Loading...
HomeMy WebLinkAboutCass Construction Inc; 2004-11-03; 34461 Part 2 of 2SHOP DRAWING TRANSMITTAL FORM FROM: DATE: Phone: FAX: PROJECT NAME: Recvcled Water Transmission Main El Camino Real 20-Inch TO: Citv of Carlsbad PROJECT NO.: 3887-H 5950 El Camino Real Carlsbad, CA 92008 OWNER: Citv of Carlsbad ATTN: Construction Manaaement and 5950 El Camino Real InsDection Division Carlsbad. CA 92008 THIS IS AN ORIGINAL THIS IS A REVISION SUBMITTAL NO.: SUBMITTAL OF SUBMITTAL NO.: SUBJECT OF SUBMITTAL: S P EC I F I CAT1 ON S ECTl ON (S) : PLAN SHEET NUMBER(S): CONTRACTOR'S CERTIFICATION: Check & Complete either (A) or (B) below: (A) We have reviewed in detail and certify that the material, equipment or construction procedure(s) contained in this submittal meet all the requirements specified in or shown on the Contract Documents, Construction Specifications and Construction Plans with no exceptions. We have reviewed in detail and certify that the material, equipment or construction procedure(s) contained in this submittal meet all the requirements specified in or shown on the Contract Documents, Construction Specifications and Construction Plans except for the followinq deviations: CONTRACTOR'S AUTHORIZED SIGNATURE: City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01300 - Shop Drawing Submittals - 8 of 8 SECTION 01 31 0 PROGRESS SCHEDULE, SUBMllTAL SCHEDULE, AND SCHEDULE OF VALUES PART 1 - GENERAL 1.1 Scope This section addresses preparation and submission of the construction progress schedule, submittal schedule, schedule of values, and other reports specified herein, including the up- to-date maintenance thereof as required. 1.2 Related Work Described Elsewhere A. Section 01 31 0 Shop Drawing Submittals 1.3 Construction Schedule A. General Immediately upon being awarded the Contract and prior to issuance of the Notice to Proceed, the Contractor shall prepare and submit to the Engineer a construction progress schedule for review and approval. The schedule shall be prepared and shall conform to the working time and time of completion established under the terms of the Contract and shall be subject to modification by and approval of the Owner. When in the opinion of the Owner, it becomes necessary to accelerate the Work, the Contractor, when so ordered, shall modify the schedule to conform to such requirements at no additional cost to the Owner. B. Schedule Preparation and Updates The Construction Schedule shall be in conformance to the requirements of Section 6-1.1.1 and Sections 6-1.2 through 6-1.8.3 of the Supplemental provisions. 1.4 Submittal Schedule A. General The Contractor shall also furnish a separate schedule along with the Construction Schedule specified herein, showing the proposed dates for submittal of shop drawings, product data and samples. B. Quantity Submit two copies of the submittal schedule to the Engineer. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 31 0 - Progress Schedule, Submittal Schedule, and Schedule of Values - 1 of 2 1.5 Schedule of Values A. General Immediately upon being awarded the Contract, and before Pre-Construction Conference, the Contractor shall prepare and submit to the Engineer, a Schedule of Values allocated to the various portions of the Work. This Schedule of Values, unless objected to by the Engineer, shall be used as the basis for the Contractor's Applications for Payment and for contract change order negotiation if necessary. B. Methodology The schedule shall list the installed value of the component parts of the Work in sufficient detail to serve as a basis for computing values for progress payments during construction. Follow the table of contents of this Project Manual as the format for listing component items. For each major line item list sub-values of major products or operations under the item, where applicable. Each item shall include a directly proportional amount of the Contractor's overhead and profit. For items on which progress payments will be requested for stored materials, break down the value into (1) the cost of materials, delivered and unloaded, with taxes paid, and (2) the total installed value. - The sum of all values listed in the schedule shall equal the total Contract sum as well as the total values of all lump sum bid items of work. C. Submittal The schedule of values must be submitted as a Shop Drawing Submittal approved by the Owner prior to commencing with the work. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 31 0 - Progress Schedule, Submittal Schedule, and Schedule of Values - 2 of 2 SECTION 01 340 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 Scope This section addresses preparation and submission of shop drawings, product data, and samples as specified herein and in the various sections of these specifications. The requirements specified herein are in addition to requirements for shop drawings, product data, samples, materials lists, substitutions of materials, or other submittals specified elsewhere in these specifications. 1.2 Definitions As used herein, the term "manufactured" applies to standard units usually mass-produced; and "fabricated" means items specifically assembled or made out of selected materials to meet individual design requirements. 1.3 General Submittal Procedures A. Scheduling Submit shop drawings, product data, and samples in accordance with the schedule specified in Section 01310. Extension of Contract time will not be granted because of the Contractor's failure to make timely submittals. Do not purchase materials or equipment or begin construction activities covered by the required submittals until submittals have been reviewed and returned. B. Transmittal Accompany each submittal with a dated, signed and sequence numbered transmittal on forms prescribed by the Engineer. Include information required by this form including project identification, name and address of Contractor and of subcontractor or supplier, a list of items included in the submittal, and identification of drawing numbers, specification section and paragraph numbers to which submittal pertains, and space for Contractor's review and approval stamp. C. Check of Returned Submittals City of Carlsbad 03/04 (DBE) Check the submittals returned for correction and ascertain if the corrections result in extra cost above that included under the Contract Documents, and give written notice within five days if, in Contractor's opinion, such extra cost results from corrections. By failing to so notify or by starting any Work covered by a submittal, Contractor waives all claims for extra costs resulting from required corrections. ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 340 - Shop Drawings, Product Data and Samples - 1 of 7 1.4 Shop Drawings and Product Data A. Shop Drawings City of Carlsbad 03/04 (DBE) The term "Shop Drawings" as used herein includes fabrication and installation, layout, and setting drawings; wiring and control diagrams; and other drawings as defined in the General Conditions. Check and verify all field measurements and submit for review, with such promptness as to cause no delay in the Work or in that of any other contractor or subcontractor, all shop or setting drawings and schedules required for the construction activities of the various trades. Shop Drawings shall be prepared at the Contractor's expense and shall be sent to the office of the Engineer, carriage prepaid. Drawings shall show all information required by the applicable technical section and shall be in sufficient detail as may be required to show that fabricated materials, equipment or systems, and the positions thereof conform to the Contract Documents. Shop Drawings shall establish the actual detail of fabricated items, indicate proper relation of adjoining construction, amplify design details of mechanical and electrical equipment in proper relation to physical spaces in the structure, and incorporate minor changes of design or construction to suit actual conditions. Shop Drawings shall be drawn to scale and shall be completely dimensioned. - 1. Composite Shop Drawings and Field Layouts Prepare and submit composite Shop Drawings and field layouts as required to solve tight field conditions and when required to coordinate the construction activities of several trades. Include dimensioned plans, elevations, sections, and details and give complete information particularly as to kinds and types of materials and equipment, size and location of sleeves, inserts, attachments, chases, openings, conduits, ducts, boxes, and structural interferences. Coordinate these composite Shop Drawings and field layouts in the field for proper relationship to construction activities of applicable trades based on field conditions. Contractor shall have competent personnel readily available for coordinating, checking, and supervising of field layouts. The procedures for submittals and resubmittals, and final distribution shall be as specified for Shop Drawings. 2. Shop Drawing Format Prepare Shop Drawings on sheet of same size as Contract Drawings or on 8E-inch by 1 1-inch three-hole punched vellum type sheets suitable for both Xerox and blue line reproduction. - ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 340 - Shop Drawings, Product Data and Samples - 2 of 7 Each Shop Drawing shall have a title block containing the following information. a. Name and location of the Project. b. Name and address of the Contractor. c. Name and address of the subcontractor, manufacturer, supplier or distributor as applicable. d. Name and address of Owner. e. Date, scale of drawings, and identification number. f. Space for the Contractor's review and approval stamp. 3. Quantity of Each Shop Drawing Submit five blue or black line prints and one reproducible transparency of each shop drawing. B. Product Data The term "product data" as used herein includes manufacturer's standard drawings, certificates of conformance, substantiating calculations and other data as defined in the General Conditions. The data shall include all information required by the applicable technical section and shall be in sufficient detail to show that manufactured materials and equipment conform to the Contract Documents. 1. Catalog Cuts Clearly mark each copy to indicate the product or model as well as optional sizes, finishes or other features proposed for use. Delete inapplicable data. 2. Submittal Preparation Bind product data with sturdy, labeled covers with an index listing the contents. Loose unbound submittals will be returned without review. Submit six copies of all product data. ,- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 340 - Shop Drawings, Product Data and Samples - 3 of 7 1.5 Samples A. B. C. D. E. F City of Carlsbad 03/04 (DBE) 1 General Furnish for review samples of the various materials, together with the finish thereon, as specified for and intended to be used on or in the Work. Samples shall be sent to the office of the Engineer, carriage prepaid. Schedule Submit samples to the Engineer for review before purchasing, fabricating, applying, or installing such materials and finishes. The Engineer will review and take action on samples within 15 working days of the Contractor's submittal. All actions will be by the Engineer in writing. Quantity Submit samples, other than field samples, in duplicate. A cover letter shall accompany the sample and shall list all items being transmitted, designating their particular usage and location in the Work and shall be identified as to manufacturer, trade name, style, model. One approved sample will be returned to the Contractor. Sample Approval - Approval of a sample shall not be taken in itself to change or modify any contract requirement. Materials, finishes. and workmanship in the completed building shall be equal in every respect to that of the approved sample. Sample Size Unless otherwise specified, samples shall be 8-inch by 1 O-inch in size and shall be limited in thickness to a minimum consistent with sample analysis. In lieu thereof, the actual full size item may be submitted. Samples of Value Samples of value may be returned to the Contractor for use in the Work after review, analysis, comparison or testing as may be required by the Engineer, provided that the location is recorded and the samples bear temporary identification as samples. ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 340 - Shop Drawings, Product Data and Samples - 4 of 7 G. Field Samples c ,..- Field samples shall be prepared at the site by the Contractor as specified in the various sections of these Specifications. Affected finished construction shall not be commenced until the Engineer has given written approval of the field samples. H. Furnish one sample of approved products, colors, or textures to the Engineer for final record. Show identification previously described including, if finish sample, manufacturer, mix proportion, name of color, building, Contractor, subcontractor, and surfaces to which applied on back of sample. 1.6 Engineer's Action A. General The Engineer will review the submittals with reasonable promptness and will affix the Engineer's initials or signature as follows: City of Carlsbad 03/04 (DBE) 1. Submittals stamped "ACCEPTED" require no further action and fabrication or construction may proceed. The Engineer will return to the Contractor the stamped transparency of Shop Drawings and two stamped copies of brochures, schedules, materials lists, and other product data, except where required otherwise. 2. Submittal stamped "ACCEPTED AS NOTED" require no further action and fabrication or construction may proceed contingent upon all corrections being made as noted. Quantities returned will be as specified for "Accepted." 3. Submittals stamped "REJECTED/RESUBMIT AS SPECIFIED" or REVISE AS NOTED/RESUBMIT" require the Contractor to resubmit them with reasonable promptness and no fabrication or construction may begin. The Engineer will return to the Contractor; one stamped transparency and one marked copy of shop drawings and one marked copy and three unmarked copies, all stamped, of brochures, schedules, materials lists, and other product data. 4. Submittals stamped "NO ACTION REQUIRED" indicate the submittal was for informational purposes only and does not require review. The Engineer will return to the Contractor the submitted materials as outlined under "Accepted." 5. Submittals stamped "SUBMITTAL NOT REQUESTED/RETURNED WITHOUT REVIEW" indicate the Contractor has submitted drawings, etc. that were not required and therefore, were not reviewed or accepted by the Engineer. ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01340 - Shop Drawings, Product Data and Samples - 5 of 7 B. C. D. E. F. City of Carlsbad 03/04 (DBE) Resubmittals If first or subsequent submittal is stamped "REJECTED/RESUBMIT AS SPECIFIED 'I or "REVISE AS NOTED/RESUBMIT," corrective action shall be taken and resubmittal procedure shall be same as for first submittal. The Contractor shall direct specific attention in writing on resubmitted Shop Drawing to revisions other than the correction requested by the Engineer on previous submittals. 1 Distribution Copies The Contractor shall be responsible for obtaining required prints and for distribution to subcontractors. Make distribution copies from the transparency bearing the Engineer's stamp. Intent of Review The Engineer will check and take action on such drawings and schedules only for conformance with the design concept of the Work and compliance with information given in the contract documents. When so directed by the Engineer, the Contractor shall make corrections required. Cost of Review - The Engineer will review the Shop Drawings as originally submitted as well as the first resubmittal thereof at his own cost. If additional resubmittals are made or required, the costs incurred by the Engineer in reviewing them shall be paid by the Contractor. Contractor's Responsibility The shop drawings, product data and supporting data shall be prepared by the Contractor or his suppliers and subcontractors, but shall be submitted as the instruments of the Contractor. The Contractor shall check the drawings of his suppliers and subcontractors as well as his own drawings before submitting them. In particular, the Contractor shall ascertain that the drawings meet all requirements of the contract Drawings and Specifications and conform to the structural and space conditions. If such shop drawings show variations from Contract Documents, whether because of standard shop practice or other reasons, the Contractor shall clearly describe in his letter of transmittal, such variations including other chanaes reauired to correlate the construction . ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 340 - Shop Drawings, Product Data and Samples - 6 of 7 G. Contractor's Review Shop Drawings when submitted to the Engineer for review shall be accompanied by a written statement signed by the Contractor, that the Shop Drawings have been checked by him and found to be in accordance with the contract Drawings and Specifications and that proper provisions has been made to accommodate abutting construction. This statement may be in the form of an approval stamp bearing the Contractor's signature. H. Substantiating Calculations Substantiating calculations, when specified, shall be prepared and signed by a California registered Civil or Structural Engineer, employed by the Contractor. I. Contractor's Responsibility for Errors The Engineer's review of Shop Drawings will be general only and shall not relieve the Contractor from responsibility for errors of any sort, for deviations from Drawings or Specifications, or for conflict with the construction activities of others that may result from such deviations. Engineer's review of a separate item does not indicate a review of an assembly in which the item functions. c PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 340 - Shop Drawings, Product Data and Samples - 7 of 7 SECTION 01 400 QUALITY CONTROL PART 1 - GENERAL 1.1 Work Included Inspection and testing laboratory qualifications, duties and responsibilities, Contractor's quality control requirements, Owner's inspection and testing. 1.2 Related Work A. Section 01300: Shop Drawing Submittals 1.3 Reference Standards Work shall conform to Federal, State and local building codes, electrical codes, fire codes, mechanical codes and plumbing codes, and to Occupational Safety and Health Act (OSHA) Regulations. Nothing in Contract Documents shall be interpreted as permission or direction to violate any governing code or ordinance. - 1.4 Submittals A. Certificates of compliance shall be submitted at Owner's request. B. Transcripts of results of acceptance to verify quality of manufactured products shall be submitted at Owner's request. 1.5 Testing Laboratorv Services Where required by these specifications, the Contractor shall hire an Owner-approved independent laboratory to perform testing and certify results. Provide labor, products, tools, instruments, water, and power as directed for sampling for required tests. Tests of products shall follow commonly recognized standards of national technical organizations, and specified sampling and testing methods. Contractor shall pay for quality assurance testing unless otherwise shown. Owner may test representative samples of each type and size of product furnished. Failure of samples to pass tests will be deemed sufficient cause to reject entire lot delivered. /-- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01400 - Quality Control - 1 of 3 1.6 Contractor's Quality Control Arrange work to be readily accessible and easy to operate and maintain where detail drawings are not included in Contract Documents, supplementary drawings or shop drawings and submittals. Combinations of manufactured equipment shall be fully compatible and work safely and successfully as a unit. Furnish necessary mountings, couplings and appurtenances with each unit. ---c Relocations or adjustment of existing facilities noted in Contract Documents shall be done as needed. If existing items are lost or damaged during construction, replace with new items of equal or better quality. Make field measurements needed to fabricate and install Work before ordering or beginning work. Make minor changes in alignments and dimensions as needed to remedy or avoid utilities and structural conflicts. 1.7 Proiect Conditions Ascertain suitability of native soil for backfill before submitting bid. If native soil is found to be unsuitable, provide suitable material for meeting compaction requirements at no additional cost to Owner. Items furnished shall be capable of fulfilling their intended purpose in environment in which they are installed. Allow for local temperature extremes, climactic conditions and corrosive environments where necessary to ensure proper functioning of furnished products. - 1.8 Unit Prices Payment for Contractor-provided testing required in Contract Documents will be included in the price bid for items of work for which Contractor-provided testing is specified. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.1 Inspection Notify Engineer of time and place of shop tests five working days before they begin. Complete manufacturing operations, checks, adjustments and tests before factory inspection. The Engineer will inspect products after delivery and throughout construction process. Products will be subject to rejection at any time on account of failure to meet Contract Documents even though samples may have been accepted as satisfactory at place of manufacture. -c City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01400 - Quality Control - 2 of 3 Before backfilling, request inspection by the Engineer to verify proper installation of buried ZI work. Before finishing, request inspection by the Engineer to verify that no surfaces to receive product have defects or errors which could result in poor or potentially defective application or cause latent defects in workmanship. 3.2 Installation/Application/Erection Install products according to manufacturer's installation and warranty requirements. Install products to tolerances recommended by manufacturer. Unless otherwise shown, install equipment true and level using precision gauges and levels. Refer variances between manufacturer's installation instructions and Contract Documents to the Engineer. Construct walls plumb, straight, level, square and true. Welds, unless otherwise shown, shall be continuous, watertight, and conforming to Structural Welding Code of American Welding Society. Welds shall be free of sharp points or edges. Pipework, valves, fittings, tanks and appurtenances shall have no leaks at design pressures. Exposed surfaces shall be finished in appearance. Grind smooth exposed welds. Round or chamfer corners of exposed structural shapes for personal protection. - Prime and paint exposed surfaces of ferrous products, piping, and conduit except for stainless steel or galvanized or sherardized surfaces or unless otherwise shown. Clean painted surfaces and touch up bare or marred spots with finish to match factory finish. 3.3 Field Qualitv Control Maintain complete set of Contract Documents at jobsite field office or superintendent's truck at all times. Frequency of sampling and testing shall be as shown, and shall be performed at such other times as necessary to document contract compliance. Notify the Engineer and regulating authorities three days before field tests. Perform field tests in presence of the Engineer who will record results. Repair damage to work that is not cause for rejection. Repair, correct or replace work failing tests or inspection. Repeat tests until results satisfy specifications. Repair damages resulting from tests END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01400 - Quality Control - 3 of 3 SECTION 01 41 0 TESTING AND INSPECTION OF EARTHWORK AND CONCRETE - PART 1 - GENERAL 1.1 Scope This section addresses testing laboratory services and inspections required during the course of construction, as specified. 1.2 Testing Laboratorv A. Selection of Laboratory Testing and inspections will be performed by the Owner or by an independent testing laboratory selected by the Owner. B. Testing Requirements Testing and inspection services which are performed will be in accordance with requirements of the Uniform Building Code, and as specified herein. 1.3 Payments A. B. C. rc Tests Showing Compliance Costs of initial testing and inspection, except as specifically modified herein, or specified otherwise in technical sections, will be paid by the Owner, providing such testing and inspection indicates compliance with Contract Documents. Initial tests and inspections are defined as the first test and inspections as specified herein. Tests Showing Failure In the event a test or inspection indicates failure of a material or procedure to meet requirements of Contract Documents, costs for retesting and re-inspection will be borne by the Contractor. Additional Tests at Owner's Request Additional tests and inspections not specified herein but requested by the Owner, will be paid for by the Owner, unless result of such tests and inspections are found to be not in compliance with Contract Documents, in which case the Owner will pay all costs for initial testing as well as retesting and re-inspection and backcharge the Contractor. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01410 - Testing and Inspection of Earthwork and Concrete - 1 of 5 D. Additional Test Due to Changes Costs for additional tests or inspections required because of change in materials being provided or change of source or supply shall be paid by Contractor direct to testing laboratory. -4 E. Correction of Deficiencies Costs for construction activities which are required to correct deficiencies shall be borne by the Contractor. F. Additional Tests to Assist Contractor Cost of testing which is required solely for the convenience of Contractor in his scheduling and performance of Work shall be borne by the Contractor. 1.4 Availabilitv of Samples A. Acquisition of Samples Contractor shall make materials required for testing available and assist in acquiring these materials as directed by Engineer. The samples shall be taken under the immediate direction and supervision of the Engineer. - B. Uncovering Construction If construction which is required to be tested or inspected is covered up without prior notice or approval, such construction may be uncovered at the discretion of the Engineer. C. Advance Notice for Inspections Unless otherwise specified, Contractor shall notify the Engineer a minimum of 10 working days in advance of required inspections. Extra construction activities resulting from a failure to notify the Laboratory shall be paid for by the Contractor. D. Cancellation of Tests or Inspection Contractor shall give sufficient advance notice to the Engineer in the event of cancellation or time extension of a scheduled test or inspection. Charges due to insufficient advance notice of cancellations or time extension shall be paid for by the Contractor. 1.5 Removal of Materials Unless otherwise directed, materials not conforming to the requirements of Contract - Documents shall be promptly removed from the Project site. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 41 0 - Testing and Inspection of Earthwork and Concrete - 2 of 5 PART 2 - PRODUCTS (Not Applicable) __- PART 3 - EXECUTION 3.1 Earthwork A. Engineer's Role The Engineer will provide continuous inspection of fill and will field test fill and earth backfill as placed and compacted, and inspect excavations and subgrade before concrete is placed and provide periodic inspection of open excavations, embankments, and other cuts or vertical surfaces of earth. The Engineer will submit a report indicating that he has observed and tested fills and that in his opinion the fills were placed in accordance with the Project Specifications. B. Removal of Unsatisfactory Material Contractor shall remove unsatisfactory material, reroll, adjust moisture, place new material, or in the case of excavations, provide proper protective measures, perform other operations necessary, as directed by the Engineer whose decisions and directions will be considered final. - C. Engineer may require deepening of footings and so order such deepening in accordance with Section 02200. D. Test and Inspection Procedure 1. General Allow sufficient time for testing and evaluation of results before material is needed. The Engineer will be sole and final judge of suitability of all materials. 2. Tests Laboratory compaction tests to be used will be in accordance with ASTM D1557-78. 3. Field Density Tests Field density tests will be made in accordance with ASTM D1556 or ASTM D2922. City of Carlsbad 03/04 (DEE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 0141 0 - Testing and Inspection of Earthwork and Concrete - 3 of 5 4. Number of Tests -_ The number of tests along the pipeline will be determined by Engineer, but generally every 300' to 400'. 5. Use of Tested Materials Materials in question may not be used pending test results. 6. Excavation and Embankment Inspection Procedure Excavation and embankment inspection procedure: Engineer will visually or otherwise examine such areas for bearing values. 3.2 Testina of Concrete A. 8. C. D. E. General Notify Engineer of brand and type of cement and sources of aggregates in time for review, sampling and testing, if required. Number of Tests At least four cylinders for each 100 cubic yards or each separate mix design of concrete of required strength in excess of 2000 psi, or fraction thereof being placed each day will be taken. - Sampling Procedures Cylinders will be taken so as to represent as nearly as possible the batch of concrete from which they are taken. Sampling procedures shall conform to ASTM C 172-82. Test Cylinders Test cylinders shall be made and cured in compliance with ASTM C 31-88, except as modified herein. Test Procedures Test cylinders from respective batches, one at age of 7 days, one at 14 days and one at age of 28 days. The fourth shall be tested as directed if concrete strength is under that specified. Cylinder testing procedures shall conform to ASTM C39- 86 for strength. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 41 0 - Testing and Inspection of Earthwork and Concrete - 4 of 5 F. ,P G. H. Slump Tests Slump tests shall be taken as required by Testing Laboratory to certify compliance with Contract Documents. Slump shall be tested in accordance with ASTM C143- 89a. Compressive Strength Minimum compressive strength of test cylinders, in pounds per square inch, shall not be less than the specified required design strength. Test Cores If minimum strengths of test cylinders fall below those specified, Engineer may require test cores from hardened concrete to be taken and tested. Each core test, if taken, shall consist of 3 cores. Costs of such cores and tests shall be borne by the Contractor. Cores shall be taken in accordance with ASTM C42-84a, from locations selected by Engineer. Contractor shall repair core holes with dry-pack or a nonshrinking mortar. 1. Test Core Strength Concrete tested by coring shall be considered acceptable if the average strength of three cores is equal to at least 85 percent of the minimum specified 28 day strength and if no single core strength is less the 75 percent of the minimum 28 day strength. 3.3 Concrete Inspections An authorized inspector of the Owner will be present at all times during placing of structural, reinforced cast-in-place concrete. Before placing concrete he will inspect and approve (if satisfactory) accuracy of all formwork and quantity and placement of all reinforcing steel. Concrete construction activities shall not proceed until inspections are complete and the inspected construction is approved. END OF SECTION .- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 0141 0 - Testing and Inspection of Earthwork and Concrete - 5 of 5 SECTION 01 500 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS .- PART 1 - GENERAL 1.1 Work Included Mobilization, storage yard, temporary utilities, security, access roads and parking areas, temporary controls and traffic regulation. 1.2 Related Work A. Section 01 040: Coordination B. Section 01 300: Shop Drawing Submittals C. Section 01590: Field Offices and Sheds D. Section 01 700: Contract Closeout 1.3 Submittals - Storage yard description shall describe Contractor's proposed methods for dust and noise control in storage areas to satisfaction of Owner. Property owner's written approval of storage yard shall be submitted along with District Planning Department permit for use of property used as storage yard for project. Conform to setbacks and other conditions required by District or County regulations or permits. 1.4 Mobilization Obtain temporary easements, which Contractor may require for construction activities outside of existing easements and/or rights of way secured by Owner, at Contractor's expense. When using vacant property to park and service and store products, obtain approval from Engineer and permit from District Planning Department. Notify adjacent property owners of this proposed use. Obtain written approval from property owner stating requirements which are a condition of this approval. Remove obstruction in right-of -way before starting construction. Where private property, such as parked cars, must be removed prior to construction, notify respective property owners 72 hours in advance of right of way clearing to allow them to remove their property. 1.5 Temporary Utilities Construction power shall be purchased or generated on-site for constructing Work where existing outlets are not available. e City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic 8, Recycled Water Transmission Mains 01 500 Construction Facilities and Temporary Controls - 1 of 4 Construction water shall be clean and free from objectionable deleterious amounts of acids, alkalies, salts, or organic materials. If water is taken through fire hydrants, coordinate and obtain appropriate equipment from the Owner. Contractor shall pay all fees and deposits required. Reserve remaining outlets for use by fire department. Unless otherwise stated, make arrangements to develop water sources, provide backflow protection and supply labor and equipment to collect, load, transport, and apply water as needed for compaction, testing, concrete work, dust control dust, and other construction use. The Contractor shall not draw water from any fire hydrant, except to extinguish a fire, without obtaining permission from the local water purveyor. - Provide safe drinking water and sanitation facilities on jobsite at all times. Construction telephone shall be available at site at all times Work is in progress. Cellular phones are acceptable. 1.6 Construction Aids Scaffolding, rigging, hoisting and services needed to safely deliver and install products shall be provided. Remove same from premises when installation is complete. 1.7 Construction Signaqe Provide two (2) 4’ x 8’ project signs mounted to 4’ x 4’ posts. Submit detailed shop drawings for approval of verbiage and appearance. As a minimum, the verbiage should contain the City’s symbol, project name, CIP number and anticipated duration of construction. - 1.8 Access Roads and Parkinq Areas Construct and maintain access or haul roads required for project, and personnel movement into and within construction and excavation areas, subject to prior approval by Owner. Access facilities shall provide for surface drainage. Install and remove earth ramps as needed to protect concrete and asphalt curbs. Areas used for temporary access, haul roads and access from public roads shall be graded and restored to original grade conditions to Owner’s satisfaction. Treat access roads and parking areas as needed to control dust and prevent tracking of mud onto paved streets. 1.9 Temporary Controls Dust control operations shall prevent construction dust from harming or annoying persons living in or occupying buildings near Work. Use water or dust preventative to control dust. Cover or wet loads of excavated material or rubbish leaving site or of material being imported to prevent blowing dust. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 500 Construction Facilities and Temporary Controls - 2 of 4 Noise control shall be done to comply with local noise ordinances. Schedule Work to comply with noise ordinances. Install sound barriers if needed to comply with noise ordinances and Contract Documents. c. Fire danger shall be minimized at and near construction site. Protect surrounding private property from fire damage resulting from construction operations. Storm water management operations shall be conducted and maintained as needed to prevent runoff or seepage from entering excavations and to control erosion in conformance with Federal, State and local regulations. Any erosion control measures required to meet Federal, State and local regulations shall be designed and provided by the Contractor and included in the contract price for the work. 1.1 0 Traffic Requlation Contractor shall implement whatever traffic control measures may be required to facilitate the Work of this contract, in accordance with the encroachment permit, the traffic control plans and the direction of the field engineer/inspector, at no additional cost to the Owner than that included in original contract. 