HomeMy WebLinkAbout; ; 1988 CAPITAL IMPROVEMENT PLAN FY 88-89; 1988-06-29COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Fiscal Year 1988-89
Adopted June 29,1988
Board of Directors
Margaret J. Bonas, President
E J. Woodward Jr., Vice Pres. John P. Henley, Secretary
Fred W. Maerkle, Treasurer Susan M. Haasl, Asst. Sec./Treas.
Managerial Staff
Robert J. Greaney, Gen. Mgr./Dist. Eng. Geoffrey A. Poole, Admin. Mgr.
Kurt B. Musser, Superintendent F. Jerry Whitley, Eng. Super.
Fiscal Year 1988-89 Capital Improvement Plan
Table of Contents
Section Page No.
Master Planned Projects
Summary of Proposed Projects 1988-2008 -1-
Estimated Yearly Expenditures -2-
Reservoir Projects
Summary of Projects and Cost Allocations -3-
Estimated Yearly Expenditures -4-
1988-89 Project Descriptions -6-
Pipeline Projects
Summary of Projects and Cost Allocations -9-
Estimated Yearly Expenditures -10-
1988-89 Project Descriptions -12-
Projects Beyond 1988-89 -17-
Operations Projects
Summary of Projects and Cost Allocations -18-
Estimated Yearly Expenditures -19-
1988-89 Project Descriptions -20-
Non-Master Planned Projects
Summary of Projects and Cost Allocations -22-
1988-89 Project Descriptions -23-
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Summary of Proposed Projects,
Cost Estimates and Allocations
1988 - 2008
Project
Reservoirs
Pipelines
Operations
Total
/
M.F.C.*
$18,400,000
9,192,111
2,510,200
$30,10^311
All Projects
-Funding Som
Cap. Sur.*
$ 660,000
1,660,719
1,243,600
$ 3,564,319
City Res.*
$ 4,240,000
3,150,575
0
$ 7,390,575
Total
$23,300,000
14,003,405
3,753,800
$41,057,205
*Funding Sources:
MJF.C. - (Major Facilities Charge) Fee Paid by New Development
Cap. Sur. - (Capital Surcharge) Portion of the Water Rate to Pay for Facility Replacement
City Res. - (City Reserves) Funds Incumbered for Rehabilitation Projects to Water Users in the
"Original City Service Area".
-1-
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Schedule of Entire Master Planned Project List
and Estimated Yearly Expenditures
Projects 1988-89
Reservoirs
Pipelines
Operations
Total Cost Est.
Funding Source
M. F. C.
Capital Surchg.
Citv Reserves
Total
$ 5,950,000
4,019,880
2.057.690
$12,027,570
$ 7,954,810
1,203,480
2.869.280
$12,027,570
Fiscal Year
1989-90 1990-91
$ 2,400,000
493,957
57.690
$ 2,951,647
$ 2,926,267
25,380
0
$2^51,647
$ 0
479,591
177.690
$ 657,281
$ 511,901
145,380
0
$ 657,281
1991-92
$ 0
172,103
537.690
$ 709,793
$ 204,413
505,380
0
$ 709,793
1992-93
$ 0
57,190
57.690
$ 114,880
$ 89,500
25,380
0
$ 114,880
5Yrs.
1993-98
$10,350,000
8,208,784
288.450
$18,847,234
$12,983,483
2,038,619
3.825.132
$18,847,234
10 Yrs.
1998-08
$ 4,600,000
571,900
576.900
$ 5,748,800
$ 5,495,000
253,800
0
$ 5,748,800
Total
1988-08
$23,300,000
14,003,405
3.753.800
$41,057,205
$30,165,374
4,179,419
6.694.412
$41,057,205
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
fiscal Year 1988-89
Reservoir Projects
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
List of Master
Cost Esti
/
Reservoir
Squires
Evans Point
"D" Expan. I
Santa Fe HI
La Costa H
"D" Expan. H
Total
\
M.F.C.
$ 5,600,000
700,000
3,000,000
4,500,000
600,000
4,000,000
$18,400,000
Planned Rese
mates and A1J
1988-2008
Funding Som
Cap. Sur.
$ 660,000
0
0
0
0
0
$ 660,000
rvoir Projects,
ocations
City Res.
