Loading...
HomeMy WebLinkAbout3190; RANCHO SANTA FE ROAD; GROUNDWATER MEASUREMENTS; 2007-05-14City of Carlsbad 5950 El Camino Real Carlsbad, CA 92009 Attention: Mr. Skip Hammann Subject: Groundwater Measurements Project: Rancho Santa Fe Road Phase I Slope Stabilization Carlsbad, California May 14, 2007 Contract No.: 89583 RECEIVED MAY1 6 2007j CITY OF CARt.SHAD ENGINEERING IflPAkTMENT CM&I DIVISION References: 1. "Geotechnical investigation & Field Review, Rancho Santa Fe Road Phase I Roadway Slope Stabilization", Contract No. 89583, April 17, 2006, prepared by Testing Engineers - San Diego, Inc. (TESD). Dear Mr; Hammann: Submitted herewith are groundwater measurements in connection with the removal of groundwater from the rock fill adjacent to the slide at the above referenced project site (see Figure No. 1, Site Location Map). Services described herein were provided by a representative of TESD from February 24, 2006 to April 13, 2007. Groundwater measurements taken prior to February 24, 2006 were recorded in the Geotechnical Investigation referenced above. Groundwater measurements were taken from 4 different locations as shown on Figure No. 2, Plot Plan. Measurements of the water elevation relative to average mean sea level within 2 large diameter dewatering wells and 2 piezometers installed by Kleinfelder Associates are provided in Table 1. It should be noted that the accuracy of the measurements are plus or minus 0.1 inches. The final slope stabilization required the completion of 2 horizontal wells extending through the slide over-excavated keyway out to the rock fill prism (i.e. "bathtub") within the new Rancho Santa Fe road: The horizontal drains provide a permanent gravity sub-drainage system for the rock fill prism. In addition, the project incorporates sub-drainage elements within the regarded slope and extending out to the closest storm drain system along Esfera Street. More detailed background information is presented in the above referenced Geotechnical Investigation. Based on groundwater monitoring, the sub-drainage components are performing in a satisfactory manner. If you should have any questions after reviewing this report, please do not hesitate to contact the undersigned at (858) 715-5800. Testing Engineers San Diego, Inc. Main: (858) 715.5800 A Bureau Veritas Company 7895 Convoy Court, Suite 18 Fax: (858) 715.5810 San Diego, CA 92111 www.us.bureauveritas.com City of Carlsbad Contract No.: 89583 Rancho Santa Fe Road Slide Respectfully submitted, Testing Engineers San Diego, Inc. A Bureau Veritas ompany 7t/ Nick Tracy, EIT Staff Engineer Attachments: Figure]: Site Location Map Figure 2: Plot Plan Figure 3: Groundwater Timeline Table I: Report of Well Measurements Van W. Olin, GE Principal GeotecF NT! V 0 : mm Distribution: (4) Addressee S:\engineer\Geotechnical Files\Projects\Currenl Projects\89583 Carlbad Agua Dulce Court'Jvlonitoring Well Measurements\89583 