HomeMy WebLinkAboutCT 73-29; Carrillo Estates; Final Soils Report; 1977-05-16WESTERN REGION 3467 Kurt2 Street California 92110 San Diego Phone (714) 224-2911 Project No. 77-105-9F May 16, 1977 Ponderosa Homes, Inc. 140 Marine View Avenue Solana Beach, California 92075 Attention: Mr. Ron Shackleford FINAL REPORT OF ENGINEERING OBSERVATION AND COMPACTION TESTING LOTS 2 THROUGH 7, 12 THROUGH 16, CARLSBAO, CALIFORNIA 22, 23, 45 THROUGH 52 AND 60 THROUGH 70 CARRILLO ESTATES UNIT NO. 1 Cr 73-.?0/ 'In accordance with your request and our agreement dated December 19, 1976, we have provided soil engineering services in conjunction with the grading of the subject site. These services included: (1) Engineering observation of the grading operation. (2) Observation of the preparation of the areas prior to placing fill . including excavating or scarifying and compacting loose surface and alluvial soils. (3) Taking field density tests in the fill placed and compacted. (4) Performing laboratory tests on representative samples of the material used for fill. GENERAL SITE GRADING period, that this work was completed between February 22, and May 3, 1977, It is our opinion, based on our observation and testing during this Associates report entitled "Soil Investigation for the Proposed Carrillo in accordance with the recommendations in the Woodward-Gizienski & Estates, Carlsbad, California" dated September 6, 1973, and the "Specifications For Controlled Fill" in our addendum letter dated October 24, 1975 entitled "Clarification of Slope Stability Analyses and Earthwork Specifications, Carrillo Estates, Carlsbad, California". z. Woodward-COyde Consukants Fill was placed, compacted, and tested on Lots 2 through 7, 22, 23, 47 through 52 and 60 through 20. Lots 12 through 16, 45 and 46 remain cut lots as designed. The grading operation essentially consisted of excavating loose alluvial soils, and the compacting of shallow loose surface soils prior to placing fill to bring the lots to design grades. was removed and replaced with nonexpansive compacted and tested material. Expansive soils encountered within the top two-feet of rough lot grade As the site grading progressed, the compaction procedures were observed, and field density tests were made to determine the relative compaction of the fill in place. Field observations and field density test results indicate that the fill has been compacted to 90% or more of maximum and the limits of compacted fill have been recorded on a copy of the laboratory density. The approximate locations of field density tests grading plan for reference. The results of field density tests and of are given on the attached forms. relative