. ft. and approximately 20 ft deep,
rough calculations for the excavation come out to at least 21,000 cubic yards of soil.
Please recalculate the quantities.
Response: Grading quantities have been revised. Sheet C-1 now shows that
14,870 cubic yards wiU be excavated and 80 cubic yards will be fiUed. This will
result in an export of 14,790 cubic yards.
12. Provide an addendum to the soUs report or letter from the soUs engineer
detennining the potential impacts, if any, that the saturated soil from the retention basin
could have on the adjacent street improvements and building. On the site plan, provide
the ADT generated from the existing use that willbe demolished.
Response: The soils engineer is currently conducting further tests to
determine the potential impacts related to the retention basin. This infonnation
wiU be provided to the City as soon as it becomes available. AdditionaUy, Sheet
A-l has been revised to now show the existing ADT that will be eliminated.
13. The letter mentioned with your recent submittal from Flores Lund Consultants
explaining the recommended constmction techniques for shoring was not included in
the submittal package. Please provide this information.
Response: The letter from Flores Lund Consultants explaining the
recommended constmction technique for shoring has been included with this
• submittal. It has been attached to this cover letter.
14. Revise the traffic report per redline comments and submit two copies of correct
report with your next submittal.
Response: The traffic report has been revised. Please find two (2) copies of
the revised report along with the redline report included with this submittal.
15. Revise the redlined SWMP and submit two copies of the revised plan with your
next submittal.
Response: The SWMP has been revised. Please find two (2) copies of the
revised report along with the redline report included with this subnuttai.
PLANNING
SYSTEMS
Thank you for your continued assistance with the planning of this project. With this
significant redesign, we are hopeful that this project design is now acceptable. We look
forward to resolving any final issues City Staff may have with the design, prior to
docketing for Design Review Board hearing.
Sincerely,
Paul J. Klukas
Director of Plaiming
cc: NeU Patel
Attachments
10
PLANNING
SYSTEMS
Citv of Carlsbad
Public Works/Parks
July 26, 2005
Mr. Kermy Booth
1530 Faraday Avenue, Suite 100
Carisbad CA 92008
Dear Mr. Booth,
I wish to thank you for your letter to Mr. Kyle Lancaster, dated July 20, 2005, regarding
the removal and relocation of the three Washingtonia Robusta palms. Although, these
palms will be planted in our right-of-way they are not in our Street Tree Inventory.
Therefore, the City does not maintain these trees. I will be forwarding your letter to the
City's Housing and Redevelopment office for their review.
Again, thank you for notifying us as to your future landscape plans and all the best to you
and staff regarding this project.
Sincerely,
Michael E. BUss
Tree Supervisor
760/434-2985
1200 Carlsbad Village Drive • Carlsbad, CA 92008 • (760) 434-2825 • FAX (760) 434-7185 @
Pi-DHES LUND
CONS ULTAIMTS
April 22» 2005
Joseph Wong Design Assodate?
2359 Fourth Avenue, Suite 300
San Diego, CA 92131
PRCUECT: Calrsbad Hampton Inn
Attention! Mr. Rid: Rounds
Dear Rick;
The purpose of thi letter is to address the alternate methods af retaining the soil adjacent to and
under the Sextan Eleven Store in order to excavate for a two-\e^fe\ below grade parking structure.
There are several altemate construction techniques to accomplish thii excavation without
compromise to the existirig Seven Seven Store, Each of these techniques are conventional and
regularly employed
In general, there ar; two separate construction methodologies. The difference between the two is,
one nnethod invoivss construction solely on the new construction site. The other method rrrrrudes
fnto the adjacent property. They are generally described as follows:
LO \X/here construction Is placed soiely on the new construction site, soldier beams usually
spaced at S* 3,c. are drilled and cast Into the ground prior to any excavation. These soldier
beams are braced approwmately 8-10 feet below the excavation with a "whaler and raker
system" whi:h are placed during the excavation. The 'Svhaler and raker system" are
essentially a diagonal bracing system which resists the horizontal thrust of the soil and
minimizes an / settlement of the adjatent property.
2.0 In the case where the acescent property is utilized, soldier beams usually spaced at 8' o.c- are
drilled and CiSt Into the ground prior to any excavation. Tbe beams are either placed under
the existtng footing or adjacent to that footing. As the excavation proceeds, at the
appropriate 13veL tie-backs are drilled and anchored back under the existing building. These
tie-backs resht the horizontal thrust of the SCMI and minimize any settlement of the ac(|acent
property.
We trust this inform ation will assist you. Should you have any questions* please call.
Very truly yours,
FLOReSI LUND CONSULTANTS
Hamid Liaghat
Senior Project Mana; jer
7220 Trade Street, Suit? 120 • SanOiego. Caltfornia 52121 - (856) 566-0626 • FAX (858) 566-0627
Ciuil and Strticturel Etui Inhering wwiM.novesHundjcotn
City of Carlsbad
Housing & Redevelopment Department
JULY 21, 2005
KIRAN PATEL
PRESIDENT
540 GOLDEN CIRCLE, SUITE 214
SANTA ANA, CA 92705
Re: DKN-Hampton Inn RP 05-03
Kiran,
Per your request, I am responding to you in writing about the Housing &
Redevelopment Departments response to the plans you provided to us in our
meeting this morning regarding the above-mentioned project. Staff is very
pleased with the effort you and your team of architects and planners have put
fon/vard in the design ofthe proposed hotel project. Based upon our preliminary
review of the project, the proposed plans appear to conform to the applicable
development standards and design guidelines ofthe Carlsbad Village
Redevelopment Master Plan. Therefore, staff believes it will be able to make a
recommendation of approval on the proposed project in the future.
We look forward to your formal resubmital of the project and a future scheduling
of the necessary public hearings. If you have any questions regarding the
information contained in this letter, please contact me at (760) 434-2813.
Sincerely,
CITY OF CARLSBAD
CLIFF JONES
Assistant Planner
Debbie Fountain, Housing & Redevelopment Director
2965 Roosevelt St., Ste. B • Carlsbad, CA 92008-2389 • (760) 434-2810/2811 • FAX (760) 720-2037 @
Citv of Carlsbad
Housing & Redevelopment Department
July 5, 2005
DKN HOTELS
540 GOLDEN CIRCLE DRIVE #214
SANTA ANA, CA 92705
SUBJECT: DKN - Hampton Inn (RP 05-03, SDP 05-04, DEV 05-19, LCPA 05-02. ZC 05-02,
GPA 05-05)
APN: 203-250-08 & 203-250-26
This letter is a follow-up to my previous letter to you, dated June 24, 2005, in which the items
necessary to complete your application for a Major Redevelopment Permit were identified. In
addition to the items listed in my previous letter. Engineering Department's comments on your
proposed project are as follows:
Enqineerinq:
Engineering issues which need to be resolved or adequately addressed prior to staff making a
determination on the proposed project are as follows:
1. Determine the size of the existing water services and meters. Will several of the existing services
be utilized or will one service line (i.e. 2" pipe and meter) be used for the entire potable water
supply? Will the existing fire sprinkler service line with back flow preventor located at the
southerly corner of the lot on Carlsbad Boulevard be abandoned since a new 6-inch pipe with
Double Detector Check Valve is proposed on Lincoln Street? In addition, the meter located in
the main entrance driveway must be located outside the driveway, so either label as "to be
abandoned" or show area of relocation.
2. Provide scaled centeriine longitudinal profile of driveway with BVC and EVC at top and bottom of
driveway.
3. In your letter, you stated that Parcels 1-4 are legal parcels. Provide proof that Parcels 1-4 are
separate legal parcels. A chain of title search may be required. If each parcel was established
by deed prior to June 1, 1956, then each parcel will be considered legal parcels. Although the
adjustment plat would legalize the parcels, there is no assurance that parcels beyond the
boundary of the adjustment plat was illegally subdivided.
4. Plot the raised median in the Carlsbad Boulevard cross-section and dimension the sidewalk.
5. Provide proof that application for permitting removal of the three trees within the public right-of-
way has been submitted to the General Services Division.
6. Although details of the underground parking drainage are not provided, filtering of the
hydrocarbons, heavy metals, etc. must be addressed on the plan and through the SWMP.
7. Revise the hydrology report per the redlined comments.
8. It appears that a new 55-foot contour line is shown on Parcel 28 to the south. Is off site grading
proposed to redirect drainage away from the subject property? If so, then temporary off-site
construction easements will ultimately be required. In the mean time, provide a letter from the
property owner giving preliminary permission to grade. An option to grading off-site would be
to allow drainage to continue to flow onto the subject property. The objective is to prevent any
2965 Roosevelt St., Ste. B • Carlsbad, CA 92008-2389 • (760) 434-2810/2811 • FAX (760) 720-2037 @
new flooding or ponding on the neighbor's property do to this development.