1.11 Unit Prices -. Payment for mobilization, demobilization, including payment for construction, modification, maintenance, removal and restoration associated with access, and storage facilities, will be included in the price bid for major items of Work for which mobilization is required. Payment for construction surveying and staking will be included in the price bid for items of Work for which alignment or limits must be staked. Payment for verification of field dimensions and utility locations will be included in the price bid for items of Work which may require relocation or refitting if field dimensions differ from those shown on plans. Payment for water to be furnished by Contractor for construction use will be included in the price bid for items to which it is appurtenant. Payment under these items will include full compensation for furnishing labor, products, tools and equipment and doing work necessary to develop sufficient water supply and furnishing necessary equipment for applying water as specified. * Payment for power to be furnished by Contractor for construction use will be included in the price bid for items to which it is appurtenant. Payment under these items will include full compensation for furnishing labor, products, tools, and equipment and doing work necessary to obtain and distribute power for construction purposes. ._ Payment for dust control, including dust palliatives and water supply and application will be included in the price bid for items of work for which dust control during construction is appurtenant. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 500 Construction Facilities and Temporary Controls - 3 of 4 Payment for costs arising from fire or prevention of fire will be included in the price bid for items of work for which fire protection during construction is needed. - Payment for noise control facilities will be included in the price bid for items of work where noise control facilities are required during construction. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 500 Construction Facilities and Temporary Controls - 4 of 4 SECTION 01 520 MAINTENANCE OF TRAFFIC AND DETOURS - PART 1 - GENERAL 1.1 Description The work of this Section includes furnishing, constructing, maintaining, and finally removing detours, road closures, lights, striping, dots, signs, barricades, fences, flares, miscellaneous traffic devices, flagmen, drainage facilities, paving, and such other items and services as are necessary to adequately safeguard the public from hazard and inconvenience. All such work shall be as provided in the specifications herein and shall comply with the ordinances, directives, and regulations of the City of Carlsbad. It is the intent of these Specifications to provide for adequate traffic detour routing and signing to maintain a smooth and safe flow of traffic through and around the construction areas. Traffic shall be maintained at those locations indicated and in conformance with the Plans and Specifications. 1.2 - 1.3 1.4 Related Work Described Elsewhere A. Shop Drawing Submittals: 01300 B. Shop Drawings, Product Data and Samples: 01340 C. Section 7-1 0 of the Supplemental Provisions Submittals A. The Contractor shall submit any proposed revisions to the traffic control plans, that were included within the construction plans, to the City of Carlsbad Traffic Department, for the their review and approval, thirty (30) days prior to the beginning of construction. No construction will be allowed until these traffic control plans have been approved by the City. B. The Contractor shall submit any proposed revisions to the traffic control plans, that were included within the construction plans, in accordance with the shop drawing submittal requirements in Sections 01300 and 01340 of these Technical Specifications. Notification A. Prior to the start of construction operations, the Contractor shall provide the City of Carlsbad police and fire departments, a construction schedule giving the expected starting date, sequence of work, timing for each phase of construction, completion date, and the name and telephone number of two responsible persons who may be contacted at any hour in the event of a condition requiring immediate correct ion. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 520 - Maintenance of Traffic and Detours - 1 of 3 B. Prior to restricting normal access from public streets to adjacent properties, the the nature of the access restriction, the approximate duration of the restriction, and the best alternate access route for that particular property. Contractor shall notify each property owner or responsible person, informing him of _- 1.5 Payment Payment for Maintenance of Traffic and Detours and for conforming to all provisions of these Specifications and all Federal, State, and Local regulations and requirements, unless otherwise specified and itemized on the bid form, shall be considered to be included in the contract unit or lump sum prices paid for the various items of work wherein maintenance of traffic and detours is required and no additional allowance will be made therefore. PART 2 - MATERIALS 2.1 Construction Siqning Construction signing used for handling traffic and public convenience shall conform to the most current edition of the State of California, Department of Transportation "Manual of Warning Signs, Lights, and Devices for Use in Performance of Work Upon Highways" and the most current edition of the "Work Area Traffic Control Handbook." All signs shall be illuminated or reflectorized when they are used during hours of darkness. All - cones, pylons, barricades or posts used in the diversion of traffic shall be provided with flashers or other satisfactory illumination if in place during hours of darkness. 2.2 Striping shall conform to the State of California, Department of Transportation, "Traffic Manual", latest edition. PART 3 - EXECUTION 3.1 General Contractor shall adhere to approved traffic control plan which is discussed in Section 1.3 Submittals. The signing, barricading, and diverting of traffic shall be subject to the approval of the City of Carlsbad. The Contractor shall maintain a 24-hour emergency service to remove, install, relocate, and maintain warning devices and shall furnish to the Owner's Representative and Police Department, names and telephone numbers of three persons responsible for this emergency service. In the event these persons do not promptly respond when notified by the Owner's Representative, the Owner's Representative reserves the right to call out other forces to accomplish such required emergency service. The Contractor will be held responsible for the cost of such emergency service. - City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 520 - Maintenance of Traffic and Detours - 2 of 3 3.2 Vehicular Traffic Control Public traffic shall be permitted to pass through the construction area with as little inconvenience and delay as possible at all locations where approved detour alternate routes are not available. Special requirements for traffic handling and permitted detours are contained in the Special Provisions. No cross streets or intersecting streets shall be closed without approval of the City of Carlsbad. Pre-timed actuation (recall) shall not be used. If inductive loops cannot be used, then video detection shall be used. c_ Prior to the start of each work day, the Contractor shall perform all necessary work incidental to and commensurate with the proper signing, detouring, barricading, etc. heretofore and hereinafter specified, that is required for that particular day's schedule of operations. No construction shall be permitted until such signing and detouring operations have been completed. At the completion of the project, the original striping pattern shall be replaced by the Contractor, unless directed otherwise by the City of Carlsbad. 3.3 Permanent Traffic Controls All existing permanent traffic control signs, barricades, and devices shall remain in effective operation unless a substitute operation is arranged for and approved by the City of Carlsbad, except inductive traffic loops, and magnetometer traffic detectors. Pre-timed actuation (recall) shall not be used. If inductive loops cannot be used, then video detection shall be used. c 3.4 Pedestrian Traffic Control A minimum of one 4-foot-wide pedestrian walkway shall be maintained and safely delineated along each public street at all times during construction. 3.5 Access to Adiacent Properties Reasonable access, as determined by the governing body, from public streets to all adjacent properties shall be maintained at all times during the construction. END OF SECTION .- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 520 - Maintenance of Traffic and Detours - 3 of 3 SECTION 01530 PROTECTION OF EXISTING UTILITIES PART 1 - GENERAL 1.1 SCOPE This section addresses verification and protection of existing utilities encountered during the course of construction. 1.2 RELATED WORK A. Section 02225: Utility Crossings B. CMWD Standard Specifications 1.3 DRAWINGS The Consulting Engineer has endeavored to determine the existence of utilities at the site of the work from the records of the owners of known utilities in the vicinity of the work. The positions of these utilities as derived from such records are shown on the Plans. The service connections to these utilities may not be shown on the Plans. - PART 2 - PRODUCTS (Not Applicable)- PART 3 - EXECUTION 3.1 CONTRACTOR'S DUTIES Prior to excavating the Contractor shall notify Underground Service Alert. The Contractor shall be responsible for verifying the actual location and elevation of all utilities in the field prior to start of construction by potholing all crossings, connections and parallel utilities which may impact the waterline installations by hand excavation methods. The Contractor shall protect all existing utilities from damage, whether they are shown on the plans or not. The existing utilities are to remain in place and be protected against damage during construction operations. The Contractor shall not interrupt existing utilities except when authorized in writing by the District. If the existing utilities interfere with construction, the Contractor shall submit drawings showing methods, material and sequences of operation for continuing construction and maintaining utility service. The Contractor shall not turn off or shut down any utilities. No additional cost will be accepted nor time extension granted, if a delay in work is caused by failure to comply with this requirement. /L- END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 530 - Protection of Existing Utilities - 1 of 1 SECTION 01 550 TRAFFIC CONTROL AND RE-STRIPING PART 1 - GENERAL 1.1 Work Included Mobilization, temporary signs, barriers, lights and flagging personnel, and striping. 1.2 Submittals The Contractor shall perform his work in accordance with the traffic control plans. 1.3 Payment All costs for the requirements in this section shall be included in the contract unit or lump sum prices for each bid item as delineated in Section 01025, and no additional allowance will be made therefore. PART 2 - MATERIALS AND EXECUTION - 2.1 General The Contractor shall implement approved Traffic Control Plans in accordance with these Specifications for all portions of this contract within or adjacent to public or private rights-of-way and streets and drives and replace all striping, reflectors, dots, or other traffic control materials. Traffic shall be maintained throughout the project in conformance with these Technical Specifications, General Requirements and the General Conditions. The Contractor shall furnish, construct, maintain and finally remove detours, road closures, lights, signs, barricades, fences, miscellaneous traffic devices, flagmen, and reconstruct paving and other such items and services as are necessary to adequately safeguard the public from hazard and inconvenience. All such work shall be as provided in the Contract Documents herein or as directed by the Owner's Representative, and shall comply with the ordinances, directives, and regulations of authorities with jurisdiction over the public or private roads in which the construction takes place, and over which detoured traffic is routed by the Contractor. It is the intent of these Specifications to provide for adequate traffic detour routing and signing to maintain a smooth and safe flow of traffic through and around the construction areas. Prior to the start of construction operations, the Contractor shall provide the fire and police departments in whose jurisdiction the project lies with the construction schedule giving the expected starting date, sequence of work, and timing for each phase of construction completion -- date, and the name and telephone number of two responsible persons who may be contacted at any hour in the event of a condition requiring immediate correction. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 550 - Traffic Control and Re-Striping - 1 of 3 2.2 Construction Signs And Barricades Construction signs and barricades used for handling traffic and for public convenience shall conform to the Traffic Control Plans furnished with the Contract Documents or as required by them and the State of California, Department of Public Works "Manual of Warning Signs, Lights, and Devices for Use in Performance of Work Upon Highways", latest edition, and "Work Area Traffic Control Handbook", latest edition. The Contractor shall refer to above mentioned document and also shall reference general provision section 7-1 0.3.1. Work provided shall conform to most stringent requirements if not stated in the project documents. - All signs and barricades shall be illuminated or reflectorized when they are used during hours of darkness. All delineators, cones, barricades or posts used in the diversion of traffic shall be provided with flashers or other satisfactory illumination if in place during darkness. The signing, barricading, and diverting of traffic shall be subject to the District. The Contractor shall maintain a 24-hour emergency service to remove, install, relocate, and maintain warning devices and shall furnish to the Owner's Representative and Police Department names and telephone numbers of three person responsible for this emergency service. In the event these persons do not promptly respond when notified by the Owner's Representative, the Owner's Representative reserves the right to call other forces to accomplish such required emergency service, and the Contractor will be held responsible for any and all costs incurred by the Owner. 2.3 Vehicular Traffic Control Prior to the start of each work day, the Contractor shall perform all necessary work incidental to and commensurate with the proper signing, detouring, barricading, etc., heretofore and hereinafter specified, that is required for that particular day's schedule of operations. No construction shall be permitted until such signing and detouring operations have been completed. At the completion of the project, the original striping pattern shall be replaced by the Contractor, unless directed otherwise by the Owner's Representative. Striping shall conform to the State of California, Department of Transportation, "Traffic Manual", latest edition. - 2.4 Permanent Traffic Controls All existing permanent traffic control signs, barricades and devices shall remain in effective operation unless a substitute operation is arranged for and approved by the RESPECTIVE AUTHORITY as a portion of vehicular traffic control above, except inductive traffic loops, and magnetometer traffic detectors. Only advance inductive traffic loops which are removed during construction, or are damaged, shall be replaced in kind by the Contractor from the nearest pullbox, all in accordance with appropriate provisions of Section 86 "Signals and Lighting" of the State Specifications (except measurement and payment), and the existing "As-Built" Plans for each particular intersection involved. Copies of these as-builts may be found in the offices of the respective authorities. Contractor shall provide and install permanent video detection systems, where indicated on Traffic Control Plans. Contractor shall provide a separate line item bid price for such devices. - City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 550 - Traffic Control and Re-Striping - 2 of 3 Any magnetometers in the streets damaged during the course of construction shall be replaced - in full up to the pullbox. Temporary splices during construction are permitted. 2.5 Blocking Of Drivewavs The Contractor shall conform to the requirements in the general provision section 7-1 0.1. The notice to the public shall conform to the example provided in Appendix “A. PART 3 - EXECUTION (Not Applicable) END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 550 - Traffic Control and Re-Striping - 3 of 3 SECTION 01 570 MAINTENANCE AND PROTECTION OF TRAFFIC - PART 1 - GENERAL 1.1 DESCRIPTION A. B. C. e. D. E. F. G. All streets, trafficways, and sidewalks shall be kept open in a safe manner for the passage of traffic and pedestrians during the construction period unless otherwise approved by the City. CONTRACTOR, at his expense, shall obtain traffic permit from the City. When required to cross, obstruct or temporarily close a street, trafficway or sidewalk, CONTRACTOR shall provide and maintain suitable bridges, detours or other approved temporary expedient for the accommodation of vehicular and pedestrian traffic. Closings shall be for the shortest time practical, and passage shall be restored immediately after completion of bacMill and temporary paving or bridging. No two adjacent streets can be closed at the same time. CONTRACTOR shall give the ENGINEER 96 hours advance notice of his proposed operations within the public right-of-ways. CONTRACTOR shall give 72 hours advance notice to owners or tenants of private property/business who may be affected by his operations. 1. CONTRACTOR will restore access to propertieshusiness as soon as possible. If primary access cannot be restored, CONTRACTOR will provide an alternate which will be predetermined with the property/business owner prior to any restrictions being done. CONTRACTOR shall provide signs, signals, barricades, flares, lights and all other equipment, service and personnel required to regulate and protect all traffic, and warn of hazards. All such work shall conform to requirements of the traffic control plans and the City of Carlsbad. Remove temporary equipment and facilities when no longer required, restore grounds to original, or to specified conditions. All open trenches shall be covered with a traffic bearing cover during non-working hours. Any damage caused to any roads which are caused by the CONTRACTOR'S activities will be promptly repaired at the CONTRACTOR'S expense. The CONTRACTOR shall also maintain all access routes free of all debris or spillage's. Concrete trucks must be washed out at a designated area on site. All access roads leading to the site must be promptly cleaned of any debris or spillage resulting from the CONTRACTOR'S operations. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 570 Maintenance and Protection of Traffic - 1 of 2 PART 2 - PRODUCTS (Not Applicable) PART 3 - MATERIALS (Not Applicable) City of Carlsbad 03/04 (DBE) END OF SECTION ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 570 Maintenance and Protection of Traffic - 2 of 2 SECTION 01 580 PROJECT IDENTIFICATION AND SIGNS PART 1 - GENERAL 1.1 DESCRIPTION A. Furnish, install and maintain temporary project identification and informational signs. B. The CONTRACTOR will include in the bid the cost to provide, install and maintain, at the worksite, two Project Identification Signs. CONTRACTOR will be required to provide the sign, mount the sign in a manner and location approved by the DISTRICT and return the sign to the DISTRICT upon acceptance of the project by the City. A sign permit, if required, will be obtained by the DISTRICT at no cost to the CONTRACTOR. C. No signs except those specified shall be displayed unless approved by DISTRICT. 1.2 SUBMllTALS A. Submit in accordance with prescribed Shop Drawing procedure. B. Include the following information: 1. Type of grade of materials. 2. Layout, size, trim, framing, supports and coatings. 3. Size and style of lettering. 4. Samples of colors. 1.3 CONSTRUCTION A. Use %-inch exterior grade plywood unless shown otherwise or approved. B. Use, trim, mitered on all edges. C. Design signs and supports to withstand 75 mile per hour wind. D. Paint with exterior gloss-finish enamel. Sign painter shall be a professional in the type work required. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 580 Project Identification and Signs - 1 of 2 1.4 INSTALLATION AND MAINTENANCE A. Location of signs shall be as directed by the DISTRICT. B. Maintain signs so they are clean, legible and upright. Keep grass and weeds cut away from signs. C. Repair and repaint damaged signs. Relocate signs as required by progress of the Work. D. Remove signs when project is completed or when directed by DISTRICT. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic i3 Recycled Water Transmission Mains 01 580 Project Identification and Signs - 2 of 2 SECTION 01 590 FIELD OFFICES AND SHEDS PART 1 - GENERAL 1.1 Work Included Temporary field off ice and accessory equipment for Owner. 1.2 Building Construction The Contractor shall provide a Class A Field Office. This office shall have a minimum floor space of 480 square feet, two partitioned offices with doors, and a window area of not less than 30 square feet. All rooms shall be equipped with telephone service that includes phone jacks for two (2) separate phone lines, one (1) dedicated fax line, and one (1) dedicated phone line for a PC modem. All doors and windows shall be provided with screens; window coverings shall be provided on all windows. The field office shall be selected and approved by the Owner before delivery and setup. The Contractor will provide, including making application and paying all costs and fees for, electrical, telephone, water, and sanitary services. All work will include, but not be limited to the following: a temporary power pole for electrical meter and service and telephone service. The field office trailer will also be equipped with water service and sanitary service. The Contractor will provide and pay for sanitary service including a septic tank mounted underneath the field office to be serviced at least once a week. An outdoor lighting fixture with 300 watt bulbs will be installed to effectively light the area around the office facility. Heating and air conditioning of sufficient capacity will be provided at no expense to the Owner to adequately control temperature in the trailer at all times. The Contractor will also construct a wooden handicap ramp with handrailing according to ADA standards for handicap access. - All facilities described herein will be removed under the Owner’s direction when the project is completed. All office furniture, equipment and supplies listed below will be in new condition and delivered and setup in the Owner’s field office trailer. The Contractor will coordinate all deliveries with the Owner’s field representative. Contractor shall also provide the office furnishings and features described in revised Table 1 “Required Field Office Characteristics” which is attached to this addendum. Contractor shall pay all monthly telephone charges and the Construction Manager will pay for all long distance charges. -c In conformance with Paragraph 8.05.5 Removal of Facilities of the Special Provisions, all computer equipment and other off ice equipment and accessories provided by the Contractor for equipping the field office shall become the property of the City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01590 - Field Offices and Sheds - 1 of 3 Contractor at the completion of the Work. Any furniture provided by the Owner or Construction Manager for use in the field office shall remain their property. 1.3 Accessory Equipment A. Electrical Outlets and Lighting Provide warm white fluorescent light fixtures to evenly illuminate the rooms to a minimum of 50 foot-candles and an average of 70 foot-candles measure at desk height. Provide a minimum 60-watt light fixture in the lavatory facility. Provide light switch in each room. Provide two duplex 120-volt outlets in each room (one only in restroom). 1.4 Unit Prices Payment for the field office,, including cost of building (or trailer), utilities, services and removal, will be proportionately spread throughout the price bids for all of the other work items shown on the bid form. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 590 - Field Offices and Sheds - 2 of 3 TABLE 1 : REQUIRED FIELD OFFICE CHARACTERISTICS Standard Specification Class "A" Field Off ice Off ice square footage Window area Number of office rooms Air conditioning Telephone service Desk 1 required Table Chairs Type Drafting tables Dimensions Drawers and locks Dimensions Dimensions Equipment Drafting stools Plan rack Type Metal stick files c. Filing cabinet Dimensions Drawers Locks Dimensions Adjustable shelves Bookcase Wastebaskets Office equipment Computer Equipment Sanitary Facilities Toilet Shower Wash basin and mirror Fixtures rc Exhaust fan City of Carlsbad 03/04 (DBE) 480 sf minimum 30 sf minimum 2 required required with answering machine 3' x 6' required 1 required 3' x 5' or 4' x 8' 4 required cushioned off ice swivel chair 1 required 4' x 6' drafting machine and parallel bar 1 required cushioned 1 required 6 required 1 required 18" wide x 30" deep x 52" high 4 required 1 required 12" deep x 48" long x 60" high 5 required 1 required copy machine fax machine on dedicated phone line wall-mounted markerboard (4' x 4') and 3 markers each in red, green, blue and black bottled water service with hot and cold water Provide equipment per specifications required not required required towel rack medicine cabinet toilet paper dispenser soap dispenser paper towel cabinet required ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 590 - Field Off ices and Sheds - 3 of 3 SECTION 01 600 MATERIAL AND EQUIPMENT PART 1 - GENERAL 1.1 Work Included Transportation and handling, storage and protection, acceptable manufacturers, and procedures for seeking substitutions. 1.2 Related Work A. Section 01300: Shop Drawing Submittals B. Section 01 400: Quality Control C. Section 01 700: Contract Closeout 1.3 Submittals Supplemental information, including certification of compliance, transcripts of acceptance tests, samples, names and addresses of nearest local representatives and list of three installations, shall be submitted at Owner's request for product substitutions. - 1.4 Qualitv Assurance If products are furnished which differ from those shown and which require changes to enclosures, mounting and support structures, power and control circuitry or other work to accommodate furnished product, provide changes required at no additional cost to Owner and of same quality as shown. 1.5 Deliverv, Storaqe and Handling Deliver products to jobsite in manufacturer's original, unopened, labeled packaging. Oil lubricated gearing, bearings and other lubricated components shall be shipped with oil soluble protective coating as described in warranty requirements or recommended by manufacturer. Coating shall provide protection for one year after final acceptance. Protect products against moisture, temperature extremes, dust, debris, tampering, vandalism, ultraviolet radiation, or damage from improper handling, storage, or exposure. Protect exposed metals from rust and corrosion even though they will be sandblasted or otherwise cleaned before painting. c Clean and protect machined surfaces and shafting from corrosion using proper type and amount of coating as described in warranty requirements to assure protection to one year after final acceptance. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01600 - Material and Equipment - 1 of 2 Store items not designed for outdoor exposure off ground and under cover. Handle products with care and using proper equipment according to manufacturer's recommendations. Lift large heavy items only at points designated by manufacturer. Do not drop, drag, bump or handle products in manner that causes bruises, cracks, scratches or other damage. Use padded slings and hooks for lifting as needed to prevent damage. Improper handling shall be cause to reject mishandled products. __ Inspect each product item for damage, defects, completeness and correct operation before installing. Notify Owner in writing if delivered or stored product is damaged. Do not repair damaged products without prior written approval. Maintain records for Owner's review of deliveries to show Contractor's order number, purchase order number and equipment number. Include labeling or shipping tag in records. PART 2 - PRODUCTS 2.1 Acceptable Manufacturers Products of listed acceptable manufacturers shall meet specifications notwithstanding the fact that manufacturer is "listed". Owner reserves right to reject submittals and products from "acceptable manufacturers" if they fail to demonstrate compliance with specifications. .- 2.2 Materials and Equipment Materials and materials sources shall be approved by Owner at least three days before use of materials in Work. Similar items on project shall be products of same manufacturer. Corresponding parts of identical products shall be interchangeable. Mating ends of pipe shall match. Design and fabrication of products shall ensure products withstand stresses and loads which may occur during testing, installation, start-up and normal operation. Furnish mounts, guides, bearing plates, flanges, anchor and attachment bolts and screws, saddles, supports, pads and skids necessary to securely mount products and equipment. PART 3 - EXECUTION (Not Applicable) END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic i3 Recycled Water Transmission Mains 01 600 - Material and Equipment - 2 of 2 ,- SECTION 01 61 0 SUPPLIERWMANUFACTURERS' SPECIAL SERVICES PART 1 - GENERAL 1.1 Scope This section covers the Work for providing special services by the suppliers and manufacturers associated with this Work. PART 2 - PRODUCTS 2.1 General Contractor, suppliers and manufacturers shall provide materials, equipment, devices, labor, travel costs and expenses as required to perform the specified services. PART 3 - EXECUTION 3.1 Installation Assistance Competent and experienced technical personnel shall represent the manufacturer of all equipment and systems as may be necessary to resolve assembly or installation problems at the worksite, or at the location where factory built equipment is being assembled by others into a larger, integrated system, which are attributable to, or associated with, the equipment furnished. - 3.2 Functional Testing Where functional testing services are called for in the Technical Specifications, or when technical assistance is necessary to resolve performance problems that may become apparent during the performance test, the manufacturer's representative shall provide such assistance as necessary to demonstrate the specified performance. 3.3 Plant Startup Where startup services are called for in the Technical Specifications, or when technical assistance is necessary due to any malfunction of the equipment or system furnished, the manufacturer's representative shall provide such services as necessary to provide the Owner with an acceptable operating facility. 3.4 Training of Owner's Personnel Where training is called for in the Technical Specifications, the manufacturer's or supplier's representative shall provide classroom and on-the-job training for the Owner's personnel in the operation and maintenance of the specified equipment. /I City of Cartsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 61 0 - SupplierWManufacturer's Special Services - 1 of 2 3.5 Scheduling and Coordination of Services The Contractor shall designate and provide one person to be responsible for scheduling, coordinating, and expediting the specified services. Scheduling the services shall be done in cooperation with, and with the approval of the Engineer and Owner's operating personnel. Such schedule shall be arranged with the appropriate subcontractors, manufacturers, and suppliers in sufficient time to assure their compliance with the service requirements. 3.6 Costs for Services Cost for providing services during installation, testing, and for the training of Owner's personnel shall be included in the costs for providing the applicable specified equipment. Where the number of days for services is stated in the Technical Specifications, this shall be considered as the minimum number of days. Should additional time be required for services, such time shall be at the expense of the manufacturer, supplier, or Contractor as applicable, and at no additional cost to the Owner. Where the number of days for services is not stated in the Technical Specifications, services shall be furnished for installation, testing, and plant startup as required to provide the Owner with a satisfactory operating facility. END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 61 0 - Supplier's/Manufacturer's Special Services - 2 of 2 SECTION 01 630 PRODUCT OPTIONS AND SUBSTITUTIONS PART 1 - GENERAL 1.1 Scope This section addresses procedures for submittal of requests for substitution for materials specified in these specifications by proprietary names. 1.2 General Requirements A. B. C. D. E. Standard Products Whenever in the specifications products are by reference standard, any product meeting the standards referenced may be used. Information on such products shall be submitted in accordance with Section 01300. Proprietary Products Whenever in the specifications any material, article or process is indicated or specified by trade, patent or proprietary name or name of manufacturer such specification for material, article or process, unless marked "no substitution", shall be deemed to be followed by the words "or equal as accepted in writing by the Engineer", and will be considered as a substitution. Selection of Proprietary Product Where more than one proprietary name is specified, the Contractor may provide any one of the materials or equipment specified. Only one brand, kind or make of material or equipment shall be used for each specific purpose throughout the Work notwithstanding that similar materials or equipment of two or more manufacturers or producers may be specified for the same purpose. Substitution Request Procedure Submit a written request on the enclosed form for proposed substitutions to the Engineer not later than 35 days after date of "Notice of Award". Proposed substitutions relating to a particular subcontract or trade shall be submitted at one time. If the Engineer accepts any proposed substitutions, such acceptance will be set forth in a Change Order. No substitution will be considered after this 35 day period. Contractor's Responsibility for Construction Modifications Drawings have been detailed in compliance with ICBO Evaluation Report for material specified. If a proposed substitute material is accepted by the Engineer, the Contractor will assume the responsibility for construction modifications and City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 630 - Product Options and Substitutions - 1 of 7 additional costs required by reason of this acceptance. If the substitution results in a decrease in cost, the amount is to be submitted for consideration. - F. Systems of Like Manufacture Where materials or items of manufacturer are specified in groups and are made or furnished by one manufacturer, no substitution will be considered that is not made or furnished similarly by one manufacturer. Where the Contractor proposes to use a system of equipment other than that specified or detailed on the Drawings the substitution shall be proposed as a complete system. 