compaction, expressed as a percent of maximum laboratory density, dry density, optimum moisture content, grain size distribution, plasticity Laboratory tests to determine moisture-density relationships, maximum characteristics, and strength and swell characteristics were performed on representative samples of the material used for fill. The results of laboratory tests are given on the attached forms. FINISH GRADE SOIL CONDITIONS During the grading operation certain lots were specially treated to provide a specified depth of selected soil at rough grade. Laboratory tests and visual inspection indicate that nonexpansive fill was placed within 2 feet of rough grade on all fill lots and fill portion of cut-fill lots. On Lots 2, 5, 6, 7, 22, 23 and 64 through 70, potentially expansive soil was excavated and replaced with nonexpansive fill to a depth of 2 feet below rough lot grade within the limits of the entire level lqt. A visual inspection of cut Lots 12 through 16, 45 and 46 at completion of grading indicates that potentially expansive soil is not evident at rough grade surface. - FOUNDATION RECOMMENDATIONS - ALL LOTS placed on nonexpansive undisturbed soil or nonexpansive properly compacted (1) Foundations for single or two-story residential structures fill may be designed for a bearing pressure of 2,000 psf (dead plus live lot grade. Footings should have.a minimum width of 12 inches. This loads) at a depth of 12 inches below compacted fill or undisturbed cut bearing pressure may be increased by one-third for loads that include wind or seismic forces. ' Ponderosa Homes, Inc. Project NO. 77-105-9F ' 14ay 16, 1977 Page 3 i (2) Structures that will not tolerate differential settlements should not be located within 5 feet of the top of a slope. Footings (such as foundations, swimming pools, concrete decks, walls, etc.) located closer than 5 feet from the top of a slope should be extended in depth until the outer bottom edge of the footing is 5 feet horizontally from the outside face of the slope. LIMITATIONS The elevations of compaction tests shown as finished grade (FG) tests correspond to the elevations shown on the grading plans for "Carlsbad Tract No. 73-29, (Carrillo Estates No. l)," dated February 22, 1977, and locations shown in this report are based on field surveys established prepared by Rick Engineering Company, San Diego, California. Elevations by others. Rough lot grade is defined as that grade set in the field by the grade checker from reference stakes established by the surveyor, and represents rough grade at the time we were inspecting the removal and replacement of expansive soils. Likewise, the depths of undercutting of expansive with the