9. The D-25 drain outlet manhole cannot be placed in the sidewalk. Place the manhole behind the
sidewalk. Propose a public drainage easement over the manhole.
10. Revise the attached Water System and Sewer System Analysis Plans per redlined comments.
Submit two copies of corrected plans with next submittal.
11. The grading quantities indicate that 2,047 cubic yards of soil will be excavated and according to
your response letter, this amount includes excavation for the garage. However, given that the
lower level garage is 28,251 square feet and approximately 20 feet deep, rough calculations
for the excavation come out to at least 21,000 cubic yards of soil. Please recalculate the
quantities.
12. Provide an addendum to the soils report or letter from the soils engineer determining the potential
impacts, if any, that the saturated soil from the retention basin could have on the adjacent
street improvements and building. On the site plan, provide the ADT generated from the
existing use that will be demolished.
13. The letter mentioned with your recent submittal from Flores Lund Consultants explaining the
recommended construction techniques for shoring was not included in the submittal package.
Please provide this information.
14. Revise the traffic report per redlined comments and submit two copies of corrected report with
your next submittal.
15. Revise the redlined Storm Water Management Plan and submit two copies of the revised plan
with your next submittal.
Please return all attached redlined plans and documents with next submittal. To discuss
all Engineering Department related concerns, please contact David Rick at (760) 602-2781.
Please contact my office at (760) 434-2813 if you have any questions regarding the information
contained in this letter.
Sincerely,
CLIFF JONES
Assistant Planner
Kenny Booth, Planning Systems
David Rick, Engineering Department
City of Carlsbad
Housing & Redevelopment Department
June 24, 2005
DKN HOTELS
540 GOLDEN CIRCLE DRIVE #214
SANTA ANA, CA 92705
SUBJECT: DKN - Hampton Inn (RP 05-03. SDP 05-04, DEV 05-19, LCPA 05-02, ZC 05-02,
GPA 05-05)
APN: 203-250-08 & 203-250-26
Thank you for applying for a Land Use Permit in the City of Carlsbad. The Housing and
Redevelopment Department, together with other appropriate City departments, has reviewed
the above-mentioned applications as to their completeness for further processing.
The applications are incomplete, as submitted. Attached are two lists. The first list is
information that must be submitted to complete your applications. This list of items must be
submitted directly to the Housing & Redevelopment Office. All list items must be
submitted simultaneously and a copy of this list must be included with your submittal.
No processing of your application can occur until the applications are determined to be
complete. The second list includes issues of concern to staff, which must be addressed prior to
staff making a recommendation on the project. When all required materials are submitted to
the Redevelopment Office, the City has an additional thirty (30) days to make a determination
of completeness. If the applications are determined to be complete, processing for a decision
on the application will be initiated. In addition, please note that you have six months from the
date the application was initially filed, March 2, 2005, to either resubmit the applications or
submit the required information. Failure to resubmit the applications or to submit the materials
necessary to determine your applications complete shall be deemed to constitute withdrawal of
the applications. If an application is withdrawn or deemed withdrawn, a new application must
be submitted.
Please contact my office at (760) 434-2813, if you have any questions or wish to set up a
meeting to discuss the application.
Sincerely,
CLIFF JONES
Assistant Planner
c: Debbie Fountain, Housing & Redevelopment Director
Van Lynch, Planning
David Rick, Engineering
2965 Roosevelt St., Ste. B • Carlsbad, CA 92008-2389 • (760) 434-2810/2811 • FAX (760) 720-2037 @
DKN Hampton Inn
06/24/2005
Page 2 of 4
LIST OF ITEMS NEEDED
TO COMPLETE THE APPLICATION
No. RP 05-03, SDP 05-04, DEV 05-19, LCPA 05-02, ZC 05-02, GPA 05-05
Housing & Redevelopment and Planning: The Housing & Redevelopment Department and
Planning Department have completed their review of the subject project for application
completeness. The applications and plans submitted for this project are incomplete at this time.
Please resubmit 5 sets of plans addressing the following incomplete items:
1. The side yard setback for the southern sideyard off Lincoln shall be 10 feet (8'11"
proposed). Please correct sheet A-1 and A-2 civil sheet.
2. Please correct roof plan and key maps to reflect the most southern wall elevation (on left as
looking form Lincoln Street (see item #1 above).
3. The portion of the property that falls within the V-R zoning requires a minimum of a 5:12
roof pitch. Please modify the plans accordingly (roof plan).
Engineering:
Engineering comments are forthcoming and will be sent under a separate cover.
DKN Hampton Inn
06/24/2005
Page 3 of 4
ISSUES OF CONCERN
No. RP 05-03, SDP 05-04, DEV 05-19, LCPA 05-02, ZC 05-02, GPA 05-05
Staff has completed a review of the subject project for issues of concern. The following items
need to be resolved or adequately addressed prior to staff making a final determination on the
proposed project: (Please note, the issues are listed under the department which identified
them as an area of concern.)
Housmg & Redevelopment and Planning:
1. The proposed project design and architectural materials do not promote the Village
character, design, and scale. The plans are very corporate architecture and very
manufactured in appearance. Staff advises the applicant to consider more of a Craftsman
Style or an Old World design consistent with the design of the Carlsbad Inn located north of
the project site or the Best Western View Lodge located to the south. The Village Design
Guidelines (attached) should be reviewed carefully and greater attention should be provided
to the design of the project. Sample materials provided do not reflect the desired Village
character.
2. Staff still has concerns with the front elevation of the building. Staff would like to see a
grand entryway to the project such as the one provided at the Best Western View Lodge.
Staff suggests enhanced paving, a semi-circle entrance, and possibly a fountain at the entry
way to the hotel.
3. The building elevations are still relatively flat. Greater building articulation is necessary
along all building elevations particularly off the highly visible front elevation off of Carlsbad
Boulevard. A hotel within the Village needs to be able to stand-alone and have a unique
look.
4. The northwest portion of the building has a great street presence, which can be very
desirable as recreational space for hotel guests to observe street traffic. This location
would be a great location for creating a small coffee shop or delicatessen for hotel guests to
get a quick snack or drink or just relax and observe street activity.
5. Staff encourages the applicant to make use of the views available at the subject property.
Staff suggests balconies be provided along front and rear elevations. This will help to break
up the dullness of the inherently flat building faces.
6. Staff has concerns with the massing of the roof. Please provide more articulation to the
roof.
7. The elevation which faces onto Lincoln Street should have a faux entrance and architectural
relief to break up this rather flat elevation. The elevations should appear as front elevations
for better street presence as opposed to a rear elevation and the "back" of a building. The
other residences on the street have balconies which give a better street presentation. The
hotel could step back the upper floor and provide decks with railings to achieve this look.
There is a concern that there will be a large and abrupt vertical wall surface within the
proposed design.
DKN Hampton Inn
06/24/2005
Page 4 of4
8. With the new roof pitch, it would be possible to enclose the mechanical in the ceiling area
as opposed to having a/c units at each room. We have other projects in the City that have
done this successfully.
9. Staff suggests that rockwork be provided along the building elevations instead of the
cultures stone. The rockwork gives more texture to the building.
10. Staff noted that the application of random shutters and window types are a bit too random.
Please choose a window type that supports the overall Village Design theme.
11. As part of the design review process, the Design Review Board must be satisfied that the
applicant has made an honest effort to conform to each of the ten basic principles outlined
in the Village Design Guidelines. A copy of the design guidelines has been attached for
your review. Some suggestions from the design guidelines are as follows:
• Provide for variety and diversity of building forms. An informal building character and a
sense of individuality is desired. Each building shali express its uniqueness of structure
and not mere copies of generic building types, which might be found anywhere. Staff
suggests the applicant pay greater attention to the design of the front entrance of the
project and provide a grand entryway to the buildings entrance off of Carlsbad
Boulevard.
• Provide a variety of setbacks along any commercial block front. Varied setbacks
provide a desired informality and diversity of appearance and allow for greater
landscaping.
• Break larger building forms into smaller units through the use of recessed facades.
Fagade projections as well as entry way recesses are elements which add richness to
the Village facades through the creation of shadows and the contrast between sunny
and shady surfaces.
• Design visual interest in all sides of the building. Greater articulation should be
incorporated into all sides of the building and the upper levels should be stepped back
from the lower levels to reduce the overall mass of the structure.