1.3 Requirements for Submittinq Substitutions A. B. C. D. Substantiating Data The Contractor shall submit with his written request for a proposed substitution all data substantiating his request as well as a "Certificate of Suitability" certifying that the proposed substitution is equal or better in all respects to that specified and that it will, in all respects perform the function for which it is intended. The Contractor shall include with his request all required samples. All written requests and data for proposed substitutions shall be submitted in three copies. Determination of Equality It shall be the responsibility of the Contractor to submit complete information to the Engineer so that proper evaluation can be made. The burden of proof of equality of the substituted item shall be on the Contractor. Acceptance of such substitutions is entirely at the discretion of the Engineer and Owner. All materials or items of manufacture, which the Contractor proposes to substitute for those specified, must be accepted by the Engineer before they may be ordered. -I List of Accepted Substitutions The Engineer will issue to the Contractor a list setting forth those items for which substitutions are accepted. No substitution will be accepted for any materials or item of manufacture called for in the Contract Documents which is not of equal quality and which does not possess equal design or color characteristics to those of the specified material or item. Denial of Substitution If, in the opinion of the Engineer or Owner, the proposed substitution is not equal or better in every respect to that so indicated or specified, or was not submitted for acceptance in the manner outlined above, the Contractor shall furnish the specified materials. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 630 - Product Options and Substitutions - 2 of 7 ..-- E. Responsibility for Coordinating Substitutions with Construction Trades It shall be the responsibility of the Contractor, in proposing a substitution for any item herein specified, to inform all other trades, vendors, and subcontractors of the effects said substitution will have upon their work or products. Failure to so notify shall require that the Contractor make payments arising from alterations in specified materials or methods necessary to complete the Work in an approved and acceptable manner. 1.4 Contractor's Responsibility for Cost of Substitution Reviews The Contractor shall bear all costs by Engineer and Owner to review Requests for Substitutions. Review costs shall be deducted on a regular basis from monthly progress payment. Any and all design change costs, if any, because of an approved substitution will be borne by the Contractor. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION .- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 630 - Product Options and Substitutions - 3 of 7 SUBSTITUTION REQUEST FORM TO: City of Carlsbad 1635 Faraday Avenue Carlsbad, CA 92008 PROJECT NAME: El Camino Real / Cassia Road 24” And 30” Domestic Water Transmission Mains FROM CONTRACTOR: We hereby submit for consideration the following product substitution of specified item for above project: DRAWING OR SHEET NUMBER SECTION NO, - OR PARAGRAPH SPECIFIED ITEM Proposed substitution: Attach complete dimensional information and technical data, including laboratory tests, if applicable. Include complete information on changes to Drawings andhr Specifications which proposed substitution will require for its proper installation. Submit with request all necessary samples and substantiating data to prove equal quality and performance to that which is specified. Clearly mark manufacturer’s literature to indicate equality in performance. Differences in quality of materials and construction shall be indicated.. Fill in Blanks Below: A. Does the substitution affect dimensions shown on Drawings? Yes - No - If yes, clearly indicate changes. B. Will the undersigned pay for the changes to the project design, including engineering and detailing costs caused by the requested substitution? C. What effect does the substitution have on other trades? D. What effect does substitution have on applicable code requirements? E. What is the ICBO Approval Number? City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 630 - Product Options and Substitutions - 4 of 7 F. Differences between proposed substitution and specified item: G. Manufacturer's guarantees of the proposed and specified items are: Same -Different-( Explain) CONTRACTOR'S CERTl FlCATiON OF PERFORMANCE AND ASSUMPTION OF LIABILITY FOR EQUAL PERFORMANCE Submitted By: Signature Title -- Firm For use by Design Engineer: - Accepted - Accepted as Noted - Not Accepted - Received Too Late - Approved as Alternate-See Bid Form BY Date Remarks Address Telephone Date Signature must be by person having authority to legally bind his firm to the above terms. Failure to provide legally binding signature will result in retraction of approval. Concurrence By: Owner City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 630 - Product Options and Substitutions - 5 of 7 SUBSTITUTION REQUEST FORM .- TO: City of Carlsbad 1635 Faraday Avenue Carlsbad, CA 92008 PROJECT NAME: El Camino Real 20-Inch Recvcled Water Transmission Main FROM CONTRACTOR: We hereby submit for consideration the following product substitution of specified item for above project: DRAWING OR SHEET NUMBER OR PARAGRAPH SPECIFIED ITEM SECTION NO. - Proposed substitution: Attach complete dimensional information and technical data, including laboratory tests, if applicable. Include complete information on changes to Drawings and/or Specifications which proposed substitution will require for its proper installation. Submit with request all necessary samples and substantiating data to prove equal quality and performance to that which is specified. Clearly mark manufacturer's literature to indicate equality in performance. Differences in quality of materials and construction shall be indicated.. Fill in Blanks Below: A. Does the substitution affect dimensions shown on Drawings? Yes - No - If yes, clearly indicate changes. B. Will the undersigned pay for the changes to the project design, including engineering and detailing costs caused by the requested substitution? C. What effect does the substitution have on other trades? D. What effect does substitution have on applicable code requirements? -_ ~~~~~ ~~ ~ ~~~~~ E. What is the ICBO Approval Number? City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 630 - Product Options and Substitutions - 6 of 7 Differences between proposed substitution and specified item: G. Manufacturer's guarantees of the proposed and specified items are: Same - Different-( Explain) CONTRACTOR'S CERTIFICATION OF PERFORMANCE AND ASSUMPTION OF LIABILITY FOR EQUAL PERFORMANCE Submitted By: For use by Design Engineer: Accepted - Accepted as Noted - Not Accepted - Received Too Late - Approved as Alternate-See Bid Form - Signature Title - Firm Remarks Address Telephone Date Signature must be by person having authority to legally bind his firm to the above terms. Failure to provide legally binding signature will result in retraction of approval. Concurrence By: Owner City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 630 - Product Options and Substitutions - 7 of 7 ~~ SECTION 01700 CONTRACT CLOSEOUT PART 1 - GENERAL 1.1 Work Included Specific administrative procedures, closeout submittals, and forms to be used at substantial completion and final completion of Work, and project record documents. 1.2 Related Work A. Section 01 300: Shop Drawing Submittals B. Section 01400: Quality Control C. Section 01 41 0: Start-up and Testing Procedure D. Section 01 71 0: Cleaning and Final Cleaning E. Section 01 730: Operating and Maintenance Data and Training - 1.3 Qualitv Assurance Upon completion of Contract, Work shall be finished, tested and ready for operation. Work shall fulfill its intended purpose as described in Contract Documents, in submittals, and in manufacturer's literature. Where connections or disruptions have been made to existing work, repair, reactivate, refill and recharge components, restoring them to preconstruction conditions. Follow procedures of authorities having Ownership or jurisdiction for work involving existing utilities and services. 1.4 Project Record Documents Final record drawings shall be prepared from survey notes, field notes and system demonstration logs and shall be submitted in ink on sepia mylar prints bearing seal of registered land surveyor who performed survey for record drawings. Note hydraulic and electric equipment control settings used for system demonstration on record drawings. Record changes neatly and accurately using 1/8-inch size lettering and dimensions. Monument survey showing record locations of monuments or benchmarks disturbed and reset by Contractor shall be sealed by surveyor and submitted to Owner. 1.5 Unit Prices .- Payment for record drawings required in Contract Documents will be included in the price bid for items of work for which record drawings are required. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01700 - Contract Closeout - 1 of 2 50% of the lump sum bid price after Contractor submits record drawings for initial review by the Owner. 50% of the lump sum bid price after Contractor submits final record drawings incorporating or responding to the comments of Owner. 1.6 Warrantv Warranties shall cover improper assembly or erection, defective workmanship and products, and incorrect or inadequate operation. For equipment bearing manufacturer's warranty in excess of one year, furnish copy of warranty to Owner named as beneficiary. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.1 Adjusting and Cleaning Valve box cover elevations are not shown on drawings. Determine and set cover elevations in field so that finished rim elevations are flush with finished pavement where directed by Owner's Representative. - 3.2 Extra StocMSpare Parts Spare parts required shall be delivered in manufacturer's original containers labeled to completely describe contents and equipment for which it is furnished. END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 700 - Contract Closeout - 2 of 2 SECTION 01 71 0 CLEANING AND FINAL CLEANING PART 1 - GENERAL 1.1 Work Included Cleaning during construction and final cleaning on completion of the Work. Provisons noted in Section 7-8 of the supplemental provisions. 1.2 Cleanina Durinq Construction Maintain areas covered by Contract, adjacent properties, and public access roads. Keep these areas free from waste, debris and rubbish caused by construction. Conduct cleaning and disposal to comply with local ordinances and antipollution laws. Do not burn or bury rubbish and waste materials on project site. Do not dispose of volatile wastes, such as mineral spirits, oil or paint thinner, in storm or sanitary drains. Do not dispose of wastes into streams or waterways. Use only cleaning materials recommended by manufacturer of surface to be cleaned. - Wet down dry materials and rubbish to prevent blowing dust. Provide containers for collection and disposal of waste materials, debris and rubbish. Clean public access roads to site. Remove material falling from haul trucks. 1.3 Final Cleaninq Restore construction areas to preconstruction conditions after completing of Work and immediately before final inspection. Restore lines and grades of areas used for earthwork storage. Clean, sweep, and wash Work and equipment including finishes. Remove grease, dust, dirt, stains, labels, fingerprints and foreign materials from sight- exposed interior and exterior finished surfaces. Polish surfaces so designated. Repair, patch and touch up marred surfaces to specified finish to match adjacent surfaces. Broom-clean paved surfaces. Rake-clean other surfaces of grounds. Y Remove from Owner's property temporary structures and materials, equipment and appurtenances not required as part of, or appurtenant to, completed Work. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01710 - Cleaning and Final Cleaning - 1 of 2 After Work is complete, remove from site loose concrete, lumber, wire, aggregate or rock piles, reinforcing, rubbish, debris and materials not incorporated in Work. Remove excess pointing mortar materials and other debris within pipes. - 1.4 Unit Prices Payment for cleaning will be included in items of Work to which cleaning is appurtenant. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) City of Carlsbad 03/04 (DBE) END OF SECTION -, ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01 71 0 - Cleaning and Final Cleaning - 2 of 2 c PART 1 - SCOPE SECTION 01720 RECORD DRAWINGS 1.1 General Requirements Contractor shall keep accurate and legible records on a single set of full size project blueline prints of the Drawings. Make the record drawings available for review by Owner in Contractor's field office. Maintain record drawings on an up-to-date basis with all entries reviewed by Resident Engineer. Protect the record set from damage or loss. 1.2 Detailed Requirements The Contractor shall provide Record Drawings which shall clearly show all differences between the contract Work as drawn and as installed for all concealed construction, as well as construction added to the Contract which is not indicated on the Contract Drawings. Concealed shall mean construction installed underground or in an area which cannot be readily inspected by use of access panels, inspection plates or other removable features. -c Show all changes in the Work, or Work added on the Record Drawings in a contrasting color. In showing changes in the Work, or added Work, use the same legends that are used on the Contract Drawings. Indicate exact locations by dimensions and exact elevations. Give dimensions from a permanent point. Record by marking on the Drawings all changes in the Work which occur during construction, including adding approved change orders. Show locations by key dimensions, depths, elevations of all underground lines, conduit runs, sensor lines, valves, capped ends, branch fittings, pull boxes, etc. Record information on how to maintain and/or service concealed Work. Make a record of finalized hydraulic and electrical equipment control settings in the tables and spaces provided on the Drawings. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01720 - Record Drawings - 1 of 2 PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.1 General Deliver the marked record set of Drawings to the Owner prior to acceptance of the Work. END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01720 - Record Drawings - 2 of 2 SECTION 01730 OPERATING AND MAINTENANCE DATA AND TRAINING PART 1 - GENERAL 1.1 Work Included Operation and maintenance manual. Training of Owner's personnel 1.2 Related Work A. Section 01300: Shop Drawing Submittals 1.3 Submittals Operation and Maintenance manual shall be submitted. Training outline shall be submitted for instruction program for Owner's personnel. Equipment data sheets shall be submitted for equipment furnished under each specification section. Include data sheets in Operation and Maintenance Manual. .I 1.4 Operation and Maintenance Manual Prepare and submit 3 copies of Operation and Maintenance Manual containing Shop Drawings, Catalog Data, Installation or Application Instructions, and operation and Maintenance Instructions requested in Contract Documents. Deliver copies in D-ring binders tabbed and indexed by specification sections. Include table of contents. Label binders with project name. Each section of Operation and Maintenance Manual shall include: A. B. C. D. E. F. G. Equipment data sheet describing function of equipment. Catalog data Shop drawings Installation or application instructions Operation and maintenance instructions Parts lists Serial numbers. List name, address and telephone number of vendor. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01730 - Operating and Maintenance Data and Training - 1 of 2 Before requesting payment for 80 percent completion point for the total contract, submit two of six required copies of the Operation and Maintenance Manual containing copies of material available at that time. -_ Within 30 days after approval by Owner of the two-copy submittal, submit remaining four copies of Operation and Maintenance Manual. 1.5 Unit Prices Payment for operation and maintenance manuals required in Contract Documents will be included in the price bid for items of work for which sections of Operation and Maintenance Manuals are required. Payment for operation and maintenance training required in Contract Documents shall be included in the price bid for items of work for which operation and maintenance training is required. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION -. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 01730 - Operating and Maintenance Data and Training - 2 of 2 SECTION 021 30 REMOVAL AND RESURFACING OF PAVEMENT SURFACES PART 1- GENERAL 1.1 Description Street pavement and surfaces shall be removed and replaced in all areas of construction excavation in conformance with details shown on the Plans and/or as specified herein. Resurfacing of existing pavement and surfaces damaged or removed in connection with the construction of project improvements including all appurtenances, shall conform to the provisions of permits issued by the local governing body, agency or association having jurisdiction of public and private streets for work performed within the rights-of-way of the respective governing body, agency or association. 1.2 Related Work Described Elsewhere The Contractor shall refer to the following Specification section(s) for additional requirements: A. Earthwork: Section 02200 B. C. Cast-in-Place Concrete: Section 03300 Asphaltic Concrete Pavement: Section 0251 0 c 1.3 Submittals Submittals shall be provided as required in the related section(s) of the Specifications for the appropriate material. 1.4 Pavment Payment for the Work in this section shall be included as part of the lump sum or unit-price bid amount for which such Work is appurtenant thereto. PART 2 - MATERIALS AND EXECUTION 2.1 Earthwork Earthwork shall conform to the provisions of Section 02200, Earthwork. 2.2 Pavement Removal A. General: Street pavement or existing road surfacing shall be removed within the limits of all construction excavations prior to proceeding with excavation operations of any nature. Surplus material shall be removed as specified in the Specifications. Prior to removal of existing surfacing, pavement cuts for pipelines shall be made as shown on the Plans and/or specified herein. All pavement cuts for pipelines shall be neat and straight along both sides of the trench and parallel City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 021 30 - Removal and Resurfacing of Pavement Surfaces - 1 of 3 B. C. D. to the alignment of the pipe to provide an unfractured and level pavement joint for bonding existing surfacing with pavement replacement. Where large irregular surfaces are removed, such trimming or cutting as hereinafter provided shall be parallel with roadway centerline or at right angles to the same. All cut edges shall provide clean, solid vertical faces free from all loose material. Portland Cement Concrete Surfaces: Concrete pavement, including cross gutters, curbs and gutters, sidewalks, driveways, and concrete surfaces of whatever nature, shall be saw cut to a minimum depth of 2Z-inches prior to removal in accordance with details shown on the Plans or as specified herein. Said saw cut shall be made at the edge of the trench and/or excavation. With the written permission of the Owner's Representative pneumatic tools or other approved equipment may be used to cut concrete pavement prior to removal at the limits of the excavation. In such an event, the saw cut as provided herein, shall be made after backfilling, and the additional concrete pavement shall be removed and disposed of by the Contractor prior to resurfacing. Plant Mix Surfacing (Asphalt Concrete Pavement): Streets, alleys and areas surfaced with asphalt concrete pavement shall be initially cut by means of pneumatic pavement cutters or other approved equipment at the limits of the trench and/or excavation prior to removal of surfacing. Pavement saw-cutting will be required within the right-of-way of the county roads and highways, or as required by local governing bodies. Road-Mixed Surfacing: Streets, alleys and areas surfaced with road-mixed surfacing shall be cut at the limits of the trench and/or excavation prior to removal of existing surfacing. Cuts may be made with pneumatic tools or other approved equipment. The extra trimming width by saw cuts prior to resurfacing will not be required unless otherwise specified. 2.3 Asphalt Concrete Resurfacing In all areas in which the surface is removed, broken, or damaged by equipment, or in which the ground has caved in or settled due to the installation of the improvements, the surface shall be restored to the original grade and crown section by the Contractor at his own expense. In the absence of specific designation on the Plans, and where the street has been improved with roadway surface, base course, curb, sidewalk or gutter, trenches, or damaged sections shall be restored with the type of improvement conforming to that which existed at the time the Contractor entered upon the Work. Prior to resurfacing, the existing surfacing shall be removed as provided above. All Work shall match the appearance of the existing improvements and finished pavement shall not deviate from existing grade by more than 1/8- inch in 10-feet and shall be free from ruts, depressions, and irregularities. Where large irregular surfaces are to be resurfaced, existing surfacing shall be cut and removed as provided herein. Asphaltic emulsion shall be applied to the vertical faces of all asphaltic concrete pavement against which the pavement replacement materials are to be placed. The completed surface, when ready for acceptance, shall be thoroughly compacted, true to grade and cross section, and shall be free from ruts, depressions, and irregularities. I City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 021 30 - Removal and Resurfacing of Pavement Surfaces - 2 of 3 Asphalt pavement shall be replaced 1-inch thicker than that removed. Aggregate base shall be a minimum of 4-inches thick. The trench section shall be lapped at least 12-inches on each side and shall be hand raked so that the lapped section will feather-in smoothly with the existing pavement. The resulting edge of contact between the new and existing pavement on each side shall parallel the existing trench and be a straight and neat join line. - 2.4 Resurfacinq of Concrete Surfaces Portland concrete cement pavement surfaces shall be replaced in kind, with an aggregate base layer 8-inches minimum thickness. Minimum thickness of concrete pavement shall be equal to that removed. Portland cement concrete sidewalks shall be replaced to the nearest scoreline or over a sufficient width to replace any portions of the sidewalk damaged, fragmented, cracked, or otherwise made unusable as a result of construction operations. Minimum thickness of concrete shall be 4-inches. 2.5 Portland Cement Concrete Portland cement concrete shall be Class B and shall conform to Section 40 of the State Standard Specifications and the Specifications. Concrete shall be placed over the width of the excavated trench where the edge of the trench is more than 2-feet from the edge of an existing concrete excavation and is within 2-feet of the existing gutter. r.- 2.6 Temporary Pavinq All pavement removal for trenching operations shall be replaced with 2-inches of temporary paving mix after compaction is approved by the Owner's Representative or within three days after the installation of the pipe, whichever comes first. Cross streets and all accesses shall be paved with temporary pavement on the same day that excavation is made. Temporary pavement shall be maintained so that a smooth traversable surface is available at all times for vehicular traffic, free from ruts, depressions, holes, and loose gravel. Cost for temporary paving shall be included in the contract unit prices for the Work, and no extra compensation will be made to the Contractor. END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 021 30 - Removal and Resurfacing of Pavement Surfaces - 3 of 3 SECTION 02223 TRENCHING, BACKFILLING, AND COMPACTING PART 1 - GENERAL 1.1 Description A. This section includes materials, installation, and testing of trench excavation, backfilling, and compacting. 1.2 Reference Standards A. The publications listed below form part of this specification to the extent referenced and are referred to in the text by the basic designation only. Reference shall be made to the latest edition of said standards unless otherwise called for. ASTM D1556 - ASTM D2922 - ASTM D3017 - ASTM D1557 - - ASTM D4253 - ASTM D4254 - ASTMD75 - ASTMC90 - ASTMA82 - Standard Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method Standard Test Methods for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth) Standard Test Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth) Test Method for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3(2,700 kN-m/m3)) Standard Test Methods for Maximum Index Density and Unit Weight of Soils Using a Vibratory Table Standard Test Methods for Minimum Index Density and Unit Weight of Soils and Calculation of Relative Density Standard Practice for Sampling Aggregates Standard Specification for Load bearing Concrete Masonry Units Standard Specification for Steel Wire, Plain, for Concrete Reinforcement 1.3 Related Work Specified Elsewhere A. Construction Plans. B. C. D. Utility Crossings: Section 02225 E. General Concrete Construction: Section 03300. F. General Piping Systems and Appurtenances: Section 15000. Earthwork and Repairs in Citv, Countv, and State Riqhts of Wav A. Shop Drawing Submittals: Section 01300. Removal and resurfacing of Pavement Surfaces: Section 021 30. 1.4 rc Conform to the requirements and provisions of the permits issued by those agencies in addition to the requirements of these Standard Specifications. If a ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 - Trenching, Backfilling and Compacting - 1 of 12 City of Carlsbad 03/04 (DBE) 1.5 1.6 1.7 1.8 permit is not required, earthwork and repairs shall conform to the standards of the agency in whose right of way the work is done in addition to the requirements of these Standard Specifications. - Safetv Precautions A. Observe safety precautions in all phases of the work. Included shall be trench shoring, bracing, lighting, and barricades as dictated by reason and by the Safety Orders of the Division of Industrial Safety, State of California (CAL OSHA). Acquire an exemption letter or trenching permit from the California Division of Industrial Safety (CAL OSHA) and comply with Labor Code Section 6705, Excavation Plans For Worker Protection. Submit a copy of the exemption letter or trenching permit with excavation plans to the District prior to excavation work. Obstructions A. The Contractor's attention is directed to the possible existence of pipe and other underground improvements which may or may not be shown on the Plans. The Contractor shall preserve and protect any such improvements whether shown on the Plans or not and expose such improvements in advance of the pipeline construction to allow for changes in the alignment as necessary. Where it is necessary to remove and replace or to relocate such improvements in order to prosecute the work, they shall be removed, maintained, and, permanently replaced by the Contractor at his expense. Existing underground utilities shall be protected in place. - Submittals A. B. C. Submit shop drawings in accordance with Specification Section 01 300. Submit a report from a testing laboratory verifying that imported material is asbestos-free and conforms to the specified gradations or characteristics. Pipe Zone and Bedding Material: Submit current certification and test results for all utility pipe zone and bedding material. Pipe zone and bedding material will conform in all respects to the latest edition of the Carlsbad Municipal Water District Engineers Design and Processing Manual. Shoring: Prior to excavating submit shop plans and pertinent structural calculations for the shoring design. The shoring must be designed by a structural engineer and must comply in all respects to the Contract Documents, to all safety regulations and requirements, and to the plans and contract documents. D. Testing for Compaction The District or the agency having jurisdiction over the area of the work will require the Contractor to test for compaction as described below: Determine the density of soil in place by the sand cone method, ASTM D 1556 or by nuclear methods, ASTM D 2922 and D 3017. Determine laboratory moisture-density relations of soils by ASTM D 1557. A. -. B. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 -Trenching, Backfilling and Compacting - 2 of 12 1 C. Determine the relative density of cohesion less soils by ASTM D 4253 and D 4254. D. Sample backfill materials by ASTM D 75. E. "Relative compaction" is the ratio, expressed as a percentage, of the in place dry density to the laboratory maximum dry density. F. Make excavation for compaction tests at the locations and to the depths designated by the District's Representative. Backfill and re-compact the excavations at completion of testing. When tests indicate that the compaction is less than the specified relative compaction, rework and retest those areas until the specified relative compaction has been obtained. 1.9 Pipe Beddinq A. The pipe bedding shall be defined as a layer of material immediately below the bottom of the pipe and extending over the full trench width in which the pipe is bedded. Thickness of pipe base shall be a minimum of 6 inches. 1.10 Pipe Zone A. The pipe zone shall include the full width of trench from the bottom of the pipe to a horizontal level 12 inches above the top of the pipe. Where multiple pipes are placed in the same trench, the pipe zone shall extend from the bottom of the lowest pipe to a horizontal level above the top of the highest or topmost pipe. Thickness of pipe zone above the highest top of pipe shall be a minimum of 12 inches. _I 1.1 1 Trench Zone A. The trench zone includes the portion of the trench from the top of the pipe zone to the bottom of the pavement zone or to the existing surface in unpaved areas. 1.1 2 Upper Zone A. The upper zone includes the asphalt concrete and aggregate base pavement section placed over the trench backfill. 1.1 3 Water for Construction A. Water supplied by the District, for whatever needs and uses, shall be paid for in accordance with the rates and rules of the District. The only exception is by written agreement with the District. - B. If District water is not available, the Contractor shall be responsible for supplying the construction water. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 - Trenching, Backfilling and Compacting - 3 of 12 PART 2 -MATERIALS 2.1 2.2 2.3 I Native - -., Earth Backfill - Trench Zone A. Native earth backfill used above the pipe zone shall be excavated fine grained materials or loose soil free of asbestos, organic matter, roots, debris, rocks larger than 3 inches in diameter, clods, clay balls, broken pavement, and other deleterious materials. Sand Equivalent for said material shall be 30 or better. Backfill material shall be so graded that at least 40% of the material passes a No. 4 sieve. The coarser materials shall be well distributed throughout the finer material. 5ackfill materials that are obtained from trench excavated materials to the extent such material is available, shall be either screened directly into the trench or screened during the trenching operation. If screened during trenching, Lhe material shall be maintained free of unscreened material during the handling and backfilling process. Hand selecting of rocks from earth as it is placed into the trench will not be permitted in lieu of the specified screening. Under no circumstances will native earth backfill be allowed or used in the pipe base or pipe zone areas. .-... :mxorted Material for Backfill - Trench Zone h Imported material shall conform to that specified for native earth backfill or imported sand. - b?gor%ed Sand - Pipe Beddinq and Pipe Zone A, !illported sand used in the pipe base and pipe zone shall consist of natural or manufactured granular material, or a combination thereof, free of deleterious ;’mounts of organic material, mica, loam, clay, and other substances. Under no circumstances will decomposed granite or native earth backfill be allowed or used in the pipe base or pipe zone areas. Impoi’ted sand shall have the following gradation or similar: City of Carlcbad 03/04 (DEE) Sieve Size 3/8-i tich NG.4 N0.30 No.100 No.200 Percent Passing Bv Weiqht 100 75 -100 12- 50 5- 20 0- 15 Imported sand shall have a sand equivalent (S.E.) of 30 or greater as determined by the latest version of Test Method No. Calif. 217. ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 - Trenching, Backfilling and Compacting - 4 of 12 2.4 Rock Refill for Foundation Stabilization A. - Rock refill shall be crushed or natural rock having the following gradation: _c Sieve Size 3 inches 1-1/2 inches 3/4- i nc h N0.4 No.30 No.200 Percent Passing Bv Weiqht 100 70 -100 60 -100 25- 55 10- 30 0- 15 2.5 Granular Material For Backfill A. Where crushed aggregate base is called for in these specifications or in the Standard Drawings, the granular material for backfill shall be free of asbestos, organic materials, clay balls, and shall have the following gradation: Sieve Size 1 -inch 3/4-inch 1/2-inch 3/8-inch No.8 N0.4 Percent Passing Bv Weiaht 100 90 - 100 40- 70 20- 50 0- 10 0- 5 B. Whenever the phrase "crush aggregate base backfill material" is used in these Standard Specifications, it shall mean granular material for backfill as described above in 2.5.A. C. Excavated material may be used for backfill provided it conforms to the Standard Specifications for structural backfill material. 2.6 Concrete For Below Ground Installations A. Concrete for anchors, collars, encasements, supports, and thrust blocks shall be Class A for reinforced items and Class C for un-reinforced items per Standard Specification Section 03300, except use rapid set concrete mix where indicated. Concrete slurry backfill, when required, shall be in accordance with Table 201- 1.1.2 (A), 1 OO-E- 100. B. Provide anchor blocks at valves in pipe having rubber gasket bell and spigot or unrestrained mechanical joints. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 - Trenching, Backfilling and Compacting - 5 of 12 C. D. Provide support blocks at all valves. Provide thrust blocks at fittings in pipe having rubber gasket bell and spigot or unrest rained mechanical joints. -- 2.7 Water For Compaction A. Water used in compaction shall have a maximum chloride concentration of 500 mg/l, a maximum sulfate concentration of 500 mgA, and shall have a pH of 7.0 to 9.0. Water shall be free of acid, alkali, or organic materials injurious to the pipe or coatings. Salt water will not be allowed. 2.8 Soil Sterilant A. The sterilant shall be Oust (EPA regulation #352-401) as manufactured by E. I DuPont Nemours and Company or approved equal. PART 3 - EXECUTION 3.1 General The Contractor shall perform all site grading, soil sterilant application, structure excavation and backfill, trench excavation and backfill for pipelines and conduits, and other earthwork required to complete the work under this contract. Included are all necessary clearing, grubbing, grading, and excavation of all classes and of whatever substance encountered, stockpiling, backfilling, compaction, controlling water, bracing excavations, stabilizing subgrade, protecting existing structures and facilities, complying with conditions of permits and safety regulations, cleaning up debris, papers and loose rocks, restoring fences and other disturbed property, maintaining trees which are not permitted to be removed, and disposing of excess material, and such supplementary operations as are necessary to properly complete the entire work indicated or specified. - 3.2 Trenching Subject to Permit Conditions Trenching within public rights-of-way controlled by a state, county or city, or trenching within railroad rights-of-way shall be in accordance with requirements and provisions of the permits issued by those agencies for the construction within their respective rights-of-way. Such permit requirements and provisions which are more restrictive than those specified herein, shall take precedence and supersede the provisions of these Specifications. 3.3 Protection of Workmen Excavations shall be so braced or sheeted so as to provide conditions under which workmen may work safely and efficiently at all times. The latest revision of the rules, orders and regulations of the Division of Industrial Safety of the State of California shall be complied with. - City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 -Trenching, Backfilling and Compacting - 6 of 12 3.4 Public Safety Barriers shall be placed at each end of all excavations and such places as may be necessary along excavations to warn all pedestrian and vehicular traffic of such excavations. Lights shall also be placed along excavations from sunset each day to sunrise of the next day until such excavation is entirely refilled. Material for backfill or for protection of excavation in public roads from surface drainage shall be neatly placed and kept shaped so as to cause the least possible interference with public travel. Free access must be provided to all fire hydrants, water valves, meters, and private drives, or other property or facilities that may have routine use. 3.5 Support of Adiacent Propertv Excavations shall be so braced, sheeted, and supported that the ground alongside the excavation will not slide or settle, and all existing improvements of any kind, either on public or private property, will be fully protected from damage. Damage to adjacent property or to the work occurring through settlements, water or earth pressures, slides, caves or other causes due to failure of lack of sheeting or bracing or improper bracing, or through negligence or fault of the Contractor in any other manner, shall be repaired by the Contractor at his own expense. 