HomeMy WebLinkAboutCT 74-21; Carlsbad Crossroads Phase I; Soils Report; 1987-04-15IJr 2. 2% 50
/--
-
-
-
-
-
-
-
.-
SAN DIEGO GEOTECHNICAL CONSULTANTS, INC.
SOIL ENGINEERING 8 ENGINEERING GEOLOGY
ApriL 15, 1987
Ninteman Construction Company 1465 Morena Boulevard San Diego, California 92110
Attention: Mr. Mat Reno
Job No. 05-6983-001-00-10 Log No. 7-1418
SUBJECT: SOILS COMPACTION REPORT Precise Grading Completed - Building Pads Only Carlsbad Crossroads, Phase I Buildings A,B.C, and D Carlsbad, California
References: (1) San Diego Geotechnical Consultants, Inc., November 20. 1986, "Foundation Investigation, Carlsbad Oaks Business Center, Lots 3-6, Carlsbad, California," Job No. 30065-00
(2) San Diego Geotechnical Consultants, Inc., February 19, 1987, "As-Graded Geotechnical Report, Final Report of Mass Grading, Carlsbad Oaks Business Center, Carlsbad Tract 74-21, Carlsbad, California" Job No. 05-l 079-002-00-l 0
Gentlemen:
This report p~resents the results of our testing and observation
performed during precise grading at the above referenced site.
Field density test locations are shown on the Plot Plan, Plate 1.
test results are tabulated on Table I, "Results of Compaction
Tests."
The purpose of-the grading and compaction was to: (1) precise
grade the building pad and (2) perform remedial grading
overexcavation and moisture conditioning within the building pad
- area. ENGINEERING DEPT. LIBRARY City of Carlsbad 2075 Las Palmas Drive - . Carlsbad CA 92009-4859
6455 NANCY RIDGE DRIVE . SUITE 200 l SAN DIEGO, CALIFORNIA 92121 l (6191587-0250
-
-
-
-
-
-
.-
-
Ninteman Construction Company April 15, 1987 Job No. 05-6983-001-00-10 Log No. 7-1418 Page 2
1.0 PREVIOUS GRADING
The site consists of two previously rough graded lots within
the Carlsbad Oaks Business Center. The lots were rough
graded using the observation and testing services of San
Diego Geotechnical Consultants, Inc. The As-Graded
Geotechnical Report for the mass grading on this subject is
referenced above. Up to 55 feet of compacted fill was
placed during rough grading. The fill materials varied from
silty sands to clayey silts and clays. The contact between
fill and bedrock materials at the surface is shown on Plate
1.
2.0 OVEREXCAVATION OF BUILDING AREA
Due to the variable fill depths and transition conditions on
the site, individual recommendations were provided for each
building pad to address specific conditions. On all
buildings the upper two feet of the recompacted fill
material was moisture conditioned to at least five percent
over optimum moisture content during placement. Over-
excavation of the bedrock portion of the building pad was
performed as described in the following paragraphs. The
lateral extent of all overexcavations was five feet outside
of all footings.
2.1 Building A
The maximum depth of fill below Building A was
estimated at 11 feet. Because Building A was placed
across a cut-fill transition, the building area was
overexcavated to a depth of three feet below the bottom
of proposed footings. This resulted in a total depth
of excavation of five feet.
.
-
-
-
-
-
-
-
2.3 Buildings C and D
-
-
-
-
-
-
Ninteman Construction Company April 15, 1987
Job No. 05-6983-001-00-10 Log No. 7-1418 Page 3
2.2 Building B
The maximum expected depth of fill underlying
Building B was five feet. Because Building B also
crossed a cut/fill transition, cut materials were
removed to a depth of three feet below lowest adjacent
finish grade and replaced as a uniformly compacted
fill.
Since Buildings C and D were not placed over transition
areas, no overexcavation below footing elevation was
considered necessary. These two buildings were over-
excavated two feet below slab elevation to perform
moisture conditioning.
