HomeMy WebLinkAboutRP 86-12; 7 Eleven & Pepi's Pizza; Redevelopment Permits (RP) (2)7-ELEVEN FOOD STORES • DEVELOPMENT DEPARTMENT
7777 ALVARADO ROAD #417 • LA MESA, CALIFORNIA 92041 • PHONE (619) 466-0711
December II, 1986
City of Carlsbad
Development Processing
Services Division
2075 Las Palmas Drive
Carlsbad, CA 92009-4859
Dear Sir:
Thank you for your notification that the plan check deadline for
PC# 56-2 (201 Oak Avenue Pizza Restaurant) has been extended to
1/2/87.
Because of the exorbitantly, high permit and facilities fees, this
project is not economically feasible and has been abandoned.
Sincerely,
Lynne Ridgway
Construction Coordinator
South Pacific Division
LR:bam
cc; Larry Luhnow
Steve Ray
Steve Hauser Engineering
DIVISION (IF
• J THE SOUTHLAND C»3 CORPORATION
Costa Real
VgV? Municipal Water District
Ik
^^^^^C^ 5950 El Camino Real, Carlsbad, CA 92008
Telephone: (619)438-2722
Engineering Dept: 438-3367
DATE: June 17, 1986
TO: City of Carlsbad
Land Use Planning
Carlsbad, California 92008
ATTN: Brian Hunter
SUBJ: R.P. 86-12 - 7-11 Store & Pepi's Pizza (Remodel)
South East Corner Carlsbad Boulevard and Oak Avenue
CRMWD Project No. 85.117
The subject project has been reviewed by the District's
Engineering Department to determine the extent of District's
involvement regarding existing and proposed water system to serve
proposed project as follows:
YES NO
Are there transmission lines that affect project? ( ) (X)
Are there existing facilities that will have to be
reconstructed? ( ) (X)
Are there new facilities that will have to be
constructed? ( ) (X)
Are there existing District agreements that have
financial impact on the project? (X) ( )
We have the following specific recommendations:
1. The entire water system for subject project be
evaluated in detail to insure adequate capacity for
domestic, landscaping and fire flow demands.
2. The developer and his engineer schedule a meeting with
the District Engineer and establish water system layout
prior to the water system improvement plans being
drawn.
Page 2
Brian Hunter
June 17, 1986
3. The project currently has six water meters that
presently provide service to the existing businesses.
Regarding fees and deposits: The developer will be
responsible for the major facility charge and direct connection
surcharge which will be collected at time of issuance of building
permit. Please contact Mr. Jerry Whitley if you have any
questions regarding this project.
Very truly yours.
William E. Blakesley
District Engineer
WEB:sja
CRMWD 85.117
cc: Mike Smith, Fire Marshal
Dave Houser, Asst. City Engineer
f ^
DEVELOPMENTAL • • 1200 ELM AVENUE
SERVICES mr^T^^M CARLSBAD, CA 92008-1989
LAND USE PLANNING OFFICE ^^^^^ 438-5591
Citp of taxlihah
June 9, 1986
Wolfe-Woods & Associates
4215 Spring Street, Suite 215
La Mesa, California 92041
RE: RP 86-12 (7 ELEVEN FOOD & PEPI'S PIZZA)
The Planning Director and the City Engineer have
reviewed the application you submitted for the above-referenced
project. Based upon this review, it has been determined that
there are problems associated with your application which must be
addressed before this application can be scheduled for a Planning
Commission hearing. The problems or issues are listed below.
Also, the name of the project planner and project engineer is
provided. You should set up a meeting to discuss the
issues with the appropriate staff member. Once the problems/
issues have been addressed, your application will then be
scheduled for a hearing
PROBLEMS/ISSUES: (PLANNING)
Project Planner
Nancy Rol 1 man
1. Par ki ng
^. 24" back-up space
3. Entry from Carlsbad Blvd.
has problems
4. Queuing (access/circulation)
5. Show drainage method
Project Engineer
Cl yde Wi c kham