Monitoring Wells.doc 2 4 .t l* \' 3.1 e JSITE LOCATION 4 . SCALE 1:24 000 Ref: USGS 7.5 minute Rancho Santa Fe Quadrangle, latest rev. 1983. NOTE: This figure may contain areas of color. TE-U.S. Labs cannot be responsible for any subsequent misinterpretation of the information result- ing from black and white reproductions of this figure. Testing Engineers - U.S. Labs, Inc. 4 7895 Convoy Court, Suite 18 San Diego, CA 92111 rnzzmmmm IDJI Tel: (858) 715-5800 Fax: (858) 715-5810 Title Site Location Map Project: Rancho Santa Fe Rd. Slide I Drwn: NJT Contract No: 89583 Date: May, 2007 Figure: 1 - I ... . • Legend: I DW-N I Dewatering Well North N [9w-SI Dewatering Well South IKA-1DI Kleinfelder Associates Deep Piezometer I - . . -- 2D KleinfelderKleinfelder Associates Deep Piezometer2 NOTE: This figure may contain areas of color. TE-U.S. Labs cannot be responsible for any subsequent misinterpretation of the information result- Testing Engineers - U.S. Labs, Inc. 0 7895 Convoy Court, Suite 18 San Diego, CA 92111 ORPOMM MorwX—Mill Tel: (858) 715-5800 Fax: (858) 715-5810 Title Plot Plan Project: Rancho Santa Fe Rd. Slide I Drwn: NJT Contract No: 89583 Date: Figure: ing from black and white reproductions of this figure. May, 2007 2 Groundwater Timeline 315 310 w . 305 C 300 295 290 285 3/24/2006 EW-Nbrth - EWSouth KA1 $ KA2 6/7/2006 8/21/2006 11/4/2006 1/18/2007 4/3/2007 Date Note: Piezometers KA1 and KA2 were removed December, 2006 with the last measurements taken on December 14, 2006. NOTE: This figure may contain areas of color. TE-U.S. Labs cannot be responsible for any subsequent misinterpretation of the information resuft- ing from black and white reproductions of this figure. Testing Engineers - U.S. Labs, Inc. 7895 Convoy Court, Suite 18 San Diego, CA 92111 Tel: (858) 715-5800 Fax: (858) 715-5810 Title Groundwater Timeline Project: Rancho Santa Fe Rd. Slide I Drwn: NJT Contract No: 89583 Date: May, 2007 Figure: 3 TABLE I GROUNDWATER MEASURMENTS Contract Number: 89583 Project Name: Rancho Santa Fe Road Slide Location: Carlsbad, California Monitoring Well Monitoring Well KA1D Water KA2D Water Date North Water South Water Elevation Elevation Elevation (feet) Elevation (feet) (feet) (feet) Z/'Z4/Ieuut) 261.6b 311.25 304.60 2/27/2006 287.83 309.50 304.66 2/28/2006 287.84 309.10 304.52 3/1/2006 290.38 287.96 308.71 304.51 3/2/2006 290.71 287.81 308.50 304.39 3/3/2006 287.84 308.63 304.31 3/6/2006 287.81 308.22 304.12 3/7/2006 287.79 309.51 303.96 3/8/2006 290.99 287.82 309.45 304.00 3/9/2006 290.97 287.82 308.88 304.28 3/10/2006 290.92 ' 287.81 308.66 304.22 3/11/2006 290.91 287.92 308.41 304.11 3/13/2006 291.63 287.95 337.97 303.90 3/14/2006 291.60 287.94 307.84 303.96 3/15/2006 291.66 287.90 307.76 303.90 3/16/2006 291.60 287.89 307.64 303.90 3/17/2006 291.52 287.73 307.56 303.86 3/20/2006 291.22 287.78 307.46 303.80 3/21/2006 291.09 287.79 307.37 303.75 3/22/2006 291.01 287.77 