$ 3,740,000
500,000
0
0
0
0
Total
$10,000,000
1,200,000
3,000,000
4,500,000
600,000
4,000,000
$ 4,240,000 $23,300,000
-3-
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Schedule of Master Planned Reservoir Projects
and Estimated Yearly Expenditures
Reservoir
Project
Squires
Funding Source
M. F. C.
Capital Surchg.
Citv Reserves
Total
Evans Point
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
"D" Expan. I
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
1988-89
$4,150,000
$ 2,324,000
290,500
1.535.500
$ 4,150,000
$ 1,200,000
$ 700,000
0
500.000
$1,200,000
$ 600,000
$ 600,000
0
0
$ 600,000
Fiscal \
1989-90
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 2,400,000
$ 2,400,000
0
0
$ 2,400,000
'ear
1990-91
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ o
1991-92
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
1992-93
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
5Yrs.
1993-98
$ 5,850,000
$ 3,276,000
409,500
2.164.500
$ 5,850,000
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
10 Yrs.
1998-08
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
Total
1988-08
$10,000,000
$ 5,600,000
660,000
3.740.000
$10,000,000
$ 1,200,000
$ 700,000
0
500.000
$1,200,000
$ 3,000,000
$ 3,000,000
0
0
$ 3,000,000
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Schedule of Master Planned Reservoir Projects
and Estimated Yearly Expenditures
Reservoir
Project
Santa Fe III
Funding Source
M. F. C.
Capital Surchg.
Citv Reserves
Total
La Costa II
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
"D" Expan. II
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
1988-89
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ o
$ 0
$ 0
0
0
$ 0
Fiscal \
1989-90
$ 0
$ 0
0
0
$ o
$ 0
$ 0
0
0
$ o
$ 0
$ 0
0
0
$ o
'ear
1990-91
$ 0
$ 0
0
0
$ o
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ o
1991-92
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ o
$ 0
$ 0
0
0
$ o
1992-93
$ 0
$ 0
0
0
$ o
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
5Yrs.
1993-98
$ 4,500,000
$ 4,500,000
0
0
$4,500,000
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ o
10 Yrs.
1998-08
$ 0
$ 0
0
0
$ o
$ 600,000
$ 600,000
0
0
$ 600,000
$ 4,000,000
$ 4,000,000
0
0
$4,000,000
Total
1988-08
$ 4,500,000
$ 4,500,000
0
0
$4,500,000
$ 600,000
$ 600,000
0
0
$ 600,000
$ 4,000,000
$ 4,000,000
0
0
$ 4,000,000
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$10,000,000
Revenue Percentage
of
Source Benefit
M.F.C. 56.0 %
C.S. 6.6
C.R. 37.4
/j i^i. / i^
i ''""' t[\ il
I/ti 1^ 1 t
_. I IO*«fI J 1 1 1
Project iQundgry [_ .
i
ARLSBAD .__!.
PROJECT LOCAT
PROJECT TITLE
Squires Reservoir
Scheduled Expenditures for 5 Year Period
1988-89
$2,324,000
237,900
1,552,100
. 1 • • . isif &'^•^y$&
•'ii } rf~\ ii
\ _M«Bllx '
V s*^*
—-;— +
i/' i
ION
1989-90
0
0
0
1990-91
0
0
0
DESCRIPTION: The firs
scheduled to begin with th
voir, chloramination facili
improvements will increas
gallons and provide unifoi
JUSTIFICATION: These
the existing Squires Reserv
lining and covering.
1991-92
0
0
0
t phase of the
e construction
ties and pump
e the usable si
m chlorinatioi
, facilities will
'oir to be take
SCHEDULING: Construction on the fii
begin during calendar year 1988.
1992-93
0
0
0
Cost
Beyond
1993
$ 3,276,000
386,100
2,187,900
JOB NO.