3.6 Existing Improvements The Contractor's attention is directed to the possible existence of pipe and other underground improvements which may or may not be shown on the plans. The Contractor shall preserve and protect any such improvements whether shown on the plans or not. Where it is necessary to remove and replace or to relocate such improvements in order to prosecute the work, they shall be removed, maintained, and permanently replaced by the Contractor at his expense, except as otherwise provided in the General Provisions. - 3.7 Drainaqe Control A. Control of Surface Drainage The Contractor shall control grading in a manner to prevent water running into excavations. Obstruction of surface drainage shall be avoided and means shall be provided whereby storm and wastewater can flow uninterrupted in existing gutters, other surface drains or temporary drains. B. Preservation of Existing Drainage Except as shown on the Plans, existing drainage patterns shall be preserved. Where construction methods cause a temporary obstruction of drainage patterns temporary facilities adequate for expected flows and a means of emergency removal of the obstruction shall be provided. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 -Trenching, Backfilling and Compacting - 7 of 12 3.8 Compaction Requirements Unless otherwise shown on the Plans or otherwise described in the Specifications and required by the agency having jurisdiction over the area of the work, relative compaction in pipe trenches shall be a minimum as follows: - A. B. C. D. E. Pipe bedding - 90% relative compaction. Pipe zone - 90% relative compaction. Trench zone - 90% relative compaction. Upper one foot of trench zone shall be 95% relative compaction Upper zone - 95% relative compaction. 3.9 Sheeting, Shorinq, and Bracing of Trenches Trenches shall have sheeting, shoring, and bracing conforming with 29CFR 1926, Subpart P-Excavations, CAUOSHA requirements, and the District's requirements. 3.10 Sidewalk, Pavement, and Curb Removal Cut and remove bituminous and concrete pavements regardless of the thickness, and curbs and sidewalks prior to excavation of the trenches with a pavement saw, hydrohammer, or pneumatic pavement cutter. Width of the pavement cut shall be at least equal to the required width of the trench at ground surface. Haul pavement and concrete materials from the site. Do not use for trench backfill. - 3.1 0 Dewatering Provide and maintain means and devices to remove and dispose of all water entering the trench excavation during the time the trench is being prepared for the pipelaying, during the laying of the pipe, until cement mortar of exterior joints has set hard, when concrete is being deposited and during the hydration process, and until the backfill at the pipe zone and trench zone has been completed. These provisions shall apply during the noon hour as well as overnight. Dispose of the water in a manner to prevent damage to adjacent property and in accordance with regulatory agency requirements. If feasible, dewatering flows shall be discharged to storm drain facilities in accordance with Riverside County Flood Control and Water Conservation District requirements. Contractor shall be responsible for obtaining a permit and performing monitoring and reporting to Regional Water Quality Control Board (RWQCB). Do not drain trench water through the pipeline under construction. 3.1 2 Material Replacement Remove and replace any trenching and backfilling material which does not meet the Specifications, at the Contractor's expense. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 - Trenching, Backfilling and Compacting - 8 of 12 3.13 Trench Widths Pipe trench widths in the pipe zone will be limited as follows: - Minimum Maximum Pipe Diameter Trench Width Trench Width 4" through 12" O.D. + 12" O.D. + 16" 14" through 48" O.D. + 16" O.D. + 24" Trench width at the top of the trench will not be limited except where width of excavation would undercut the structural support of adjacent structures and footings. Where shoring or encasement is required, trench widths shall be increased accordingly. 3.14 Trench Excavation A. Perform all excavation regardless of the type, nature, or condition of the material encountered to accomplish the construction. Do not operate excavation equipment within 5 feet of existing structures or newly completed construction. Excavate with hand tools in these areas. B. Excavate the trench to the lines and grades shown on the Plans with allowance for pipe thickness, sheeting and shoring if used, and for pipe base. If the trench is excavated below the required subgrade, refill any part of the trench excavated below the subgrade at no additional cost to the District with imported sand. Place the refilling material over the full width of trench in compacted layers not exceeding 6 inches deep to the established grade with allowance for the pipe base. Compact refill material to 95% of maximum density. C. Trench depth shall accommodate the pipe and the pipe base at the elevations shown in the profile on the Plans. No pipe shall be installed without a designed profile unless approved by the District. D. Construct trenches in rock by removing rock to a minimum of 6 inches below bottom of pipe and backfilling with imported sand. 3.15 Location of Excavated Material During trench excavation, place the excavated material only within the working area or within the areas shown on the Plans. Do not obstruct any roadways or streets. Conform to federal, state, and local codes governing the safe loading of trenches with excavated material. 3.16 Length of Open Trench A. The total length of open trench shall not exceed 200 feet including excavation, pipeline installation and backfill in any one location. c B. Complete backfilling and temporary or first layer paving not more than 80 feet in the rear of pipelaying. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 - Trenching, Backfilling and Compacting - 9 of 12 C. Where pipelines are located beneath or adjacent to existing paved roads, backfill all trenches at the end of each workday and place temporary or first layer of paving. Clean all new and adjacent existing paved surfaces of residual excavated and backfill materials. Perform dust control operations in these areas with a brush or vacuum type mobile street sweeper. No open trenches will be allowed in these areas. - D. Provide ingress and egress to buildings and property at all times. Provide traffic rated steel plates for covering for vehicular access and protect excavations which must remain open beyond the initial day of the excavation. 3.17 Foundation Stabilization After the required excavation has been completed, the District will inspect the exposed subgrade to determine the need for any additional excavation. It is the intent that additional excavation be conducted in all areas within the influence of the pipeline where unacceptable materials such as soft, spongy or deleterious materials exist at the exposed grade. Over excavation shall include the removal of all such unacceptable material that exists directly beneath the pipeline to a minimum width equal to the maximum trench width and to a depth determined by the District. Backfill the trench to the established subgrade of the pipe base with rock refill material for foundation stabilization. Place the foundation stabilization material over the full width of the trench and compact in layers not exceeding 6 inches deep to the required grade. Place imported sand on the compacted foundation stabilization and apply water to wash the sand into the voids of the rock refill material. Continue this procedure until the voids of the rock refill have been filled with imported sand. Do not apply water in such quantities that it will damage the integrity of the compacted foundation. - 3.1 8 Concrete for Below Ground Installations Place concrete between the undisturbed ground and the pipe or fittings to be restrained or supported. Quantity or bearing area of the concrete against undisturbed ground shall be as shown on the Standard Drawings, Plans, or as directed by the District. Provide temporary support on the pipe, fittings, or valves until the concrete has obtained a 3-day cure. Place concrete such that the pipe joints, fittings, or valves are accessible for repairs. Spade or rod the concrete during placement to eliminate honeycombing. Backfilling of the trench adjacent to the concrete will not be allowed until the concrete has cured for at least 3 days. Allow concrete to cure for at least 7 days prior to subjecting the concrete to pipeline pressure. Where rapid set concrete mix has been used, the 3-day and 7-day cure time is not required. Backfill the rapid set concrete mix as soon as the concrete is hard (approximately one to two hours) and place pipeline into service. -. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 -Trenching, Backfilling and Compacting - 10 of 12 3.1 9 Trench Backfilling .- A. c B. C. D. E. F. Place the specified thickness of pipe bedding material over the full width of trench and compact to the specified relative compaction. Grade the top of the pipe base ahead of the pipelaying to provide firm, continuous, uniform support along the full length of the trench for the pipe, fittings, and valves. Excavate bell holes at each joint to permit proper assembly and inspection of the entire joint. Fill and compact the area excavated for the joints with the pipe base material. After the pipeline has been bedded and the cement mortar used in the exterior joints has set hard, place pipe zone material simultaneously on both sides of the pipe, fittings, and valves, keeping the level of backfill the same on each side. Carefully place the material around the pipe so that the pipe barrel is completely supported and that no voids or un-compacted areas are left beneath the pipe. Use particular care in placing material on the underside of the pipe to prevent lateral movement during subsequent backfilling. Do not drop sharp, heavy pieces of material directly onto the pipe or the tamped material around the pipe. Compact material in the pipe zone by hand tamping only. Care shall be exercised in backfilling to avoid damage to pipe coatings and polyethylene encasement. Push the native earth backfill or imported material for backfill carefully onto the imported sand previously placed in the pipe zone.' Do not permit free fall of the material until at least 2 feet of cover is provided over the top of the pipe. Compact backfill material in the trench zone to the specified relative compaction by mechanical compaction or hand tamping. Place and compact pipe zone material in layers not exceeding 12 inches of compacted thickness. Place and compact native earth or imported material for backfill in the middle zone in layers not exceeding 6 inches of compacted thickness. 3.20 Mechanical Compaction or Hand Tamping Place imported sand and backfill materials in uniform layers of the indicated thickness. Compact each layer to the required minimum relative compaction at the optimum moisture content. Do not use heavy duty compaction equipment with an overall weight in excess of 125 pounds until backfill has been completed to a depth of 2 feet over the top of pipe. Do not use high impact hammer type equipment except where the pipe manufacturer warrants in writing that such use will not damage the pipe. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02223 -Trenching, Backfilling and Compacting - 11 of 12 3.21 Dispose of excess excavated material offsite. Contractor shall make his own arrangements for the disposal of the excess material and bear all costs incidental to such disposal. Over undeveloped property or street frontage] excess material may be disposed of within the right of way by spreading, provided that rocks or lumps which cannot be readily covered by spreading are removed. Disposal of Excess Excavated Material a 3.15 Soil Sterilant A. General The Contractor shall treat the finished subgrade of specified areas with an approved soil sterilant. B. Areas Requiring Soil Sterilant All areas which are to receive bitumastic pavement] including embankments] walkways, drainage structures, parking, and road areas, require soil sterilant. Other areas requiring soil sterilant are storage reservoir or pond surfaces which are to receive any lining material of less than 3-inches in thickness and lining perimeter areas to a distance of 5-feet from the edge of lining material. C. Material and Application The sterilant shall be applied in a liquid or dry form and at a uniform rate of 10 to 12 ounces of dry sterilant per acre in accordance with the manufacturer's directions. At the option of the Engineer, the area shall then be lightly sprinkled with water to prevent loss of sterilant or scuffing. END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic 8, Recycled Water Transmission Mains 02223 - Trenching, Backfilling and Compacting - 12 of 12 .,-- SECTION 02225 UTILITY CROSSINGS PART 1 - GENERAL 1.1 Description Where utilities cross the pipeline trench but do not conflict with the permanent Work to be constructed, the Contractor shall follow the procedures given below and as indicated on the Plans and in the Specifications. For utility crossings not shown on the Plans, follow the General Provisions and the instructions of the Engineer. 1.2 Related Work Described Elsewhere A. Section 02200: Earthwork 1.3 Submittals (Not Applicable) 1.4 Payment Payment for the Work in this section shall be included as part of the lump-sum or unit-price bid amount for which such Work is appurtenant thereto. PART 2 - MATERIALS 2.1 Replacement in Kind Except as indicated below or as specifically authorized by the Engineer, the Contractor shall reconstruct utilities with new material of the same size, type, and quality as that removed. 2.2 Vitrified Clav Sewer Pipe and Couplings For sewer pipe eight inches in diameter or under, replacement shall consist of plain-end pipe conforming to ASTM C700. Compression coupling shall conform to ASTM C594; Band seal couplings or approved equal. At least two lengths of pipe shall be used in crossing the trench section as shown on the details on the Plans or in the Special Provisions. PART 3 - EXECUTION 3.1 Notification The Contractor shall notify the utility owner 48 hours in advance of the potholing and at the beginning of construction and will coordinate the construction schedule with the utility service requirements. c City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02225 - Utility Crossings - 1 of 2 3.2 Exposing Utilities in Advance It shall be the Contractor's responsibility to determine the true location and depth of all utilities and service connections which may be affected by or affect the Work. He shall also determine the type, material, and conditions of these utilities. In order to provide sufficient lead time to resolve unforeseen conflicts, order materials, and take appropriate measures to ensure that there is no delay in Work, the Contractor shall expose all utilities in advance of submittal of shop drawings and lay diagrams for the pipeline construction. All costs incurred in exposing utilities shall be borne by the Contractor. ---. 3.3 Protect in Place The Contractor shall protect all utilities in place, unless abandoned, and shall maintain the utility in service, unless otherwise specified on the Plans or in the Specifications. 3.4 Cut and Plug Ends The Contractor shall cut abandoned utility lines and plug the ends of lines larger than 18-inch diameter with brick and mortar, unless otherwise specified on the Plans or in the Specifications. Abandoned facilities smaller than 18 inches in diameter shall be plugged with concrete. The pipe shall be disposed of as unsuitable material by the Contractor. 3.5 Remove and Reconstruct - Where so indicated on the Plans or in the Specifications or as required by the Engineer, the Contractor shall remove the utility and after passage, reconstruct it with new materials. The Contractor shall take appropriate measures to provide temporary service for the disconnected utility. All reconstruction work shall be in accordance with the applicable specifications. 3.6 Compaction A. 6. C. Utilities Protected in Place: Contractor shall take special precautions to compact under and around the utility to ensure that no voids are left. Utilities Reconstructed: Prior to replacement of the utility, the trench shall be backfilled and compacted by approved means to an elevation one foot above the top of the ends of the utility. A cross trench of the proper width shall be excavated for the utility and it shall be laid, backfilled, and compacted as specified herein or as required by the Engineer. Alternate Construction - Sand Slurw: Sand slurry consisting of one sack (94 pounds) of Portland cement per cubic yard of sand and sufficient moisture for workability may be substituted for other backfill materials to aid in reducing compaction difficulties. Specific methods and procedures must be submitted for the approval of the Engineer prior to construction. City of Carlsbad 03/04 (DBE) END OF SECTION ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 02225 - Utility Crossings - 2 of 2 SECTION 02510 - ASPHALTIC CONCRETE PAVEMENT PART 1 - GENERAL 1.1 Description The Contractor shall construct asphaltic concrete pavements for roads, parking areas, aprons, sidewalks, and other work involving asphaltic concrete, all as shown on the Plans. Asphaltic concrete shall conform to all requirements of the latest revision of the Standard Specifications for Public Works Construction (P.W.C.) and specified herein. 1.2 Related Work Described Elsewhere A. Section 02200: Earthwork B. Section 01300: Shop Drawings 1.3 Submittals Contractor shall furnish submittals in accordance with the requirements of Section 01 300, Shop Drawing Submittals. The following submittals are required: _c Submit six (6) copies of a report from a testing laboratory verifying that aggregate material is asbestos-free and conforms to the specified gradations or characteristics. 1.4 Pavrnent Payment for the Work in this section shall be included as part of the unit price or lump sum bid amount stated in the Proposal. 1.5 Testinq for Compaction A. The Owner will test for compaction as described herein and in Section 02200, Earthwork. B. Determine the density of existing soil in place by the Sand Cone Method, ASTM D1556. C. Determine laboratory moisture-density relations of soils by ASTM D1557. D. Determine the relative density of cohesionless soils by ASTM D4253 and D4254. E. Sample backfill materials by ASTM D75. c F. "Relative compaction" is the ratio, expressed as a percentage, of the in-place dry density to the laboratory maximum dry density. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 0251 0 - Asphaltic Concrete Pavement - 1 of 4 G. Compaction shall be deemed to comply with the specifications when no more than one test of any three consecutive tests falls below the specified relative compaction. The one test shall be no more than three percentage points below the specified compaction. The Contractor shall pay the costs of any retesting of Work not conforming to the specifications. - PART 2 - MATERIALS 2.1 Soil Sterilant The sterilant shall be Oust (EPA regulation #352-401) as manufactured by E.I. DuPont Nemours and Company (Wilmington, Delaware), or approved equal. 2.2 Amreqate Base Course The base materials shall conform to Section 200-2.2, crushed aggregate base of the Standard Specifications for P.W.C. The Contractor may elect to use on-site materials which shall conform to Section 200-2.5, Processed Miscellaneous Base of the Standard Specifications for P.W.C. 2.3 Prime Coat Prime coat shall be liquid asphalt, Grade SC-250 as specified in Section 203-2 of the - Standard Specifications for P.W.C. 2.4 Tack Coat If paving over existing pavement, a tack coat shall be applied, either AR1000 paving asphalt or SS-1 h in accordance with Section 302-5.4 of the Standard Specifications for P.W.C. 2.5 Asphalt Concrete Pavement Asphalt concrete shall consist of Type II mineral aggregate conforming to the requirements specified in Section 203-6.3.2 of the Standard Specifications for P.W.C. using a medium coarse Class B grading mixed with a bitumen content of 4.5% to 5.8% of the dry mineral aggregate, bitumen shall be RC85-100 penetration paving asphalt. 2.6 Seal Coat Seal coat shall be SS-I h asphalt emulsion. PART 3 - EXECUTION - 3.1 Subrrrade Preparation Scarify 6-inches below subgrade, bring to optimum moisture content, and compact to a relative dry density of 90%. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 0251 0 - Asphaltic Concrete Pavement - 2 of 4 3.2 Soil Sterilant Soil sterilant shall be spread uniformly upon the prepared subgrade at the rate of 10 to 12 ounces of dry sterilant per acre, in accordance with the manufacturer's recommendations, from outside of curb to opposite outside of curb for the full width of roadways or parking area to be paved or surfaced. c 3.3 Aaareqate Base Course Base material shall be furnished, placed and compacted for asphalt concrete pavements as shown on the Plans and specified herein. The spreading and compacting shall conform to Section 301-2 of the Standard Specifications for P.W.C. 3.4 Prime Coat After completion of the subgrade, a prime coat of liquid asphalt, specified in 2.2, shall be pressure-spray applied at a rate of approximately 0.25 gallons per square yard. In the event an aggregate base is specified, the prime coat shall be applied after completion of the base course. Liquid asphalt shall be prevented from spraying on adjacent ground, structures, curbing and fencing. 3.5 Tack Coat Over existing pavement, a tack coat shall be applied in accordance with Section 302-5.3 of the Standard Specifications for P.W.C. 3.6 Asphaltic Concrete Pavement Materials and workmanship for asphalt concrete shall conform to the applicable provisions of Section 203-6 of the Standard Specifications for P.W.C. and the following provisions: Asphaltic concrete pavement shall be spread in one course by means of a Barber- Greene paving machine, or approved equal. It shall be spread to a depth to achieve a compacted thickness as shown on the Plans. The completed surface shall be thoroughly compacted, smooth and true to grade and cross-section, and free from ruts, humps, depressions and irregularities. When a straight edge is laid on the finished surface and parallel to the centerline, the surface shall not vary more than 1/8-inch in 10-feet. 3.7 Seal Coat A seal coat of mixing type emulsion liquid asphalt shall be applied to all asphaltic concrete pavements. The emulsion shall be SS-1 h and shall be applied at the rate of 0.1-gallon per square yard. The Contractor shall have the option of closing the sealed area to traffic for at least 7-days or blotting with sand and sweeping with the area being open to traffic as soon as cover material is laid. _- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 0251 0 - Asphaltic Concrete Pavement - 3 of 4 3.8 Adiust Valve Box Rings and Covers - The Contractor shall adjust all valve box rings and covers to grade within 30 days after final paving of each street in which the pipelines are installed. END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic 8, Recycled Water Transmission Mains 0251 0 - Asphaltic Concrete Pavement - 4 of 4 SECTION 03300 CONCRETE CONSTRUCTION PART 1 -GENERAL 1.1 Description The Work under this section includes all cast-in-place concrete, complete. 1.2 Related Work Described Elsewhere The Contractor shall refer to the following Specification section(s) for additional requirements: A. Shop Drawing Submittals: 01300 B. Testing and Inspection: 01 41 0 1.3 Submittals Contractor shall furnish submittals in accordance with the requirements of Section 01 300, Shop Drawing Submittals. The following submittals are required: A. The mix design shall be submitted for review and approved before placing of any - concrete. B. The Contractor shall submit reinforcing Shop Drawings and placing drawings for all reinforcing. Placing drawings shall indicate all openings, including additional reinforcing at openings and corner bar arrangements at intersecting beams, walls, and footings as indicated in the Plans. C. The Contractor shall submit a certified mill copy of mill tests on each heat showing physical and chemical analysis of reinforcing steel. D. The Contractor shall submit a proposed sequence of placing concrete, showing proposed beginning and ending of individual placements. Placement of concrete shall be consistent with indicated construction joints. 1.4 Payment A. Measurement: If concrete is a pay item in the Contract Documents, the measurement shall be in accordance with the dimensions shown on the Plans. cc B. Payment: Payment shall be at the bid price per cubic yard in place, complete, including forming, reinforcement, and such embedded items as are shown on the Plans. Payment for concrete construction for which no pay item is provided shall be considered included as part of the lump-sum or unit-price bid amount for which such Work is appurtenant thereto. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 1 of 18 PART 2 - MATERIALS 2.1 General A. Cement: Cement shall be Portland cement, Type II, conforming to ASTM C150 (unless otherwise specified). B. Aggregates: Aggregates shall conform to ASTM C33 and shall be free from any substances that will react with the cement alkalies. C. Reinforcement: Reinforcement shall conform to ASTM A61 5, Grade 40 or 60. Tie wire shall be annealed wire not lighter than 16 gauge. Wire fabric shall conform to ASTM A185. D. Waterstops: Waterstops shall be of polyvinyl material. The material shall be resistant to chemical action with portland cement, shall be resistant to alkalies, and shall not be affected by mildew or fungus. It shall show no effect when immersed for ten days in a 10% solution of sulfuric or hydrochloric acids, saturated lime solution, or salt water. All waterstops shall be such that any cross section will be dense, homogeneous, and free from porosity and other imperfections. They shall be symmetrical in shape. When tested in accordance with the applicable test methods of Federal Standard No. 601, the material shall meet the following requirements: Tensile strength, psi, minimum 2,000 Elongation, ultimate, percent, minimum 250 Compression set, percent, maximum 30 Tensile strength after accelerated aging 80 Water absorption, percent by weight, maximum 0.5% (48 hours, 70°C, 300 psi) percent, minimum Durometer hardness, Shore A 70-80 E. Water: Water should be clean and potable. F. Admixtures: All concrete shall contain Master Builders Pouolith polymer-type water- reducing admixture and an air-entraining admixture (Type MBVR), to prevent segregation, improve workability, and reduce the quantity of mixing water, both in strict accordance with the manufacturer's recommendations. Resulting entrained air shall be 3% to 5%. Where controlled setting and/or controlled rate of hardening is required, the admixtures shall be a formulation that provides this control without loss in strength when compared with the normal setting formulation. The manufacturer shall make available at no cost upon 72 hours notice, the services of a qualified full- time field representative to assure proper use of the admixture. G. Forms: Form lumber shall conform to specified paragraphs in the Standard Grading Rules No. 16 of the West Coast Lumber Inspection Bureau effective September 1 , 1970. Plywood shall be Douglas fir, Class 1, Exterior B-B concrete panels, conforming to U.S. Product Standard PSI-66 and shall be edge sealed. I_ City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 2 of 18 H. Premolded Expansion Joint Filler: Premolded expansion joint filler shall be preformed, non-extruding-type joint filler constructed of closed cellular sponge rubber of firm texture conforming to ASTM D1752, Type I. I. Curing Compound: Curing compound shall conform to ASTM C309. J. Joint Sealant: The joint sealant shall be a two part, gray, non-staining, non-sagging, polyurethane sealant, which cures at ambient temperature to a firm, flexible, tear- resistant rubber. The sealer shall be resilient and have excellent recovery characteristics after extended periods of compression or elongation. Sealant shall be PRC 270 or approved equal. Technical Requirements Consistency Gun Grade Tack Free Time 24 hours at 75°F and 50% R.H. Pot Life 1 to 3 hours Hard ness 30 Shore A, *5 Elongation 750% Shrinkage Negligible Tensile Strength, ASTM D412 Peel Strength on Concrete Temperature Service Range 325 psi 12 P.L.I. Cohesive -40°F to 175°F Joint primer shall be compatible with sealant. Joint backup material shall be closed cell polyethylene rod, 3/4-inch diameter. Bond breaker tape shall be compatible with sealant. K. Epoxy Bonding Compound: Epoxy bonding compound shall be Concresive 1001 LPL and shall be applied in accordance with manufacturer's instructions. 2.2 Concrete Requirements A. Classes of Concrete: Concrete shall be of three classes, referred to as Class A, Class B, and Class C. Anchors, thrust blocks, encasements, cradles, surface slope protection, cut off walls, and other similar items shall be constructed of a minimum of Class B Concrete. Class C concrete may be used as fill for unauthorized excavation, thrust blocks and pipe encasement where approved by the Owner's Representative. All other concrete shall be Class A. B. Strength Requirements: Class A concrete shall not be less then 3,000 psi compressive strength at 28 days and contain not less than six sacks of cement per cubic yard of concrete. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 3 of 18 2.3 Class B concrete shall not be less than 2,500 psi compressive strength at 28 days and contain not less than five sacks of cement per cubic yard of concrete. - Class C concrete shall not be less than 2,000 psi compressive strength at 28 days and contain not less than four sacks of cement per cubic yard of concrete. C. Mix Design: The mix designs shall be prepared at the Contractor's expense by an independent inspection and testing laboratory acceptable to the Owner's Representative in accordance with Section 01 41 0, Testing and Inspection and shall show the expected strength and corresponding slump and all ingredient weights and other physical properties necessary for the design mix. Mix design shall be submitted for review and approved in accordance with Section 01300, Shop Drawing Submittals, before placing of any concrete. Aggregate size shall be as follows: Sections 8-inches or less in thickness shall be 3/4-inch maximum (combined gradation). Sections greater than 8-inches shall be 1 %-inches maximum. Mix design for pumped concrete shall produce a plastic and workable mix. The percentage of sand in the mix shall be based on the void content of the coarse aggregate. - D. Slump: Vertical wall sections and columns shall be four to five inches. Slabs, beams, and footings shall be three to four inches. E. Workability: Concrete shall be of such consistency and composition that it can be worked readily into the forms and around the reinforcement without excessive spading and without permitting the materials to segregate or free water to collect on the surface. The proportions shall be adjusted to secure the lowest water-cement ratio which is consistent with good workability, a plastic, cohesive mixture, and one which is within the specified slump range. To avoid unnecessary changes in consistency, the aggregate shall be obtained from a source which will ensure uniform quality, moisture content, and grading during any single day's operation. Materials shall be handled in such a manner that variations in moisture content will not interfere with production of concrete of the specified degree or uniformity and slump. Formwork - A. Design of Forms: The Contractor shall be responsible for the design and construction of forms. Forms shall be designed on the basis of deflection and stress and shall be adequately braced. The allowable deviation in all exposed finished City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 4 of 18 c surfaces shall not exceed 1/8-inch in ten feet. All concrete shall be formed, unless shown otherwise on the Plans. B. Classes of Forms: Class I forms shall have smooth surface plywood, 5/8-inch minimum thickness. Face and edges of forms shall be coated with a two-coat system of one component polyurethane coating applied by roller at the rate of 500 square feet per gallon. Class II forms shall be metal or smooth planed boards or plywood in good condition, with boards free from large or loose knots with tongue and groove or ship lap joints. Forms shall be oiled. C. Location of Forms: Class II forms may be used for exterior concrete surfaces which are below one foot of finish grade. Class I forms shall be used for all other surfaces. D. Tolerances: The following table indicates tolerances or allowable variations from dimensions or positions of all structural concrete work: Maximum Tolerance Sleeves and inserts +1/4" - 1/8" Projected ends of anchor bolts +1/4" - 0.0" Anchor bolt setting +1/16" - 1/16" Concrete walls and slabs +1/8" - 1/8" in 10-feet Finished concrete, all locations +1/4" - 1/4" in 10-feet not listed above Regardless of the tolerances listed above, it shall be the responsibility of the Contractor to limit deviations in line and grade to tolerances which will permit proper installation and operation of mechanical equipment piping. E. Removal of Forms and Shoring: The following table indicates the minimum allowable time after the last cast concrete is placed before forms or shoring may be removed: Sides of footings 24 hours Walls and columns 48 hours Vertical sides of beams, girders, and similar members 48 hours Slabs, beams and girders 10 days Shoring for slabs, beams, and girders 21 days Forms shall not be removed from concrete which has been placed with outside air temperature below 50°F without first determining by cylinder tests if the concrete has properly set without regard for time. No heavy loading on green concrete will be permitted. Immediately after forms are removed, the surface of the concrete shall be carefully examined and any irregularities in the surface shall be repaired and finished as specified hereinafter. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic i3 Recycled Water Transmission Mains 03300 Concrete Construction - 5 of 18 F. Waterstops: Waterstops shall be of the shapes and dimensions shown on the Plans. Waterstops shall be properly heat-spliced at ends and intersections to ensure continuity. Splicing shall be in accordance with the manufacturer's instructions. Forms for construction joints shall be constructed in such a manner as to prevent injury to waterstops. Waterstops shall be securely held in position in the construction joints by wire ties, continuous bars, and rings as indicated. Waterstops shall be installed in all construction joints in hydraulic structures and in all joints subjected to groundwater. 2.4 Reinforcing (Non-Prestressed) A. General Requirements: All reinforcing steel shall be delivered to the site bundled and tagged with identifying tags. All reinforcing steel shall be bent cold and shall be bent in accordance with the details on the Plans and as recommended in ACI 315. Reinforcing steel, before being positioned, shall be free from loose mill and rust scale and from coating that may destroy or reduce the bond. Where there is delay in depositing concrete, reinforcement steel shall be reinspected and cleaned when necessary by abrasive sandblasting. Reinforcing steel shall not be straightened or rebent in a manner that will injure the material. Bars with bends not shown on the Plans shall not be used. PART 3 - EXECUTION 3.1 Concrete Construction A. Mixing: Concrete shall be site mixed or ready mixed and shall conform to the following requirements: Site Mixed Concrete: The mixing equipment shall be capable of combining the aggregates, cement, and water within the specified time into a thoroughly mixed and uniform mass and discharging the mixture without segregation. Mixing shall be done in a batch mixer of approved type which will ensure a uniform distribution of the materials throughout the mass. The equipment at the mixing plant shall be so constructed that all materials, including the water entering the mixing drum, can be accurately proportioned and controlled. The cement and aggregate shall be proportioned by weight. Each entire batch shall be discharged before recharging. The volume of the mixed materials per batch shall not exceed the manufacturer's rated capacity of the mixer. Mixing time shall be as follows: For mixer of a capacity of one cubic yard or less, 1 -1/2 minutes after batching is -_ completed. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 6 of 18 .- _I- For mixers of capacities larger than one cubic yard, the time of mixing shall be 1-1/2 minutes plus 30 seconds for each additional 1/2 cubic yard capacity or fraction thereof in excess of one cubic yard. The mixer shall revolve at a uniform rate as specified by the manufacturer for the mixing equipment. Ready-Mixed Concrete: Ready-mixed concrete shall conform to ASTM C94 with the following additional requirements: Water shall not be admitted to the mix until the drum has started revolving. The right is reserved to increase the required minimum number of revolutions or to decrease the designated maximum number of revolutions allowed, if necessary, to obtain satisfactory mixing, and the Contractor will not be entitled to additional compensation because of such increase or decrease. The retempering of concrete or mortar which is partially hardened will not be permitted. B. Conveying: Concrete shall be conveyed from the mixer to the place of final deposit by methods which will prevent the separation or loss of the materials. Equipment for chuting, pumping, and pneumatically conveying concrete shall be of such size and design as to ensure a practically continuous flow of concrete at the delivery end without separation of the materials. Chutes and devices for conveying and depositing concrete shall be so designed and used that the concrete shall be directed vertically downward when discharged from the chute or conveying device. Chutes for conveying concrete shall be kept thoroughly cleaned by washing and scraping. C. Placing: Placement of concrete shall be consistent with indicated construction joints. Wye walls at the top of hydraulic structures shall be placed monolithic with the main structural wall. After review of the proposed sequence of placing concrete, this sequence shall be adhered to, except when specifically permitted otherwise by the Owner's Representative. The Contractor shall notify the Owner's Representative of his readiness, not just his intention to place concrete in any portion of the Work. This notification shall be such time in advance of the operation as the Owner's Representative deems necessary for him to make final inspection of the preparations at the location of the proposed concrete placing. All forms, steel, screeds, anchors, ties, and inserts shall be in place before the Contractor's notification of readiness is given to the Owner's Representative. Concrete shall not be placed until all reinforcement is securely and properly fastened in its correct position and loose form ties at construction joints have been retightened, nor until all dowels, bucks, sleeves, hangers, pipes, conduits, bolts, wires, ceiling insert, and any other fixtures required to be embedded therein have been placed and adequately anchored, nor until the forms have been cleaned and coated as specified. Subgrade shall be moistened and forms shall be wetted before concrete is placed. Concrete shall be deposited at or near its final position to avoid segregation caused by rehandling or flowing. Concrete shall not be deposited in large quantities in one City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 7 of 18 place and worked along the forms with a vibrator or shovel. No concrete shall be dropped freely into place from a greater height than six feet in unexposed Work and four feet in exposed Work. Tremies shall be used where the drop exceeds these limits. -. In order to assure that there will be no interruption in continuous placing, the Contractor shall have available standby concrete mixing equipment ready for use in case of breakdown or he shall make arrangements, satisfactory to the Owner's Representative, with the supplier of concrete, if transit mix concrete is being used so that the Owner's Representative may be assured that once placement is started, it can be completed without interruption. The vibrating equipment, including standby equipment, shall be at the site and tested in the presence of the Owner's Representative during the day preceding the planned day of placement. Appropriate mechanical vibration shall be used in placing concrete to eliminate rock pockets and voids, to consolidate each layer with that previously placed, to completely embed reinforcing bars and fixtures and to bring just enough fine material to exposed surfaces to produce a smooth, dense, and even texture. Vibrators shall be of the high-frequency internal type and the number in use shall be ample to consolidate the incoming concrete to a proper degree within 15 minutes after it is deposited in the forms. In all cases, at least two vibrators shall be available at the site. The use of external vibrators for consolidating concrete will be permitted when the concrete is otherwise inaccessible for adequate consolidating, provided the forms are constructed rigidly enough to resist displacement or damage from external vibration and the vibrators are approved by the Owner's Representative. - Concrete shall be placed solidly against the forms so as to leave no voids, with measures taken to ensure that all concrete is compact. If for any reason the surfaces or interiors indicate voids or are in any way defective, such concrete shall be repaired as directed by the Owner's Representative. Defective Work shall be repaired as specified hereinafter. No concrete shall be placed during rainstorms. Concrete placed immediately before rain shall be protected to prevent rain water from coming in contact with it. Sufficient protective covering shall be kept on hand at all times for this purpose. 1. Placing Temperatures a. Hot Weather: When the weather is such that the temperature of the concrete as placed would exceed 90°F, the Contractor shall employ ice or other effective means of cooling the concrete during mixing and transportation so that the temperature of the concrete as placed will not exceed 90°F. Precautions shall be taken when placing concrete during hot weather to eliminate early or "flash" setting of concrete. This includes protection of reinforcing from direct sunlight to prevent heating of reinforcing, placing concrete during cooler hours of the day and the proper and timely application of specified curing methods. - City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 8 of 18 All cracks that occur in line with reinforcing bars due to "flash" setting of concrete shall be repaired by the Contractor at his own expense. These cracks are in addition to the cracks defined in Subsection 3.4, Repair of Defective Concrete. There will be no additional reimbursement to the Contractor for costs incurred for placing concrete in hot weather. b. Cold Weather: Suitable equipment for enclosing and heating freshly placed concrete and maintaining the required curing conditions shall be furnished by and at the expense of the Contractor and shall be approved by the Owner's Rep resentat ive. When the temperature of the surrounding atmosphere is 40°F or, as determined by the Owner's Representative, is likely to fall below this temperature, the mixing water shall be heated to but not exceed 140°F. Under no circumstances shall the heated water be permitted to come in contact with the cement before the cement is added to the batch. Concrete, when placed in the forms during cold weather, shall have a temperature of not less than 55°F. All materials shall be free from ice, snow, and frozen lumps before entering the mixer. The air and forms in contact with the concrete shall be maintained at temperatures about 40°F for at least the first five days and above 35°F for the remainder of the curing period. Reinforcing shall be protected and shall be maintained at temperatures about 50°F until concrete is placed around the bars. The temperature protection equipment, the curing water and the removal of forms shall be handled and applied so that ambient and concrete surface temperatures, as indicated by suitable thermometers installed outside of the concrete and two inches inside the surface of the concrete, may be determined by direct observation. All thermometers shall be furnished by the Contractor. There will be no additional reimbursement made to the Contractor for costs incurred for placing concrete during cold weather. D. _- Pumping Concrete: Equipment: Pump size shall be based on rate of concrete placement, length of delivery pipe or hose, aggregate size, mix proportions, vertical lift and slump of concrete. Minimum inside diameter of pipe or hose shall be based on the maximum aggregate size as follows: 3/4-inch maximum aggregate 1 %-inch maximum aggregate 2-inches minimum ID 4-inches minimum ID Aluminum pipes shall not be used for delivery of concrete to the forms. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 9 of 18 Pumping: Before pumping is started, the delivery pipe or hose shall be primed by pumping mortar through the line using five gallons of mortar for each 50-feet of delivery line. - E. Construction Joints: Construction joints shall be made only where shown on the Plans, unless otherwise permitted by the Owner's Representative. In case of emergency, construction joints shall be placed as directed by the Owner's Representative. After the pour has been completed to the construction joint and the concrete has hardened, the entire surface of the joint shall be thoroughly cleaned of surface laitance, loose or defective concrete and foreign material. Clean aggregate shall be exposed by sandblasting the surface of construction joints before the new concrete is placed. Except when otherwise shown on the Plans, after the surfaces have been prepared to the satisfaction of the Owner's Representative, all horizontal construction joints shall be covered with a layer of mortar approximatelytwo inches in thickness and shall be spread uniformly and worked thoroughly into all irregularities of the surface. The mortar shall have the same proportions of cement and sand as the regular concrete mixture. The water-cement ratio of the mortar in place shall not exceed that of the concrete to be placed upon it and the consistency of the mortar shall be suitable for placing and working. Where indicated on the Plans, expansion joints shall be provided with continuous edge reservoirs which shall be filled with a joint sealant. The material used for forming the reservoirs shall be left in place until immediately before the grooves are cleaned and filled with joint sealant. After removing edge forms from the reservoir, all grout, loose concrete, and fins shall be removed after which the slots shall be sandblasted. The reservoirs shall be allowed to become thoroughly dry, after which they shall be blown out and immediately thereafter, they shall be primed and filled with the expansion joint sealant and back-up materials. The primer used shall be supplied by the same manufacturer supplying the joint sealant. -. Construction joints shall be keyed, unless otherwise detailed. Keyways shall be formed by beveled strips or boards placed at right angles to the direction of shear. Except where otherwise shown on the Plans or specified, keyways shall be at least 1%-inches in depth over at least 25% of the area of the section. When it is necessary to make a joint because of an emergency, reinforcing steel shall be furnished and placed across the joint as directed by the Owner's Representative. Furnishing and placing such reinforcing steel shall be at the Contractor's expense. F. Embedded Items: Anchor bolts and all other embedded items shall be set accurately and held securely in position in the forms until the concrete is placed and set. All special castings, channels, or other metal parts that are to be embedded in the concrete shall be approved prior to and again after installation. All nailing blocks, plugs, strips, etc., necessary for the attachment of trim, finish and similar work, shall be approved prior to installation by the Contractor. Aluminum surfaces to be embedded or which are in contact with concrete shall, before installation, be given one coat of zinc chromate primer in accordance with 4 City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 10 of 18 United States Joint Army-Navy Specification JAN-P-735 or the equivalent. The paint shall be allowed to dry before the aluminum is placed in contact with the concrete. Submerged aluminum surfaces in contact with concrete or masonry shall receive one heavy coat of alkali-resistant bituminous paint in accordance with U.S. Military Specification MIL-P-6883. The paint shall be applied as it is received from the manufacturer without addition of any thinner. G. Curing: All concrete shall be cured for not less than 14 days after placing, in accordance with the methods specified herein for the different parts of the Work and described in detail in the following paragraphs: Surface to be Cured Method Unstripped wooden forms 1 Vertical and horizontal construction joints and walls Surfaces requiring architectural finish or which are to be plastered or tiled or upon which concrete topping is to be placed All concrete surfaces not specifically provided for elsewhere in this subsection Method 1 : Method 2: Method 3: Method 4: City of Carlsbad 03/04 (DBE) 2 3 4 Wooden forms shall be wetted immediately after concrete has been placed and shall be kept wet with water until removed. The exposed concrete surfaces shall then be cured by Method 2, 3 or 4. The surface shall be covered with burlap mats which shall be kept wet with water for the duration of the curing period. The surface shall be kept wet with water for the duration of the curing period. This shall be accomplished by keeping the forms wet prior to stripping and by means of an approved combination of fog nozzlers, soaker-type hoses, handsprinkling, and burlap or other types of mats. No curing compound may be applied to surfaces cured under Method 3. The surface shall be sprayed with a liquid curing compound which will not affect the bond of paint to the concrete surface. It shall be applied in accordance with the manufacturer's instructions at a maximum coverage rate of 300-square feet per gallon in such a manner as to cover the surface with a uniform film which will seal thoroughly. The exterior surfaces of buried portions of partially buried walls shall be given two additional coats of curing compound at the specified coverage rate, making three coats in all. ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 1 1 of 18 Surfaces which are to receive Method 4 curing shall be reviewed prior to placement with respect to anticipated weather conditions and placement procedures, whereby Method 3 curing may be required as directed by the Owner's Representative. - Where the curing compound method is used, care shall be exercised to avoid damage to the seal during the curing period. Should the seal be damaged or broken before the expiration of the curing period, the damaged portions shall be repaired immediately by the application of additional curing compound. Whenever curing compound may have been applied to surfaces against which concrete subsequently is to be placed and to which it is to adhere, the curing compound shall be entirely removed by sandblasting prior to the placing of new concrete. Where curing compound is specified, it shall be applied immediately after completion of the finish on unformed surfaces and within two hours after removal of forms on formed surfaces. Repairs required to be made to formed surfaces shall be made within the said two hour period; provided, however, that any such repairs which cannot be made within the said two hour period shall be delayed until after Method 3 has been applied. When repairs are to be made to an area on which curing compound has been applied, the area shall first be sandblasted to remove the curing compound, after which repairs shall be made as specified hereinafter. H. Installation of Pipelines Through Concrete - 1. Pipes in Place: whenever a pipeline of any material terminates at the surface or continues through a structural wall, slab, or sump, the Contractor shall, where possible, install in advance of placing concrete the fitting or special casting required for the particular installation. Welding of wall flanges to reinforcing steel shall not be permitted and shall be cause for rejection. 2. Formed Openings: Whenever any run of pipe is installed subsequent to placement of concrete, the Contractor shall accurately position the required opening in the concrete for such pipelines. Openings shall be of sufficient size to permit final alignment of pipelines and fittings without deflection or offsets of any kind and to allow adequate space for satisfactory packing where pipe passes through the wall to ensure water tightness around openings so formed. The boxes or cores shall be provided with continuous keyways to hold the filling material in place, and they shall have a slight flare to facilitate grouting and the escape of entrained air during grouting. Formed openings shall be provided with reinforcement as indicated on the Plans. 3. Non-shrink Grout: Non-shrink grout shall be Master builders "MASTERFLO" 71 3 grout or approved equal. Grout shall not contain any ferrous materials. - Before placing the grout, concrete surfaces shall be abrasive cleaned and shall be coated with an epoxy bonding compound. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 12 of 1 8 I. .- 4. Placing of Grout: The pipe, castings, or conduits, as specified, shall be grouted in place by pouring in grout under a head of at least four inches. The grout shall be poured or rammed into place to fill completely the space between the pipes, castings, or conduits and the sides of the openings so as to obtain water tightness through the wall itself. The grouted area shall then be water cured. Surface Finishes: Concrete surface finishes shall be in accordance with the concrete finish schedule indicated below: CONCRETE FINISH SCHEDULE Finish Area F- 1 F-2 F-3 Exterior walls below grade not exposed to water. Exterior and interior walls exposed to water. Walls of structures or buildings exposed to view. Underside of formed floors or slabs. Slabs and floors to be covered with concrete. Slabs and floors not water bearing. Slabs and floors which are water bearing. Slabs and floors of structures or buildings exposed to view (includes sidewalks). Exposed edges of slabs, floors, and wall tops. s- 1 s-2 s-3 s-4 E- 1 The following finishes shall be used for vertical concrete surfaces and for underside of formed slabs: Finish F-1 : Finish F-2: Finish F-3: ,- City of Carlsbad 03/04 (DBE) No special treatment other than repair of defective concrete and filling depressions deeper than 1/2-inch and filling tie holes. Repair of defective concrete, removal of fins, filling depressions 1/4-inch or deeper and filling tie holes. Finish 2 shall be a preparation finish for surfaces receiving Finish 3. Upon completion of Finish F-2, fill all depressions and air holes with mortar. Predampen surfaces and then spread a slurry consisting of one part cement (including an appropriate quantity of white cement) and 1- 1/2 parts sand passing the No. 16 sieve, by damp loose volume, over the surface with clean burlap pads or sponge rubber floats. Any surplus shall be removed by scraping and then rubbing with clean burlap (sack finish). ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 13 of 18 After proper and adequate vibration and tamping, the following finishes shall be used for horizontal concrete surfaces: Finish S-1 Screeded to grade and left without special finish. Finish S-2 Smooth steel trowel finish. Finish S-3 Steel trowel finish free from trowel marks. The finish shall be smooth and free of all irregularities. (Note shall be made where moving mechanical equipment is located). Finish S-4 Steel trowel finish without local depressions or high points and shall be given a light hair-broom finish. Stiff bristle brooms or brushes shall not be used. Brooming shall be parallel to slab drainage. Finish E-1 : Exposed edges of all slabs, floors and tops of walls shall be edged with a 1/4-inch radius edger or chamfered as shown on the Plans. Edges shall include any line where placement is stopped. All wall and slab surfaces at edges shall be protected against concrete spatter and shall be thoroughly cleaned upon completion of each placement or adjacent placement of concrete. 3.2 Form Construction Requirements A. All forms shall be true in every respect to the required shape and size, shall conform to the established alignment and grades, and shall be of sufficient strength and rigidity to maintain their position and shape under the loads and operations incident to placing and vibrating the concrete. B. Suitable and effective means shall be provided on all forms for holding adjacent edges and ends of panels and sections tightly together and in accurate alignment so as to prevent the formation of ridges, fins, offsets, or similar surface defects in the finished concrete. The forms shall be tight in order to prevent the loss of mortar and fines during placing and vibration of the concrete. C. Cleanout and inspection openings shall be provided at the bottom of each lift of forms. The size, number, and location of such openings is subject to the approval of the Owner's Representative. D. Exterior corners in concrete members shall be provided with 3/4-inch chambers. Re-entrant corners in concrete members shall not have fillets, unless otherwise shown on the Plans. Adequate and suitable means shall be provided for removing all forms without injury to the surface of the finished concrete. E. A sufficient number of forms shall be provided to permit a reasonable and coordinated rate of progress to be maintained. If, in the opinion of the Owner's Representative, additional forms are required to maintain the necessary progress, such additional forms shall be provided. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 14 of 18 F. Where metal rod ties extending through the concrete are used to support or to strengthen forms, the rod ties shall remain embedded and shall terminate not less than one inch back from the formed face or faces of the concrete. The maximum diameter of removable cones for rod ties shall not exceed one inch, and all such fasteners shall be such as to leave holes of conical shape for reaming and patching. Wire ties for holding forms will not be permitted. No form-tying device or part thereof or other than metal shall be left embedded in the concrete, nor shall any be removed in such a manner as to leave a hole extending entirely through the concrete member. The use of form or form-tying methods which cause spalling of the concrete upon form stripping or tie removal will not be permitted. Form ties shall be provided with integral waterstops. All vertical surfaces of concrete members shall be formed, except where the placement of the concrete against the ground is called for on the Plans or explicitly authorized by the Owner's Representative. The dimensions of concrete members shown on the Plans apply to formed surfaces, except where otherwise indicated, and not less than one inch of concrete shall be added where concrete is permitted to be placed against trimmed undisturbed ground in lieu of forms. Such permission will be granted only for members of comparatively limited height and where the character of the ground is such that it can be trimmed to the required lines and will stand securely without caving or sloughing. G. c Forms shall be maintained at all times in good condition, particularly as to size, shape, strength, rigidity, tightness, and smoothness of surface. Forms, when in place, shall conform to the established alignment and grades. Before concrete is placed, the forms shall be thoroughly cleaned. The surfaces of all Class I forms shall be treated with a bond breaker as specified hereinbefore. Class II forms shall be treated with a non-staining mineral oil or other lubricant approved by the Owner's Representative. Any excess lubricant shall be satisfactorily removed before placing the concrete. In addition, all plywood not treated with the bond breaker specified above, shall be given a preliminary oil treatment by the form manufacturer or shall be oiled by the Contractor at least two weeks in advance of its use as forms. Care shall be exercised to keep form oil off the surface of steel reinforcement and other metal items to be embedded in concrete. H. Forms may be reused if they are in good condition and if approved by the Owner's Representative. In determining the extent to which forms may be reused, particular attention shall be given to maintaining a uniform surface texture on all exposed concrete surfaces. Light sanding between uses will be required wherever necessary, in the opinion of the Owner's Representative, to obtain such uniform texture. Unused tie rod holes shall be plugged with corks, shaved flush, and sandpapered on the concrete surface side. Patching of forms other than filling tie rod holes will not be permitted, except in the case of Class II forms. The use of metal patching discs on Class I forms will not be permitted. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 15 of 18 3.3 Reinforcinrr (Non-Prestressed) - A. Placing: Reinforcement steel shall be accurately positioned in accordance with the Plans and secured by using annealed wire ties or suitable clips at intersections and shall be supported by concrete or metal supports, spacers or metal hangers. Metal clips or supports shall not be placed in contact with the forms. Tie wires shall be bent away from the forms in order to provide the specified concrete coverage. Bars, additional to those shown on the Plans, which may be found necessary or desirable by the Contractor for the purpose of securing reinforcement in position, shall be furnished and installed by the Contractor at his own expense. All reinforcement shall be placed a minimum of 2-inches clear of any metal pipe or fittings. Reinforcing dowels, where required or ordered, shall be set in place prior to placing concrete; they shall not be pressed into the concrete after the concrete has been placed. Wire mesh used for reinforcement shall be rolled flat before placing concrete and shall be supported and tied to prevent movement during concrete placement. Dowels for masonry walls shall be accurately positioned to occur at reinforced block cells. The Owner's Representative shall approve all dowel locations prior to placing of any concrete. B. Splices: When it is necessary to splice reinforcement at points other than shown on the Plans, the splice shall be 36 bar diameters. Unless otherwise shown, splices in horizontal bars shall be staggered with splices 36 bar diameters with 18-inches minimum. Laps of wire mesh shall be one width of wire spacing, and adjoining sheets shall be securely tied together with No. 14 tie wire, one tie for each two running feet. Wires shall be staggered and tied in such a manner that they cannot slip. .- 3.4 Repair of Defective Concrete A. General: As soon as forms are removed, all surfaces shall be carefully examined and all rough sections, rock pockets, and defective areas shall be removed and replaced. The material used for repair purposes shall consist of a cement mortar composed of one part cement well mixed with three parts sand by volume and only enough water so that the mortar will ball together when molded by slight pressure of the hands. The mortar shall be thoroughly compacted into place. Sand shall pass a No. 16 sieve. Defective surfaces to be repaired shall be cut back from true line a minimum depth of one inch over the entire area. Feathered edges shall be avoided. All surface laitance or soft material, and not less than 1/32-inch depth of the surface film from all sound concrete, shall be removed by means of an efficient sandblast. -_ City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 16 of 1 8 .- E- Dry-pack mortar shall be placed and packed in layers having a compacted thickness of 3/8-inch. Surfaces of each layer shall be scratched to promote bonding of next layer. Before the mortar is applied, the surfaces of the sandblasted concrete shall be coated with an epoxy bonding compound. Major defective area repairs are defined as follows: 1. Areas of more than one foot square and deeper than the reinforcing steel. 2. Major repair areas shall be filled with pneumatically-applied concrete after surfaces have been sandblasted. For major repairs, the filling shall be reinforced and doweled securely to the old concrete. The exposed surface shall be neatly finished to match the surface and texture of the adjacent concrete. All patches shall be cured by Method 2. Holes left by tie-rod cones shall be reamed with suitable toothed reamers so as to leave the surfaces of the holes clean and rough. These holes then shall be repaired in an approved manner with mortar and epoxy and cured in accordance with the requirements of the curing section of the Specifications. Other imperfections having a depth greater than their least surface dimension shall not be reamed, but shall be repaired in an approved manner with epoxy bonding compound and dry packed mortar. All repairs shall be built up and shaped in such a manner that the completed surface will conform to the finish requirements of this specification using approved methods which will not disturb the bond or cause sagging or horizontal fractures. Surfaces of said repairs shall receive the same kind and amount of curing treatment as required for the concrete in the unrepaired section. B. Cracks in Hydraulic Structures: Concrete cracks greater than 1/64-inch in width shall be repaired by cutting out a square edge joint 1/2-inch wide by one inch deep, preparing all exposed surfaces of the joint, installing a back-up rod, priming of the joint and application of the polyurethane joint sealant in accordance with the joint sealant section of this specification. Alternate methods of crack repair used by the Contractor which utilize epoxy adhesive injection methods shall be subject to the approval of the Owner's Representative. Full height vertical cracks and full width horizontal cracks greater than the above- specified width shall be assumed to occur and the Contractor shall make allowance in his bid for the repair of specified cracks. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic 8t Recycled Water Transmission Mains 03300 Concrete Construction - 17 of 18 3.5 Enforcement of Concrete Strength Requirements A. Compressive Strength: Compressive strength shall be determined at the end of seven days and 28 days on standard six by 12-inch test cylinders in accordance with ASTM C39. The compressive strength shall not be less than 3,000 psi for Type A concrete and 2,000 psi for Type C concrete at 28 days. - B. Concrete Cylinders: The Owner's Representative will take three concrete cylinders for each 50 cubic yards of concrete and each day's pour. The Contractor shall furnish the concrete and cylinders for such tests. Cylinders will be cured under job conditions. Slump tests will be in accordance with ASTM C143. C. Cylinder Tests: If any cylinders fail to meet the strength requirements for the portion of the structure in which the concrete is used, core tests will be taken at the Contractor's expense to demonstrate the adequacy of the concrete in place. If both core tests and cylinder tests fail to meet the Specifications, the concrete shall be considered defective and shall be replaced or adequately strengthened in a manner satisfactory to the Engineer. END OF SECTION -.. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 03300 Concrete Construction - 18 of 18 SECTION 09870 TAPE WRAP AND CONCRETE MORTAR COATING _- PART 1 -GENERAL 1.1 Description A. The steel pipe shall be coated with polyethylene tapes in accordance with AWWA C214. Fittings and specials shall be coated with cold-applied polyethylene tapes in accordance with AWWA C209. A reinforced cement mortar shield shall be applied in accordance with AWWA C205. Any modifications to the aforementioned standards are as stated herein. 1.2 Related Work Elsewhere The Contractor shall refer to the following specification section(s) for additional requirements: A. Shop Drawings Submittals: 01 300 8. Earthwork: 02200 C. Painting and Coating: 09900 D. c Petrolatum Wax Tape Coating: 09902 E. Cement Mortar Lined Steel Pipe: 15076 1.3 Qualifications of Manufacturers A. Manufacturer to demonstrate a minimum of five years’ successful application of tape coating system on similar diameter steel water pipelines as specified herein. 1.4 Submittals A. List of tape coating materials indicating manufacturer, product numbers, and thickness of materials related to tape system for joints and repairs. B. Certification of test results for each batch of liquid adhesive and each tape material specified shall be in accordance with AWWA C214. C. Tape application procedure approved by tape manufacturer. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09870 - Tape Wrap and Concrete Mortar Coating - 1 of 9 1.5 Coordination With Tape Manufacturer ---_ A. The pipe manufacturer shall require the tape material manufacturer to furnish qualified factory technical representative to visit the site for technical support at the beginning of the pipe installation as may be necessary to instruct Contractor on appropriate tape application methods in the field or to resolve problems. This visit shall be coordinated to allow City Inspection and Maintenance Staff to participate in the instruction. The Contractor shall allow time for representative to give field taping instructions to his workforce. PART 2 - MATERIALS 2.1 2.2 2.3 2.4 Polvethvlene Tape Coatinq A. Provide polyethylene tape coating in accordance with AWWA C214 with a reinforced cement mortar shield in accordance with AWWA C205 and as specified herein. Plant and field applied liquid adhesive, polyethylene tape, and plant and field applied repair tape shall be furnished by a single manufacturer. The physical properties of tape materials shall meet or exceed the requirements of AWWA C214 when tested in accordance with the methods described in Section 5.3, “Coating System Tests”. B. The tape coating systems consist of an exterior polyethylene tape over the primed metal surface of steel pipe with a reinforced cement mortar coating applied over the tape system. Tape coating systems are specified for: - 1. Normal plant cold-applied tape 2. 3. Plant cold-applied tape for special sections, connections and fittings, and plant repairs of cold-applied tape Field joint, field coated fittings and repair of field cold-applied tape. Liquid adhesive A. Liquid adhesive shall consist of a mixture of suitable rubber and synthetic compounds and a solvent in accordance with AWWA C214. The liquid adhesive shall be Polyken #lo39 primer. Storage Primer A. Storage primer on the exposed steel at the tape cutbacks shall be Polyken #924. Plant Applied Polyethvlene Tape System, Polyken YGlll (80 mil) A. B. Liquid adhesive shall be Polyken #lo39 primer. Anti-corrosion inner layer tape shall be Polyken #989 (20 mil), black. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09870 - Tape Wrap and Concrete Mortar Coating - 2 of 9 C. D. First mechanical outer layer tape shall be Polyken #955 (30 mil), gray. Second mechanical outer layer tape shall be Polyken #956 (30 mil), white. c E. Reinforced cement mortar shield 3/4" thick. F. Weld Stripping Tape shall be Polyken #933 (25 mil), if required. 2.5 Plant Cold-Applied Tape Coatings for Special Sections, Connections and Fittings, and Plant Repair Cold-Applied Polyethylene Tape Material A. Liquid adhesive shall be Polyken #lo39 primer. B. Anti-corrosion inner layer shall be Polyken #932-50 (50 mil), black. C. Mechanical layer outer tape for plant fittings and plant repair cold-applied polyethylene tape shall be Polyken #955 (30 mil), white. D. Reinforced cement mortar shield 3/4 thick. E. Weld stripping tape shall be Polyken #933 (25 mil), if required. 2.6 Field Joint, Field Coated Fittings, and Field Repair Cold-Applied Polvethvlene .