3.0 PREPARATION OF EXPOSED GROUND
The exposed subgrade soil in areas of the overexcavation was
scarified 8 to 12-inches, brought to near optimum moisture
conditions and compacted to at least 90 percent relative
compaction.
4.0 SOIL TYPES
The soils encountered during grading generally consisted of
silty sands and clays. During excavation for the eastern
portion of-,building A, very hard bedrock was encountered.
The ripping and removal of this material required the use of
a D8L Dozer. Oversized rock removed during grading was
broken down to less than 12-inch maximum diameter prior to
placement or stockpiled for later use in non-structural
.
-
-
-
-
.-
-
-
-
-
-
-
-
-
Ninteman Construction Company April 15, 1987 Job No. 05-6983-001-00-10 Log No. 7-1418 Page 4
areas. The soil types used as fill are tabulated in Table
11, "Laboratory Test Results." All fill materials were
derived from the area of overexcavation.
5.0 FILL PLACEMENT
Fill soils were placed in 6 to 8 inch lifts, brought to the
proper moisture content and compacted to a minimum of 90
percent of the maximum density as determined by ASTM
D1557-78. The equipment used for removal and recompaction
consisted of one John Deere 860 Scraper, one 613 Scraper,
one 126 Grader, one D6 Dozer, one D8L Dozer, and one 915
Trackloader with sheepsfoot drum compactor. Grading
operations were started and completed to fine grade during
the period covered by this report, March 26 to April 10,
1987.
Density tests were made in accordance with ASTM D2922-81
(Nuclear Gauge Method). Results of the density tests made
during the recompaction of the fill are tabulated in
Table I. Results of the maximum density and optimum
moisture determination of the various soils encountered are
tabulated in Table II, "Laboratory Test Results".
-
-
,-
.-
.-
.-
.-
.-
-
Ninteman Construction Company April 15, 1987
Job No. 05-6983-001-00-10 Log No. 7-1418 Page 5
6.0 CONCLUSIONS AND RECOMMENDATIONS
6.1 Compaction
Based on the results of the observations and testing
noted herein, it is our opinion that the grading and
compaction was performed in general accordance with our
recommendations and the requirements of the City of
Carlsbad.
6.2 Moisture Conditioning
The results of our testing and observations indicate
that the upper two feet of slab subgrade within
building areas have been moisture conditioned to at
least five percent over optimum moisture content. In
order to maintain this moisture content, periodic
sprinkling of the building pad is recommended. Prior
to construction, moisture testing should be performed
by the geotechnical consultant to confirm that moisture
conditions are as recommended.
6.3 Foundation and Slab Recommendations
6.3.1 General
The results of our testing and observation
indicate that the existing surface soils exhibit
a high to very high expansion potential (see
Reference). The following recommendations are
provided for the design of footings and slabs
based on the expansion potential of the soils
presently at the site. ,-
-,
..-
.-
.-
--
.-
~,-
-
.~-
Ninteman Construction Company April 15, 1987 Job No. 05-6983-001-00-10 Log No. 7-1418 Page 6
Our recommendations are considered generally
consistent with the Standards of Practice. The
potential for favorable foundation performance
can be further enhanced by maintaining uniform
moisture conditions throughout the Life of the
structure.
The footing configurations and reinforcement
recommendations herein should not be considered
to preclude more restrictive criteria by the
governing agencies or by structural consider-
ations. A Structural Engineer should evaluate
configurations and reinforcement requirements
for structural loadings, shrinkage and
temperature stresses.
6.3.2 Foundations
It is anticipated that a shallow foundation
should be suitable to support the proposed
structures. All footings for building should be
founded entirely in the recompacted fill. Based
on soil conditions, continuous footings should
be reinforced with at least two No. 5 bars
placed one at the top of the stemwall and one at
the bottom of the footing.
Footings should have a width of at least
12-inches, and should be founded at Least
24-inches below lowest adjacent finish subgrade.