Total
Cost
Estimate
$5,600,000
660,000
3,740,000
improvements to the Squires Reservoir is
of a 10 million gallon above-ground reser-
ing system. The cumulative effect of these
orage capacity of the District by 75 million
i treatment.
accomplish the aforementioned and allow
n out of service at a future date for possible
st phase of improvement is scheduled to
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
C.S. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$ 1,200,000
Revenue Percentage
of
Source Benefit
M.F.C. 58.0 %
CS. 0.0
C.R. 42.0
PROJECT TITLE
Evans Point Reservoir
Scheduled Expenditures for 5 Year Period
1988-89
$ 700,000
0
500,000
^x i A A jVG'fi O
W%> fe L* /-^/ ^clyrggg' /%fj
7- «^4r^ ^*i%Ssii^^^_ "*fc ?^^tt?\it */ ^S /jfe-_^^?*^'^^-•- c$r' fc /5 sjfswf^ / ^^^fcsSv^k.a W// 1 ^x4^N•is<&@> ' ^ — \wrOiMS 1iil.o D/CLI---- - —
ti$I!H
^T^rrii^liKff^mt-"ill>si
-T? •fa-
fi • • / "/ ^^ i( Res. Site
* J /! [_/i i i i
•H
^\
i ! A*^*PROJECT LOCATION
1989-90
0
0
0
1990-91
0
0
0
1991-92
0
0
0
1992-93
0
0
0
Cost
Beyond
1993
$ 0
0
0
JOB NO.
Total
Cost
Estimate
$ 700,000
0
500,000
DESCRIPTION: The Evans Point Reservoir is a 2.5 million gallon facility that will
be utilized by development in the area, as well as the southern section of the original
city service area. The District has selected a site for the reservoir that meets the
hydraulic gradient requirements of the area.
JUSTIFICATION: Future demands in the area will reauire storage of this magni-
tude at the displayed project location.
SCHEDULING: The District is waiting for title to the reservoir site before and work
begins on the reservoir. This is anticipated to occur in F.Y. 1988-89.
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
C.S. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$ 3,000,000
PROJECT TITLE
"D" Expansion I
JOB NO.
Revenue
Source
Percentage
of
Benefit
Scheduled Expenditures for 5 Year Period
1988-89 1989-90 1990-91 1991-92 1992-93
Cost
Beyond
1993
Total
Cost
Estimate
M.F.C.
C.S.
C.R.
100.0
0.0
0.0
$ 600,000
0
0
2,400,000
0
0
0
0
0
0
0
0
0
0
0
0
0
0
$3,000,000
0
0
DESCRIPTION: Expansion of the existing 2.5 million gallons of capacity at the "D"
Reservoirs is required to satisfy the demands of the rapidly developing southwestern
quadrant of the District. The first increment of the expansion is the addition of 8
million gallons of storage.
_ .r\L,|0i0Li—rcejm.j;..-,-!i I i
Existing
•D' Res" Site
-._..._.
I J
/•• !-
"4I IbiM Jou (Iif* l»l| K
M'Otl tt*1StMClI lUUDlUl CI
JUSTTFICATTQN: Future demands in the area will require storage of this magni-
tude at the displayed project location.
SCHEDULING: Site acquisition is needed in fiscal year 1988-89 to allow for con-
i^S.".'•'.'.. *»c, !\ I—-——,
PROJECT LOCATION
struction in '89-'90.
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
C.S. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Fiscal Year 198&-S9
Pipeline Projects
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Summary of Proposed Master Planned Pipeline Projects,
Cost Estimates and Allocations
1988-1989
Project
ECR Madonna -
Tamarack
ECR & PAR
+ PR Sta.
ECR-S. of Camno.
Vida Robles
(2) W.L. ECR- PAR
to Faraday
PAR Assessment
District
Potential Oversizing
Costs
Total
M.F.C.
$ 1,541,240
381,250
187,500
585,507
281,813
57,190
$ 3,034,500
Cap. Sur.
*
$ 151,600
0
0
0
0
0
$ 151,600
City Res.
$ 833,780
0
0
0
0
0
$ 833,780
Total
$2,526,620
381,250
187,500
585,507
281,813
57,190
$ 4,019,880
-9-
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Schedule of Master Planned Pipeline Projects
and Estimated Yearly Expenditures
Pipeline
Projects
ECR - Madonna
to Tamarack
Funding Source
M. F. C.
Capital Surchg.
Citv Reserves
Total
ECR & PAR
+ PR Sta.
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
ECR-S. of Cmn.