measurements made by and grades set by the contractor's grade soil and/or depths of placement of nonexpansive soil were in accordance checker. This report covers the fill placed under our observation during the well as the backfill in utility trenches located within 5 feet of a dates specified herein. Additional fill placed after these dates, as building and greater than 12 inches deep, or,any trench 5 feet or more from a building and in excess of 5 feet in depth, should be compacted with the earthwork specifications for the project. This office should under the observation of this office and tested to assure compliance be contacted at least 24 hours prior to backfilling operations. Utility service trenches within 5 feet of a building thatare perpendicular to the building footings and are less than 12 inches wide and less than 3 feet deep are not subject to this recommendation. The inspections of foundation preparation, types of materials and soil placement and compaction, as well as tests of compactionmade during the period of our services on the subject site, were in accordance with the local acceptable standards for this period. The conclusions or opinions drawn from the tests and site inspecti,ons apply only to our work with rwpPtt to grading, and represent'condi,tions at the date of our final in>pecti,pn. runuer'usa nuiiic'b, IIIC. ' Project No. 77-105-9F . May 16, 1977 Page 4 Woodward-CDyde Consultants We will accept no responsibility for any subsequent changes made to the site by others, or by uncontrolled action of water, or by failure of water. others'to properly repair damages caused by uncontrolled action of .WOODWARD-CLYDE CONSULTANTS Steven C. SCH/RPW/EHP/cl Attachements (4) Ponderosa Homes, Inc. - Solana Beach (2) Ponderosa Homes, Inc. - Irvine COMPACTION TEST RESULTS ,JOE NAYC CARRILLO ESTATES UNIl 1 DATE REronTED 3-1 6-77 JOB NUMBER 77-105-9F DATEsCovfREDFebruary 28 through March 15, 1977 PAGE 1 OF / 3 FEB 28 " - MAR 1 MAR 2 " MAR 3 " b1A.R 4 " MAR 7 " MAR 8 " " MAR 9 s1010.14.29 1 2 3 4 5 6 7 8 9 10 11 12 14 13 15 16 17 18 19 20 21 23 22 24 25 26 27 28 29 30 31 32 33 34 35 36 ' 37 38 39 LOT 139 141 140 1 38 29 LOT 29 '28 30 29 30 LOT 141 139 138 140 142 LOT 28 30 31 29 30 LOT 28 25 25 26 27 LOT 29 31 32 30 28 LOT 26 25 27 29 31 LOT 33 . 21 365 ' 365' 369' 369 ' 41 0' 413' 417' 41 6' 420' 420' ' 373' . 