Footings may be designed for an allowable dead
plus live load bearing pressure of 2,000 pounds
per square foot with a one-third increase for
..-
-
-
-
_
Ninteman Construction Company April 15, 1987 Job No. 05-6983-001-00-10 Log No. 7-1418
Page 7
short-term wind or seismic loads. Where footing
are located adjacent to utility trenches, they
should extend below a one-to-one plane projected
upward from the inside bottom corner of the
trench.
6.3.3 Slabs
We recommend that slabs be constructed a minimum
of four inches in actual thickness and be rein-
forced with at least 6x6/10-10 welded wire mesh
placed at mid-height of the slab. Actual design
of on-grade slabs may be based upon a modulus of
subgrade reaction of 200 pounds per cubic
foot. We recommend that slabs be underlain by
at least four inches of crushed rock or clean
washed sand to act as a capillary break. If a
moisture membrane is used, we recommend that it
be overlain by at least two inches of sand to
decrease the likelihood of curing problems.
6.3.4 Lateral Load Resistance
Lateral loads against buildings may be resisted
by friction between the bottom of footings and
the supporting soils. An allowable friction
coefficient of 0.30 is recommended. Alter-
natively, passive pressure equal to an
equivalent fluid weight of 215 pounds per cubic
foot acting against the footings may be used,
provided the footings are poured tight against
undisturbed soils. This value includes a factor
of safety of 1.5.
.-
.-
.-
.-
.-
__
,-
Ninteman Construction Company Job No. 05-6983-001-00-10 April 15, 1987 Log No. 7-1418 Page 8
6.3.5 Expected Settlement
For footings supported on the properly
recompacted fill and sized for the recommended
bearing pressures, total and differential
settlements are not expected to exceed one inch
and three-quarters of an inch, respectively.
6.4 Drainage
The performance of foundations is highly dependent upon
maintaining adequate surface drainage both during and
after construction. The ground surface around
structures should be graded so that surface water will
be carried quickly away from the building without
ponding. The minimum gradient within ten feet of the
building will depend upon surface landscaping. In
general, paved or lawn areas should have a minimum
gradient of five percent. Roof drains should he
carried across all backfilled areas and discharged at
least ten feet away from structures. Planters should
be constructed so that moisture is not allowed to seep
into the foundation areas or beneath slabs and
pavements.
6.5 Retaining Walls
The active earth pressure for the prevailing on-site
soil may be based on an equivalent fluid pressure of 40
pounds per cubic foot. The active earth pressure
should be used for retaining walls which are free to
yield at the top (unrestrained). For retaining walls
which are braced at the top, an equivalent fluid
pressure of 60 pounds per cubic foot should be used,
.
.,.~.
-
.-
.-
.-
_-
.-
-
.-
-
-
-
Ninteman Construction Company April 15, 1987 Job No. 05-6983-001-00-10 Log No. 7-1418 Page 9
based on the at-rest soil condition. The above values
should he modified to take into account any surcharge
loads, sloping backfill or other externally applied
forces.
Passive pressures used for design of retaining walls
were presented previously in Section 6.3.4, "Lateral
Load Resistance."
6.6 Trench Backfill
Utility trench and/or wall backfill consisting of the
on-site material types should be placed by mechanical
compaction to a'minimum of 90 percent of the laboratory
maximum density.
6.7 Foundation Observations
6.8
All excavations should be observed by the geotechnical
consultant prior to placement of forms, reinforcement
or concrete, for verification of conformance with the
intent of these recommendations. All excavations
should be trimmed neat, level, and square. All loose
or sloughed material should be removed prior to the
placement of concrete. Materials from footing
excavations should not be spread in slab-on-grade areas
unless compacted to a minimum relative compaction of
go-percent.
Reactive Soils
The results of sulfate testing performed on soils
obtained in our borings indicate that Type 11 cement
should be used for concrete which will he in contact
-
-
-
-
Ninteman Construction Company April 15, 1987 Job No. 05-6983-001-00-10 Log No. 7-1418 Page 10
with the on-site soils. Results of these sulfate tests
are included in Table B-3.