Vida Robles
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
1988-89
$ 2,526,620
$ 1,541,240
151,600
833.780
$ 2,526,620
$ 381,250
$ 381,250
0
0
$ 381,250
$ 187,500
$ 187,500
0
0
$ 187,500
Fiscal \
1989-90
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
'ear
1990-91
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
1991-92
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
1992-93
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ o
$ 0
$ 0
0
0
$ 0
5Yrs.
1993-98
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
10 Yrs.
1998-08
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
Total
1988-08
$ 2,526,620
$ 1,541,240
151,600
833.780
$ 2^26,620
$ 381,250
$ 381,250
0
381.250
$ 381,250
$ 187,500
$ 187,500
0
0
$ 187,500
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Schedule of Master Planned Pipeline Projects
and Estimated Yearly Expenditures
Pipeline
Projects
(2) W.L. ECR -
PAR to Faraday
Funding Source
M. F. C.
Capital Surchg.
Citv Reserves
Total
PA.R. Assmnt.
District
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
Potential Over-
sizing Costs
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
1988-89
$ 585,507
$ 585,507
0
0
$ 585,507
$ 281,813
$ 281,813
0
0
$ 281,813
$ 57,190
$ 57,190
0
0
$ 57,190
Fiscal Year
1989-90 1990-91
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 57,190
$ 57,190
0
0
$ 57,190
$ 0
$ 0
0
0
$ o
$ 0
$ 0
0
0
$ 0
$ 57,190
$ 57,190
0
0
$ 57,190
1991-92
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 57,190
$ 57,190
0
0
$ 57,190
1992-93
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 57,190
$ 57,190
0
0
$ 57,190
5Yrs.
1993-98
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 285,950
$ 285,950
0
0
$ 285,950
10 Yrs.
1998-08
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
$ 571,900
$ 571,900
0
0
$ 571,900
Total
1988-08
$ 585,507
$ 585,507
0
0
$ 585,507
$ 281,813
$ 281,813
0
281.813
$ 281,813
$ 1,143,800
$ 1,143,800
0
0
$ 1,143,800
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$ 2,526,620
PROJECT TITLE
36" W.L. in El Camino Real From Madonna Hill to Tamarack
JOB NO.
Revenue
Source
Percentage
of
Benefit
Scheduled Expenditures for 5 Year Period
1988-89 1989-90 1990-91 1991-92 1992-93
Cost
Beyond
1993
Total
Cost
Estimate
M.F.C.
C.S.
C.R.
61.0
6.0
33.0
$ 1,541.238
151,597
833,785
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
$ 1,541,238
151,597
833,785
PROJECT LOCATION
DESCRIPTION: Installation of approximately 12,000 feet of 36" waterline is re-
quired to replace and enlarge the District's ECR transmission main from Madonna
Hill to to Tamarack Ave. The poorly aligned existing steel main will be abandoned
and replaced with a line of sufficient size to adequately supply the northern half of
the District.
JUSTIFICATION: Construction is required to replace the existing line and meet
anticipated future demands of the area.
SCHEDULING: The pipeline is under design with construction expected to begin
during calendar year 1988.
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
OS. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$ 381,250
PROJECT TITLE
16" W.L. & P.R. Sta. - N.E. Corner P.A.R. & E.C.R.
Revenue Percentage Scheduled Expenditures for 5 Year Period
nf
Source Benefit 1988-89
M.F.C. 100.0 % $ 381,250
C.S. 0.0 0
C.R. 0.0 0i
NV !__\_A!flE°SI____^
Uopos / | 1 ,'
i J l|l&n^l/ 1 1 ^<-^'LAS J / ' 1 ' f- -» --
'ALMAS Dfl / 1 /
: £/ \ X ^~=-
<&/ \ FtAhCUO 1 -^~.ASi>*~lvr \T 1 y/! \ft^
'PROJECT LOCATION
1989-90
0
0
0
1990-91
0
0
0
DESCRIPTION: Installal
pressure regulating statior
Carlsbad's improvements
tied into the future pipelir
area around the District's
JUSTIFICATION: Consti
the area.
SCHEDULING: The pipe
pleted during the last quar
1991-92
0
0
0
1992-93
0
0
0
Cost
Beyond
1993
$ 0
0
0
JOB NO.
Total
Cost
Estimate
$ 381,250
0
0
tion of approximately 2,000 feet of 16" waterline and a
t is under construction in conjuntion with the City of
to Palomar Airport Road. Once completed, this line will be
les in El Camino Real to provide high pressure water to the
office.
