HomeMy WebLinkAbout1988-11-01; City Council; Resolution 88-380m 4' IJ 0 0 1 2 3 4 RESOLUTION NO. 88-380 A RESOLUTION OF THE CITY OF CARLSBAD, CALIFORNIA, CONTROL FACILITY CAPITAL IMPROVEMENT PROGRAM BUDGET. APPROVING THE REVISED 1988-89 ENCINA WATER POLLUTION WHEREAS, the Encina Water Pol 1 ution Control Faci 1 i ty Joi r 5 11 Committee has voted to recommend the proposed revision of the Capital 6 7 8 9 10 11 12 Program 1988-89 Budget for approval ; and WHEREAS, the City Manager recommends and the City Council concul proposed Revised 1988-89 Encina Capital Improvement Budget should be ay WHEREAS, the City of Carlsbad intends to join with other En Agencies in the issuance of debt to finance all costs related to Phase IV project; and WHEREAS, all cost related to Encina Phase IV project as refle 13 by the City from future debt issues. 14 Encina Capital Improvement Budget, Exhibit A attached hereto, may t: California, as follows: 16 NOW, THEREFORE BE IT RESOLVED by the City Council of the City ( 15 17 1. That the above recitations are true and correct. 18 Capital Improvement Program Budget is approved. 19 2. That the Revised 1988-89 Encina Water Pol 1 ution Contr 20 PASSED, APPROVED AND ADOPTED at a regular meeting of the Ca 21 AYES: Council Member Lewis, Kulchin, Pettine, Mamaux and Larc 23 following vote, to wit: 22 Counci 1 held on the Is t day of November 9 24 ATTEST: 27 26 ABSENT : None 25 NOES: None 28 ALETHA L. RAU (SEAL j ,. b 4" 4b Fy 1m% w' REuIsEI)mxNAw mFxNEMxr EAHl El I "A" ' TuxBzr - Enclna WFCF (Unit I) Facility Phnning ad EIR Effort: PhMe PI3 D-iW Canstnrticn Ccnstnrtim Ccnstructim Management Off ice Engineering Phase N Cmtingencies Plant ~eh~bilitaticn4 Capitdl Jmpisitions Regia ~oluticn5 solids F4anag-t PIO, financial h instituticm Caposting Pilot Project Site Bcquisiticn h plrchase phase I Design Caratruction Phase 11 Design/ccnstructicn EIR, financial arrargenrents, Site arplisiticn h garchase W I (Design) Ccnstruction Phase I1 Design h Cmstructia Ocean Outfall (Unit J) arrqemxits, etc. ~nctna-~nly solutian6 etc. Effluent Punp No. 3 EIR, -1-7 Ccz-structicd %ase IV Canstructicn Parael mtfa119 Joint System Meterig d Cmtingencies 3,7 Planning, Design, Construct. 7 1 I: 1983-89 1990-91 1989-90 I I 50,600 1,520,840 1,000,Ooo 50, m 48,300 178,900 15,050,400 1,000,ooo 900, OOO 1,459, !500 50,000 200, ooo 16,418,600 1,592,200 ~,ooo 200,OOo 1,~,OOo 1,460,000 1,000,0006 5oo,m6 ~ 1,800,0086 5, loo, o006 I (131,200) 2,779,400 2,779,400 350, ooo - -. 1 TClIAL - With Reg. Solids Manage. 26,150,2006 23,739,3006 4,067,4406 WrZIL - With Encina-cxlly Soluticn6 22,510,200 21,439,300 4,067,440 FxILm REmAcPlENplO 865,000 865,000 865,000 Ref: t 1991-92 1992- 93 1993.-08 1,368,200 132,700 75,000 3,Ooo,oIx, 200,000 200,ooo 2,250,000 100,ooO 1,368,200 132,700 75,000 3,Ooo,oIx, 200,000 200,ooo 2,250,000 100,ooO 4,145,000 4,145,000 3, 250, 000 5, loo, 0006 4.000,000~ 32,730, OOO , 5,920,900 41,230,000 4,445,000 ~ 6,875,d 41,980,0006 300,0006 I 865,000 12,975,000 865,000 Footnotes: 1. Phase IV costs expressed at mid-pint of cxnstructicn (a? actual costs when available). All other costs e €XIU.A=5500. Therefore, 'Total" alums include both present wrth and projected mrth values and have lin Does mt include Units B thrcqh H. Those units' CIP is prepared and administered by the Cities of Carlsba 2. cUlp1a in !?Y 1988/89. 3. PaSaing permits fran Carlsbad, AFCD, Cmstal Canissicn, and ra9cB. 4. Major capital cutlays tokard plant rehabilitaticn fran mmal wet. 5. Based m Phase 11 NSSS EYoject Report and January 1988 U@ated Project Report. All estimates will be re: 6. These expenses wld be incurred cnly if a rqiaal soluticn is not izplemented. 7. Plannirq and EIR efforts for 3rd and 4th effluent pmp, surge torar extensian and interim flow ecpalizat: 8. Credit CqJdL to difference between finds collected in FY 1987/88 ($342,000) ad actual antract a!Kamt '$: 9. May be permanent flow eqmlizatian or partial parallel. 10. 'Kese fur& accunulated and held by Mividual zgencies. Frx33/89. included raaler Unit I.