- Tape A. Primer shall be Polyken #1029. B. Joint filler tape to be Polyken #939. C. Field joint, field fitting, and field repair outer layer tape shall be Polyken #932, (50 mil). D. Mechanical layer outer tape for field joint, field fittings and field repair shall be Polyken #932-50, continue inner layer with 50% overlap. PART 3 - EXECUTION 3.1 Polvethylene Tape Coating A. Apply polyethylene tape coating to pipe in accordance with AWWA C214. Apply polyethylene tape coating to fittings and specials in accordance with AWWA C209. Apply the reinforced cement mortar shield in accordance with AWWA C205. Any modifications to the aforementioned standards are as stated herein. c B. Certificate of Compliance: Prior to shipment of pipe, furnish a certificate of compliance stating that tape materials and work furnished hereunder will comply or have complied with the requirements of these specifications and AWWA C214 and C209. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09870 - Tape Wrap and Concrete Mortar Coating - 3 of 9 3.2 Straight Run Pipe Application A. For straight run pipe, plant applied conditions, the polyethylene tapes shall be a four layer system consisting of: (1) liquid adhesive; (2) corrosion prevention tape (inner layer); (3) mechanical protective tape (first outer layer); (4) mechanical protective tape (second outer layer) B. Perform the entire coating operation at a single facility/manufacturer operation by experienced workers skilled in the application of polyethylene tapes and cement mortar coating under qualified supervisors. Do not allow additional offsite handling following initial set-up of pipe sections from applications of primer to mortar coating. C. All equipment for blasting and application of the tape coating system shall be of such design and condition to comply with all the requirements of AWWA C214 and these specifications. Immediately repair or replace equipment that, in the opinion of the Engineer, does not produce the required results. Include equipment and a repair procedure for correcting defective tape application for use under this specification in the steel pipe fabrication plan. Make available for review a copy of this portion of the fabrication plan, and any updates, at the location of the coating operation, and a repair procedure for correcting defective tape application. Remove the exterior weld bead along the entire exterior surface of the pipe. The exterior weld bead shall be flush with the exterior surface of the pipe with a tolerance of plus 1/32-inch. ^4 D. E. Surface preparation shall conform to AWWA C214 and the following. 1. Bare pipe shall be clean of all foreign matter such as mud, mill lacquer, wax, coal tar, asphalt, oil, grease, or any contaminants. Remove welding slag or scale from all welds by wire-brushing, hammering, or other satisfactory means. Remove welding splash globules prior to priming. 2. Prior to blast cleaning, inspect surfaces and, if required, preclean in accordance with the requirements of SSPC SP-1, Solvent Cleaning, to remove oil, grease, and all foreign deposits. Remove visible oil and grease spots by solvent wiping. Use only approved solvents that do not leave any residue. Include in the manufacturer’s fabrication plan the cleaning solvent applications procedure and safety precautions. F. Blast cleaning shall conform to AWWA C214 and the following. 1. Blast the pipe surface using a commercially available shot grit mixture to 6, Commercial Blast Cleaning. achieve a prepared surface equal to that which is specified in SSPC SP- - City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09870 - Tape Wrap and Concrete Mortar Coating - 4 of 9 exterior blast cleaning in such a manner as not to endanger the mortar lining in the pipe. Completely remove corrosion and foreign substances from the exterior of the pipe in the cleaning operation, and apply liquid adhesive after completion of blast cleaning. 3. Achieve from abrasive blasting an anchor pattern profile a minimum of 1 .O mil, but not exceeding 3.0 mils. Measure the anchor pattern or profile of the blasted surface using comparator tape as specified herein. 4. Inspect the blast cleaned exterior pipe surface for adequate surface preparation prior to application of the liquid adhesive. Surface comparator tapes are to be used by the manufacturer in at least eight random areas, along any given 40-foot length of pipe. The results of the surface comparator tapes are to be documented on the quality control sheet for each pipe section. 5. Coat each pipe section with liquid adhesive and tape within the same day of being blast cleaned. Do not allow blasted and/or blasted and primed pipe to sit overnight. All blasted and primed pipe must be coated by the end of the day. No coating will be permitted on pipe sections showing evidence of rust. G. Liquid adhesive application shall conform to AWWA C214 and the following. c 1. Prior to liquid adhesive application, clean the pipe surface free of foreign matter such as sand, grease, oil, grit, rust particles, and dirt. 2. Apply the liquid adhesive in a uniform thin film at the coverage rate recommended by the manufacturer. Meet the recommendations of the manufacturer for the state of dryness of the liquid adhesive prior to the application of the inner layer of tape. 3. Limit the application of liquid adhesive to that length of pipe which can be taped within the same workday. Pipe coated with liquid adhesive that was not taped within the same workday shall be rejected at the discretion of the Engineer. The liquid adhesive shall be removed and the surface shall be reprimed. 4. Protect liquid adhesive coated pipe sections from moisture, dirt, sand, and other potentially contaminating materials 5. Apply storage primer to the exposed steel pipe at tape cutbacks to prevent oxidation of the cleaned metal surface. Apply minimum of 1.5 mils and maximum of 2.5 mils of storage primer to exposed steel per the manufacturer's recommendations. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09870 - Tape Wrap and Concrete Mortar Coating - 5 of 9 H. Inner layer tape application: City of Carlsbad 03/04 (DBE) 1. - Apply the inner layer tape directly onto the primed surface using approved mechanical dispensing equipment to assure adequate, consistent tension on the tape as recommended by the tape manufacturer. Use rollers to apply pressure on the tape as it comes in contact with the pipe. Make necessary adjustments to mechanical application equipment to assure a uniform, tight coating. Maintain a tight, smooth, mechanically induced, wrinkle-free coating throughout the application process. 2. The application of tension shall be such that the width of tape will be reduced between 1% to 2 percent of tape width prior to the pull. Provide a pressure readout gauge and chart recorder, suitable to the Engineer, with the tape let-off machine to document the tape tension during application. 3. Apply inner layer tape at a minimum roll temperature of 70°F. Continuously monitor the temperature of the tape within 12 inches of the point of contact with the pipe surface. Use a chart recorder, suitable to the Engineer, to document the temperature of the tape during application. Sections where the tape application tension and temperature is not maintained within manufacturer’s recommendations shall be rejected and the tape removed from the entire pipe section and reapplied. - 4. Continuously electronically test the inner tape layer at 6,000 volts immediately following application of the tape by a holiday tester permanently mounted to the tape application station and equipped with an indicator light and audio buzzer, suitable to the Engineer to alert the workmen of the presence of holidays in the coating system. 5. Spirally wrap the inner layer tape over longitudinally or spirally welded pipe. Provide a 1 -inch minimum tape overlap. 6. Splice each new roll by overlapping the new tape over the end of the preceding roll by at least 6 inches. Perform this end lap splice by hand or by a mechanical applicator so that the splice is wrinkle free and maintains the continuity of the inner wrap coating. Maintain the wrapping angle of the new roll parallel to that of the previous roll. 7. Provide tape cutbacks based on the joint type required, cutting the tape edge parallel to the end of the pipe. Perform cutbacks using a cutting device that is guided from the end of the pipe to insure a uniform, straight cutback. ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09870 - Tape Wrap and Concrete Mortar Coating - 6 of 9 I. Mechanical outer layer tape application. 1. 2. Apply the first mechanical outer layer of tape over the inner layer tape using the same type of mechanical equipment used in the application of the inner layer tape. No overlap splice of the other layer coinciding with the overlap splice of the inner layer will be permitted. Provide a minimum 6-inch separation between overlap of splices. Apply two mechanical outer layers of tape as specified herein. The inner layer tape shall be electrically tested, inspected, and approved prior to the application of the first mechanical outer layer tape and the first mechanical outer layer tape shall also be visually inspected and approved prior to the application of the second mechanical outer layer tape. Ensure that both mechanical outer layer tapes are smooth, tight and wrinkle-free. Apply mechanical outer layer tapes in accordance with the requirements for the inner layer tape, except that the minimum tape roll application temperature shall be 90°F. Monitoring for tension and temperature will be required for the mechanical outer layer tapes. The use of rollers to apply pressure on the tape is not required during application of the mechanical outer layer tapes. Holiday testing of the mechanical outer layer tapes is not required during tape application. Test the complete tape system prior to coating as specified herein. J. Apply a reinforced cement mortar shield over the outer layer of tape in accordance with AWWA C205. Cement mortar shall be 3/4" thick in accordance with Section 15076, paragraph 2.9. K. Storage primer application shall conform to AWWA C214 as modified herein: 1. Prior to storage primer application, clean the pipe surface free from foreign matter such as sand, grease, oil, grit, rust particles and dirt. 2. Apply primer only to a dry pipe surface. Whenever the ambient air temperatures are cold enough to cause gelling of the primer, the use of heaters will not be permitted to return the primer back to a fully liquid state. Use new primer at a minimum of 40°F. 3. Apply storage primer to the exposed steel pipe at tape cutbacks to prevent oxidation of the cleaned metal surface. Apply minimum of 1.5 mils and maximum of 2.5 mils of storage primer to exposed steel per the manufacturer's recommendations. Do not place storage primer on the edge of the steel plate. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09870 -Tape Wrap and Concrete Mortar Coating - 7 of 9 Fittinqs Coated at the Plant A. - Coat fittings that cannot be machine coated in accordance with AWWA C209 using materials as specified herein. Weld bead preparation, surface preparation, blast cleaning and liquid adhesive shall be as specified for straight run pipe. Apply an inner layer tape of Polyken #932-50 with a l-inch minimum tape overlap on all plant coated fittings. Apply an outer layer of cold-applied polyethylene tape as specified herein with a 55 percent overlap on all plant- coated fittings. Provide a minimum thickness of 110 mils for the total tape coat system for plant-coated fittings. B. Test all completed tape coated fittings in the presence of the Engineer with an electrical flaw detector prior to the application of the cement mortar coating. Applied voltage shall be in the range of 11,000 to 15,000 volts. Repair any holidays found. C. Repair cement mortar coating defects in accordance with the approved repair procedures. D. Apply cement mortar coating in accordance with AWWA C205, over the tape- coated fittings after completion of tape coating, testing and inspections. 3.4 Tape Application to Fittings. Specials and Pipe Joints (Field) .-_ A. Filler tape shall be used to fill voids on fittings, specials, welds, and pipe joints. B. All bell and spigot joints, lap joints, and other locations where voids will otherwise exist shall be provided specially shaped filler tape applied after priming. C. Field pipe joints shall be prepared as required by the paragraph entitled "Pipe Surface Preparation," except that shop blasted surfaces that have been coated with a storage primer or an epoxy coating may be power-tool cleaned instead of abrasive-blast cleaned. The power tool cleaning shall be done in accordance with SSPC-SP2: Pipe ends not effectively protected with a storage primer shall be abrasive blasted to SSPC-SP6. D. The tape system for pipe joints is shown in Section 2.6. 3.5 Inspection of Tape Coating Perform all tape coating work in accordance with AWWA C209 Section 5. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09870 - Tape Wrap and Concrete Mortar Coating - 8 of 9 3.6 Protectinq Coated Pipe IC A. The CONTRACTOR shall protect all coated surfaces from damage prior to and during the pipe installation in accordance with these specifications. €3. In transporting the coated pipe, it shall rest in saddles shaped to the outside diameter of the coated pipe. The saddles shall be in contact with the bottom of the pipe along an arc of at least 60 degrees. Saddles shall be completely lined with adequate padding. No nails or any other fasteners that may damage the coating will be allowed in the installation of the padding of the saddles. C. While laying tape coated steel pipe, the pipe shall not be rolled or skidded when it is in contact with the ground at any point. Immediately before the coated pipe is lowered into the trench the CONTRACTOR shall provide a visual and holiday inspection of the coating on the entire pipe coating system. Coated pipe shall be lowered into the trench using saddled, not choked, belt slings. The use of chains, hooks, or other equipment which might damage the pipe coating will not be permitted. All other pipe handling equipment and methods shall be approved by the ENGINEER. Pipe stored alongside of the trench shall be supported on padded skids, sand bags, or rock-free sand berms. END OF SECTION .- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09870 - Tape Wrap and Concrete Mortar Coating - 9 of 9 SECTION 09900 PAINTING AND COATING PART1 - GENERAL 1.1 Description This section described the requirements for the preparation of surfaces and subsequent application of protective coatings. The Contractor shall furnish all labor, materials and equipment required for satisfactory completion of all items contained herein. The Contractor shall furnish all necessary safety equipment and protective clothing, as well as be responsible for proper instruction and supervision of their use. Requirements for steel storage reservoirs are specified elsewhere in the Specifications. 1.2 Related Work Described Elsewhere The Contractor shall refer to the following Specification section(s) for additional requirements: A. Shop Drawing Submittals: 01300 B. Testing and Inspection: 01410 1.3 Submittals Contractor shall furnish submittals in accordance with the requirements of Section 01 300, Shop Drawing Submittals. The following submittals are required: - A. Submit a chart of the manufacturer's available colors for color selection well in advance of painting operation. B. Submit manufacturer's data sheets showing the following information: 1. Recommended surface preparation. 2. Minimum and maximum recommended dry-film thicknesses per coat for prime, intermediate, and finish coats. 3. Percent solids by volume. 4. Recommended thinners. 5. Statement verifying that the selected prime coat is recommended by the manufacturer for use with the selected intermediate and finish coats. 6. Application instructions including recommended application, equipment, humidity, and temperature limitations. 7. Curing requirements and instructions. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09900 - Painting and Coating - 1 of 10 C. Submit certification that all coatings conform to applicable local Air Quality Management District rules and regulations for products and application. - 1.4 Pavment Payment for the Work in this section shall be included as part of the lump-sum or unit-price bid amount for which such Work is appurtenant thereto. PART 2 - MATERIALS 2.1 General A. B. C. D. All materials shall be those of current manufacture and shall meet all applicable regulations for the application and intended service. All coats of any particular coating system shall be of the same manufacturer and shall be approved by the manufacturer for the intended service. In the event that a product specified herein is no longer manufactured or does not meet current regulations, the Contractor shall provide a substitute, currently manufactured product of at least equal performance which meets all applicable regulations subject to Engineer's approval, at no additional cost. All materials shall be delivered to the Project Site in their original, unopened containers bearing the manufacturer's name, brand, and batch number. Standard products of manufacturers other than those specified will be accepted when it is proved to the satisfaction of the Engineer they are equal in composition, durability, usefulness and convenience for the purpose intended. Paint listed in the system refers to products of the following manufacturers and distributors: Ameron Corrosion Control Division, Brea, CA I. C. Devoe, Louisville, KY Engard Coating Corporation, Long Beach, CA E. I. DuPont de Nemours & Company, Los Tnemec Company, Inc., Kansas City, MO, Angeles, CA 641 41 All surfaces to be coated or painted shall be in the proper condition to receive the material specified before any coating or painting is done. No more sandblasting or surface preparation than can be coated or painted in a normal working day will be permitted. All sharp edges, burrs, and weld spatter shall be removed. All concrete and masonry surfaces shall cure 30 days prior to coating or painting. Surface preparation, prime coatings, and finish coats for the various systems are specified herein. Unless otherwise noted, all intermediate and finish coats shall be of contrasting colors. It is the intent that the coating alternates specified herein serve as a general guide for the type of coating desired. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09900 - Painting and Coating - 2 of 10 2.2 Valves IC A. c B. C. Exterior Coating: Coat metal valves located above ground, in vaults or in structures the same as the adjacent piping. If the adjacent piping is not coated, then coat valves per this Specification section unless otherwise noted. Apply the specified prime coat at the place of manufacture. Apply intermediate and finish coats in the field. Finish coat shall match the color of the adjacent piping. Coat handwheels and floor stands the same as the valves. Coat the exterior of buried metal valves at the place of manufacture per this specification. Coating (Devoe Alternate): Prime coat shall be BarRust 231 or Devran 200 applied at 2 to 3 mils dry-film thickness. Intermediate coat shall be Devran 224H Epoxy applied at 2 to 4 mils dry-film thickness. Finish coat shall be 379 Urethane applied at 2 to 3 mils dry-film thickness. Interior Lining: Valves 4-inches and larger shall be coated on their interior metal surfaces excluding seating areas and bronze and stainless-steel pieces. Sandblast surfaces in accordance with SSPC-SP-10 (near white blast cleaning). Remove all protuberances which may produce pinholes in the lining. Round all sharp edges to be coated. Remove any contaminants which may prevent bonding of the lining. Coat the interior ferrous surfaces using one of the following methods: 1. 2. 3. 4. Apply powdered thermosetting epoxy per the manufacturer's application recommendations to a thickness of 10 to 12 mils. Apply two coats of polyamide epoxy to a dry-film thickness of 10 to 12 mils total. Follow the manufacturer's application recommendations including minimum and maximum drying time between the required coats. Apply two coats of Tnemec Series 140 (for potable water) or Series 69 (for non- potable water), or equal, to a dry film thickness of 10 to 12 mils total. Follow manufacturer's application recommendations including minimum and maximum drying time between required coats. Apply two coats of Devoe Bar-Rust 233H Epoxy applied to a dry-film thickness of 6 to 8 mils, each. Total dry-film thickness shall be 10 to 12 mils minimum. All epoxy lining shall be applied at the factory by the manufacturer of the valve, and shall meet current Volatile Organic Compound (VOC) content regulations. Epoxy lining for potable water valves shall also be listed by National Sanitation Foundation (NSF) for contact with potable water. Test the valve interior linings at the factory with a low-voltage holiday detector. The lining shall be holiday free. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09900 - Painting and Coating - 3 of 10 2.3 Metal, Interior and Exterior, Normal Exposure A. General: The Contractor shall paint all exposed steelwork, non-galvanized handrails, exposed pipework, fittings, all mechanical equipment, pumps, motors, doors, door frames and window sash with this coating system. All metalwork previously given a shop prime coat approved by the Owner's Representative shall be touched up as required in the field with Tnemec Series 4 Versare Primer or equal. B. Surface Preparation: All exterior metal surfaces which are to be painted shall be commercial blast cleaned per Specification SP-6 (commercial blast cleaning) except as otherwise specified, in locations where sandblasting would damage previously coated surfaces and installed equipment, and in locations where dry sandblasting is prohibited. The above locations in which SP-6 commercial sandblasting is not possible shall be given a SP-3 power tool cleaning. This sandblasting shall be done not more than 8 hours ahead of the painting, subject to humidity and weather conditions between the time of sandblasting and painting operations. If any rusting or discoloration of sandblasted surfaces occurs before painting, such rusting or discoloration shall be removed by additional sandblasting. Sandblasted surfaces shall not be left overnight before painting. .--- C. Coating (Tnemec Alternate): Prime coat or spot prime coat as required shall be Tnemec Series 4 Versare primer applied to a dry-film thickness of 2 to 3.5 mils. Two or more finish coats of Tnemec Series 2H Tneme-Gloss enamel shall be applied to a thickness of 1.5 to 3.5 mils. Total dry-film thickness of the complete system shall be 7 mils, minimum. - D. Coating (Devoe Alternate): Prime coat or spot prime as required shall be 4140 Q. D. Alkyd Primer. Two or more finish coats of Devshield 4328 Alkyd applied to a dry-film thickness of 1.5 to 2 mils, each. Total dry-film thickness of the complete system shall be 5 mils, minimum. 2.4 Metal, Submerged or Intermittently Submerned A. B. C. D. General: All submerged metalwork, gates, equipment, valves, exposed pipework and all other metalwork within areas which will be submerged, except as noted hereinafter, shall be painted with this coating system. Surface Preparation: All metal surfaces shall be field sandblasted according to SSPC-SP-10 (near white blast cleaning). Coating (Tnemec Alternate): Prime coat shall be Tnemec Series 69 Epoxoline II applied to a dry-film thickness of 4 to 6 mils. Two finish coats of Tnemec Series 69 Epoxoline II shall be applied to a dry-film thickness of 4 to 6 mils each coat. Total try- film thickness of the complete system shall be a minimum of 12 mils. .-4 Coating (Devoe Alternate): Apply two coats of Bar-Rust 233H Epoxy applied to a dry-film thickness of 6 to 8 mils each coat. Total dry-film thickness of the complete system shall be a minimum of 12 mils. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09900 - Painting and Coating - 4 of 10 .~ - 2.5 Metal, Severe Exposure to Moisture or Chemical Fumes -- A. Surface Preparation: All metal surfaces shall be field sandblasted according to SSPC-SP-10 (near white blast cleaning). B. Coating (Tnemec Alternate): Prime coat shall be Tnemec Series 104 H. S. Epoxy to a dry-film thickness of 6 to 10 mils. One or more finish coats of Tnemec Series 104 H. S. Epoxy topcoat shall be applied. Total dry-film thickness shall be a minimum of 12 mils. C. Coating (Devoe Alternate): Prime coat shall be Catha-Coat 304V Zinc, 2 to 3 mils dry-film thickness. Intermediate coat shall be Devran 224H Epoxy applied at 4 to 6 mils dry-film thickness. Finish coat shall be Devthane 379 Urethane applied at 2 to 3 mils dry-film thickness. Total dry-film thickness shall be 8 mils minimum. 2.6 Metal, High-temperature Exposure A. General: Engine mufflers, exhaust systems and other metal surfaces subjected to high temperatures shall be coated with this system. B. Surface Preparation: Surface shall be field sandblasted in accordance with SSPC- SP-10 (near white blast cleaning). C. Coating (Tnemec Alternate): One coat of Tnemec Series 90-96 Tneme-Zinc to a minimum total dry-film thickness of 2 to 3.5 mils. D. Coating (Devoe Alternate): One coat of Catha-Coat 304V Zinc to a dry-film thickness of 2 to 4 mils. 2.7 Metal, Galvanized, Aluminum, Copper, or Brass A. Surface Preparation: Surfaces shall be solvent cleaned in accordance with SSPC- SP-1 (solvent cleaning) and SSPC-SP-2 (hand tool cleaning). B. Coating: Pre-treatment prime coat shall be Tnemec Series 32-1 21 5 Tneme-Grip or Sinclair 7113 Wash Primer applied at 0 mil dry-film thickness. Next, apply recommended coating or paint for the particular surface to be coated. C. Coating (Devoe Alternate): Pre-treatment prime coat shall be Devoe BarRust 231 primer applied at 3 mil dry-film thickness. Next, apply recommended coating or paint for the particular surface to be coated. 2.8 Metal, Buried A. General: The Contractor shall coat all buried metal which includes valves, bolts, nuts, structural steel and fittings. It does not include steel storage reservoirs. B. Surface Preparation: Sandblast to SSPC-SP-6 (commercial blast cleaning) City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09900 - Painting and Coating - 5 of 10 C. Coating (Tnemec Alternate): Prime none. Finish with two coats of Tnemec Series 46-465 H. B. Tnemecol or equal at 10 to 12 mils dry-film thickness, each. Total dry-film thickness shall be 20 mils minimum. D. Coating (Devoe Alternate): Prime with Devtar 221 (5A) Epoxy applied at 8 mil dry- film thickness. Two coats of Devtar (5A) Epoxy applied at 8 mils dry-film thickness, each. Total dry-film thickness shall be 24 mils, minimum. PART 3 - EXECUTION General A. The Contractor shall arrange with the Owner's Representative in accordance with Section 01410, Testing and Inspection, so that all surface preparation may be inspected and approved prior to the application of any coatings. B. The Contractor is hereby notified that the Engineer will inspect the Work prior to the expiration of the warranty period and all defects in workmanship and material shall be repaired by the Contractor, at his own expense. Workmanship A. B. C. D. It is the intent of the Specifications that finishes shall be provided which meet standards for best grades of painting. Drop cloths shall be placed where required to protect floors, surfaces and equipment from spatter and dropping, not to receive paint or coatings. The Contractor shall take all necessary precautions to protect all adjacent Work and all surrounding property and improvements from any damage whatsoever as a result of the painting and coating operation. Only good, clean brushes and equipment shall be used and all brushes, buckets, and spraying equipment shall be cleaned immediately at the end of each painting period. Each coat of paint shall be of the consistency as supplied by the manufacturer, or thinned, if necessary, and applied in accordance with manufacturer's instructions. Each coat shall be well brushed, rolled or sprayed to obtain a uniform and evenly applied finish. Work shall be free from "runs", "bridges", "shiners", or other imperfections due to faulty intervals. Particular care shall be taken to obtain a uniform unbroken coating over all bolts, threads, nuts, welds, edges and corners. Paint shall not be applied in extreme heat, in dust or smoke laden air, or in damp or humid weather, unless written permission of the Engineer is obtained. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic 8, Recycled Water Transmission Mains 09900 - Painting and Coating - 6 of 10 ,- c E. If paint is applied by spray, the air pressure used shall be within the ranges recommended by both the paint and spray equipment manufacturers. Spray painting shall be conducted under controlled conditions and the Contractor shall be fully responsible for any damage occurring from spray painting. F. Care shall be exercised not to damage adjacent Work during sandblasting operations. Stainless steel need not be sandblasted. Blasted surfaces shall not be left overnight before coating. All dust shall be removed from the surface following sandblasting. 3.3 Application Procedures A. Surfaces to be Coated: All surfaces of materials furnished and constructed are to be painted or coated per the Specifications except as indicated below. B. Surfaces Not To Be Coated: The following surfaces shall not be coated unless otherwise noted on the Plans and shall be fully protected when adjacent areas are painted. Aluminum grating Grease fittings Nameplates on Aluminum surfaces Hardware machinery Bearings Lighting fixtures Machined surfaces Pipe interior* Brass and copper tubing, Metal letters Shafts submerged* Mortar-coated pipe and fittings Stainless steel Buried pipe Switch plates Couplings * unless specifically required on the Plans or elsewhere in the Specifications C. Protection of Surfaces Not To Be Coated: Surfaces not intended to be painted shall be removed, masked, or otherwise protected. Drop cloths shall be provided to prevent paint materials from falling on or marring adjacent surfaces. Working parts of mechanical and electrical equipment shall be protected from damage during surface preparation and painting process. Openings in motors shall be safely masked to prevent paint and other materials from entering the motors. All masking materials shall be completely removed and surfaces cleaned at completion of painting operations. D. Weather Conditions: Paint shall not be applied in the rain, wind, snow, mist, and fog or when steel or metal surface temperatures are less than 5°F above the dew point. Paint shall not be applied when the relative humidity is above 80%, the air temperature is above 9O"F, or the temperature of metal to be painted is above 125°F. Alkyd, chlorinated rubber, inorganic zinc, silicone aluminum, or silicone acrylic paints shall not be applied if air or surface temperature is below 50°F or expected to be below 50°F within 24 hours. Epoxy, coal tar epoxy, acrylic latex, and polyurethane paints shall not be applied on an exterior or interior surface if air or surface temperature is below 50°F or expected to drop below 50°F within 24 hours. c. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09900 - Painting and Coating - 7 of 10 3.4 Surface Preparation A. General: Sandblast or prepare only as much surface area as can be coated in one day. All sharp edges, burrs, and weld spatter shall be removed. Epoxy-coated pipe that has been factory coated shall not be sandblasted. B. SSPC Specifications: Wherever the words "solvent cleaning", "hand tool cleaning", "wire brushing", or "blast cleaning" or similar words are used in the Specifications or in paint manufacturer's specifications, they shall be understood to refer to the applicable SSPC (Steel Structures Paint Council, Surfaces Preparation Specifications, ANSI A1 59.1) Specifications listed below: SP-1 Solvent Cleaning SP-6 Commercial Blast Cleaning SP-2 Hand Tool Cleaning SP-7 Brush-off Blast Cleaning SP-3 Power Tool Cleaning SP-8 Pickling SP-5 White Metal Blast Cleaning SP-10 Near White Blast Cleaning Oil and grease shall be removed from aluminum and copper surfaces in accordance with SSPC SP-1 using clean cloths and cleaning solvents. Weld spatter and weld slag shall be removed from metal surfaces. Rough welds, beads, peaked corners, and sharp edges including erection lugs shall be ground smoothly in accordance with SSPC SP-2 and SSPC SP-3. Welds shall be neutralized with a chemical solvent that is compatible with the specified coating materials using clean cloths and chemical solvent. C. Abrasive Blast Cleaning: Dry abrasive blast cleaning shall be used for metal surfaces. Do not recycle or reuse contaminated blast particles. Dry clean surfaces to be coated by dusting, sweeping, and vacuuming to remove residue from blasting. Apply the specified primer or touch-up coating within the period of an 8-hour working day. Do not apply coating over damp or moist surfaces. Reclean prior to application of primer or touch-up coating any blast cleaned surface not coated within said 8-hour period. Prevent damage to adjacent coatings during blast cleaning. Schedule blast cleaning and coating such that dust, dirt, blast particles, old coatings, rust, mill scale, etc., will not damage or fall upon wet or newly coated surfaces. 3.5 Procedures for the Application of Coatinas A. The recommendations of the coating manufacturer shall be followed, including the selection of spray equipment, brushes, rollers, cleaners, thinners, mixing, drying time, temperature and humidity of application, and safety precautions. -4 City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic 8t Recycled Water Transmission Mains 09900 - Painting and Coating - 8 of 10 .- _..- 3.6 B. Coating materials shall be kept at a uniform consistency during application. Each coating shall be applied evenly, free of brush marks, sags, runs, and other evidence of poor workmanship. A different shade or tint shall be used on succeeding coating applications to indicate coverage where possible. Finished surfaces shall be free from defects or blemishes. C. Only thinners recommended by the coating manufacturer shall be used. If thinning is allowed, do not exceed the maximum allowable amount of thinner per gallon of coating material. D. Apply a brush coat of primer on welds, sharp edges, nuts, bolts, and irregular surfaces prior to the application of the primer and finish coat. The brush coat shall be done prior to and in conjunction with the spray coat application. Apply the spray coat over the brush coat. E. Apply primer immediately after blast cleaning and before any surface rusting occurs, or any dust, dirt, or any foreign matter has accumulated. Reclean surfaces by blast cleaning that have surface colored or become moist prior to coating application. 1. Paint Mixing: Multiple-component coatings shall be prepared using all the contents of each component container as packaged by the paint manufacturer. Partial batches shall not be used. Multiple-component coatings that have been mixed beyond their pot life shall not be used. Small quantity kits for touch-up painting and for painting other small areas shall be provided. Only the components specified and furnished by the paint manufacturer shall be mixed. For reasons of color or otherwise, additional components shall not be intermixed, even within the same generic type of coating. 2. Field Touch Up of Shop-Applied Prime Coats: Organic Zinc Primer: Surfaces that are shop primed with inorganic zinc primers shall receive a field touch up of organic zinc primer to cover all scratches or abraded areas. Organic zinc coating system shall have a minimum volume solids of 54% and a minimum zinc content of 14pounds per gallon. Coating shall be of the converted epoxy, epoxy phenolic, or urethane type and shall be manufactured by the prime coat and finish coat manufacturer. 3. Other Primers: Surfaces that are shop primed with other than organic zinc primer shall receive a field touch up of the same primer used in the original prime coat. Dry-Film Thickness Testinn and Repair A. Special Instructions to the Contractor: The Contractor shall furnish to the Owner at no charge for use during execution of the Work, necessary dry-film thickness gauge and electrical flaw detection equipment. The Contractor shall perform the holiday (pinholes) inspection in the presence of the Owner's Representative, and the Contractor shall monitor wet film measurements throughout the application of each coat of coating. -- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09900 - Painting and Coating - 9 of 10 B. Coating Thickness Testing: Coating thickness specified for steel surfaces shall be measured with a magnetic-type dry-film thickness gauge. Dry-film thickness gauge shall be provided as manufactured by Mikrotest or Elcometer. Each coat shall be checked for the correct dry-film thickness. Measurement shall not be made until a minimum of eight hours after application of the coating. Non-magnetic surfaces shall be checked for coating thickness by micrometer measurement of cut and removed coupons. Contractor shall repair coating at all locations where coupons are removed. - C. Holiday Testing: The finish coat (except zinc primer and galvanizing) shall be tested by the Contractor in the presence of the Engineer for holidays and discontinuities with an electrical holiday detector of the low-voltage, wet-sponge type. Detector shall be provided as manufactured by Tinker, Rasor, K-D Bird Dog, or approved equal. D. Repair: If the item has an improper finish, color, insufficient film thickness, or holidays, the surface shall be cleaned and top-coated with the specified paint material to obtain the specified color and coverage. Visible areas of chipped, peeled, or abraded paint shall be hand or power-sanded, feathering the edges. The areas shall then be primed and finish coated in accordance with the Specifications. Work shall be free of runs, bridges, shiners, laps, or other imperfections. 