•uction is required to meet anticipated future demands of
line is currently under construction and should be com-
ter of calendar year 1988.
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
CS. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$ 187,500
Revenue
Source
M.F.C.
C.S.
C.R.
/ \s
pNj^
X*- y_r,
._.-.._ _-LL_
:/ f $?'
PRO
PROJECT TITLE
16" W.L. in E.C.R. So. of Camino Vida Robles
Percentage Scheduled Expenditures for 5 Year Period
nf
Benefit 1988-89
100.0 % $ 187,500
0.0 0
0.0 0
Jy ^ -— —CAM£>%C£T& \a ^<~ "ViZHT*"0
7 ^r<^- LAS i
Vj^^x^t?3 PALMAS OR
-
1 ^
^"^="" W
/%
JECT LOCATION
1989-90
0
0
0
1990-91
0
0
0
1991-92
0
0
0
Cost
Beyond
1992-93 1993
0 $ 0
0 0
0 0
JOB NO.
Total
Cost
Estimate
$ 187,500
0
0
DESCRIPTION: Installation of approximately 1,300 feet of 16" waterline is required
to connect the existing 16" line in El Camino Real with another existing 12" transmis-
sion main south of La Costa Blvd. This project will provide increased water availabil-
ity for the southwest portion of the District.
JUSTIFICATION: Consti
the area.
SCHEDULING: Pipeline
F.Y. 1988-89.
nction is required to meet anticipated future demands of
design and possibly construction is expected to occur in
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
C.S. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$ 585,507
Revenue
Source
M.F.C
CS.
C.R.
Percentage
of
Benefit
100.0 %
0.0
0.0
PROJECT TITLE
(2) 16" W.L. in E.C.R. from P.A.R. to Faraday
Scheduled Expenditures for 5 Year Period
1988-89
$ 585,507
0
0
-W ^k
PROJECT LOCATION
1989-90
0
0
0
1990-91
0
0
0
1991-92
0
0
0
1992-93
0
0
0
Cost
Beyond
1993
$ 0
0
0
JOB NO.
Total
Cost
Estimate
$ 585,507
0
0
DESCRIPTIQN: Installation of approximately 4,300 feet of 16" waterline is required
to install 2 watermains in El Camino Real in conjunction with the City of Carlsbad's
El Camino Real Median Project. The lines will complete the high pressure connec-
tion from the new P.R. station at P.A.R. and E.C.R.
JUSTIFICATION: Consti
the area.
SCHEDULING: Pipeline
F.Y. 1988-89 dependent or
•uction is required to meet anticipated future demands of
design and possibly construction is expected to occur in
i the status of the City's project .
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
CS. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$ 281,813
PROJECT TITLE
Palomar Airport Road Assessment District
JOB NO.
Revenue
Source
Percentage
of
Benefit
Scheduled Expenditures for 5 Year Period
1988-89 1989-90 1990-91 1991-92 1992-93
Cost
Beyond
1993
Total
Cost
Estimate
M.F.C.
C.S.
C.R.
100.0 %
0.0
0.0
$ 281,813
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
$ 281,813
0
0
j»USM
DESCRIPTION: Installation of approximately 6,500 feet of 16" waterline is required
to provide service to landowners in the Palomar Aitport Road Assessment District.
The waterline will begin just west of Palomar Oaks Way, follow the realigned Palo-
mar Airport Road and terminate at the District's Palomar Vault, located just east of
Paseo del Norte.
JUSTIFICATION: Construction is required to meet anticipated future demands of
the area.
SCHEDULING: Pipeline design and possibly construction is expected to occur in
F.Y. 1988-89 dependent on the status of the City's project.
PROJECT LOCATION
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
CS. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Fiscal Year 3588-89
Pipeline Projects Summary
Beyond F.Y. 1988-89
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Schedule of Master Planned Pipeline Projects to be Constructed
after 1988-89 and Estimated Yearly Expenditures
Hydraulic
Gradient
700
580
580-C
550
550-E
500
490
430
384
349
318
255
Oversizing
Total Cost Est.