307.28 303.69 3/23/2006 290.86 287.85 307.26 303.70 3/24/2006 290.74 287.86 307.32 303.76 3/27/2006 290.54 287.74 307.32 303.68 3/28/2006 290.52 287.75 307.31 303.68 3/29/2006 290.51 287.74 307.32 303.64 3/30/2006 290.53 287.75 307.26 303.62 3/31/2006 290.52 287.75 307.26 303.62 4/3/2006 290.48 287.74 307.21 303.10 4/4/2006 290.46 287.73 307.27 303.53 4/5/2006 290.45 287.74 307.31 303.59 4/6/2006 290.75 287.96 307.35 303.53 4/7/2006 290.83 287.97 307.22 303.59 4/10/2006 290.72 287.89 308.24 303.62 4/11/2006 290.64 287.87 307.23 303.52 4/12/2006 290.62 287.91 307.19 303.60 4/13/2006 290.57 '287.86 307.23 303.61 4/14/2006 290.53 287.82 307.28 303.66 4/17/2006 290.47 287.79 307.79 303.56 4/18/2006 290.48 287.80 307.21 303.60 4/19/2006 290.49 287.80 307.30 303.62 4/20/2006 290.49 287.81 307.31 303.61 TABLE I GROUNDWATER MEASURMENTS Contract Number: 89583 Project Name: Rancho Santa Fe Road Slide Location: Carlsbad, California Monitoring Well Monitoring Well KAI D Water KA2D Water Date North Water South Water Elevation Elevation - Elevation (feet) Elevation (feet) (feet) (feet) 4I21I200 290.39 27.79 306.91 303.62 4/24/2006 290.46 287.80 307.27 303.53 4/25/2006 290.44 287.80 307.28 303.56 4/26/2006 290.63 287.96 307.50 303.76 4/27/2006 290.62 287.95 307.49 303.71 4/28/2006 290.43 287.67 307.27 303.49 5/1/2006 290.43 287.80 307.35 303.54 5/2/2006 290.42 287.78 307.36 303.51 5/3/2006 290.42 287.78 30737 303.49 5/4/2006 290.41 287.78 307.35 303.46 5/5/2006 290.40 287.78 307.31 303.51 5/8/2006 290.37 287.76 307.37 303.46 5/9/2006 290.44 287.83 307.42 303.48 5/10/2006. 290.39 287.79 307.38 303.41 5/11/2006 290.39 287.79 307.38 303.40. 5/12/2006 290.35 287.'9 307.26 303.4 5/15/2006 290.36 287.79 307.37 303.36 5/16/2006 290.34 287.75 307.31 303.30 5/17/2006 290.34 287.78 307.34 303.32 5/18/2006 290.34 287.78 307.34 303.27 5/19/2006 290.33 287.77 307.30 303.23 5/22/2006 290.33 287.80 307.38 303.32 5/23/2006 290.33 287.78 307.24 303.20 5/24/2006 290.33 287.78 307.24 303.20 5/25/2006 290.33 287.78 307.29 303.25 5/26/2006 290.32 287.85 307.48 303.43 5/30/2006 290.35 287.76 307.26 303.15 5/31/2006 290.35 287.77 307.48 303.15 6/1/2006 290.36 288.77 307.29 303.15 6/2/2006 290.37 287.78 307.29 303.13 6/5/2006 290.39 287.78 307.34 303.06 6/6/2006 290.38 287.77 307.34 303.04 6/7/2006 290.38 . 287.77 307.34 303.03 6/8/2006 290.38 287.77 307.33 303.03 6/9/2006 290.34. 287.75 307.32 303.02 6/12/2006 290.94 287.77 307.33 303.00 6/13/2006 290.30 287.76 307.25 302.96 6/14/2006 290.28 287.78 307.26 302.97 6/15/2006 290.26 287.77 307.32 302.98 6/16/2006 290.26 287.77 307.36 303.01 6/23/2006 290.24 287.78 307.37 302.83 TABLE I GROUNDWATER MEASURMENTS Contract Number: 89583 Project Name: Rancho Santa Fe Road Slide Location: Carlsbad, California Monitoring Well Monitoring Well KA1 D Water KA2D Water Date North Water South Water Elevation Elevation Elevation (feet) Elevation (feet) (feet) (feet) 6/30/2006 290.23 261.1b iUI.b( iUi.1 7/7/2006 290.13 287.75 307.95 303.39 7/10/2006 290.09 287.74 308.09 303.38 7/11/2006 290.08 287.74 308.11 303.69 7/12/2006 290.08 287.74 308.06 303.36 7/13/2006 290.03 287.74 308.08 303.34 7/14/2006 290.02 287.75 308.7 303.35 7/17/2006 289.95 287.73 308.02 303.29 7/18/2006 289.94 287.74 308.05 303.3 7/19/2006 289.92 287.73 . 