HomeMy WebLinkAboutRP 97-05; Hoenig Residence; Redevelopment Permits (RP) (3)Memorandum
TO: Management Analyst, Craig Ruiz
FROM: Associate Engineer, Clyde Wickham
DATE: September 30, 1997
RE: RP 97 - 05, Hoenig Residence
We have completed our review of the redevelopment permit identified above.
The addition of a driveway, a garage, and the increased setbacks are fine. We
have no comment or conditions to add, otherthan the usual, to obtain standard
right of way permits for the driveway approach and apron.
If you have any questions, please don't hesitate to call me at extension 4353.
Clyd6 Wickham
Associate Engineer, Land Use Review Division
c: Bob Wojcik
Principai Engineer, Land Use Review Division
September 9.1997
TO: Mike Peterson, Building Department
Clyde Wickham, Engineering Department
FROM: Management Analyst, Housing and Redevelopment Department
REDEVELOPMENT PERMIT RP97-05
In July of this year. Redevelopment Permit RP97-05 was submitted for your review. At
that time, you had no conunents on the project. To address the concems of this
department, the applicant has revised their project. The changes to the project include
the addition of a driveway, a garage, and increased building setbacks. If you could
please review the new plans at your earUest convenience and provide me with you
conunents, I would be greatly appreciative.
If you have any questions about the above information, or the attached plans, please call
me at x2817.
Thank you.
Craig D. Ruiz
F:\Memo\RP9705-2 09/26/97
Citv of Carlsbad
Housing & Redevelopment Department
July 29 1997
Seth Hoenig
2714 Madison Street
Carlsbad, CA 92008
Subject: Redevelopment Permit No. 97-05, Single Family Addition at 2714
Madison Street
Dear Mr. Hoenig:
Thank you for submitting your application for a Redevelopment Permit for your property
located at 2714 Madison Street. Your administrative redevelopment permit application
was received for processing on June 30, 1997 and has been deemed complete for further
processing as of the date of this correspondence. Although your application has been
deemed complete for fiirther processing, there are some changes/corrections to the plans
that will need to be resolved before the Housing and Redevelopment Director will be able
to provide you with final approval of your application.
As part of staffs review, you application and plans were forwarded to the Engineering,
Planning and Building Departments for their review. Based on the subject review, the
following corrections and/or changes must be made to the plans you originally submitted
for approval:
v/^ 1. The Carlsbad Village Master Plan sideyard setback requirement is 10% of the
property width. The property is 60 feet wide which corresponds to a 6 foot sideyard
setback. The plans indicate that the proposed setback to be 5 feet,9 inches. Please
revise the plans accordingly.
^y^l. The Master Plan requires additions to existing buildings to provide parking per
existing parking standards. The parking requirement for a single family home is a two
car garage.
s/3. The plans indicate a 3 foot separation between the addition and an existing storage
building. The Building Code requires a 6 foot separation between structures.
\. The building elevations do not indicated the total building height. Please revise the
plans to show the height of the building.
F:\Redevelopment\Project\RP9705 Plan Check 07/29/97
2965 Roosevelt St., Ste. B • Carlsbad, CA 92008-2389 • (619) 434-2810/2811 • FAX (619) 720-2037 ®
5. Previously, you had inquired about a waiver of the requirement for providing
sidewalk improvements. The sidewalk requirement is based upon the cost valuation
of the proposed improvements. For a single family addition, this requirement is
imposed on improvements exceeding $50,000. When you resubmit your revised
plans, staff will determine if the improvements are required. Ifthe improvements
exceed $50,000, staff does not have the authority to waive the requirement. However,
you would have the ability to appeal the decision of the Housing and Redevelopment
Director to the Design Review Board.
Once the above referenced changes have been made, please resubmit four (4) copies of
the revised plans to my office for continued processing. Once you have submitted your
revised plans and staff has determined them acceptable, we will be able to proceed with
the public review and comment period on you proposed project. Once the public review
and comment period is complete and staff has verified that the appropriate corrections
have been made to the project plans, a final approval can be granted. Once approved,
staff can then complete the process by issuing the final notice to announce the appeal
period of the Housing and Redevelopment Director's decision. The total public review
and comment period is approximately 20 days. No action can be taken to approve a
building permit until the redevelopment permit is issued following completion of the
comment and appeal periods. Therefore, you are encouraged to make the required
corrections/changes to your project plans and retum them as quickly as possible so that
we may continue the process.
If you have any questions about the above information, please call me at (760) 434 2817.
Sincerely,
Craig D. Ruiz
Management Analyst
c: Community Development Director
Senior Planner, B. Hunter
Associate Engineer - Clyde Wickham
Principle Building Inspector - P. Kelly
F:\Redevelopment\Project\RP9705 Plan Check 07/29/97
Memorandum
To: Craig Ruiz, Management Analyst
From: ASSOCIATE ENGINEER, Clyde Wickham
Date: 25 July 1997
Re: Redevelopment Permit, 97 - 05, Hoenig Residence
I have reviewed the above mentioned application and have no comment
or conditions to apply to this request.
If you need additional information or assistance, please contact this
office.
ryaje Vvfckham
Associate Engineer
Land Use Review Division
c: City Engineer
Principal Engineer, Land Use Review Division
June 27, 1997
TO: VAN LYNCH, PLANNING
FROM: DEBBIE FOUNTAIN, HOUSING AND REDEVELOPMENT
RE: APPLICATION FOR ADMIN. REDEVELOPMENT PERMIT
Attached please find an application and two copies of the related plans for an
administrative redevelopment permit to add 500 square feet to an existing single family
home at 2714 Madison Street. The payment for the $150 required fee is also attached.
Would you please process the attached application into the permit system? Please forward
the receipt for payment of fees to my office with a copy of the application and noted
redevelopment permit number. The two copies of the plans may be submitted to the
Assistant Planning Director and Principal Civil Engineer for assignment. I will then
complete the remainder of the processing requirements.
Thanks for your assistance. If you have any questions, please contact my office at X2935.