3.7 Cleanup Upon completion of all painting and coating Work, the Contractor shall remove all surplus materials and rubbish. The Contractor shall repair all damage and shall leave the premises in a clean and orderly condition. -_ END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09900 - Painting and Coating - 10 of 10 .- SECTION 09902 PETROLATUM WAX TAPE COATING PART1 - GENERAL 1.1 Scope This section covers the work necessary to furnish and install petrolatum wax tape coating on pipe, pipe flanges, fittings or other buried pipeline appurtenances, complete, as indicated on the plans and specified herein. 1.2 Submittals During Construction Submit manufacturer's technical product data, details, installation instructions and general product recommendations in accordance with the requirements of Section 01 300. 1.3 Product Identification The use of a manufacturer's name and model or catalog number is for the purpose of establishing the standard of quality and general configuration desired only. Products of other manufacturers will be considered in accordance with the Contract Documents. .c PART 2 - MATERIALS 2.1 General Wrap all exposed surfaces of buried ferrous pipe, flanges, couplings and other pipeline appurtenances (including bolts, nuts, etc.) with petrolatum wax tape, unless another corrosion protection system (other than a factory-installed paint coating) is otherwise specified or indicated by the Contract Drawings. Exposed piping shall be wrapped only where specifically called out on the Drawings. Ductile iron pipe encased with polyethylene sheathing shall not be wrapped with this product. 2.3 Primer Exposed surfaces shall be prime coated with a blend of petrolatum, plasticizer, and corrosion inhibitor having a paste-like consistency. The material shall have the following properties: Pour Point 400-100" F Flash Point 350" F minimum Approximate Coverage Color Brown 1 gal/lOO square feet rc The primer shall be Trenton Wax-Tape Primer or equivalent. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09902 - Petrolatum Wax Tape Coating - 1 of 3 2.3 WaxTape Two types of petrolatum wax tape shall be available from the manufacturer: one type for buried installations and another type for above-ground installations. 2.3.1 Buried Installations The covering material shall be a plastic-fiber felt tape, saturated with a blend of petrolatum, plasticizers, and corrosion inhibitors that is easily formable over irregular surfaces. The tape shall have the following properties: Color: Brown Thickness 70-90 mils Dielectric Strength 170 volts/mil Tape Width 6 inches Saturant Pour Point 115" - 125°F Wax tape shall be Wax-Tape #1 as manufactured by The Trenton Corporation (Ann Arbor, Michigan), or approved equal. 2.4 Outer Covering The primed and wax-tape wrapped surface shall be wrapped with a plastic tape covering consisting of three (3) layers of 50 gauge, clear, polyvinylidene chloride, high cling _- membranes wound together as a single sheet. The material shall have the following properties: Width Thickness Dielectric Strength Water Absorption Color 6 inches 1.5 mils 2000 volts/mil Neg I ig i ble Clear The outer covering shall be Trenton Poly-Ply or approved equal. 2.5 Other Petrolatum Wax Tape Svstem Components Any components not listed above, but required for a complete petrolatum wax tape coating system as recommended for this application by the manufacturer shall be provided at no additional cost to Owner. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09902 - Petrolatum Wax Tape Coating - 2 of 3 PART 3 - EXECUTION cl 3.1 General The petrolatum wax tape system shall be installed in conformance with the manufacturer’s recommendations and as shown or specified by these Contract Documents. END OF SECTION /-- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 09902 - Petrolatum Wax Tape Coating - 3 of 3 SECTION 13120 CATHODIC PROTECTION BY SACRIFICIAL ANODES ‘- PART 1 - GENERAL 1.1 Scope Of Work This section describes all materials and installation requirements to install cathodic protection and corrosion monitoring facilities on the City of Carlsbad, 30-inch and 24-inch El Camino Real Potable Water Transmission pipeline. The materials include sacrificial anodes, test stations, wiring, insulating flange kits can continuity bonds. The Work also includes all personnel, equipment, labor and incidental materials to install, activate and test these facilities. 1.2 References The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designations only. ASTM 83-90 ASTM B8-86 ASTM C94-81 ASTM D1248 ASTM D2220 AWWA C217-90 MIL-C-18480A (Military Specs) NACE RPOl69-96 NACE RP0286-97 NACE RP0375-94 Soft of Annealed Copper Wire Concentric-Lay-Stranded Copper Conductors Ready-Mix Concrete Polyethylene Plastics Molding and Extrusion Materials PVC Insulation for Wire and Cable, 75’ C Operation Cold-Applied Petrolatum Tape and Petroleum Wax Tape Coatings for the Exterior of Special Sections, Connections, and Fittings for Buried Steel Water Pipelines Coating Compound, Bituminous, Solvent, Coal Tar Base Recommended Practice “Control of External Corrosion on Underground or Submerged Metallic Piping Systems”. Electrical Isolation of Cathodically Protected Pipelines Wax Coating Systems For Underground Piping Systems UL 83-80Thermoplastic-Insulated Wires UL 486-76 Wire Connectors and Soldering Lugs for Use with Copper Conductors City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 20-Cathodic Protection - 1 of 14 1.3 Definitions I A. CONTRACTOR: The licensed, qualified construction firm selected by the OWNER to have prime responsibility for the completion of the work. B. OWNER: The City of Carlsbad C. ENGINEER: contact between the OWNER and the CONTRACTOR. The OWNER'S representative who is assigned to be the direct D. INSPECTOR: The OWNER'S representative designated to have project inspection responsibilities. E. CORROSION ENGINEER: The individual, accepted by the OWNER but retained by the CONTRACTOR, who is trained, experienced and qualified in the installation and testing of cathodic protection systems for buried pipelines. 1.4 Related Work Described Elsewhere A. Shop Drawing Submittals: 01 300 B. Petrolatum Wax Tape Coating: 09902 C. Cold-Applied Plastic Tape Pipe Coating with Mortar Overcoated: 09870 1.5 Submittals The following information shall be submitted for approval of the ENGINEER in accordance with Section 01300 of these specifications. A. Catalog Cuts (5 copies): 1. Pre-packaged magnesium anodes 2. Bare magnesium anodes 3. At-grade test boxes 4. Shunts 5. Split-bolt connectors 6. Brass tags 7. Wire and cable 8. Insulating flange kit 9. Wax tape wrap 10. Alumino-thermic weld kit 11. Weld caps and primer 12. Bitumen coating 13. Warning tape City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 20-Cathodic Protection - 2 of 14 c B. C. D. Qualifications: Qualifications of the CORROSION ENGINEER retained by the CONTRACTOR for cathodic protection installation supervision and testing purposes. The CORROSION ENGINEER shall be experienced with buried water line cathodic protection and either be a registered professional corrosion engineer in the State of California or a NACE International certified Cathodic Protection Specialist. Test Results: 1. Insulator tests 2. Continuity tests 3. Anode testing and cathodic protection performance As-built Drawinqs: The CONTRACTOR shall maintain as-built drawings showing the exact locations of all insulators, anodes, wire runs and corrosion monitoring test stations. Location changes from the design drawings shall be indicated in red. These drawings shall be submitted to the ENGINEER before the work is considered complete. PART 2 - MATERIALS Materials and equipment furnished under this section of the specifications shall be the standard product of manufacturers regularly engaged in the manufacturing of such products and shall be the manufacturer's latest standard design that complies with specification requirements. All materials and equipment shall bear evidence of U.L. approval when U.L. standards exist. I 2.1 Maqnesium Anodes A. Backfill Method: Either pre-packaged or bare magnesium anodes can be used. Single anodes shall be pre-packaged ingots in a permeable cloth bag in special backfill. Clustered anodes can either be bare ingots backfilled with a slurry of special backfill or pre-packaged ingots. B. Capacity: All anodes shall be high potential magnesium ingots with a theoretical energy content of 1000 ampere-hours per pound and a minimum useful output of 500 ampere-hours per pound. ..-- C. Chemical Composition (High Potential Magnesium): Aluminum 0.01 percent (max) Manganese 0.5 to 1.3 percent Zinc 0.002 percent (max) Copper 0.02 percent (max) Nickel 0.001 percent (max) Iron 0.03 percent (max) Silicon 0.002 percent (max) Other 0.05 percent each (rnax) Magnesium Balance and 0.3 percent total (max) City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 2Mathodic Protection - 3 of 14 D. Open Circuit Potential: The open circuit potential of all anodes shall be between 1.65 and 1.75 volts DC versus a copper-copper sulfate reference electrode. __ E. Ingot Size and Weight: Anodes shall be 48-pound magnesium ingots with a trapezoidal cross section. Ingot size shall be 32 inches long. F. Anode Construction: Anodes shall be cast magnesium with a galvanized steel core rod. Recess one end of the anode to provide access to the rod for connection of the lead wire. Silver braze the lead wire to the rod and make the connection mechanically secure before brazing. Insulate the connection to a 600 volt rating by filling the recess with epoxy and covering any exposed bare steel core or wire with heat shrinkable tubing. The insulating tubing shall extend over the lead wire insulation by not less than one-half inch. 2.2 Special Backfill for Pre-Packaqed or Slurrv Backfilled Anodes: A. Composition: Low resistivity backfill mix for pre-packaged and clustered (slurry) anodes: Gypsum 75% Powdered Bentonite 20% Anhydrous Sodium Sulfate 5% Backfill grains shall be such that 100 percent is capable of passing through a screen of 100 mesh. Backfill shall be firmly packed around the anode such that the ingot is approximately in the center of the backfill and surrounded by at least two inches of backfill material. The resistivity of the backfill shall be no greater than 50 ohm-cm when tested wet in a soil box with no extraordinary means of compaction. - B. Pre-Packaged Backfill: Dry powder contained in a permeable cloth bag suitable for direct burial. See soaking requirements in Section 3.0 C. Clustered Anode Backfill: Backfill\water mixture or slurry. 2.3 At-Grade Test Stations A. Test Box: At-grade test boxes shall be round, pre-cast concrete with dimensions of 14-1/4 inches O.D. by 9 inches I.D. by 12 inches high, similar to Christy G5 Utility Box with a cast iron supporting ring and lid, and shall have sufficient strength to support occasional vehicular traffic. The lid shall be cast with the legend "CP Test" using letters not less than 1-1/2 inches high. B. Brass Tags: All test leads shall be identified in each test box with 1-1/2 inch diameter brass tags with a 1/8-inch diameter hole. ---c C. Shunts: Anode test boxes shall have 0.01 ohm shunts rated at 6 amperes, Holloway Type RS or equal, and accurate to plus or minus one percent. City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 20-Cathodic Protection - 4 of 14 D. Split Bolt Connector: Split bolt connectors shall be UL 486 copper or brass and sized to accommodate the lead wire and shunt being used. .- E. Concrete Pad: Test boxes mounted in un-paved areas shall have a 26 inch by 4-inch thick reinforced concrete pad constructed of ASTM C94 Ready-Mix concrete. 2.4 Wire And Cable A. Standard: All wire shall be single conductor, stranded copper of the gauge indicated. Wire sizes shall be based on American Wire Gauge (AWG). Copper wire shall be in conformance with ASTM Standards 83 or B8. Wire with high molecular weight polyethylene (HMWPE) insulation and shall conform with the requirements of ASTM D1248m Type 1, Class C, Grade 5. Wire with THWN insulation shall conform with the requirements of ASTM D2220. B. Wire size: As shown in the drawings. 2.4 Insulating Flange Kit .c A. Gasket. ANSI B-16.21, full faced, Type “E” phenolic material with rectangular nitrile or Viton O-ring seal for operation between 20°F and 150°F. Gaskets shall be suitable for the temperature and pressure rating of the piping system in which they are installed. B. Insulating Sleeves. 1/32-inch thick tube, full length, laminated glass material as per NEMA LI-1 G10 for operation between 2OoF and 15OoF. For installation at threaded valve flanges, the sleeves shall be half-length. C. Insulating Washers. 1/8-inch thick laminated glass sheet material as per NEMA LI- 1 G10 for operation between 2OoF and 1 5OoF. D. Steel Washers. 1/8-inch thick cadmium plated steel to be placed between the nut and the insulating washer. 2.5 Wax Tape Wrap A. Intended Application. All buried pipe and fitting surfaces such as valves, flanges, couplings, adapters, insulating flanges, etc., that are not tape and mortar coated shall be wrapped with a petrolatum wax tape coating in accordance these specifications. B. Standard: Wax tape materials shall be per this specification section, AWWA C-217 and Specification Section 09902. C. Primer. All surfaces shall be prime coated with a blend of petrolatum, plasticizer, inert fillers, and corrosion inhibitor having a paste-like consistency. City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 2Mathodic Protection - 5 of 14 D. Wax Tape. Fitting covering material shall be a synthetic felt tape, saturated with a blend of petrolatum, plasticizers, and corrosion inhibitors that is easily formable over irregular surfaces. A compatible petrolatum filler should be used to smooth over irregular s u rfaces . -_ E. Plastic Wrap. The primed and wax-tape wrapped fitting shall have an outer plastic tape covering or wrap consisting of 1.5 mil polyvinylidene chloride or metallocene resin material. The tape shall have high dielectric strength, be stretchable and be able to conform well to irregular shapes. The outer covering shall be Trenton Poly-Ply, Denso Poly-wrap or equivalent. 2.6 Alumino-Thermic Welds A. 6. C. D. E. Alloy and Size: Cable-to-metal connections shall be made by the alumino-thermic welding process as illustrated in the drawings. Weld charge size, alloy and mold size are dependent upon the material to which the welds are attached and the size of the copper wire and shall be as specified by the manufacturer of the weld kit. The CONTRACTOR shall ensure that the correct charges are used. Weld Mold: Welds on horizontal surfaces are illustrated in the drawings. A special mold is required for attaching welds to vertical or sloped surfaces. Primer: Weld cap primer shall be an elastomer-resin based corrosion resistant primer for underground services such as Royston Roybond Primer 747 or equivalent. Weld cap: Alumino-thermic welds shall be sealed with a pre-fabricated plastic cap filled with formable mastic compound on a base of elastomeric tape. Weld caps shall be Royston Handy Cap 2 or equivalent. Coating: Bitumastic coatings shall be cold-applied, black, thixotropic material containing plasticized coal tar pitch, solvents, and special fillers per MIL-C- 18480A such as Carboline Bitumastic 50, Tnemec 40-H-413, Tape-coat TC Mastic or 3M Scotch Clad 244. Apply to at least 20 mils thickness. .- 2.7 Plastic Warninq Tape A. Tape: Plastic warning tape for buried test leads in cable trenches shall be a minimum of four (4) mils thick and six-inches (6) wide, inert plastic film designed for prolonged use underground. The tape shall have the words, "CAUTION: Cathodic Protection Cable Below," or similar, clearly visible in repeating patterns along its entire length. City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 ILO-Cathodic Protection - 6 of 14 PART 3 - EXECUTION - Corrosion protection installations shall conform to NACE Publication RPO169-92 Recommended Practice, "Control of External Corrosion on Underground or Submerged Metallic Piping Systems". The installation of corrosion protection facilities shall be supervised by the CORROSION ENGINEER. 3.1 Sacrificial Anodes _- c. A. B. C. D. E. F. Lead Wire Inspection: All lead wires shall be inspected to ensure that the wire is securely connected to the anode core and that the lead wire insulation has sustained no damage. Loose or broken anode lead wire-to-anode connections shall require complete replacement of the anode and lead wire assembly. Location: Anodes are to be installed in augured holes placed off of the pipe the distance shown in the drawings. Anode positions shall be as close to the pipe stations indicated in the drawings; however they can be adjusted to facilitate installation or to avoid interference with existing structures. Alternate anode positions greater than 20 feet from the station specified must be approved by the ENGINEER. The CONTRACTOR must identify final locations of all anodes on the as-built drawings. Offset From Pipe: Anode holes shall be offset from pipeline by 10 feet where possible. If the desired offset places the anode close to a metallic pipeline always place the anode between the protected pipe and the nearby pipe even if the offset from the protected pipe is less than 10 feet. The anode shall be no closer than 2 feet to the nearby pipe. Handling: Care shall be taken to ensure that anodes are never lifted, supported, transported, or handled by the lead wire. All anodes shall be lowered into the hole using a sling or a rope. Anode Depth: Anode hole depth shall be 12 feet. If rock in encountered when auguring anode holes, the ENGINEER shall be consulted for direction. Prepackaged Anodes: Single, pre-packaged anodes are installed at alternate anode sites. 1. Packaged Anode Inspection: Each pre-packaged anode shall be inspected to ensure that the backfill material completely surrounds the anode and that the cloth bag containing the anode and backfill material is intact. Anode ingots shall be centered within a permeable cloth bag. If the prepackaged anodes are supplied in a waterproof container or covering, that container or covering shall be removed before installation. 2. Pre-Soaking Requirements: All prepackaged anodes shall be completely submerged in water for 30 minutes before being placed in the hole. Once in the hole, 15 gallons of water shall be poured on top of the anodes such that they are completely covered with water. Allow the anodes to soak for a minimum of 30 minutes before any soil backfill is added. City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 20-Cathodic Protection - 7 of 14 G. H. I. 3. Soil Backfill: Backfill with native, rock-free (1/2-inch maximum rock size) soil such that the soil backfill is level with the top of the anode. Add an additional 5 to 10 gallons of water to the hole to completely saturate the soil around the anode. Allow the anode and soil to soak for 15 minutes (minimum) before completing the backfill operation. - Bare (Clustered) Anodes: At clustered anode sites two bare anode ingots shall be installed side-by-side as shown in the drawings. 1. Anode Pairs: Bare anodes can be touching in the hole. Note: Contractor may opt to install two prepackaged anodes in the same manner to eliminate the need for slurry; however, the hole must be large enough to allow the prepackaged anodes to be placed vertically, side-by-side in the hole. 2. Slurry Backfill: Mix special backfill with minimum water such that the backfill is the consistency of white glue, motor oil or syrup. Add enough water so that the mixture can be poured. Pour the backfill such that the ingots are covered over approximately 6 inches. Tamp with a long rod so that there are no pockets or voids in the slurry. 3. Anode Bottom: Do not let the bottom of the anode touch the soil. Provide a non-metallic cradle or stand-off such that the backfill completely encases the anode ingots. Anode Hole Backfill: After the anodes have soaked in the hole or covered with slurry, or hole is backfilled with native trench spoil (not sand) with all stones over 1/2-inch diameter removed. Backfill the trench or hole in 18-inch lifts and carefully tamp to compact the soil. No voids shall exist around the anode bags and the anode lead wire shall not be damaged. - Anode Connection in Test Box: Shunts shall be attached to the cathode (pipe) lead wires with split-bolt connectors as shown in the drawings; however, the anode lead shall be left unconnected in the test box. The split-bolt for connecting the anode lead to the shunt shall be securely attached to the shunt for connection to the anode when the cathodic protection system is activated. 3.2 At-Grade Test Stations A. Locations: At-grade corrosion monitoring test boxes shall be located just behind the curb or pavement at the side of the road. Wire runs shall be jetted under the pavement or trenched as directed by the Engineer. Contractor must be careful not to damage existing utilities. B. Soil Access: Native soil shall be accessible inside all test boxes. The test boxes shall not be filled with sand, gravel, rocks, concrete or any other foreign material. Plastic risers which may be used to protect the test wires during construction shall be removed. -4 City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 20-Cathodic Protection - 8 of 14 _.- - 3.3 C. D. E. F. G. Test Wire Connections: Test leads shall be attached to the pipe or casing using the alumino-thermic weld process as shown in the drawings. A single 18-inch slack wire coil shall be placed at each weld. Brass Tag Markings and Attachment: Brass tags shall be die stamped as indicated in the drawings with %-inch high characters. The tags shall be securely attached to the test leads with uninsulated No. 14 copper wire. Splice, Depth and Slack: All buried lead wires shall be installed without splices. Where a trench is required, it shall be a minimum depth of 24 inches. All lead wires shall terminate in a test box and shall have 18 inches of slack coiled inside the test box. Wire Trench: The bottom of the finished trench shall be sand or stone-free earth. Lead wire shall be centered in the bottom of the trench, covered and tamped in 6 inch layers of stone free earth. Soil compaction shall be as specified elsewhere in these specifications. Do not stretch or kink the conductor. Care shall be taken when installing wire and backfilling trench so insulation is not broken, cut or bruised. If wire insulation is damaged during installation, it shall be rejected and replaced completely at the CONTRACTOR'S expense. All rejected wire shall be removed from the job site at the close of each workday. Do not place roots, wood scraps, organic matter or refuse in the backfill. Concrete Pad: A 26 inch square by 4 inch thick reinforced concrete pad with No. 4 bar reinforcement as shown in the drawings is required around each at-grade test station that is not located in a paved area. lnsulatinq Flange Kit A. 6. C. D. Standard: Insulators shall be installed and tested in accordance with this specification and NACE RP0286-97 Electrical Isolation of Cathodically Protected Pipelines. Flange Kit Preparation: Insulating kits shall be installed as shown on drawings and as recommended by the manufacturer. Moisture, soil, or other foreign matter must be carefully prevented from contacting any portion of the mating surfaces prior to installing insulator gaskets. If moisture, soil, or other foreign matter contacts any portion of these surfaces, the entire joint shall be disassembled, cleaned with a suitable solvent, and dried prior to reassembly. Pre-Assembly: All insulating flange kits 20-inches or greater shall be pre-installed and tested in the pipe spool before the spool is installed in the ditch. If possible, smaller flanges shall be pre-installed and tested above grade. Component Compatibility: The CONTRACTOR shall be responsible to provide insulating flange kits fit up properly. Specifically, the CONTRACTOR shall verify the following: the bolts or studs are the correct material and size; there are the correct number of bolts (studs), nuts, sleeves, insulating washers and steel washers; the gasket sealing surfaces match up properly on both flanges; there is enough clearance for the sleeves between the bolts or studs and the flange hole. City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 20-Cathodic Protection - 9 of 14 E. Alignment: Alignment pins shall be used to properly align the flange and gasket. F. Bolt Tightening: The manufacturer's recommended bolt-tightening sequence shall be followed. Bolt insulating sleeves shall be centered within the insulation washers so that the insulating sleeve is not compressed and damaged. '1 3.4 G. Testing: All insulating flanges must be tested as specified below. All buried insulating flanges must be tested before backfilling and before the wax tape primer and wrap are applied. Wax Tape Wrap A. Critical Installation Requirements. Wax tape primer, filler or wrap shall completely fill all irregular surfaces and be applied as described below. B. Primer. Surfaces must be cleaned of all dirt, dust and loose rust or mill scale by wire brush and by wiping with a clean cloth. The surface shall be dry. Apply primer by hand or brush. A thin coating of primer shall be applied to all surfaces and worked into all crevices, including the gap between meeting flanges. The primer shall be applied generously around bolts, nuts, tie rods and in threads, and shall completely cover all exposed surfaces and fill all voids. The primer should overlap the pipe coating by a minimum of 3 inches. C. Filler. Additional primer or filler shall be applied to smooth out irregular surfaces so that the petrolatum saturated tape can be easily applied. - D. Petrolatum Saturated Tape. The petrolatum can be applied immediately after primer and/or filler application. Short lengths of tape shall be cut and carefully molded around each individual bolt, nut, tie rod and stud-end. Coupling tire rods and odd surfaces must be individually wrapped to ensure complete coverage with tape directly against all surfaces. After all bolts and odd surfaces are covered, the tape shall be circumferentially wrapped over the item as appropriate with sufficient tension and pressure to provide continuous adhesion without stretching the tape. The tape shall be formed by hand into all voids and spaces. There shall be no gaps or air spaces under the tape. The tape shall be applied with at least a 55% overlap. The wax-tape system shall have a minimum thickness of 50 mils over smooth surfaces and 100 mils over sharp projections such as bolts, nuts and metal edges. E. Outer Covering. The clear plastic outer covering shall be applied by hand such that the material conforms and adheres to the petrolatum tape surface. Two layers of plastic outer wrapping shall be applied. F. Protection From Backfill Damage: Wax tape is susceptible to damage when backfilling, especially when backfilling with gravel that is dropped from a height of several feet. Contractor shall carefully backfill all wax taped components making sure that the surface is protected and that there is no erosion or damage to the tape. I City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 20-Cathodic Protection - 10 of 14 PART 4 - TESTING AND INSPECTION Y 4.1 4.2 .- 4.3 Test Lead and Bond Wire Welds A. Responsibility: The CONTRACTOR shall be responsible for testing all test leads and bond wire welds. The INSPECTOR shall observe testing at his or her discretion. B. Test Method: All completed wire connection welds shall be tested for strength by striking the weld with a sharp blow with a two-pound hammer while pulling firmly on the wire. Welds failing this test shall be re-welded and re-tested. Wire welds shall be spot tested by the INSPECTOR OR ENGINEER. After backfilling pipe, all test lead pairs shall be tested using a standard ohmmeter for broken welds. C. Acceptance: Welds not loosened or broken by the hammer test can be backfilled. The resistance of test leads shall not exceed 150% of the total wire resistance plus the meter wire resistance as determined from the length and published wire data. Bond wire acceptance shall be determined by the continuity test results. Test Lead Trenching And Backfill A. Responsibility: The depth, trench bottom padding, and backfill material shall be inspected by the INSPECTOR at his or her discretion prior to backfilling. B. Method: The depth, trench bottom padding, and backfill material shall be visually inspected prior to backfilling. C. Jetted or Bored Wire Runs: The INSPECTOR shall verify that the bore hole does not interfere with existing utilities. D. Acceptance: Conformance with these specifications. Pipeline Continuitv A. B. C. Testing Requirement: Pipe reaches along which all joints are welded do not require continuity testing. All reaches that contain one or more bonded joints or one or more mechanical joints, such as a valve, flanges or in-line appurtenances, shall be tested for continuity. Responsibility: The CONTRACTOR shall measure the linear resistance of sections of pipe that require continuity testing. All testing shall be done by the CORROSION ENGINEER in the presence of the ENGINEER at his or her discretion. Method: Resistance shall be measured by the linear resistance method. A direct current shall be impressed from one end of the test section to the other (test station to test station) using DC power supply (battery). A voltage drop is measured for several current levels. The resistance (R) is calculated using the equation R = dV/I, where dV is the voltage drop and I is the current. The resistance shall be calculated for three or four different current levels. City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 2Mathodic Protection - 1 1 of 14 D. Acceptance: Acceptance is reasonable comparison of the measured resistance with the calculated or theoretical resistance. The measured resistance shall not exceed the theoretical resistance by more than 130%. The CONTRACTOR shall submit calculations of the theoretical resistance and the measured value of resistance for each section of pipe tested. __ E. Deficiencies: If discontinuities or high resistance joints are found, it is the CONTRACTOR’S responsibility to locate, excavate, and repair all bonds that are found to be discontinuous. Continuity tests shall be repeated after repairs are made. 4.4 Anodes And Cathodic Protection Performance A. Responsibility: The CONTRACTOR is responsible for providing the proper rated potential anode, sufficient anode lead wire length and the proper anode hole depth. The CONTRACTOR shall be responsible for insuring that the anode pre- packaged backfill sack is intact and that the wire leads are soundly attached. The CORROSION ENGINEER shall test each installed anode for wire connection integrity and for open-circuit potential after the anodes are installed. B. Notification for Testing: The CONTRACTOR shall notify the ENGINEER at least five days in advance of anode installation and five days in advance of activation and testing by the CORROSION ENGINEER. At his or her discretion, the anode installation shall be witnessed by the ENGINEER or INSPECTOR. Cathodic Protection Performance Test Method: The performance of the cathodic protection system will be tested by the CORROSION ENGINEER. The testing shall include: measurement of all open-circuit anode potentials; pipe-to-soil potentials at each test station and other locations as necessary before the anodes are connected; initial anode currents after connecting anode leads to the pipe leads; and the pipe-to-soil potential at each previously tested site with all anodes connected. Pre- and post cathodic protection potentials at points at least 100 feet away from the test station (anodes) to verify that the pipeline is fully protected. Adequate protection shall be as defined in NACE RPO169. - C. D. Test Report: The CORROSION ENGINEER shall immediately report all system deficiencies to the ENGINEER. Upon completion of the testing, the CORROSION ENGINEER shall submit a report to the ENGINEER which includes all test results, conclusions regarding the performance of the system and recommendations for maintenance and monitoring. E. Repairs: The CONTRACTOR shall perform repairs due to system installation deficiencies reported by the CORROSION ENGINEER. These repairs and system re-testing shall be provided at no additional cost to the OWNER. F. Acceptance: The system will be accepted if all anodes, test stations, and supporting facilities are installed according to the drawings and these - specifications and are in proper working order. The CONTRACTOR is not responsible for the performance of the system if the proper materials are used and installed correctly. City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 13120-Cathodic Protection - 12 of 14 4.5 lnsulatinq Flanqe Kits c- A. Responsibilitv: Insulators shall be tested and certified by the Corrosion Engineer. Testing shall be done in the presence of the Engineer and the Owner at their discretion. 6. Test Method: The assembled flange shall be tested with an insulator testing device (Le., Gas Electronics Model 601 Insulation Checker) specifically designed for this purpose. Additional testing shall include measurement of pipe-to-soil potentials, using a copper-copper sulfate reference electrode, with contacts made to either side of the insulator. C. Notification for Inspection: The Contractor shall notify the ENGINEER at least five days in advance of the testing of insulator installations. D. Acceptance: The installation shall be considered complete when the testing device indicates that no shorts or partial shorts are present and the potentials on either side of the insulator differ by at least 20 millivolts. If shorts are detected the Contractor shall assist the qualified CORROSION ENGINEER in finding partial shorts or shorted bolts. All disassembly and re-assembly necessary to gain the acceptance of the qualified Corrosion Engineer shall be done at the Contractor's expense. 4.6 Wax Tape Coating A. Responsibility: ENG IN EER or INSPECTOR. All wax tape coating applications shall be inspected by the 6. Notification for Inspection: The CONTRACTOR shall notify the ENGINEER at least five days in advance of completion of wax tape applications. C. Test Method: Each tape wrapped component shall be visually inspected. Backfilling shall not be done until this inspection is complete and the tape wrap application is approved by the ENGINEER. D. Backfill Protection: The ENGINEER or INSPECTOR shall also observe the backfill operation to insure protection of the wax tape. E. Acceptance: Conformance with this specification section City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 20-Cathodic Protection - 13 of 14 4.7 Compliance With Specifications -. A. Deficiencies: Any deficiencies or omissions in materials or workmanship found by these tests shall be rectified by the CONTRACTOR at his expense. Deficiencies shall include but are not limited to: unconnected or broken anode or test leads; incorrect anode type; improper or un-clean wire trench backfill; lack of 18 inches slack wire on each test lead in each test box; shorted or partially shorted insulators; inadequate insulator coating; broken wires or wire connections; failure to notify the ENGINEER in sufficient time to test buried insulators; high metallic pipeline resistance; and improperly mounted or located test boxes. END OF SECTION -. City Of Carlsbad 03/04 (DEC) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 131 2Mathodic Protection - 14 of 14 SECTION 15000 GENERAL PIPING SYSTEM AND APPURTENANCES c PART 1 - GENERAL 1.1 Description This Section describes the requirements and procedures for piping systems (pressure pipe) and appurtenances that apply to a number of other complimentary Specification Sections. The items are listed in this Section to avoid repetition in Sections elsewhere. This Section includes, but is not limited to: Temporary above ground piping (high line), connections to existing piping field touch up, grooved end or shoulder couplings, warninglidentification tape, tracer wire, abandonment and removal of existing facilities, and salvage. 