6.9 Temporary Excavations
Temporary construction excavations may be made
vertically without shoring to a depth of 5 feet below
the adjacent surrounding grade. For deeper cuts, the
slopes should be properly shored or sloped back at
least 1 :l (horizontal:vertical) or flatter. The
exposed slope face should be kept moist (but not
saturated) during construction to reduce local
sloughing. No surcharge loads should be permitted
within a horizontal distance equal to the height of cut
from the toe of the excavation unless the cut is
properly shored. Excavations that extend below an
imaginary plane inclined at 45 degrees below the edge
of any nearby adjacent existing site facilities should
be properly shored to maintain the foundations support
of the adjacent structure. All excavations and shoring
systems should meet the minimal requirements given in
Article 6 of the State of California Occupational
Safety and Health Standards.
7.0 SUMMARY
Our description of grading operations, as well as
observations and testing services herein, have been limited
to those grading operations performed between March 23, and
April 10, 1987. No representations are made as to the
quality or extent of materials not observed, or for any
subsequent changes made to this site.
Ninteman Construction Company April 15, 1987 Job No. 05-6983-001-00-10 Log No. 7-1418 Page 11
Elevations and test locations noted in the attached Table I
and Plate 1 are estimated from field surveys done by
others. Based upon our observations and testing, it is our
opinion, as aforementioned, that the work performed has been
accomplished in accordance with our recommendations as well
as the requirements of the regulating agencies. This report
should be considered subject to review by the controlling
authorities.
Professional judgements represented in this report are based
partly on our evaluations of the technical information
gathered, our understanding of the proposed construction,
and our general experience in the geotechnical field. Our
engineering work and judgments rendered meet or exceed the
standard of care of our profession at this time. No other
warranty, expressed or implied, is made as to the
conclusions and professional advice included in this report.
.~-
.-
_-
.~-
.-
_-
..-
-.
Ninteman Construction Company April 15, 1987 Job No. 05-6983-001-00-10 Log No. 7-1418 Page 12
The opportunity to be of service is appreciated. If you have any
questions, please call.
Very truly yours,
SAN DIEGO GEOTECHNICAL CONSULTANTS, INC.
Erik 3. Nelson Staff Engineer
LfJJJk W. Lee Vanderhurst, C.E.G. 1125 Reeistration Ex Chyef Geologist'
Regist;ati& Expires: 3-31-91 Chief Engineer
EJN:WLV:AFB:m,pb
Attachments: Plot Plan, Plate 1 Tables I and 11
Distribution: (6) Addressee
TABLE I
RESULTS OF COMPACTION TESTS
05-6983-
08 NO.: 001 -00-10 NAME: Carlsbad Crossroads DATE: April 87
MOISTURE UNIT DRY EST NO. DATE RELATIVE EfEyATTy;N COW$NT “;p”c”:;Y COMPACTION so’L