• Utilize applied surface ornamentation and other detail elements for visual interest and
scale.
• Emphasize cottage form, scale, and character. The use of gable roofs, varied roof
heights, and dormers help create interesting detail and are encouraged to enhance the
area's Village character.
• Incorporate an abundance of landscaping Into the project.
• Incorporate benches and low walls along public pedestrian frontages such as Carlsbad
Boulevard.
Landscape Plan Review:
Comments on the preliminary landscape plan are forthcoming and will be sent to you under a
separate cover.
PLANNING
SYSTEMS Dl
LAND USE/COASTAL PLANNING
LANDSCAPE ARCHITECTURE • LA3900
POLICY AND PROCESSING
ENVIRONMENTAL MITIGATION
May 27, 2005
Cliff Jones
CITY OF CARLSBAD
Housing & Redevelopment Department
2965 Roosevelt St. Ste B.
Carlsbad, CA 92008
RE: RP 05-03/SDP 05-04/DEV 05-19/LCPA 05-02/ZC 05-02/GPA 05-05 -
DKN Hampton Inn
Dear Cliff:
Per your letter dated March 31, 2005 identifying Staff items and issues with the
submittal of the above-referenced project, the project applicant has commissioned
modifications to and the provision of additional information regarding the project. To
this end, attached with this cover letter please find a resubmittal package including:
Five (5) sets of revised plans
Redlined Grading and Drainage Plan
3 copies of Preliminary Storm Water Management Plan
3 copies of revised Preliminary Hydrology Report
Redlined Hydrology Report
3 copies of revised SoUs Report
Redlined Soils Report
3 copies of revised Traffic Study
Redlined Traffic Study
Materials board and color samples
Water Analysis
Sewer Analysis
Shoring construction techniques letter by Flores Limd Consultants
With regard to the specific items and issues identified in the draft March 31 letter, the
foUowing is a discussion of the method in which the redesigned project addresses the
general issues, followed by a specific response to each item/issue identified by City
Staff, in the order presented in your draft letter.
Items Needed to Complete the Application
Planning
1. The General Plan designation and zoning for the residentially zoned property
wUl need to be changed. The proposed General Plan Land Use designation will need to
be changed to Recreation Tourist (RT). The Commercial Tourist (C-T) Zoning wiU
1530 FARADAY AVENUE • SUITE 100 • CARLSBAD, CA 9200^ • (760) 931-0780 • FAX (760) 931-5744 • info@pIanningsystems.net
implement the RT General Plan Land Use designation. Please modify the plans
accordingly (refer to item #3 for format and language).
Response: The plans have been moditied to correctly show fhe proposed
General Plan Amendment and Zone Change. The General Plan Land Use
designation wiU be changed to Recreation Travel (RT) and zoning wUl be
changed to Commercial Tourist (C-T).
2. The project will need to discuss the impacts that will occur as a result of the
General Plan Amendment for the residentiaUy zoned property. Assembly BUI 2292
requires residential zoned land to develop to its potential. Since the project eliminates
residential units, findings wUl need to be made to justify the loss of residential imits.
Response: Assembly BiU 2292 states: "No city, county, or city and county shall,
by administrative, quasi-judicial, or legislative action, reduce, require, or permit fhe
reduction ofthe residential density for any parcel to a lower residential density that is
below the density that was utilized by the Department of Housing and Community
Development in determining compliance with housing element law. Article 10.6
(commencing with Section 65580) of Chapter 3, unless the city, county, or city and
county makes written findings supported by substantial evidence of both ofthe
following:"
(1) The reduction is consistent with the adopted general plan, including the housing
element.
The current General Plan designations for the subject site are Residential High
Density (RH) and ViUage (V). The RH designation allows for up to 23 dweUing
imits per acre with a growth management control point of 19 dwelling units per
acre. The subject site is approximately .84 acres in size. However, only .49 acres
of the site are within the RH General Plan Designation. Based on the growth
management control point, this would allow for a potential 9 residential units on
the parcel.
The applicant is proposing to amend the General Plan designation of this portion
of the site to Recreation Tourist (RT). Doing so would eliminate 9 potential
residential units from the site. However, these 9 imits will be deposited into the
City of Carlsbad excess dwelling unit bank to be allocated and utUized in a more
appropriate, residentiaUy compatible location. Authorized withdrawals from
the bank wiU be granted for qualifying projects elsewhere within the city.
Therefore, the 9 residential units presently aUowed for on this site by the City of
Carlsbad General Plan wUl be utUized (pursuant to existing City Council policy)
elsewhere in the city and thus, not be eliminated.
(2) The remaining sites identified in the housing element are adequate to accommodate
the jurisdiction's sha re ofthe regional housing need pursuant to Section 65584.
The subject site wUl be eliminating 9 potential residential units from the property
as a result of implementation of the proposed General Plan Amendment. The
PLANNING
SYSTEMS a
aUowable land use on the subject site will be changed from Residential High
Density (RH) to Recreation Tourist (RT). Through implementation of this
General Plan Amendment, the 9 residential dwelling units wiU be transferred to
be held in the City's exc ess dwelUng unit bank. Currently over 3,000 dwelling
units exist in this bank. Authorized withdrawals from the bank may be granted
for qualifying projects anywhere within the city. The qualifying projects are
limited to the following types of development proposals:
1. Housing for low-income famUies;
2. Senior housing;
3. Housing located within either of the City's two, official,
redevelopment areas;
4. Transit orientated/"smart growth" developments;
5. Conversions of general plan land use designations from non-
residential to residential; and
6. Single-family developments in in-fUl areas, under stipulated
conditions.
Remaining undeveloped parcels within the City of Carlsbad that comply with
one or more of the preceding conditions wUl be allocated the 9 dwelling units
from the subject site. More importantly, the dweUing units can be transferred to
a site more conducive to high density residential development. We conclude
that the subject site is not optimal for RH usage due to the following site-specific
reasons:
1. The subject site is currently legaUy non-conforming to the existing
zoning. The existing Surf Motel lays half within the ViUage (V) General
Plan designation and half within the Residential High Density (RH)
General Plan designation. A General Plan Amendment would give the
site a General Plan designation of VUlage (V) and Recreation Tourist (RT).
This will make the proposed Hampton Inn a legally conforming use.
2. The site is surrounded by commercial and tourist commercial uses,
and is thus more compatible with those uses.
3. The City is desirous of providing sufficient tourist-serving uses in
close proximity to the beach area.
4. The adopted Local Coastal Program for the area, (MeUo I) identifies
provision of tourist-serving uses as a high priority land use for the subject
area.
Therefore, it would be expected that other properties within the city are mere
adequate in location, size, and shape to accommodate the site's presently -
allocated 9 dwelling units.
Include the following information on the title sheet:
PLANNING
SYSTEMS
a. Application types submitted and assigned application numbers to the upper
right comer.
Response: All plan sheets have been revised to show the correct
application numbers (RP 05-03/SDP 05-04/DEV 05-19/LCPA 05-02/ZC
05-02/GPA 05-05) in the upper right comers.
b. Name of sewer, water, and school districts providing service to the project.
Response: , The names of the sewer, water, and school districts
providing service to the project have been added to the Cover Sheet (CS).
c. Please remove "CUP Number" from "Project Summary Table".
Response: The note "CU P Number" has been removed from the
"Project Summary Table".
d. Correct the "Existing Zone" to state "Existin g Zone: R-3 and V-R District 9".
Response: The "Existing Zone" no te has been revised to now state
"Existing Zone: R-3 and V-R District 9".
e. Correct the "Propose d Zone" to state "Proposed Zone: C-T and V-R District
9 (to remain)".
Response: The "Prop osed Zone" note has been revised to now state
"Proposed Zone: C-T an d V-R District 9(to remain)".
f. Correct the "Existing General Plan" to state " Existing General Plan: RH, V".
Response: The "Existing General P lan" note has been revised to now
state "Existing General Plan:RH,V".
g. Correct the "Propose d General Plan" to state "Proposed General Plan : RT
and V (to remain)".
Response: The "Prop osed General Plan" note has been revised to
now state "Proposed Ge neral Plan: RT and V(to remain)".
h. Correct the "Existing Land Use Designation" to state "Existing Land Use
Designation: Overlay Zones (Beach Overlay Zone & Coastal Zone)".
Response: The "Existing Land Use Designation" note has been
revised to now state "Existing Land Use Designat ion: Overlay Zones
(Beach Overlay Zone & Coastal Zone)".
i. Correct the "Existing Land Use" to state "Exi sting Land Use: Motel,
Restaurant, Single FamUy".
