COMPLETENESS REVIEW
PROJECT ID: SDU 01-35 DANNA SECOND DWELLING UNIT
The Engineering Department has completed its review of the above referenced project.
Engineering staff does not have any comments to add to the project. Please add the following
conditions of approval to the approving resolution:
NOTE: Unless specifically stated in the condition, all of the following conditions, upon the
approval of this proposed tentative map, must be met prior to approval of a building permit.
1. Prior to hauling dirt or construction materials to or from any proposed construction site
within this project, Developer shall apply for and obtain approval from, the City Engineer
for the proposed haul route.
2. Prior to issuance of any building permit, Developer shall comply with the requirements of
the City’s anti-graffiti program for wall treatments if and when such a program is formally
established by the City.
3. Prior to the issuance of a building permit, the developer shall submit an erosion
control plan with the building plans for City approval. Said erosion control shall
be in place prior to beginning any construction or earthwork.
4. Developer shall cause property owner to enter into a lien contract with the City for the
future public improvement of Oak Ave along the subdivision frontage for a half street
width of 30 feet. Public improvements shall include but are not limited to paving, base,
sidewalk, curb and gutter, and streetlights.
5. Prior to approval of any grading or building permits for this project, Developer shall
cause Owner to give written consent to the City Engineer to the annexation of the area
shown within the boundaries of the subdivision into the existing City of Carlsbad Street
Lighting and Landscaping District No. 1, on a form provided by the City Engineer.
Wa- .. ..
H:\LIBRARY\ENG\WPDATA\MISCCOMPREV
c.
6. Prior to issuance of building permits, Developer shall pay all fees, deposits, and charges
for connection to public facilities. Developer shall pay the San Diego County Water
Authority capacity charge(s) prior to issuance of Building Permits.
The Developer shall install potable water services and meters at a location approved by
the District Engineer.
The Developer shall install sewer laterals and clean-outs at a location approved by the
District Engineer.
This project is approved upon the express condition that building permits will not be
issued for the development of the subject property, unless the District Engineer has
determined that adequate water and sewer facilities are available at the time of
occupancy.
7.
8.
9.
If you or the applicant has any questions regarding the above, please either see or call me at
extension 2781.
David Rick
Assistant Engineer - Development Services Division
H:LIBRARY\ENG\WPDATAWlSC\COMPREV