(96) TYPE
1 03-26-87 367.5 19.4 103.2 91 1
2 03-26-87 368 19.1 102.6 90 1
3 03-26-87 367 24.0 95.8 92 2
4 03-26-87 367 20.4 101.8 87 3 Retest on #5
5 03-26-87 367 19.1 105.5 90 3
6 03-26-87 368 19.5 102.8 90 1
7 03-26-87 368 19.0 104.1 91 1
a 03-30-87 369 24.2 95.1 92 2
9 03-30-87 369 24.5 94.5 91 2
10 03-30-87 370 21.8 99.5 87
2
1 Retest on /I12
11 03-30-87 370 19.8 102.2 90 1
12 03-30-87 370 20.4 102.5 90 1
13 03-30-87 369 25.0 95.7 92 2
14 03-30-87 370 24.5 97.2 94 2
15 04-01-87 371 17.5 104.5 92 1 Retest on F23
16 04-01-87 371 17.6 105.3 93 1 Retest on f/24
17 04-01-87 370.5 17.0 105.9 93 1 Retest on #34
18 04-01-87 371 18.1 102.5 90 1
19 04-01-87 370 18.5 103.3 91 1
20 04-01-87 370 17.9 102.8 90 1
21 04-01-87 369 19.1 106.1 91 3
22 04-02-87 371.5 18.0 104.3 90 3
23 04-02-87 371.5 19.3 102.7 90 1
24 04-02-87 371.5 19.0 103.8 91 1
25 04- 12-87 371.6 19.6 102.6 90 1
26 04-02-87 369 19.5 103.4 91 1
27 04-02-87 368 19.7 107.1 90 4
28 04-02-87 370 19.2 104.1 90 3
29 04-02-87 368 18.4 102.5 90 1
30 04-02-87 369 19.3 103.6 91 1
31 04-02-87 369 19.1 100.5 88
2. :
Retest on H32
32 04-02-87 369 16.9 105.3 93
33 04-02-87 370 18.7 107.4 92 3
34 04-02-87 370.8 19.2 106.2 91 3
35 04-02-87 370 20.2 102.2 90 1
36 04-03-87 a~368 19.3 103.5 91 1
37 04-03-87 368 19.4 104.1 92 1
38 04-03-87 369 18.9 105.4 90 3
SEE PLAN FOR TEST LOCATIONS
‘SAND-CONE TEST, ALL OTHERS NUCLEAR DENSITY TESTS
‘TEST FAILED, SEE RETEST
SAN DIEGO GEOTECHNICAL CONSULTANTS. INC.
-
.-,
~~.
.~-
.~~.
..-
,~-
-
-
-
-
-
TABLE I
RESULTS OF COMPACTION TESTS
05-6983-
OS NO.:- - - NAME: cn l-l..&
EST NI
39 )4-03-B' 370 19.4 103.4 91 1
40 )4-03-8' 370 19.9 102.4 90 1
41 )4-03-B. 370 19.5 106.3 91 3
42 14-03-B 369 18.8 107.0 92 3
43 )4-07-8. 367 14.9 109.8 92 4
44 14-07-B 368 15.4 110.1 92 4
45 )4-07-B' 367 15.6 106.4 91 3
46 14-07-8 368 13.7 107.5 90 4
47 14-07-B' 368 14.7 107.0 90 4
48 14-07-B 369 19.4 102.5 90 1
49 14-07-B' 369 18.7 103.7 91 1
50 14-08-B 370 19,l 103.5 92 1
51 14-08-B' 370 25.6 97.6 94 2
52 14-08-B 370 28.6 94.5 91 2
53 14-08-B 364 17.4 115.4 97 4
54 14-08-B 364 18.3 107.2 90 4
55 14-08-B' 366 20.2 105.2 93 1
56 14-08-B 366 19.7 104.0 92 1
57 14-10-8' 372 18.6 106.3 94 1
58 14-10-B 372 ,19.3 101.9 90 1
59 14-10-B 372 18.9 106.9 93 1
DATE DEPTH/ iLEVATl0
hOISTlJF
CoxT:N
UNIT OR’ OENSIT’ (PCF)
Cl-OSSrO< . _
RELATIVE :OMPACTIO
(%)
SEE PLAN FOR TEST LOCATlONS
SAND-CONE TEST. ALL OTHERS NUCLEAR DENSITY TESTS
TEST FAILED, SEE RETEST
- -
SOlI rypi -
-
ATE: April 87
SAN OIEGO GEOTECHNICAL CONSULTANTS. INC.
.-
TABLE II
LABORATORY TEST RESULTS
05-6983-001-00-10
OS NO.: NAME: Carlsbad Crossroads
SOIL TYPE CLASSIFICATION
1 Light silty SAND gray green
2 Black to medium brown silty CLAY
3 Medium greenish brown silty CLAY
4 Light brown silty SAND orange
DATE: April 1987
MAXIMUM OPTIMUM
“:E::y MOISTURI (%)
113.5 13.5
103.4 19.2
116.5 12.9
118.9 13.2
SAN OlEGO GEOTECHNLCAL CONSULTANTS, IN<