PLANNING
SYSTEMS D
Response: The "Existing Land Use " note has been revised to now
state "Existing Land Use: Motel, Restaurant, Sin gle Family".
j. Please include an open space calculation. A minimum of 20% of the site must
be maintained as open space. The areas that qualify as open space include;
landscape planters, open space pockets, balconies, and patios. No parking
spaces or drive aisles are permitted in the open space calculation.
Response: An open space calculation has been added to the Cover
Sheet (CS). The percentage of the site that will be maintained as open
spaces is calculated at approximately 31.5%.
4. Please indicate on the site plan, through shading, the portion of the project that
falls within the V-R restrict 9 zoning designation. Please note that the minimum roof
pitch within V-R District 9 is 5:12 and the permitted height of the buUding is 45 feet if
the project is located over parking, which in this case it is. Staff suggests the applicant
consider using the allowable increase in roof height in order to create a front elevation
that is grander, and visually appealing (for more information on staff's is sues of
concem related to the front elevation of the project and the overall design of the project
refer to page 4). Please modify the plans accordingly.
Response: The Site Plan (Sheet A-l) has been revised to show the portion of
the project that falls within the V-R District 9 zoning designation. The project has
been redesigned to incorporate a buUding height of 45 feet for the portion of the
hotel within the V-R zone. This has allowed for the front elevation of the project
to become grander and more visually appealing. The revised front elevation can
be seen on Sheet A-8.
5. Please dimension the widths of the driveway entrance and exit.
Response: The driveway entrance and exit have been dimensioned. This can
be seen on Sheet A-l.
6. Compact parking spaces are a minimum width of 8 feet by 15 feet. Sheets A-5
and A-6 show compact spaces being 7.5 feet wide. Standard parking spaces are a
minunum width of 8.5 feet and 170 square feet in area. The supporting columns wiU
need to be shown outside of the parking area such that the parking space is fiee and
clear of any stmctures. Please review aU parking spaces and label aU compact spaces as
such. In addition please number aU parking spaces. Please correct and revise the plans
as necessary.
Response: The underground parking garage has been revised. AU compact
spaces now measure at least 8 feet by 15 feet. Standard spaces measure a
minimum of 8.5 feet by 20 feet. AU supporting columns have been shown
outside of the parking area. AdditionaUy, all parking spaces have been properly
labeled and numbered. Underground parking can be seen on Sheets A-5 and A-
6.
PLANNING
SYSTEMS
7. Show finished and existing grades on all elevations and building sections.
Response: All building sections and elevations have been revised to now
show finished and existing grades.
8. Please add the top of waU and bottom of waU heights for the retaining walls on
the civil plan, sheet C-1.
Response: Sheet C-1 has been revised to now show top of waU and bottom of
wall heights for aU retaining walls.
9. Provide a sign plan showing conceptual signage for the building along with a
summary table with the following information:
a. Total buUding street frontage;
b. Total sign area allowed (1 square foot of signage per linear foot of building
frontage);
c. Total sign area proposed.
Response: A sign plan has been added to the drawings. This can be seen on
Sheet A-11. The sign plan shows the total building street frontage, total sign area
allowed, and total sign area proposed.
10. Submit a constmction materials board and color samples.
Response: A materials board and color samples for the project have been
included with this submittal.
Engineering
1. A Storm Water Management Plan completed, sealed and signed by a registered
civil engineer.
Response: A Storm Water Management Plan (SWMP) has been completed by
Aquaterra Engineering and is included with this submittal.
2. On the preliminary grading and drainage plan:
a. Plot or identify with fhe location of the nearest fire hydrant and distance from
building to said hydrant.
Response: The nearest fire hydrant and distance from the pioject has
been added to Sheet C-1.
b. Screen existing faciUties and darken proposed facUities to make more
distinguishable.
Response: Existing facilities have been screened and proposed
facUities darkened to make the Civil Plans (C-1 and C-2) more
distinguishable.
PLANNING
SYSTEMS
c. Add potable and peak potable water and fire flow demand in gpm.
Response: Potable and peak potable water and fire flow demand in
gpm have been added to Sheet C-1.
d. Add sewer generation rate in mUlion gallons per day.
Response: Sewer generation rate in million gallons per day has been
added to Sheet C-1.
e. Under "Constmction Legend for Surface Improvements" note No. 4, change
"Private to "Public".
Response: Note No. 4, under "Con stmction Legend for Surface
Improvements" has been changed from "Private" to "PubUc" .
f. Identify the street signs along the property frontage, including the "Beg in
Park Parallel" and "End Parking to the Comer" signs.
Response: Street signs, including " Begin Park ParaUel" and "End
Parking to the Comer", along the property frontage have been added to
Sheet C-1.
g. Identify Bus Stop on Carlsbad Blvd.
Response: The Bus Stop on Carlsbad Blvd has been added to Sheet
C-1.
h. Specify that the water line in Carlsbad Blvd. is ACP and show connecting line
in Oak.
Response: . The water line in Carlsbad Blvd is now shown as ACP and
cormects into the existing line in Oak. This can be seen on Sheet C-1.
i. Show southerly continuation of sewer main in Carlsbad Blvd.
Response: The southerly continuation of the sewer main in Carlsbad
Blvd has been show on Sheet C-1.
j. Add water meter symbols on Lincoln Street and irrigation BFP sjmnbol on
Carlsbad Blvd. The notes have leaders pointing at nothing. Also, plot aU water
service lines.
Response; Water meter symbols have been added to Lincoln Street
and irrigation BFP symbols have been added to Carlsbad Blvd.
AdditionaUy, aU water service lines have been plotted. These can be seen
on the CivU Plan (C-1).
PLANNING
SYSTEMS
k. Provide cross sections at the northerly and southerly boundary of Parcel
three.
Response: Cross sections at the northerly and southerly boundary of
Parcel 3 have been shovm. These can be seen on Sheet C-2.
I. Plot the water main in Lincoln Street and show all service lines to the subject
property.
Response: The water main in Lincohi Street and all servioe lines have
been plotted on Sheet C-1.
m. Determine if the wood fence along the Lincoln Street frontage will remain or
be removed.
Response: The wood fence along the Lincoln Street frontage wiU be
removed.
n. Add Top of Wall/Bottom of Wall elevations to those retaining walls that do
not provide this information.
Response: Sheet C-1 has been revised to now show top of wall and
bottom of wall heights for all retaining waUs.
3. Plot intersection site distance for a vehicle exiting the driveway on Carlsbad
Blvd. and a trash tmck backing into Lincoln Street from the Service Entrance. Also, will
the service entrance primarily be used for deliveries?
Response: Intersection site distance has been added to Sheets C-1 and C-2 for
the driveway on Carlsbad Blvd. The sight distance from the Lincoln Street
driveway has not been plotted because the 330 foot sight distance extends
beyond the intersections of Oak Avenue to the north and Pine Avenue to the
south making the sight distance issue of no traffic safety consequence. The
service entrance willbe utUized primarUy for deUveries.
4. On Carlsbad Blvd., show sidewalk as existing and plot transition with abutting
frontages. On Lincoln Street, plot existing sidewalk fronting the 7-Eleven Shopping
Center,
Response: The sidewalk on Carlsbad Blvd has been shown as existing and
the transition with abutting frontages has been plotted. AdditionaUy, the
existing sidewalk fronting the 7-Eleven Shopping Center has been plotted. These
can be seen on Sheet C-1.
5. Provide a cross sectional of the driveway ramp and include BVC and EVC at the
base of the driveway. Also, plot percent grade of the parking lot ramps and add vertical
curves as needed.
PLANNING
SYSTEMS CIM
Response: A cross sectional of the driveway ramp has been added to Sheet
C-2. BVC and EVC are shovm at the base of the driveway. The percent grade of
the ramps has also been shown.
6. The trash receptacles are placed on the north side of the Service Entrance on
Sheet C-1 and on the south side on Sheet A-l. Since the driveway approadi complies
with City standards for separation from property line on Sheet C-1, this design should
prevail.
Response: The trash receptacles wiU be located on the north side of the
service entrance as shown on Sheet C-1. Sheet A-l has been revised to also show
the trash receptacle on the north side.
7. Are Parcels 1-4, as described in the title report, separate legal parcels? If so, an
adjustment plat may be necessary to consolidate the parcels into one. Provide
documentation to support status.
Response: Parcels 1-4 are separate legal parcels. An adjustment plat
application will be submitted to the Engineering Department.
8. Correct the street sections plotted on Sheet C-1. Identify east and west side of the
cross section and show sidewalk on the east side of Carlsbad Blvd. as non-contiguous.