373' 377' 377' 37i I 424' 424 ' 428' 428' 431 ' 431 ' 426'~ 430' 431 ' 434' 434' 434' 437' 437' 437' - 437' 435' 440' 439 ' 440' 444' 442' 446' 450' 9.3 9.9 11.7 10.5 9.9 9.3 11.1 9.3 16.9 15.6 16.3 10.5 11.1 9.9 16.3 14.9 10.5 9.9 14.3 14.9 10.5 14.3 18.3 13.0 15.6 10.5 15.6 14.9 15.6 14.9, 14.3 15.6 15.6 14.3 14.9 13.0 15.6 14.9 10.5 115.2 113.6 114.4 117.5 115.0 115.9 117.0 115.7 112.8 108.6 107.6 114.2 114.1 115.3 108.4 109.2 115.5 116.1 107.1 108.1 114.2 110.0 102.2 110.7 107.2- 104.5 113.3 107.1 106.9 106.0 107.9 103.6 104.7 104.9 103 :2 106.0 104.5 103.0 114.2 125.5 125.5 125.5 125.5 125.5 125.5 125.5 125.5 117.0 117.0 117.0 125.5 125.5 125.5 117.0 125.5 117.0 125.5 125.5 117.0 125.0 112.0 117.0 117.0 117.0 112.5 125.5 117.0 117.0 117.0 117.0 112.0 112.0 112.0 91.7 90.4 91.3 93.6 91.6 92.3 93.2 92.0 96.3 92.8 92.0 91 .o 91.9 90.9 92.6 93.4 92.0 92.5 91.7 92.2 91.5 91.3 93.9 94.4 91.6 90.3 92.9 91.6 91.2 90.5 92.1 92.4 93.3 93.6 112.0 ~. 92.2 114.0 92.9 114.0 91.6 125.5 91.0 114.0 90.3 COMPACTION TEST RESULTS ,JOB NAME C,V?RlLLO ESTATES UNIT 1 DATE REPORTED 3-1 6-77 " MAR 9 40 LOT 21 454 I 9.9 116.1 125.5 92.5 MAR 10 41 42 " 43 44 45 MAR 11 46 47 " 48 49 50 'FtAR 12' 51 52 53 54 55 ~~ MAR 14 56 57 " 58 59 60 62 61 ' . 63 64 MAR 15 65 66 67 " 68 69 70 LOT 34 450' 12.3 107.1 114.0 94.0 35 452' 16.3 110.1 114.0 96.6 36 456' 12.3 104.0 114.0 91.2 36 460' 16.3 106.0 114.0 93.0 37 464' 14.9 104.1 114.0 91.3 LOT 59 59 58 26 27 LOT 49 49 49 49 49 LOT 20 19 314' 318' 321 ' FG 447.2' FG 443.6' 356' 365' 360' 370' 374' 11.1 9.9 14.9 18.3 18.3 11.1 9.9 10:5 10.5 9.9 461 ' 458' 14.3 13.0 21 461 ' 10.5 50 477' 49 16.3 480' 13.6 20 464' 28 FG 442.1 ' 13.6 29 18.3 FG 441 .O' 30 FG 440.9' 19.0 18.3 115.9 114.0 107.8 104.1 103.9 114.1 115.1 ~ ~~ 116.1 115.2 116.3 125.5 92.3 125.5 90.9 117.0 92.0 114.0 90.9 114.0 91.3 125.5 91.0 125.5 91.7 125.5 92.6 125.5 91.9 125.5 92.7 108.7 117.0 92.0 109.9 117.0 93.9 114.7 125.5 91.3 109.1 108.0 117.0 92.3 117.0 93.2 108.8 117.0 92.8 103.9 114.0 90.9 104.9 114.0 92.0 104.8 114.0 91.9 LOT 31 FG 442.0' 19.8 32 FG 445.6' 19.0 104.2 114.0 91.5 104.2 114.0 91.4 33 FG 449.5' 18.3 103.8 114.0 90.9 34 FG 454.1 ' 18.3 103.9 114.0 91.0 35 36 FG 459.3' FG 464.5" 18.9- 103.9 114.0 91.0 ~~ 19.0 104.2 114.0 91.5 COMPACTION TEST RESULTS ' Jom NAME CARRILLO ESTATES UNIT NO. 1 DATE REPORTED 3-23 77 JOB NUMSLR 77-105-9F 1 DATES COVERED March 16 through March 19, 1977 PACE or 3 MTI NVYBE" nsr "0l.T""' .,I- LOC*TIOY CL~.YAIIO" SDYIINI UBDIIAIORV RCLITIY~, . D"" rr. O="*,,V ?c, 0m.ln CDYCICTIOY I.-IT.T or OF IT*, rcc x 0. LL.. OW.. MARCH 16 71 72 73 74 75 76 .~ MARCH 17 77 78 79 80 81 83 82 MARCH 18 84 85 86 87 89 88 90 91 92 93 MARCH 19 94 95 96 97 98 99 100 101 102 LOT 48 LOT 50 LOT 48 LOT 49 LOT 19 LOT 38 LOT 37 LOT 38 LOT 20 LOT 18 LOT 137 LOT 139 LOT 141 LOT 138 LOT 140 LOT 142 LOT 135 LOT 137 LOT 139 LOT 141 LOT 17 LOT 19 LOT 39 LOT 21 LOT 20 LOT 19 LOT 18 LOT 17 LOT 37 LOT 38 LOT 39 LOT 40 484 ' 484' 488 ' 466' 466' 468 ' 470' 469 ' 469 ' 380 ' 380' 380' 384 ' 384 ' 384 ' 