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
1988-89
Fiscal Year
1989-90 1990-91
$ 0
0
0
31,340
0
0
0
405,427
0
0
0
0
57.190
$ 493,957
$ 493,957
0
0
$ 493,957
$ 0
0
0
0
0
0
0
0
0
0
422,401
0
57.190
$ 479,591
$ 479,591
0
0
$ 479,591
1991-92 1992-93
1
$ 0
0
0
114,913
0
0
0
0
0
0
0
0
57.190
$ 172,103
$ 172,103
0
0
$ 172,103
$ 0
0
0
0
0
0
0
0
0
0
0
0
57.190
$ 57,190
$ 57,190
0
0
$ 57,190
5Yrs.
1993-98
$ 4,180,140
467,751
0
0
0
0
2,899,030
0
0
95,013
280,900
0
285.950
$8,208,784
$5,045,933
1,509,119
1.653.732
$8,208,784
10 Yrs.
1998-08
$ 0
0
0
0
0
0
0
405,427
0
0
0
0
571.900
$ 571,900
$ 571,900
0
0
$ 571,900
Total
1988-08
$ 4,180,140
467,751
0
146,253
0
0
2,899,030
405,427
0
95,013
422,401
0
1.086.610 .
$9,983,525
$6,820,674
1,509,119
1.653.732
$9,983,525
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Fiscal Year 1988-89
Operations Projects
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Schedule of Master Planned Operations Projects,
Cost Estimates and Allocations
1988-Buildout
Project M.F.C. Cap. Sur. City Res. Total
Telemetry $ 646,200 $ 507,600 $ 0 $ 1,153,800
A. Kelly
Oper.Cntr. 1,264,000 736,000 0 2,000,000
Cogen. Sta. 600,000 0 0 600,000
Total $2,510,200 $1,243,600 $ 0 $3,753,800
-18-
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Schedule of Master Planned Operations Projects
and Estimated Yearly Expenditures
Operations
Project
Telemetry
Funding Source
M. F. C.
Capital Surchg.
Citv Reserves
Total
A. Kelly
Oper. Center
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
PAR Cogen. Sta
Funding Source
M.F.C.
Capital Surchg.
Citv Reserves
Total
1988-89
$ 57,690
$ 32,310
25,380
0
$ 57,690
$ 2,000,000
$ 1,264,000
736,000
0
$2,000,000
$ 0
$ 0
0
0
$ o
Fiscal Year
1989-90 1990-91
$ 57,690
$ 32,310
25,380
0
$ 57,690
$ 0
$ 0
0
0
$ 0
$ 120,000
$ 0
120,000
0
$ 120,000
$ 57,690
$ 32,310
25,380
0
$ 57,690
$ 0
$ 0
0
0
$ 0
$ 480,000
$ 0
480,000
0
$ 480,000
1991-92
$ 57,690
$ 32,310
25,380
0
$ 57,690
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ o
1992-93
$ 57,690
$ 32,310
25,380
0
$ 57,690
$ 0
$ 0
0
0
$ o
$ 0
$ 0
0
0
$ 0
5Yrs.
1993-98
$ 288,450
$ 161,500
126,900
0
$ 288,450
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
10 Yrs.
1998-08
$ 576,900
$ 323,100
253,800
0
$ 576,900
$ 0
$ 0
0
0
$ 0
$ 0
$ 0
0
0
$ 0
Total
1988-08
$ 1,153,800
$ 646,200
507,600
0
$ 1,153,800
$ 2,000,000
$ 1,264,000
736,000
0
$2,000,000
$ 600,000
$ 600,000
0
0
$ 600,000
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$ 1,153,800
Revenue Percentage
of
Source Benefit
M.F.C. 56.0 %
C.S. 44.0
C.R. 0.0
iiMBAX IOR
1
1
{SM} Allan Kelly f
\j^P Operations
\ Center
\ P£LOt££S-sz^=!
PROJECT LOCAT
PROJECT TITLE
Telemetry
Scheduled Expenditures for 5 Year Period
1988-89
$ 32,310
25,380
0
s-—- .
. \-
*f^f
( V-
\_A1Q£ORL^___
r^^1
"1
ION
1989-90
32,310
25,380
0
1990-91
32,310
25,380
0
1991-92
32,310
25,380
0
DESCRIPTION: The District realizes t
lance. Therefore, the majority of existing
lating stations are currently being integr
Future expenditures totaling $1.5 millioi
system operations.