Also, extend base an additional 6 inches beyond curve.
Response: The street sections are now plotted on Sheet C-2 and have been
corrected. The east and west side of the cross sections have been labeled and the
sidewalk on the east side of Carlsbad Blvd has been shown as non-contiguous.
Additionally, the base has been extended an additional 6 inches beyond the
curve.
9. Plot the location of all tree trunks within the pubUc right-of-way. Determine
whether the trees wiU remain or be removed. Permission from the General Services
Division of the City Parks and Recreation Department must be granted for any trees to
be removed within the pubUc right-of-way.
Response: All trees located within the public right-of-way have been shown
on the Landscape Sheet 1. AU 10 trees will remain, with 3 trees being relocated
within the right-of-way.
10. Cleary plot the proposed sidewalk as contiguous with the proposed curb and
gutter on Lincoln Street. It appears that the sidewalk is proposed as non-contiguous
with the sidewalk. Clearly show that the sidewalk wiU end at the southem boundary of
the Lincoln Street project frontage and that sidewalk does not exist along the southem
abutting property. Plot edge of pavement and flow line and/or spot elevations within
this area to iUustrate adequate drainage and pavement transition. Add detail if needed.
Response: The sidewalk on the west side of Lincoln has been redrafted to be
contiguous with the curb. However, please note that an existing sidewalk is
situated at the southerly boundary line.
PLANNING
SYSTEMS E3M
11. Show drain inlet and duel altemating pimips for the ramp leading to the garage.
How wUl the underground garage drain? WUl rain/irrigation water reach this area?
How wUl water from periodic deaning of garage be extracted? Provide explanation on
plans.
Response: The specifics of the subterranean garage drainage systems have
not been designed at this discretionary review phase, consequently they have not
been shown on the plans. Ultimately, the garage floors will have sumps to
coUect any wash down or storm water on those levels. The collected waters shall
be fUtered, pumped and discharged into the rain garden located in the southwest
comer of the site.
12. Plot all existing and proposed sewer laterals and water service lines. Provide
pipe material and size. Include water line and DDC valve for fire sprinkler system. If
any of the existing water services and meters is not going to be used, identify as
abandoned. Meters shall be placed in the public right-of-way. Check valves shall be
placed on private property.
Response: AU existing and proposed sewer laterals and water service lines
have been plotted on Sheet C-1. Pipe material and size has also been shown. All
meters have been placed in the public right-of-way and check valves have been
placed on private property.
13. Correct the attached redUned hydrology report and submit two copies of
corrected plan with your next submittal.
Response: The hydrology report has been revised. Three copies of the
revised report have been included with this submittal. The redlined report has
also been included.
14. Drainage on Parcel 28 appears to flow northerly toward the subject property. A
retaining waU is proposed at the property line. This waU wiU block drainage as
designed. Provide a means to prevent ponding in this area.
Response: Sheet C-1 has been revised to show how the onsite drainage
system wUl pick up the storm water from Parcel 28. Calculations of the
discharged water have been included in the Preliminary Hydrology Report.
15. Place D-25 manhole within the public right-of-way so that City may access for
cleaning outlet.
Response: A D-25 manhole has been placed within the public right-of-way
for City access.
16. Per the Storm Drain Legend, the "V" designatio n indicates that the minimum
size of the proposed yard drain is 12". This size seems excessive. It appears that a lesser
size would be adequate. Please reevaluate.
10
PLANNING
SYSTEMS a
Response: The "V" designation and corresponding 12" yar d drain have
been removed. Sheet C-1 now shows the minimum pipe size to be 6".
17. Provide a detail of the proposed waU on the north side of the driveway ramp.
Given the depth of the excavation, height of the wall to support the underground
parking, the location at the property line and close proximity to the 7/11 Store, there are
concems about potential effects the excavation and wall could have on the neighboring
property. In addition, it does not appear that enough space exists between the proposed
wall and property line to accommodate an underground drainpipe. A cross section
would help iUustrate the proposed design.
Response: The retaining wall location along the driveway ramp has been
shifted to aUow for back waU drainage. Sheet A-10 now shows a detailed cross
section of the proposed ramp near the 7-11 property line. AdditionaUy, a letter
from Flores Lund Consultants explaining the recommended constmction
techniques used to brace/shore the adjacent 7-11 building in order to avoid any
impacts to that building during excavation has been included with this
submittal.
18. Include the excavation quantities for the garage.
Response: The original earthwork quantities did include the excavation for
the garage.
19. Address the issues/comments redlined in the soils report.
Response: The soils report has been revised in accordance with Staff
recommendation. Three copies of the revised report have been included with
this submittal. The redlined report has also been included.
20. On Sheet CS, the owner's name should be the s ame as the name of the ovmer in
the title report. However, sheet CS states that the owner is DKN Hotels. The title report
states that the estate is vested in "Dahya Bhai L. Patel and Shantaben Patel, husband
and wife as joint tentants, as to Parcels, 1,2, and 3 and Dahya Patel, a married man as his
sole and separate property, as to Parcel 4. Please clarify. Correct property owner need
to be placed on Sheet CS.
Response: The Cover Sheet (CS) has been revised to be consistent with the
title report. Tlie owner on the Cover Sheet (CS) is now Usted as Dahya Bhai L.
Patel and Shantaben Patel.
21. Correct the ADT on Sheet CS to read 8/unit = 808 ADT. Also subtract existing
ADT to establish net increase.
Response: ADT on the Cover Sheet (CS) has been revised. It now reads
8/unit = 808 ADT.
22. Indicate on cover sheet that fire sprinklers will be installed.
PLANNING
SYSTEMS a 11
Response: A note indicating that fire sprinklers will be instaUed has been
added to the Cover Sheet (CS).
23. Some of the bearings and distances vary several feet or minutes from record
information. Please correct accordingly.
Response: The bearings and distances along the site boundaiy are based on a
recent field survey of the property. This data will be supported by the
information provided in the Boundary Adjustment application.
24. Add a note to the plans stating that the overhead utUities along Lincoln Stieet
frontage wiU be placed underground.
Response: A note has been added to Sheet C-1 stating that overhead utilities
along Lincoln Street willbe placed imderground.
25. On Sheet A-10 (Building Sections), show adjacent buUdings such as 7-Eleven.
Also plot groimd water table and identify lateral loads from excavation for undergroimd
garage based on 1:1 inclination.
Response: Sheet A-10 has been revised to show the adjacent 7-Eleven
buUding. The geotechnical report describes the ground water to be 33 to 38 feet
below grade, which willbe below the stmctural footings.
26. Are any doors, meters or other routinely accessed facUities located behind the 7-
Eleven buUding? If so, how will access be maintained given that the grade wiU be
lowered for the driveway ramp?
Response: To our knowledge, no routinely-accessed doors, meters, or
faciUties are located behind the 7-Eleven.
27. Correct the traffic study per redlined comments.
Response: The traffic report has been revised. Three copies of the revised
report have been included with this submittal. The redlined report has also been
included.
28. Due to proposed land use changes, provide a water and sewer analysis to
determine abiUty of existing City infrastmcture to accept any additional demand.
Response: A separate water and sewer analysis have been included in this
submittal. Each report concludes that the proposed Hampton Inn project wiU have a
minimal impact on the existing water and sewer systems.
12
PLANNING
SYSTEMS
Issues of Concem
Planning
1. .As part of the design review process, the Design Review Board must be satisfied
that the applicant has made an honest effort to conform to each of the ten basic
principles outlined in the VUlage Design Guidelines. A copy of the design guidelines
has been attached for your review. Some suggestions from the design guidelines area as
follows:
-Provide for variety and diversity of building forms. An informal buUding
character and a sense of individually is desired. Each buUding shaU express its
uniqueness of stmcture and not mere copies of generic buUding types, which
might be found anywhere. Staff suggests the appUcant pay greater attention to
the design of the front entrance of the project and provide a grand entryway to
the buildings entrance off of Carlsbad Boulevard.
-Provide a variety of setbacks along any commercial block front. Varied setbacks
provide a desired informaUty and diversity of appearance and allow for greater
landscaping.
-Break larger buUding forms into smaller units through the use of recessed
facades, Fagade projecti ons as weU as entry way recesses are elements which
add richness to the Village facades through the creation of shadows and the
contrast between sunny and shady surfaces.
-Design visual interest in all sides of the buUding. Greater articulation should be
incorporated into aU sides of the building and the upper levels should be stepped
back from the lower levels to reduce the overaU mass of the stmcture.
-UtUize appUed surface omamentation and other detail elements for visual
interest and scale.