388' 388 ' 388 ' 388' 472' 472' 474' FG 466.9' FG 471.6' FG 474.7' FG 475.4' FG 469.9' FG 476.4' FG 471.9' FG 476.5' FG 476.3' 488 ' 13.0 13.0 12.3 12.3 11.7 13.6 13.0 13.0 13.0 14.3 9.9 9.3 9.9 14.9 12.3 13.6 14.9 13.0 13.6 12.3 14.3 13.0 14.9 19.0 19.0 18.3 19.0 19.6 18.3 19.6 18.3 19.0 - 105.7 106.0 107.8 105.5 106.0 106.7 105.7 105.0 106.9 105.0 114.8 115.0 115.9 106.2 106.0 107.9 105.7 107.0 105.8 106.6 108.7 105.0 105.0 104.1 103.5 104.7 104.1' 104.7 104.2 103.1 104.0 103.6 117.0 117.0 117.0 114.0 117.0 114.0 11 11' 11' 11 12 12 12 4.0 4.0 4.0 4.0 5.5 5.5 5.5 117.0 117.0 117.0 117.0 117.0 117.0 117.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 90.2 91.2 90.5 90.1 93.0 93.5 92.5 92.0 93.6 92.0 91.2 91.5 92.2 90.6 90.8 92.2 90.3 90.4 91.5 93.5 92.8 92.2 92.2 91.3 91.8 90.6 91.5 91.7 91.5 91.2 90.5 90.8 COMPACTION TEST RESULTS JOBNAME CARILLO ESTATES UNIT 1 JOB NUMBER 77-105-9F I DATE*COVERED February 28, through March 24, 1977 107.0 117.0 91.5 MAR 21 103 1 04 " LOT 65 '. 388' 13.0 LOT 133 3821 9.9 LOT 131 366' 10.5 LOT 132 378' 9.9 LOT 134 390' 13.6 LOT 136 390' 14.9 LOT 140 390' 12.3 LOT 138 390' 12.3 117.0 125.5 93.2 _. 115.8 125.5 92.2 105 114.0 109.0 109.2 108.9 108.8 108.5 108.0 125.5 118.0 118.0 118.0 118.0 117.0 118.0 90.9 92.2 108 109 110 92.3 92.5 92.1 91.9 91.5 90.5 90.0 94.4 MAR 22 111 112 114 113 " LOT 142 390' 12.3 LOT 65 LOT 141 391 ' 394 ' 394' 12.3 11.7 ,13.0 106.9 106.2 ~~ LOT 139 115 116 117 119 120 118 LOT 137 LOT 135 LOT 133 394' 394' 14.3 12.3 397 ' 14.3 13.0 397' 14.9 400' 14.3 403' 394' 14.9 398' 14.3 ,14.3 401 ' 13.0 387' 107.5 106.0 104.0 106.1 106.7 106.8 105.2 104.6 104.5 104.5 105.6 103.3 103.0 105.8 103.1 106.8 114.0 114.0 114.0 114.0 114.0 114.0 114.0 93.1 91.3 93.2 LOT 142 LOT 140 LOT 141 LOT 142 93.5 93: 6 92.4 93.3 93.4 93.4 93.7 92.6 90.7 90.3 90.4 92.6 MAR 23 121 122 123 124 " LOT 3 LOT 2 112.0 112.0 LOT 3 112.0 114.0 114.0 114.0 114.0 114.0 114.0 125 LOT 2 LOT 4 LOT 142 405' 405' 13.0 13.6 FG 405.4' 19.0 126 127 128 LOT 141 LOT 140 LOT 139 FG 403.1' FG 398.9' 20.2 FG 396.4' 19.0 18.3 129 130 MAR 24 131 133 " LOT 138 FG 395.4' 132 LOT 137 FG 395.7' 19.8 19.0 1 34 LOT 136 FG 396.2' LOT 135 FG 396..3' 20.2 19.0 L 104.0. 114.0 91.3 106.0 114.0 92.9 104.0 114.0 91.3 105.0 114.0 92.1 COMPACTION TEST RESULTS JonN*ML CARILLO ESTATES UNIT 1 DATE REPORTEDMAY 16, 1977 JOB NUMBER 77-105-9F I DATESCOVERED MARCH 25, THROUGH APRIL 5, 1977 PAGE 1 or 4 MAR 25 MAR 28 M4R 29 MAR 30 MAR 31 APR 1 APR 4 APR 5 135 136 137 138 139 140 141 142 143 144 145 146 147 1 48 1 49 150 151 152 153 154 155 156 158 157 159 160 161 162 163 164 165 166 167 168 170 169 171 172 LOT 3 LOT 64 LOT 63 LOT 66 LOT 65 LOT 4 LOT 58 LOT 59 LOT 49 LOT 