JUSTIFICATION: Telem
management.
SCHEDULING: Annual e
1992-93
32,310
25,380
0
Cost
Beyond
1993
$ 484,650
380,700
0
JOB NO.
Total
Cost
Estimate
$ 646,200
507,600
0
be importance of constant facility surveil
; reservoirs and primary metering and regu-
ated into the telemetry/control system,
i may include computer control of water
etry/Control systems are essential for effective water
xpenditures are expected through buildout.
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
CJ5. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$ 2,000,000
PROJECT TITLE
Allan O. Kelly Operations Center
JOB NO.
Revenue
Source
Percentage
of
Benefit
Scheduled Expenditures for 5 Year Period
1988-89 1989-90 1990-91 1991-92 1992-93
Cost
Beyond
1993
Total
Cost
Estimate
M.F.C.
C.S.
C.R.
63.0 %
0.0
$1,264,000
0
736,000
0
0
0
0
0
0
0
0
0
0
0
0
$0
0
0
$ 1,264,000
0
736,000
Allan Kelly
Operations
Center
PROJECT LOCATION
DESCRIPTION: Construction drawings are being done for the Allan O. Kelly Op-
erations Center. The building is approximately 13,000 square feet and will house all
of the District's departments under one roof. The cost breakdown for the entire
complex is $1,500,000 for the main building and $ 500,000 for revitalization of the
existing warehouse.
JUSTIFICATION: Expansion of the District's activities and size of staff have made
the existing arrangement inefficient and impractical.
SCHEDULING: Design is currently underway and construction is expected to begin
prior to the end of calendar year 1988.
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
OS. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Fiscal Year 1988-89
Non-Master Planned Projects
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
Location
Arbuckle PL
Cherry St.
Chinquapin St.
Harrison & Locust
Hope & Home
Total
College Blvd.
Location
Oak & Tyler
Oak & Roos'vlt
Total
List of Non- Master Planned Projects,
Cost Estimates and Allocations
1988-89
Pipeline Replacement
M.F.C. Cap. Sur. City Res.
$ 0 $ 0 $ 25,000
0 0 30,000
0 0 30,000
0 0 70,000
0 0 90,000
$ 0 $ 0 $ 245,000
P.R. Stations
$ 75,000 $ 0 $ 0
Appurtenance Replacement (Valves)
M.F.C. Cap. Sur. City Res.
$ 0 $ 0 $ 8,000
0 0 6,000
$ 0 $ 0 $ 14,000
Total
$ 0
30,000
30,000
70,000
90,000
$ 245,000
$ 75,000
Total
$ 8,000
6,000
$ 14,000
-22-
COSTA REAL MUNICIPAL WATER DISTRICT
Capital Improvement Plan
COST ESTIMATE
$ 259,000
PROJECT TITLE
Village Area Rehabilitation
JOB NO.
Revenue
Source
Percentage
of
Benefit
Scheduled Expenditures for 5 Year Period
1988-89 1989-90 1990-91 1991-92 1992-93
Cost
Beyond
1993
Total
Cost
Estimate
M.F.C
C.S.
C.R.
Dev.
0 %
0
100
0
0
259,000
Future
Costs to be
Deter-
mined
$0
0
259,000
0
ft
PROJECT LOCATION
DESCRIPTION: The following projects are scheduled for the 1988-89 fiscal year
Village Area Rehabilitation:
$25,000 Cherry St. (400') $30,000
Harrison & Locust (500') 70,000
Oak & Roosevelt (Valves) 8,000
Arbuckle PI. (400')
Chinquapin (500')
Hope & Home (1,000')
Oak & Tyler (Valves)
40,000
90,000
6,000
JUSTIFICATION: Construction is required to rehabilitate existing facilities.
SCHEDULING: Construction is anticipated to begin on some of the aforementioned
projects in the first half of F.Y. 1988-89.
Revenue Sources: M.F.C. - Major Facilities Charge Paid by New Development
OS. - Capital Surcharge Placed on the Water Rate to Pay for Rehabilitaion of Existing Facilities
C.R. - City Reserves Encumbered for Rehabilitation Projects which are a Benefit to Water Users in the "Original City Service Area"
Dev. - Facilities Funded by Developers in Addition to M.F.C. Charges