-Emphasize cottage form, scale, and character. The use of gable roofs, varied
roof heights, and dormers help create interesting detaU and are encouraged to
enhance the area's ViUa ge character.
-Incorporate an abundance of landscaping into the project.
-Incorporate benches and low walls along public pedestrian frontages such as
Carlsbad Boulevard.
Response: The proposed project has made an honest effort to conform to
each of the ten basic principles outlined in the Village Design Guidelines:
1. Development shall have an overall informal character.
The overall character of the proposed project wiU remain informal
through the use of a variety of wall plains, rooflines and handcrafted
13
PLANNING
SYSTEMS
detailing, architectural accent features and quality materials.
2. Architectural design shall emphasize variety and diversity.
The proposed project has incorporated a variety of architectural design
features through the use of detaUing and materials. The stone finish on
the lower level provides for a strong visual base for those viewing from a
distance while providing a highly-textured warm material for the up
close pedestrian. The finish above the base is cement plaster, providing
for a lighter mid section. The building is capped by a heavy concrete
shake roofing material with painted wood bracket and fascia detaUing.
The windows, some rectangular and some arched, are surrounded with
plaster casement detailing. Some are articulated with wood shutters, and
others with false balcony metal raUings. The variety and diversity of
materials and detaiUng throughout the building add interest to the
building itself and to the neighboring stmctures.
3. Development shall be small in scale.
The proposed project wiU maximize the usage of the site, while at the
same time the stmcture will not have any heights over 45 feet and
approximately 33% of the site wiU remain in open space.
4. Intensity of development shall be encouraged.
The project site has been designed to its fullest reasonable potential in
accordance with City guidelines. The proposed hotel wiU have 101 rooms
on approximately .84 acres.
5. All development shall have a strong relationship to the street.
The project will have a front yard setback of 5 feet. This will aUow the
project to have a strong relationship with Carlsbad Boulevard. Main
motorist and pedestrian access to the site is from Carlsbad Boulevard.
6. A strong emphasis shall be placed on the design of ground floor facades.
The ground floor fagade facing Carl sbad Boulevard will be constmcted
with stone veneer (cultured stone).
7. Buildings shall he enriched with architectural features and details.
The proposed project wiU incorporate varied setbacks along Carlsbad
Boulevard. Stone veneer and different window styles wUl enhance the
visual entrance of the buUding. A grand entryway to the hotel has been
provided.
8. Landscaping shall be an important component ofthe architectural design.
The project will have approximately 33% open space and extensive and
varied landscaping wiU compose the majority of this open space.
9. Parking shall be visually subordinated.
AU parking shall be placed underground.
14
PLANNING
SYSTEMS a
10. Signage shall be appropriate to a village character.
The tasteful prototypical Hampton Inn & Suites signage wUl be
integrated into the buUding fagade. AU signage wiU meet the
requirements of the Sign Ordinance (21.41). Approximately 150 square
feet of signage will be aUowed based upon 150 linear feet of building
frontage.
2. The established range for front yard setbacks within Land Use District 9 are 5-10
feet. In aU cases where a range has been established as the appropriate setback standard
within a given district, the top of the range is considered to the desired standard.
However, a reduction in the standard to the minimum, or anywhere within the range,
may be aUowed if the project warrants such a reduction and appropriate findings are
made:
-The reduced standard wiU not have an adverse impact on surrounding
properties.
-The reduced standard wiU assist in developing a project which meets the goals
of the ViUage Redevelopment Area and is consistent with the objectives for the land use
district in which the project is to be located.
-The reduced standard wUl assist in creating a project design which is interesting
and visually appealing and reinforces the Village character of the area.
Response: The project has proposed a 5 foot front yard setback. The ^ "
proposed project warrants such a reduction for the following reasons:
a. Surroimding properties wiU not be adversely impacted by such a reduction.
The newly constmcted hotel to the south has a front yard setback of less than 10
feet. AdditionaUy, the majority of the properties along Carlsbad Boulevard have
front yard setbacks of less than 10 feet, and thus the setbacks in the area are
compatible with the proposed setback.
b. The proposed project will meet the goals of the ViUage Redevelopment Area
in that it wiU attract additional tourist-serving uses to the ViUage, increase the
intensity of developinent within the Village, and minimize the land area required
to accommodate additional parking in the VUlage,
c. Basic design principle #5 of the ViUage Design Guidelines states that "All
development shall have a strong relationship to the street." The project has been
, designed with a 5 foot front yard setback in order to encourage a strong
relationship between Carlsbad Boulevard and the hotel. Main motorist and
pedestrian access to the site is from Carlsbad Boulevard. The major view of the
project from passing motorists in from Carlsbad Boulevard. The lobby is
accessed off Carlsbad Boulevard.
3. Please add a buUding section that includes the pool and upper and lower
parking levels. The pool and spa appear to conflict with the laundry facility below.
Please explain how the pool and spa are to be supported.
15
PLANNING
SYSTEMS
Response: A cross section has been added to show the pool and lower
parking levels. This can be seen on Sheet A-10. The laundry facilities have been
moved to the lower level.
4, Please compare the setbacks provided on the architectural plans and the dvil
plans. The setbacks along Lincoln Street are shown as 9.9 feet on the civil plans where
the architectural plans show 10 feet.
Response: The setback along Lincoln Street has been corrected and now both
the architectural and civU plans show the accurate setback of 10 feet.
5, Architectural elevations - embell ish ends and add vertical relief to long
ridgeUnes. Lincoln Street elevation needs some building articulation along face of
buUding. Consider adding windows to the west end of elevation C and on elevation F,
Response: The long Lincoln Street elevation was broken up by setting back
the two units on the south side. Additional architectural articulation was added
to the windows, Windows have been added to the west end of Elevation C and
Elevation F, These can be seen on Sheets A-7 and A-8, Additionally, varied
types of windows have been added to Elevation B on Sheet A-7, This gives the
project some building articulation along Lincoln Street.
6, Please explain the difference in the design of the windows as shown on the floor
plans. Are these air conditioning units on the plans? If so, jdease show on the elevation
plans and describe how the air conditioning units will be treated.
Response: VTAC units will be located in the front comer of each guestroom, '
Each unit wiU have a fresh air grUle on the exterior elevation. The grilles wiU be
painted the same color as the exterior plaster to minimize their presence,
7, Please specify the wall types in between units.
Response: Walls in-between the guestrooms wiU be designed to meet HUton
standards and Uniform BuUding Code requirements. The sound isolation will be
STC 52.
8, Please describe the intended use of the meeting room. Is this for guest use only?
Response: The meeting room located within the hotel will be for guest use
only. ~ ' I
h-:;-\7lA"-€.- -rr-'O '\ fOr-: (J'^ ''t^ '
Fire
1. City Engineer shaU ensure that the proposed access from Carlsbad Boulevard
confonns to the minimum design standards for Fire Apparatus Access.
Response: This statement is acknowledged by the applicant.
nk ^
16
PLANNING
SYSTEMS
2. The clear height of the Portico shall be 13'6 ", this is the only access for fire
apparatus.
Response: The entrance has been redesigned to maintain a ininimum of
13'6" c lear. This can be seen on Sheet A-8.
3. Class 2 Standpipes shaU be required on the Northwest and Southeast stairwells.
Response: Class 2 Standpipes wiU be installed in both the Northwest and
Southeast stairweUs. A note indicating this can be seen on the Cover Sheet (CS).
Thank you for your assistance with the planning of this project. We look forward to
resolving any final issues City Staff may have with the design, prior to docketing for
Design Review Board hearing.
Sincerely,
Kermy Booth
Planner
cc: NeU Patel
Paul Klukas
Attachments
17
PLANNING
SYSTEMS
f
FLORESLUND
C ON S U LTAIMTG
April 22, 2005
Joseph Wong Desii ;n Associate?
2359 Fourth Avenue, Suite 300
San Diego, CA 92101
PROIECT: Clair sbad Hatnptxin Iitn
Attention; Mr. Rid: Rounds
Dear Ride
The purpose of thi, letter is to address the alternate methods of retainmg the soil adjacent to and
under the Seven El?ven Store in order to excavate for a two-level below grade paridng stmcture
There are several altemate construction techniques to accomplish this excavatfon without
compromise to the existirig Seven Eleven Store, Each of these techniques are conventional and
regularly employed
In general, there ar 2 two separate constmction methodobgies. The difference between the two Is
one method involve construction solely on the new construction site. The other method rrrtrudes
Into the adjacent property. They are generally described as follows:
LO \X/here conslruetion Is placed solely on the new construction site, soldier beams usually
spaced at 8' D,C- are drilled and cast Into the ground prior to any excavation. These soldier
beams are b aced appnaxtmately 8-10 feet below the excavation with a -Swhaler and raker
system" whirh are placed during the excavation. The 'Svhaler and raker system" are
essentially a diagonal bracing system which resists the horizontal thrust of rhe soil and
minimizes an / settlement of the adjacent property.