50 LOT 125 LOT 126 LOT 125 LOT 126 LOT 58 LOT 57 LOT 59 LOT 58 LOT 57 LOT 57 LOT 59 LOT 58 LOT 59 LOT 108 LOT 109 LOT 107 LOT 109 LOT 59 LOT 57 LOT 58 LOT 56 LOT 48 LOT 50 LOT 49 LOT 51 LOT 57 LOT 59 LOT 48 408' 402 ' 13.0 13.6 395' 394' 13.6 14.9 FG 397.8' 14.3 412' 14.9 326 ' 14.3 330 ' 15.6 393' 14.9 393' 15.6 250 ' 13.0 255' 260' 14.3 14.3 265' 335 ' 15.6 340 ' 16.3 15.6 340 ' 344 14.3 14.9 344' 13.0 348' 348' 13.6 14.9 352 ' 352 ' 13.6 15.6 250' ' 14.3 255 ' 14.9 260' 14.9 260' 14.3 356 ' 15.6 356 ' 16.3 360 ' 15.6 360 ' 14.9 398' 398' 13.0 13.0 402 ' 13.6 402 ' 364' 13.6 14.9 364' 13.0 406 ' 13.6 103.5 106.0 104.8 104.3 103.3 104.0 104.0 103.9 103.9 105.1 106.9 105.9 105.5 105.5 104.2 105.7 104.5 106.2 105.8 105.0 105.5 105.2 106.5 105.7 104.3 104.7 106.1 105.0 103.2 105.1 104.0 107.5 107.1 106.5 105.9 105.3 105.5 104.8 114.0 114.0 114.0 114.0 114.5 114.0 114.0 114.0 114.5 114.5 114.5 114.0 114.0 114.0 114.5 114.5 114.5 114.5 114.5 114.5 114.5 114.5 114.5 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 90.7 93.0 92.0 91.6 90.3 91.3 91.3 91.2 90.6 93.2 92.0 92.7 92.5 92.. 5 91.1 92.2 91.3 92.9 92.3 92.1 91.7 91.9 93.0 92.6 91.6 91.7 93.2 92.1 90.5 92.2 91.3 94.4 94.0 92.8 93.5 92.5 92.7 91.8 COMPACTION TEST RESULTS JOE NAME CARILLO ESTATES UNIT 1 DATEREPORTED MAY 16, 1977 JOE NIJMELR 77-105-9F I DATESCOVERED APRIL 5, THROUGH APRIL 14, 1977 PAGE 2 Or4 APR 5 APR 6 APR 7 APR 8 __ APR 11 APR 12 APR 13 APR 14 173 174 1 75 1 76 177 178 179 180 182 181 183 184 185 186 188 1 87 189 190 191 192 193 194 195 196 198 197 199 200 201 202 203 204 205 206 207 208 209 210 LOT '50 LOT 2 LOT 3 LOT 4 LOT 5 LOT 6 LOT 7 LOT 23 LOT 22 LOT 23 LOT 22 LOT 23 LOT 49 LOT 51 LOT 48 LOT 50 LOT 49 LOT 51 LOT 52 LOT 56 LOT 58 LOT 57 LOT 59 LOT 48 LOT 50 LOT 52 LOT 49 LOT 51 LOT 56 LOT 55 LOT 58 LOT 57 LOT 59 LOT 48 LOT 50 LOT 52 LOT 49 LOT 51 406 ' FG 407.4' FG 411 .O' FG 414.7' FG 415.1' FG 415.0' FG 413.8' 438' 444' 441 ' FG 447.2' FG 444.0' 410' 410' 41 4' 41 4' 418' 418' 418' 368' 368' 372' 372' 422 ' 422' 422 ' 426 ' 426 ' 376' 376'. 380 380' 380 ' 430' 430 ' 430 ' 434' 434' 12.3 13.6 13.6 14.9 14.3 13.6 14.3 13.6 14.3 13.0 14.9 16.3 14.3 13.6 13.0 14.9 15.6 13.0 14.3 15.6 16.3 14.9 14.9 15.6 15.6 13.0 15.6 13.6 14.3 14.3 13.6 14.3 14.9 14.3 14.3 14.3 16.3 15.6 104.0 107.0 105.0 104.3 106.9 104.0 107.0 105.1 105.1 106.6 104.3 104.8 104.2 107.0 105.9 105.5 105.8 107.9 106.2 106.7 104.7 107.6 106.2 106.9 104.0 108.0 105.1 109.4 107.7 108.6 106.9 107.0 107.6 106.0 106.8 107.5 105.7 107.0 114.0 114.5 114.5 114.5 114.5 114.5 114.5 114.5 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.0 114.5 114.5 114.5 114.5 114.5 114.5 114.5 118.0 118.0 114.5 114.5 114.5 114.5 114.5 114.0 114.0 114.0 91.2 91.7 93.5 91.1 93.3 91.0 93.5 91 .8 92.2 93.4 91.4 91.6 91.3. 