308.03 303.3 7/20/2006 289.91 287.74 308.03 303.31 7/21/2006 289.91 287.74 308.01 303.28 7/24/2006 289.94 287.75 308.11 303.32 7/25/2006 289.96 287.75 308.13 303.31 7/26/2006 . 289.96 287.76 308.05 303.28 7/28/2006 289.94 287.5 307.97 303.23 7/31/2006 289.96 287.75 307.98 303.24 8/1/2006 289.96 287.75 307.98 303.22 8/2/2006 289.98 287.74 307.94 303.2 8/3/2006 290.00 287.75 307.98 303.13 8/8/2006 290.14 287.76 307.98 303.19 8/9/2006 290.27 287.78 308.02 303.18 8/10/2006 290.36 287.76 308.02 303.18 8/11/2006 290.51 287.77 308.03 303.17 8/14/2006 290.57 287.78 308.06 303.14 8/15/2006 290.55 287.78 308.05 303.13 8/16/2006 290.54 287.78 308.06 303.12 8/17/2006 290.53 287.78 308.04 303.13 8/18/2006 290.52 287.78 308.07 303.13 8/21/2006 290.50 287.77 308.14 303.13 8/22/2006 290.50 . 287.78 308.17 303.12 8/23/2006 290.50 287.78 308.15 303.11 8/24/2006 290.49 287.78 308.19 303.14 8/28/2006 290.50 287.77 308.26 303.11 8/29/2006 290.50 287.78 308.28 303.12 8/31/2006 290.52 287.78 308.31 303.1 9/1/2006 290.57 287.80 308.32 303.06 9/5/2006 290.39 287.92 . 308.25 303.05 9/6/2006 290.71 287.89 308.24 303.06 9/7/2006 290.66 287.88 308.3 303.08 9/8/2006 . 290.60 287.87 308.32 303.05 TABLE I GROUNDWATER MEASURMENTS Contract Number: 89583 Project Name: Rancho Santa Fe Road Slide Location: Carlsbad, California Monitoring Well Monitoring Well KA1 D Water KA2D Water Date North Water South Water I I Elevation Elevation Elevation (feet) Elevation (feet) (feet) (feet) 9/11/2006 290.55 2I.1 iu.i 9/12/2006 290.54 287.78 308.34 303 9/13/2006 290.53 287.78 308.33 303.02 9/15/2006 290.54 287.78 308.36 303.02 9/20/2006 290.52 287.80 308.35 303.01 9/28/2006 290.47 287.78 307.94 302.96 10/6/2006 290.38 287.93 308.5 302.91 10/10/2006 290.00 287.78 307.98 302.92 10/19/2006 290.40 287.78 308.36 302.88 10/24/2006 290.40 287.78 307.44 302.89 11/2/2006 290.38 287.78 308.37 302.83 11/27/2006 290.44 287.94 308.57 302.95 11/28/2006 290.44 287.94 308.56 302.25 12/7/2006 290.39 287.93 308.52 302.91 12/14/2006 290.39 287.95 308.52 . 302.91 12/27/2006 290.30 287.78 1/2/2007 290.33 287.76 1/8/2007 290.27 287.77 1/9/2007 290.26 287.78 1/10/2007 290.25 287.77 1/11/2007 290.23 287.76 1/12/2007 290.21 287.77 1/15/2007 290.14 287.75 1/19/2007 290.08 287.76 1/26/2007 289.98 287.76 1/31/2007 289.54 287.41 2/5/2007 289.90 287.75 2/16/2007 290.04 287.75 2/23/2007 290.06 287.75 3/1/2007 290.16 287.73 3/9/2007 290.24 287.75 3/16/2007 289.90 287.74 3/21/2007 290.17 287.74 3/23/2007 289.83 287.74 3/30/2007 289.77 287.74 4/5/2007 290.07 287.74 4/6/2007 290.06 287.73 4/13/2007 290.03 287.73