2.0 In the case where the adjacent property is utillzed> soldier beams usually spaced at 8' o.c are
dnlled and a.st into the ground prior to any excavation. Thc beams ar^ either placed under
the existtng footing or adjacent to that footing. As the excavation proceeds, at ffie
appropriate I jvel, tie-backs are drilled and anchored back under the existing building These
tie-backs resist the horizontal thnjst of the soil and minimize any settlement of the adjacent
property.
We trust this inform, rtion will assist you. Should you have any questtons, please call.
Very truly yours,
FLORAS LUND raAlSULTANTS
Hamid Liaghat
Senior Project Manager
7220 Trade Street Suiti 120 • SanDiego. CahTornia 92121 - (SSB) 566-0626 - FAX (858) 566-0627
CSiril and Stmctural Ert| Inuring ifln»w«.flore*luncl.ucitn
Citv of Carlsbad
Housing & Redevelopment Department
March 31,2005
DKN HOTELS
540 GOLDEN CIRCLE DRIVE #214
SANTA ANA, CA 92705
SUBJECT: DKN - Hampton Inn (RP 05-03, SDP 05-04, DEV 05-19, LCPA 05-02, ZC 05-02,
GPA 05-05)
APN: 203-250-08 & 203-250-26
Thank you for applying for a Land Use Permit in the City of Carlsbad. The Housing and
Redevelopment Department, together with other appropriate City departments, has reviewed
the above-mentioned applications as to their completeness for further processing.
The applications are incomplete, as submitted. Attached are two lists. The first list is
information that must be submitted to complete your applications. This list of items must be
submitted directly to the Housing & Redevelopment Office. All list items must be
submitted simultaneously and a copy of this list must be included with your submittal.
No processing of your application can occur until the applications are determined to be
complete. The second list includes issues of concern to staff, which must be addressed prior to
staff making a recommendation on the project. When all required materials are submitted to
the Redevelopment Office, the City has an additional thirty (30) days to make a determination
of completeness. If the applications are determined to be complete, processing for a decision
on the application will be initiated. In addition, please note that you have six months from the
date the application was initially filed, March 2, 2005, to either resubmit the applications or
submit the required information. Failure to resubmit the applications or to submit the materials
necessary to determine your applications complete shall be deemed to constitute withdrawal of
the applications. If an application is withdrawn or deemed withdrawn, a new application must
be submitted.
Please contact my office at (760) 434-2813, if you have any questions or wish to set up a
meeting to discuss the application.
Sincerely,
CLIFF JONES
Assistant Planner
c: Debbie Fountain, Housing & Redevelopment Director Greg Ryan, Fire
Van Lynch, Planning Jodee Sasway, Police
David Rick, Engineering
Pat Kelley, Building
2965 Roosevelt St., Ste. B • Carlsbad, CA 92008-2389 • (760) 434-2810/2811 • FAX (760) 720-2037 @
DKN Hampton Inn
03/31/2005
Page 2 of 5
LIST OF ITEMS NEEDED
TO COMPLETE THE APPLICATION
No. RP 05-03, SDP 05-04, DEV 05-19, LCPA 05-02, ZC 05-02, GPA 05-05
Housing & Redevelopment and Planning: The Housing & Redevelopment Department and
Planning Department have completed their review of the subject project for application
completeness. The applications and plans submitted for this project are incomplete at this time.
Please resubmit 5 sets of plans addressing the following incomplete items:
1. The General Plan designation and zoning for the residentially zoned property will need to be
changed. The proposed General Plan Land Use designation will need to be changed to
Recreation Tourist (RT). The Commercial Tourist (C-T) Zoning will implement the RT
General Plan Land Use designation. Please modify the plans accordingly (refer to item #3
for format and language).
2. The project will need to discuss the impacts that will occur as a result of the General Plan
Amendment for the residentially zoned property. Assembly Bill 2292 requires residential
zoned land to develop to its potential. Since the project eliminates residential units, findings
will need to be made to justify the loss of residential units.
3. Include the following information on the title sheet:
a. Application types submitted and assigned application numbers to the upper right corner.
b. Name of sewer, water, and school districts providing service to the project.
c. Please remove "CUP Number" from "Project Summary Table".
d. Correct the "Existing Zone" to state "Existing Zone: R-3 and V-R District 9".
e. Correct the "Proposed Zone" to state "Proposed Zone: C-T and V-R District 9 (to
remain)".
f. Correct the "Existing General Plan" to state "Existing General Plan: RH, V".
g. Correct the "Proposed General Plan" to state "Proposed General Plan: RT and V (to
remain)"
h. Correct the "Existing Land Use Designation" to state "Existing Land Use Designation:
Overlay Zones (Beach Overlay Zone & Coastal Zone)".
i. Correct the "Existing Land Use" to state "Existing Land Use: Motel, Restaurant, Single
Family".
j. Please include an open space calculation. A minimum of 20% of the site must be
maintained as open space. The areas that qualify as open space include; landscape
planters, open space pockets, balconies, and patios. No parking spaces or drive aisles
are permitted in the open space calculation.
4. Please indicate on the site plan, through shading, the portion of the project that falls within
the V-R District 9 zoning designation. Please note that the minimum roof pitch within V-R
District 9 is 5:12 and the permitted height of the building is 45 feet if the project is located
over parking, which in this case it is. Staff suggests the applicant consider using the
allowable increase in roof height in order to create a front elevation that is grander, and
visually appealing (for more information on staff's issues of concern related to the front
elevation of the project and the overall design of the project refer to page 4). Please modify
the plans accordingly.
5. Please dimension the widths of the driveway entrance and exit.
DKN Hampton Inn
03/31/2005
Page 3 of 5
6. Compact parking spaces are a minimum width of 8 feet by 15 feet. Sheets A-5 and A-6
show compact spaces being 7.5 feet wide. Standard parking spaces are a minimum width
of 8.5 feet and 170 square feet in area. The supporting columns will need to be shown
outside of the parking area such that the parking space is free and clear of any structures.
Please review all parking spaces and label all compact spaces as such. In addition please
number all parking spaces. Please correct and revise the plans as necessary.
7. Show finished and existing grades on all elevations and building sections.
8. Please add the top of wall and bottom of wall heights for the retaining walls on the civil plan,
sheet C-1.
9. Provide a sign plan showing conceptual signage for the building along with a summary table
with the following information:
a. Total building street frontage;
b. Total sign area allowed (1 square foot of signage per linear foot of building frontage);
c. Total sign area proposed.
10. Submit a construction materials board and color samples.
Engineering:
Engineering comments are forthcoming and will be sent under a separate cover.
DKN Hampton Inn
03/31/2005
Page 4 of 5
ISSUES OF CONCERN
No. RP 05-03, SDP 05-04, DEV 05-19, LCPA 05-02, ZC 05-02, GPA 05-05
Staff has completed a review of the subject project for issues of concern. The following items
need to be resolved or adequately addressed prior to staff making a final determination on the
proposed project: (Please note, the issues are listed under the department which identified
them as an area of concern.)
Housing & Redevelopment and Planning:
1. As part of the design review process, the Design Review Board must be satisfied that the
applicant has made an honest effort to conform to each of the ten basic principles outlined
in the Village Design Guidelines. A copy of the design guidelines has been attached for
your review. Some suggestions from the design guidelines are as follows:
• Provide for variety and diversity of building forms. An informal building character and a
sense of individuality is desired. Each building shall express its uniqueness of structure
and not mere copies of generic building types, which might be found anywhere. Staff
suggests the applicant pay greater attention to the design of the front entrance of the
project and provide a grand entryway to the buildings entrance off of Carlsbad
Boulevard.
• Provide a variety of setbacks along any commercial block front. Varied setbacks
provide a desired informality and diversity of appearance and allow for greater
landscaping.
• Break larger building forms into smaller units through the use of recessed facades.
Fagade projections as well as entry way recesses are elements which add richness to
the Village facades through the creation of shadows and the contrast between sunny
and shady surfaces.
• Design visual interest in all sides of the building. Greater articulation should be
incorporated into all sides of the building and the upper levels should be stepped back
from the lower levels to reduce the overall mass of the structure.
• Utilize applied surface ornamentation and other detail elements for visual interest and
scale.