93.9 92.9 9 2 .'4 92.7 94.5 93.3 93.4 91.7 93.9 92.7 93.4 91 .o 94.4 91.7 95.5 91.2 92.0 93.3 93.4 94.0 92.6 93.2 94.0 92.6 93.9 COMPACTION TEST RESULTS JOB NAME CARILLO ESTATES UNIT 1 DATE REPORTED MAY 16, 1977 JOB NUMBER 77-105-9F DATEsCOVERED APRIL 15, THROUGH APRIL 28, 1977 1 PAGE 3 or 4 " APR 15 APR 18 APR 19 APR 20 APR 21 APR 22 APR 25 APR 26 APR 27 APR 28 21 1 212 213 21 4 215 216 217 21 8 219 2 20 221 222 223 224 225 2 26 227 228 229 230 231 232 233 234 235 237 236 238 239 2 40 241 2 42 243 244 245 LOT 58 LOT 56 LOT 55 LOT 57 LOT 59 LOT 48 LOT 52 LOT 50 LOT 63 LOT 62 LOT 56 LOT 58 LOT 10 LOT 47 LOT 49 LOT 51 LOT 55 LOT 57 LOT 10 LOT 59 LOT 48 LOT 50 LOT 49 LOT 47 LOT 48 LOT 47 LOT 58 LOT 56 LOT 54 LOT 9 LOT 63 LOT 60 LOT 62 LOT 61 LOT 64 ' 384' 384 ' 388' 388' 388' 438' 438' 407 ' 438' 410' 392 ' 392 ' 392 ' 442' 442' 442 ' 396 ' 396 ' 396 ' 396 ' 446 ' 446' 450 ' 450 ' 453' 456 ' 400 ' 400 ' 400 ' 400 ' FG 413.3' FG 411.4' FG 413.5' FG 414.4' FG 400.9' 13.0 14.9 14.9 13.6 13.6 14.9 13.0 13.6 13.0 13.6 13.6 13.0 14.3 13.6 12.3 13.0 12.3 13.6 14.3 14.3 13.6 13.0 13.0 14.9 13.6 13.0 12.3 13.0 13.6 13.6 14.3 13.0 14.3 13.0 13.0 109.9 106.7 106.6 108.7 109.3 106.9 110.3 107.7 106.3 105.7 107.1 107.8 106.1 106.1 109.2 108.8 108.3 107.2 107.0 107.5 109.9 109.0 108.7 107.3 107.1 107.8 110.3 108.9 107.5 108.6 107.3 104.0 108.1 108.0 1.04.7 118.0 118.0 118.0 118.0 118.0 11 8:o 118.0 118.0 114.5 114.5 114.0 114.0 114.0 114.0 118.0 118.0 118.0 118.0 114.5 114.5 118.0 118.0 118.0 118.0 118.0 118.0 118.0 118.0 118.0 118.0 114.5 114.5 114.5 114.5 114.5 92.9 90.3 90.2 92 .O 92.6 90.5 93.5 91.2 93.0 92.4 94.0 94.4 93.1 93.1 92.6 92.1 91.8 90.8 93.5 93.5 93 .O 92.4 92.0 91 .o 90.8 91.2 93.5 92.1 91.1 91.9 93.7 I 90 .7 94.5 94.4 91.4 COMPACTION TEST RESULTS JOB NAME CARILLO ESTATES UNIT 1 DATE REPORTED MAY 16, 1977 JOB NUMBER 77-105-9F DATEBCOVERED APRIL 28, .THROUGH MAY 2, 1977 PAGE OF I APR 28 246 LOT 66 FG 396.1' 13.6 105.6 114.5 92.2 APR 29 247 ;'248 2 49 250 MAY 2 251 252 253 LOT 67 LOT 68 FG 395.4' 14.3 104.5 114.5 91.2 FG 395.7' 14.3 104.5 114.5 91.2 LOT 69 LOT 70 FG 396.0' 14.9 105.0 114.5 91.8 FG 396.0' 13.6 107.7. 114.5 94.0 LOT 52 FG 443.8' 14.9 102.3 111.5 91.7 LOT 51 FG 448.6' 13.0 105.1 LOT 50 111.5 94.3 FG 452.6' 15.6 102.0 111.5 91.5 254 LOT 49 FG 455.1' 14.9 101.3 111.5 90.9 255 256 LOT 48 ~ ~~ FG 456.6' 16.3 LOT 47 FG 458.2' 16.3 102.9 111.5 92.2 ~ ~ ~~ 100.9 111.5 90.6 c JOB NAME CARILLO ESTATES UNIT COMPACTION 1 JOE NUMBER 77-105-9F (Stormdrain Backfill) DATESCOVEREDAP~IL 26, 1977 TEST RESULTS DATE REPORTED My 16, 1977 I APR 26 SD-1 BETWEEN LOTS 29 & 30.. 