• Emphasize cottage form, scale, and character. The use of gable roofs, varied roof
heights, and dormers help create interesting detail and are encouraged to enhance the
area's Village character.
• Incorporate an abundance of landscaping into the project.
• Incorporate benches and low walls along public pedestrian frontages such as Carlsbad
Boulevard.
2. The established range for front yard setbacks within Land Use District 9 are 5-20 feet. In
all cases where a range has been established as the appropriate setback standard within
a given district, the top of the range is considered to be the desired standard. However, a
reduction in the standard to the minimum, or anywhere within the range, may be allowed if
the project warrants such a reduction and appropriate findings are made:
• The reduced standard will not have an adverse impact on surrounding properties.
• The reduced standard will assist in developing a project which meets the goals of the
Village Redevelopment Area and is consistent with the objectives for the land use
district in which the project is to be located.
DKN Hampton Inn
03/31/2005
Page 5 of 5
• The reduced standard will assist in creating a project design which is interesting and
visually appealing and reinforces the Village character of the area.
3. Please add a building section that includes the pool and upper and lower parking levels.
The pool and spa appear to conflict with the laundry facility below. Please explain how the
pool and spa are to be supported.
4. Please compare the setbacks provided on the architectural plans and the civil plans. The
setbacks along Lincoln Street are shown as 9.9 feet on the civil plans where the
architectural plans show 10 feet.
5. Architectural elevations - embellish ends and add vertical relief to long ridgelines. Lincoln
Street elevation needs some building articulation along face of building. Consider adding
windows to the west end of elevation C and on elevation F.
6. Please explain the difference in the design of the windows as shown on the floor plans.
Are these air conditioning units on the plans? If so, please show on the elevation plans
and describe how the air conditioning units will be treated.
7. Please specify the wall types in between units.
8. Please describe the intended use of the meeting room. Is this for guest use only?
Fire:
The following Fire Department issues must be must be resolved or adequately addressed prior
to staff making a determination on the proposed project:
1. City Engineer shall ensure that the proposed access from Carlsbad Boulevard conforms to
the minimum design standards for Fire Apparatus Access.
2. The clear height of the Portico shall be 13'6", this is the only access for fire apparatus.
3. Class 2 Standpipes shall be required on the Northwest and Southeast stairwells.
If you have any questions regarding Fire Department issues, please contact Greg Ryan at 760-
602-4663.
Landscape Plan Review:
Comments on the preliminary landscape plan are forthcoming and will be sent to you under a
separate cover.
Crime Prevention Plan Review:
The City's Crime Prevention Specialist typically reviews plans for larger projects in an effort to
increase security through project design. Project design recommendations have been attached
for your review. For questions regarding the attached comments, please contact Jodee
Sasway of the Carlsbad Police Department at 760-931-2195.
Date: March 11, 2005
To: Cliff Jones, Housing and Redevelopment
From: J. Sasway, Crime Prevention Specialist, Carlsbad Police Department
Subject: Hampton Inn
Plan Review Recommendations
Carlsbad Police Department's Crime Prevention Unit has provided the following optimal
security recommendations. The purpose of this document is to safeguard property and public
welfare by regulating and reviewing the design, constmction, quality of materials, use and
occupancy, location, and maintenance of all buildings and stmctures. The standards used in
this document represent model statewide standards.
• Building Placement - Creating Defensible Space
Strategies to consider:
1. Provide clearly defined transitions from public to private space. Use landscaping,
fencing and ground cover to create territoriality for the property.
2. Locate coinmon well-used areas where there is good surveillance.
3. Use natural barriers to designate space and separate activities that may conflict.
4. Design space to increase the perception of natural surveillance.
5. Consider that if people feel comfortable and safe in all areas, they are more likely to use
the areas.
• Parking Structure Considerations
Lighting
Natural surveiUance
Stair towers
Elevators
Access control
Signage
Light
•The model routine light standard in pcirking structures is 6-footcandles of uniform light at
the ground level. When lighting take into consideration the illuminance, uniformity and glare.
Natural Surveillance
• Maximize flat parking areas and minimize ramps
• Long-span constmction and high ceilings create openness and aid lighting.
• The openness of the fagade should be maximized.
• Pedestrian paths should be minimized. Concentrating more people on less paths increased
surveillance.
• Dead-end parking and nooks and crannies should be avoided
• Stair towers and elevators have been the highest risk for personal injury as they are typically
enclosed.
• Design stair towers and elevators as open as the code permits. If a stair must be enclosed,
glass walls can reduce crime.
• Parking spaces should be defined at 90 degrees instead of 45 degrees.
Access Control
• Access control and perimeter security should be considered during the design state.
• Ground level pedestrian exits that open into non-secure areas should be emergency exits
only.
•Access to the parking facility should be controlled, generally taking a ticket on entry and
interacting with a guard on exit.
• Access into the facility should be minimized.
Signage
• Place signs carefully to expedite the movement of people through the area.
• Color coding or unique memory aids help patrol quickly locate their vehicles
I Hotel Considerations
Lighting
• Light should be consistent to reduce contrast between shadows and illuminate areas.
Illuminate aisles, passageways, and recesses related to and within the building complex with a
mamtained minunum of twenty-five one hundredths (.25) of a foot-candle at the ground level
during the hours of darkness. Protect lighting devices with weather and vandalism-resistant
covers.
• Protect open parking lots with a rnaintained minimum of one (1) foot-candle of light on the
parking surface during the hours of darkness. White lights provide better vision and
surveillance capabilities than do yellow lights. Yellow lights prevent loitering because they are
monochromatic. Protect lighting devices with weather and vandalism covers. Ensure landscape
and building design does not take away from ininimum standards of lighting.
• Give the main entry and rear dock areas additional lighting during hours of darkness.
Landscaping
• Landscaping can mark the transition between zones or areas. The police department
recommends that the exterior landscaping be kept at a minimal height and fullness, giving
police, security services and the general public surveillance capabilities of the area. Growth
characteristics of plants and their placement in relation to potentially vulnerable areas are
extremely important.
• Plant low-profile bushes and shmbs, not exceeding three feet in height. Create space
between the bottom of trees and the tops of bushes or shmbs. Make sure tree canopies are not
lower than six feet. Do not plant landscaping higher than three feet in front of windows or in
parking areas.
• L£indscaping should not detract from lighting. Keep entranceways clear of clutter. Design
perimeter landscaping and burms to allow vision into the property, particularly parking areas
and building access doors.
• Apply security plants where necessaiy to prevent loitering and tampering.
Addressing
• Display street numbers prominently on the street side of the building. Place the number in a
position that is easily visible to emergency vehicles, hasting their approach. Make sure the
numbers are no less than four (4) inches in height and are a contrasting color to the building to
which they are attached. Illuminate the numbers at night.
Access Control
• All entrances except the lobby should be closed 24 hours a day and require guest card to access. This includes
intemal doors and gates to community use facilities like laundry. This further enhances the personal safety of the
guests.
• Building Recommendations
Doors
• The police department recommends that hollow steel doors be a minimum sixteen (16) U.S.
gauge and have sufficient reinforcement to maintain the designed thickness of the door when
any locking device is installed. Only use glass doors with fully tempered glass or rated burglary
resistant glazing. Protect all exterior doors with security hardware.
• Equip all doors with an astragal constmcted of steel. Ensure the astragal is a minimum of
.125 inch thick. The astragal covers and protects the opening between the door and doorframe
or other door at the locking device. The purpose of the astragal is to protect the locking device
from a cutting or prying attack. Attach tiie astragal to the outside by welding or with non-
removable bolts spaced apart on not more than ten-inch centers.
• Constmct the jamb of all aluminum frame-swinging doors to withstand 1600 pounds of
pressure in both a vertical distance of three inches and horizontal distance of one inch each
side of the strike, to prevent violation of the strike.
• Equip hotel room doors with a viewer and deadbolt lock. Equip hotel room sliding glass
doors with a security pin.
• Equip rear doors used for shipping and receiving and employee entrances with a viewer.
Windows
• Equip movable windows with security hardware and burglar resistant glazing. Cover other
vulnerable non-movable windows with burglar resistant glazing.
Roofs
• Secure all roof openings.
Trash Enclosures
• Position the trash enclosures away from areas of shipping and receiving.
This Information is a representation of information gathered on a national level. The purpose is
to provide effective and consistent information. If you would like additional assistance
conceming building security or employee security issues, please contact the Crime Prevention
Unit at (760) 931-2105.
Reviewed by: Jodeene R. Sasway
Crime Prevention SpeciaUst
Carlsbad Police Department
(619) 931-2195