138.0' 16.9 114.0 COMPACTION TEST RESULTS Jon NAME CARILLO ESTATES UNIT 1 DATEREPORTED May 16, 1977 NUMBER 77-105-9F (Sewer Trench Backfill) / D*TE~COVERED APRIL 26, 1977 PAGE sw-1 oSw-1 -*E WVYBE" n.T Ilv3C.T LOCATlOY "OISNII VI" U.0llml.r LLEY*.rIOW SO*TIN7 "ILATIYI DIN.ITV D.Y.lTY coYPIcTIou " 0. or 7I.T !4 DL, rr. rc, K, x 01 U.. DLI'I. SURFACE APR 26 SW-1 SOCCORRO LN STA 35+75 -1' 13.0 104.7 112.0 93.4 sw-2 SOCCORRO LN STA 30+90 -1' 3.6 103.5 114.0 90.7 sw-3 SOCCORRO LN SEWER LAT -1' 14.3 102.7 114.0 90.0 OPP LOT 21 1% 14C 13C 12c 11c 1 oc 9c 80 PLASTICITY CHARACTERISTICS 1 2 3 Liquid Llrnit. % SC CH NP Classification System Plasticity Index, % Classification by Unified Soil 39 58 __ 15 16 - I ZERO AIR VOIDSCURVES I I I I I I , 0 COBBLES I rn , GiidVLLl SAND 100 80 2 60 I- E 40 0 ce E 20 1000 100 10 1.0 0.1 0.01 0.001 0 GRAIN SIZE. mm I~ FILL SUITABILITY TESTS I CARILLO ESTATES UNIT 1 DRAWN BY: I+ilK CHECKED BY&/ PROJECTNO: 77-1 05-9 I DATE: 3-16-77 I FIGURENO 1 WOOOWARO-CLYDE COriSULTAHTS iooo 100 10 1.0 0.1 0.01 0.001 GRAIN SIZE, mm MECHANICAL ANALYSIS I DIRECT SHEAR TEST DATA I I I I Dry Density, pcf I103 I I 1 Initial Water Content, % Final Water Content, % Apparent Cohesion. psf PLASTICITY Ct{kRACTERISTICS COBBLES I GRA{EL I I SILT 6 CLAY , Liquid Limit. ',% Plasticity Index. % Classification by Unilied Soil Classification System ZERO AIR VOIDSCURVES SAMPLE LOCATION 40 LABORATORY COMPACTION LABORATORY COMPACTION TEST TEST METHOD:ASTMD. 1557-70A FILL SUITABILITY TESTS CARRILLO ESTATES UNIT 1 ' DRAWN BY: ~~YJIA I CHECKED BY& I PROJECT NO: 77-1 05-9F 1 DATE: 3-16-77 I FIGURENO 1 WOODWARD-CLYDE CONSULTANTS 150 14C 130 12c 11c 1 oc 9E ac PLASTICITY CHARACTERISTICS Liquid Limit, % Plasticity Index. % Classification by Unified Soil classification System ZERO AIR VOIDS CURVES 1000 100 10 1.0 0.1 0.01 0.001 GRAIN SIZE, mm MECHANICAL ANALYSIS 10 20 30 40 LABORATORY COMPACTION LABORATORY COMPACTION TEST TEST METHOD:ASTI'~D 1557-70A FILL SUITABILITY TESTS CARILLO ESTATES UNIT 1 1 DRAWN8Y:dI CHECKEDEY: EIiPI PROJECTNO: 77-105-qF I DATE: 5-12-77 I FIGURE NO: 1 PLASTICITY CtiARACTERISTICS GRAVCL SAND COBBLES I , IC, I , SILT & CLAY Llquid Limit, Plasticity Indcx. % 28 Clarsification%rUn!fied Soil Classification System ML 34 100 z 80 a -9 n a 60 ZERO AIR VOIDS CURVES GRAIN SIZE, rnrn MECHANICAL ANALYSIS DIRECT SHEAR TEST DATA 6 Dry Density. pcf Initial Water Content, % Final Water Content. % Apparent Cohesion. psi 40 LABORATORY COMPACTION LABORATORY COMPACTION TEST TESTMETHOD: ASTI! I- D 1557-70 t? FILL SUITABILITY TESTS CPFII I n F~S r.10 1 DRF.K.N6Y:M& I CWiCKEDBY: EItP 1 PROJECTh10:77-105-~F I DATE: 5-12-77 FIGURENO 2 WOODkVARD-CLYDE COHSULTANTS