1.2 Reference Standards The publications listed below form part of this specification to the extent referenced and are referred to in the text by the basic designation only. Reference shall be made to the latest edition of said standards unless otherwise called for. ANS181.1 - ANSI 81.2 - ASTM A 36/A 36M - ASTM A 47lA 47M - ASTM A 53 - ASTM A 108 - ASTM A 183 - ASTM A 283lA 283M - ASTM A 307 - ASTM A 325lA 325M - ASTM A 51 OIA 51 OM - ASTM A 512 - ASTM A 536 - ASTM A 568/A 568M - ASTM D 2000 - ASTM F 593 - ASTM F 594 - AWWA C105 - AWWA Clll - AWWA C200 - City of Carlsbad 03/04 (DBE) Unified Inch Screw Threads Gages and Gaging for Unified Inch Screw Threads Standard Specification for Carbon Structural Steel Standard Specification for Ferritic Malleable Iron Castings Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc - Coated Welded and Seamless Standard Specification for Steel Bars, Carbon, Cold Finished, Standard Quality Standard Specification for Carbon Steel Track Bolts and Nuts Standard Specification for Low and Intermediate Tensile Strength Carbon Steel Plates, Shapes and Bars Standard Specification for Carbon Steel Bolts and Studs Standard Specification for High-Strength Bolts for Structural Steel Joints Standard Specification for General Requirements for Wire Rods and Course Round Wire, Carbon Steel Standard Specification for Cold-Drawn 8uttweld Carbon Steel Mechanical Tubing Standard Specification for Ductile Iron Castings Standard Specification for Steel, Sheet and Strip, Carbon, Hot-Rolled, Structural Quality and Cold Rolled Standard Classification System for Rubber Products in Automotive Applications Specifications for Stainless Steel 8olts, Hex Cap Screws, and Studs Specification for Stainless Steel Nuts Polyethylene Encasement for Ductile-Iron Pipe Systems Rubber Gasket Joints for Ductile-Iron Pressure Pipe and Fittings Steel Water Pipe -150 mm (6") and Larger ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15000 - General Piping System and Appurtenances - 1 of 10 AWWA C203 - AWWA C213 - AWWA C606 - AWWA C900 - AWWA M11 - AWWA - Coal- Tar Protective Coatings and Linings for Steel Water Pipelines - Enamel and Tape -Hot Applied Fusion-Bonded Epoxy Coating for Interior and Exterior of Steel Water Pipelines Grooved and Shouldered Joints PVC Pressure Pipe, 100 mm (4") Through 300 mm (12") for Water Distribution Steel Pipe -A Guide for Design and Installation Guidelines for Distribution of Non-potable Water A. California Administrative Code, Title 22 NSF - National Sanitation Foundation SSPWC - Standard Specifications for Public Works Construction ("Green book") 1.3 Lining Contamination Prevention Volatile organic compounds present in the linings of items in contact with potable water or recycled water shall not exceed concentrations allowed by the latest requirements of the State Office of Drinking Water and Department of Health Services. Some products and materials may also require proof of NSF certification on the lining materials to be used. 1.4 Temporary Aboveground Pipe (High Line) High line piping, where shown on the Approved Plans or required by the District Engineer, shall be furnished, installed, disinfected, connected, maintained, and removed by the - Contractor. The contractor shall provide a submittal to the District showing pipe layout, tie-in details, materials, sizing and flow calculations, schedule and duration of use for each segment, and disinfection for all high line piping prior to ordering materials. The submittal shall be reviewed by the District Engineer prior to ordering or delivery of any materials. 1.5 Pipe Tappinq All pipe tap (wet tap) connections to existing pressure pipelines, whether for mainline extensions, temporary lines or service laterals, shall be incorporated into the design plans only upon written authorization by the District. The Contractor shall provide materials and labor to excavate, pour thrust block, backfill, compact, and repair pavement as indicated in this Section. In some cases the contractor may perform the wet tap, only with prior approval of the District. 1.6 Warninn/ldentification Tape Warninghdentification tape shall be used to identify location of underground utilities and to act as a warning against accidental dig-ins of buried utilities. Warninghdentification tape shall be used on all underground water and recycled water mains, casings, force mains, sewer mains, and all related appurtenances. Warninghdentification tape shall also be used on cathodic protection wiring systems and tracer wire brought into and out of access ports. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15000 - General Piping System and Appurtenances - 2 of 10 1.7 Curb Identification The Contractor shall mark the location of all potable water, recycled water and sewer laterals at the curb crossing by stamping the face of the curb in 50mm (2") high letters as described below: /-- A. B. C. Potable water laterals shall be stamped with a letter "W". Recycled water laterals shall be stamped with a letter "RW". Sewer laterals to be stamped with a letter "S". PART 2 - MATERIALS 2.1 Temporary Aboveground Pipe (Highline) High line piping layout, materials and appurtenances shall be as indicated on the final submittal from the shop drawing review process and shall comply with the Approved Materials List. 2.2 Grooved End Or Shouldered Couplings For Ductile Iron Or Steel Pipe Grooved end or shouldered couplings shall be in accordance with the Approved Materials List and as described below: A. Use square-cut shouldered or grooved ends per AWWA C606. Grooved-end couplings shall be malleable iron per ASTM A 47, or ductile iron per ASTM A 536. Gaskets shall be per ASTM D 2000. ZI B. Bolts in exposed service shall conform to ASTM A 183, 69 MPa (10,000 psi) tensile strength. 2.3 Warninn/ldentification Tape Warningidentification tape shall be as indicated below and in accordance with the Approved Materials List. A. Tape shall consist of one layer of aluminum foil laminated between two colored layers of inert plastic film (non-metallic) formulated for prolonged underground use that will not degrade when exposed to alkalies, acids and other destructive substances commonly found in soil. The lamination bond should be strong enough that the layers cannot be separated by hand. B. Tape shall be puncture-resistant and shall have an elongation of two times its original length before tearing or separating. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15000 - General Piping System and Appurtenances - 3 of 10 C. Tape shall bear a continuous, printed message every 16- to 36- inches warning of the installation buried below. Tape shall be colored to identify the type of utility intended for identification. Printed message and tape color shall be as follows: - Printed Messaqe Tape Color Caution: Waterline Buried Below Blue Caution: Recycled Waterline Buried Below Purple Caution: Sewerline Buried Below Green Caution: Cathodic Protection Cable Buried Below Red Caution: Electric Line Buried Below Red Ink used to print messages shall be permanently fixed to tape and shall be black in color. D. Tape shall be minimum 5 mil thick x 6" wide with a printed message on one side. 2.4 Field Touch-Up Applications All surfaces of metallic appurtenances in contact with potable water and not protected from corrosion by another system shall be shop-coated by the manufacturer. Appurtenances with damaged coatings shall be repaired or replaced as directed by the Engineer. Touch-up of damaged surfaces, when allowed by the Engineer, shall be performed in accordance with the manufacturer's recommendations. - PART 3 - EXECUTION 3.1 Temporary Aboveground Pipe (Highline) A. B. C. D. E. City of Carlsbad 03/04 (DBE) All high line piping, fittings, and service connections shall be furnished, installed, and maintained by the Contractor, and the Contractor shall make connections to a water source designated by the District, under District observation. All pipe, valves, fittings, hose and connections furnished by the Contractor shall be of good quality, clean, and suitable for conveying potable water in the opinion of the District Engineer. The high line pipe shall be installed in such a manner that it will not present a hazard to traffic and will not interfere with access to homes and driveways along its route. Valves shall be installed at 200' intervals or as directed by the District Engineer. The use of pressure reducing valves (PRV) may be required as directed by the District Engineer. The Contractor shall be responsible for disinfecting all high line, connections, - flushing, and assisting the District in taking water samples for bacteriological testing in accordance with Section 15040. ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15000 - General Piping System and Appurtenances - 4 of 10 _- 3.2 F. Following disinfection and acceptance of the high line as a potable water system, the Contractor shall maintain continuous service through the high line piping to all consumers normally served both directly and indirectly by the pipeline. G. Upon completion of the work, the Contractor shall remove the high line piping and appurtenances. H. If progress in making repairs to the high line is inadequate, the District Engineer may order necessary corrective measures. Corrective measures may consist of directing District personnel or another contractor to complete the work. All costs for corrective measures shall be borne by the Contractor. Connections To Existinq Facilities The Contractor shall furnish the tee, valves and all other materials as called for in the Standard Specifications and plan details in accordance with the Approved Materials List for cut-in installations (and wet taps, where permitted). The Contractor shall provide all equipment and labor required for the excavation and installation of the connection including but not limited to thrust blocks, backfill and pavement replacement. The Contractor shall provide the labor for service change-overs and connections to existing facilities under District observation. Emergency standby equipment or materials may be required of the Contractor by the District. r_ Cut-in tee (or wet tap, where permitted) and valve installations shall be performed as follows: A. Prior to construction, Contractor shall pothole the existing pipe at the location of the proposed connection. The District shall inspect the pothole prior to Contractor's repair of trench. Refer to Section 02225 for protection of existing facilities. Contractor shall record the following information on as-built drawings: 1. 2. 3. 4. 5. 6. 7. Pipe size, outside diameter and circumference. Pipe material such as PVC, Ductile-Iron, Steel or ACP. Pipe class and/or pressure rating. Elevation and horizontal position (coordinates). Location of collars, pipe bells, fittings or couplings, within five feet of proposed tie-in, if found. Potential conflicts with existing utilities. Location of system valves which may be required to shut down or minimize flow to existing pipeline. c B. A plan shall be submitted to the District by the Contractor which details the findings of the pothole activities and indicates specifically how the tie-in will be made and what materials will be used. Additionally, the Contractor shall indicate which system valves may need to be shut down during the construction of the connection. This plan must be reviewed by District staff and authorization given in writing to proceed. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15000 - General Piping System and Appurtenances - 5 of 10 C. To facilitate the proposed connection and allow for slight adjustments in alignment and thrust blocks for testing, the Contractor shall leave a minimum 10' gap between the new pipe installation and the proposed connection point at the existing water main. The Contractor shall leave a gap longer than 10' if conditions warrant, or if directed by the Engineer. D. The new pipeline shall have successfully passed pressure testing and disinfection and bacteriological testing in accordance with Section 15040 prior to proceeding with the connection to the existing pipeline. E. After the District Engineer has given approval to proceed with the connection, the Contractor shall schedule with the District for the cut-in or wet tap installation. 1. Shutdowns will be scheduled at the convenience of the District. Shutdowns may be scheduled for nights or weekends if required. 2. The Contractor shall give the District a minimum of seven (7) working days notice prior to any proposed excavation or shutdown of existing mains or services. Scheduling shall be subject to approval by the District. 3. The District Engineer may postpone or reschedule any shutdown operation if, for any reason, the District Engineer believes that the Contractor is improperly prepared with competent personnel, equipment, or materials to proceed with the connection. If progress in completing the connection within the time specified is inadequate, the District Engineer may order necessary corrective measures. Corrective measures may consist of directing District personnel or another contractor to complete the work. All costs for corrective measures shall be borne by the Contractor. - 4. - F. Contractor may proceed with excavation only when pothole has been completed, materials have been approved and delivered, cut-in or wet tap installation has been scheduled and a copy of the approved traffic control plan has been supplied to the District Engineer. 1. The Contractor shall saw-cut pavement, excavate and provide and install shoring and steel plating, when necessary, one day prior to the wet tap or cut-in installation. The Contractor shall provide lights, barricades and traffic control in accordance with the agency of jurisdiction and as deemed necessary for the excavation by the District Engineer. The Contractor shall de-water existing mains where cut-in installations are required in the presence of the Engineer and in accordance with Section 15040 and 02200. The Contractor shall be prepared to deal with leaking valves and water from those valves to complete the shutdown. Contractor shall be responsible for any and all damage resulting from unauthorized operation of existing District facilities. 2. 3. Only District personnel are authorized to operate existing valves. The - City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15000 - General Piping System and Appurtenances - 6 of 10 4. In areas where cut-ins are to be performed the Contractor shall line the bottom of the trench with 12" to 18" of 3/4" rock and install a 12" to 16" deep sump for dewatering the trench bottom. The District shall perform the following work for cut-in and wet taps installations: a. Cut-ins: Cut and remove portions of existing mains, and disinfect and install tees, valves, couplings, and appurtenances required to complete the closure. The Contractor shall discard pipe and appurtenances removed from service in accordance with this Section. b. Wet taps (when authorized): Disinfect and install the tapping saddle and tapping valve and perform tapping operations. After the District has performed cut-in or tapping operations, and the District Engineer has given approval to proceed, the Contractor shall complete the installation as shown on the Approved Plans in accordance with the Standard Specifications including, but not limited to: 5. 6. a. Disinfecting and installing the pipe section(s) necessary to make the closure to the new system. b. Installing and setting the valve gate well(s) in accordance with the Standard Drawings. c. Installing thrust and anchor blocks in accordance with Section 03300. d. Completing all backfill and compaction of the trench in accordance with Section 02200. e. Repairing or replacing pavement as necessary in accordance with agency of jurisdiction requirements. c 3.3 Grooved End Or Shouldered Couplings For Ductile Iron Or Steel Pipe Grooved-end or shouldered couplings shall be installed in accordance with the manufacturer's recommendations and as described below: A. Grooved-end or shouldered joint couplings shall be installed per AWWA C606 and the manufacturer's recommendations. B. Clean loose scale, rust, oil, grease, and dirt from the pipe or fitting groove and touch-up the epoxy coating as necessary, allowing time for curing before installing the coupling. C. Clean the gasket before installation. Apply a lubricant selected from the Approved Materials List to the gasket exterior including lips, pipe ends, and housing interiors. D. Fasten the coupling alternately and evenly until the coupling halves are seated. Follow the manufacturer's recommendations for bolt torque using a properly calibrated torque wrench. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15000 - General Piping System and Appurtenances - 7 of 10 3.4 Warninghdentification Tape I. Warninghdentification Tape shall be installed as described below in accordance with the Standard Drawings. A. Tape shall be placed at the top of the pipe zone 12" above and centered over the utility intended for identification. Tape used with onsite potable and recycled water irrigation systems shall be installed at 150mm 6" above the pipe. B. Tape shall be installed with the printed side up and run continuously along the entire length of the utility intended for identification. Tape shall be installed on the main piping and all appurtenant laterals, including blowoffs, air valve assemblies, fire hydrants, and services. Tape splices shall overlap a minimum of 24" for continuous coverage. C. Tape shall be installed prior to placement of the Trench Zone Backfill. 3.5 Abandonment Or Removal From Service Of Existing Facilities Before excavating for new mains that are to replace existing pipes or services, the Contractor shall make provisions for the continuation and maintenance of service to customers as directed by the District Engineer. Abandonment or removal from service of existing mains, appurtenances or water services shown on the Approved Plans or as called for by the District Engineer shall be as indicated below and in accordance with the Standard Drawings: - A. Abandonment in place: 1. 2. 3. 4. 5. 6. 7. 8. Existing pipe 4" and smaller shall have a short section of pipe removed and pipe ends encased in concrete. Existing pipe 6" through 14" shall be cut and plugged with concrete or as indicated on plans. Existing pipe 16" and larger shall be entirely filled by pressure-grouting or by blown sand to a bulkhead as indicated on plans. Existing pipe ends shall be filled with concrete in accordance with the Standard Drawings. All valves shall be turned to the closed position. Gate wells shall be cut 24" below grade and filled with concrete or removed and replaced with compacted backfill. Water service corporation stops shall be closed. Meter boxes and curb stops shall be removed. Water services to be abandoned that are connected to pipelines that will remain in service shall be abandoned in-place in accordance with the Standard Drawings. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15000 - General Piping System and Appurtenances - 8 of 10 .- 9. Sewer laterals shall be cut and plugged with concrete at the main as directed by the District Engineer for the specific circumstance and material type identified. Sewer manholes shall have the cover and frame, concrete ring, grade rings and cone section removed. Inlet and outlet piping shall be plugged with concrete, manhole void shall be filled with sand, and a 12" thick, reinforced concrete slab shall be poured over the top of remaining manhole. The Contractor shall backfill hole to ground surface with compacted select fill. 10. B. Removal by excavation: 1. 2. Existing pipe and appurtenances shall be removed from the ground as indicated on the Approved Plans or as directed by the District Engineer. Contractor shall provide measures that allow for the removal of existing sewer mains and appurtenances with no leakage of raw sewage. Transportation of sewer mains and appurtenances removed from service shall be in waterproof trucks to prevent raw sewage from leaking on public streets. 3. Removal of asbestos-cement pipe (ACP) and sewer mains and appurtenances shall be in accordance with all applicable State and Federal requirements. Legal disposal is the responsibility of the Contractor. Obtain concurrence from the agency having disposal jurisdiction with respect to disposal sites. Backfill, compaction, and surface repair of all excavations for removal of pipe and appurtenances shall be made in accordance with the Approved Plans, Section 02200 of the Standard Specifications, and the Standard Drawings. 4. 3.7 Salvaae When the Contractor is required to remove existing pipe and appurtenances, or portions thereof, from the ground, such materials may, at the discretion of the Engineer, be considered salvage. All materials identified as salvage are considered property of the District. A. The Contractor shall remove and temporarily stockpile all materials identified as salvage in a safe location that will not disrupt traffic or shall deliver salvage to the District's Field Operations Yard as directed by the District Engineer. The Contractor shall legally dispose of all other materials in an appropriate manner. Disposal is the responsibility of the Contractor. Obtain concurrence from the agency having disposal jurisdiction with respect to disposal sites and transportation methods. B. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15000 - General Piping System and Appurtenances - 9 of 10 3.8 Reconnections - A. The Contractor may encounter unused service laterals or appurtenant piping connected to an existing pipeline being replaced. Laterals and appurtenance piping that will not be connected to the new pipeline shall be abandoned as described above. B. Existing service laterals or appurtenances shall be connected to new pipelines as shown on the Approved Plans or as directed by the District Engineer in accordance with the Standard Drawings. END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 1 5000 - General Piping System and Appurtenances - 10 of 10 ,-- SECTION 15040 TEST1 NG, FLUSH1 NG AND DlSl N FECTlO N PART 1 - GENERAL 1.1 Description This section designates the requirements for field testing, flushing and disinfection of all water mains intended for the conveyance of potable water or recycledheclaimed water under pressure. Where the words "potable water" are used to describe a process, the Contractor shall assume that process applies fully to recycled or reclaimed water mains. The Contractor shall furnish all labor, materials (including water), tools, and equipment necessary to provide and complete field testing, flushing and disinfection as specified. All pipelines shall be tested for watertightness by subjecting each section to Hydrostatic Pressure and Leakage Tests in accordance with the applicable requirements of AWWA C600 and the Carlsbad Rules and Regulations for Construction of Potable Water Mains, except as modified herein. It shall be the Contractor's sole responsibility to plan his construction activities to allow and facilitate testing, flushing and disinfection of all sections of potable water lines. It shall be the Contractor's sole responsibility to obtain any and all permits required to carry out the Work specified herein. .- 1.2 Related Work Described Elsewhere The Contractor shall refer to the following Specification section(s) for additional requirements: A. Shop Drawing Submittals: 01 300 B. Testing and Inspection: 01410 1.3 Submittals Contractor shall furnish submittals in accordance with the requirements of Section 01 300, Shop Drawing Submittals. The following submittals are required: A. The Contractor shall submit a detailed plan showing how the Contractor intends to test, flush and disinfect the pipeline and Dechlorinate the water from flushing, prior to the submittal of Shop Drawings for the steel pipe. 1.4 Payment Payment for the Work in this section shall be included as part of the lump-sum or unit-price bid amount for which such Work is appurtenant thereto. .- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15040 - Testing, Flushing and Disinfection - 1 of 5 PART 2 - MATERIALS 2.1 General The Contractor shall furnish all labor, water, chemicals, and equipment necessary for completing the disinfection process and for obtaining, transporting and testing samples as specified herein. The use of chlorine solutions is anticipated as the active disinfecting agent. The Contractor shall be solely responsible for the safe and proper handling of the chlorine compounds or other hazardous chemicals utilized. Only chlorine from a hypochlorite solution or a gas-to-solution injector will be allowed. Direct injection of chlorine gas is prohibited. Hypochlorite solutions must be pre-mixed and fed to tanks or piping and not placed dry. Containers and equipment used in sampling must be clean and free of contamination. Sampling bottles shall be furnished by the testing lab and they will collect samples. All water mains above 12 inches in diameter shall require the chlorine gas method applied by a certified chlorination company. PART 3 - EXECUTION 3.1 General Do not allow chlorinated water to remain in contact with the internal waterway ports of pumps, valves, and sensor line assemblies for longer than is necessary. 3.2 Pressure Testing --.L A. Procedure: After the pipe and all appurtenances have been laid and sufficiently backfilled for required restraint, they shall be subjected to a four hour hydrostatic pressure test. This test shall consist of applying to the pipeline a pressure of 50 psi in excess of the designated working pressure specified by the class of pipe, unless otherwise specified on the Plans or in the Specifications, at the point of test application. For pipe sizes in excess of 16-inch diameter, they shall be tested at a pressure based on hydraulic gradient elevation (H.G.L.) as shown on the drawings. If no test H.G.L. is shown, the pipeline at the low point in test section shall be pumped to a hydrostatic test pressure of 50 psi. in excess of the working pressure. Pressure shall be maintained for an eight (8) hour duration and shall be re-pumped when it falls to an amount of 5 p.s.i. Pressure tests or a retest shall be conducted subsequent to any trench backfill compactive effort with heavy duty compacting equipment having an overall weight in excess of 100 pounds. Some hydraulic equipment such as buttetfly valves have a maximum working water pressure less than the test pressure. The Contractor shall apply a minimum back pressure on these closed devices equal to the difference between the test pressure and the rated pressure of the device. The test shall be made prior to connecting the new line with existing pipe and mains. The test shall further be conducted with valves open, and the open ends of pipes, valves, and fittings suitably closed. Valves shall be operated and checked prior to the test period. No leakage shall be allowed when testing across any valves. -, City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15040 - Testing, Flushing and Disinfection - 2 of 5 .- B. C. D. E. Maximum Length of Pipe: Maximum length of pipe to be included in any one test shall be no more than 2,500-feet or the distance between valves, whichever is greater. The Contractor shall provide suitable test bulkheads, blocking, and fittings to permit such sectionalizing. Preparation: The test shall be applied at an approved outlet or fitting located within an elevation of 5-feet of the lowest point of the pipe section to be tested. The Contractor shall provide and later securely plug such fittings. The line shall be filled slowly and maintained at operating pressure for a period of at least 24 hours prior to testing to satisfy any system water absorption. While filling and immediately prior to testing, all air shall be expelled from the pipeline. Where air valves or other suitable outlets are not available, approved taps and fittings shall be provided at all high points and later securely plugged. Pressure Testing: After the 24-hour soak period, the pressure in the pipeline shall be pumped up to the specified test pressure. When the test pressure has been reached, the pumping shall be discontinued until the pressure in the line has dropped 5-psi, at which time the pressure in the pipeline shall again be pumped up to the specified test pressure. This procedure shall be repeated until eight hours have elapsed from the time the specified test pressure was first applied. At the end of this period, the pressure shall be pumped up to the specified test pressure for the last time. Leakage: Leakage shall be considered as the total quantity of water pumped into the pipeline during the eight hour period, including the amount required in reaching the specified test pressure for the final time. Leakage shall not exceed the rate as specified for the type of pipe material being tested. If the leakage exceeds the rate, as specified elsewhere, the Contractor shall, at his own expense, locate and make all repairs as necessary until the leakage is within the specified allowance. Allowable leakage for piping having threaded, brazed, welded, flange or mechanical joint shall be zero. The test shall be repeated until the leakage does not exceed the specified leakage rate. All visible leaks shall be repaired regardless of the amount of leakage. 3.3 Flushinq All potable water mains and services shall be flushed with potable water (or water as otherwise approved by the Owner and regulatory agencies) after completion of construction and prior to disinfection. The Contractor shall provide a sufficient number of suitable outlets at the end@) of the line(s) being flushed in addition to those required by the Plans to permit the main to be flushed with water at a velocity of at least 2.5-feet per second over its entire length. The outlets provided shall meet the requirements for fittings as specified for the type of main constructed. The velocity through outlets and fittings shall not exceed 25 fps during the flushing operation. Drainage facilities shall be constructed such that the water lines cannot be contaminated through ,- the flushing outlet. The Contractor shall be solely responsible for providing a source of water for flushing and the methods for discharge of the water, including all associated costs and permits. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15040 - Testing, Flushing and Disinfection - 3 of 5 3.4 ,-. A. Procedure: After pressure testing and prior to acceptance of the Work, the entire pipeline, including all valves, fittings, hydrants, service laterals, and other accessories, shall be disinfected in accordance with AWWA C651 and Carlsbad Rules and Regulations for Construction of Potable Water Mains. B. Disinfection - Potable Water Mains: After flushing, all mains and services shall be disinfected with chlorine gas (as provided in Subsection 2.1) solution, which shall be water mixed and introduced into the mains to produce a dosage of not less than 50 mg/l nor more than 100 mg/l in all sections of the pipeline and appurtenances. Treated water shall be retained with system for a minimum period of 24-hours and shall produce at the end of the retention period a chlorine residual of not less than 25 mg/l in all sections being disinfected. If the tests are not satisfactory, the Contractor shall provide additional disinfection at his expense as required until all tests are to the satisfaction of the Owner. During the disinfection process, all valves, hydrants, and other accessories shall be operated. After chlorination, the water shall be flushed from the line at its extremities until the replacement water tests are equal chemically and bacteriologically to those of the permanent source of supply. The placing of HTH capsules or powder in pipe sections during the laying process WILL NOT be considered adequate disinfection, The Contractor shall keep adequate chlorine residual testing and indicating apparatus available on the site during the entire disinfection period. After final flushing, the flushing fittings shall be plugged with devices intended for this purpose at the pressure class of the pipe. Where water main is coated, plugs and outlets shall be similarly coated. -. C. Discharge of Chlorinated Water 1. Disposal or discharge to sewer systems, storm drains, drainage courses or surface waters of chlorinated water is prohibited. All chlorinated water shall be de-chlorinated prior to discharge. 2. The reducing agent for neutralization shall be applied to the water as it exits the piping system. The Contractor shall monitor the chlorine residual during the discharge operations. Total residual chlorine limits in these locations, and for the discharge of de-chlorinated water from the testing of pipelines to surface waters of the San Diego Region are as follows: Total Residual Chlorine Effluent Limitations 30-Day Average - 0.002 mg/l Average Daily Maximum - 0.008 mg/l Instantaneous Maximum - 0.02 mg/l 4 The various methods of dechlorination available can remove residual chlorine to concentrations below standard analytical methods of detection, 0.02 mg/l, which will assure compliance with the effluent limit. The Contractor will perform all City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15040 - Testing, Flushing and Disinfection - 4 of 5 necessary tests to ensure that the total residual chlorine effluent limitations listed above are met. 4. If a suitable point of discharge can not be found for the de-chlorinated or the neutralized water, the Contractor shall haul the flushed water to a site suitable for discharge. The Contractor shall include all costs for the discharge of chlorinated water into his bid. 5. In locations where no hazard to the environment is evident based on the joint examination describe above, the de-chlorinated water may be broadcast for dust control on the surface of the immediate site. Care shall be exercised in broadcasting the water to prevent runoff. D. Bacteriologic Samples: 1. One sample of water for the specified bacteriologic test shall be taken from each end of the disinfected main (located downstream of the point of introduction of chlorine disinfectant). For mains over 2,500-feet in length, additional samples shall be taken at intermediate points in such a manner that at least one additional sample is taken for each 2,500-feet of main. 2. An independent, State-certified laboratory will petform bacteriological sampling and testing of all new system installations. The testing methodology employed by the laboratory shall be as set forth in "Standards Methods for the Examination of Water and Waste Water" (current edition). Testing requirements are as set forth in the California Domestic Water Quality and Monitoring Regulations and commensurate with current requirements for surface water testing. The laboratory will analyze the samples for the presence of coliform bacteria and heterotrophic-type bacteria (heterotrophic plate count). Proper chain of custody procedures shall be followed in the handling of the water samples. The evaluation criteria employed by the District for a passing test sample is as follow: a. Coliform bacterial: no positive sample b. Heterotrophic plate count (HPC): 500 colony forming units/ml or less. E. Redisinfection If the initial disinfection fails to produce satisfactory coliform bacteriological test results, the pipeline system shall be re-chlorinated, flushed and re-sampled. If the initial test result of the heterotrophic plate count is greater than 500 units/ml the system shall be re- flushed and re-sampled. If the second set of samples does not produce satisfactory results for the heterotrophic plate count, the pipeline system shall be re-chlorinated] flushed, and re-sampled. The chlorination, flushing and sampling procedure shall continue until satisfactory results are obtained. Re-disinfection and retesting shall be at the Contractor's expense. -- END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15040 - Testing, Flushing and Disinfection - 5 of 5 SECTION 15056 DUCTILE IRON PIPE AND FllTlNGS PART 1 - GENERAL 1.1 Description This section designates the requirements for the manufacture and installation of ductile iron pipe, abbreviated DIP, to be furnished and installed by the Contractor at the location and to the lines and grades shown on the Plans as herein specified. 1.2 Related Work Described Elsewhere The Contractor shall refer to the following Specification section(s) for additional requirements: A. Shop Drawing Submittals: 01300 B. Testing and Inspection: 01410 C. Earthwork: 02200 D. Concrete Construction: 03300 E. Painting and Coating: 09900 F. Testing, Flushing, and Disinfection: 15040 1.3 Submittals The Contractor shall furnish submittals in accordance with Section 01 300, Shop Drawing Submittals. Submittals are required for the following: A. Submit Shop Drawings, material lists, manufacturer's literature and catalog cuts of, but not limited to, the following: Lay Diagrams and Schedule Protective Coatings and Linings Dimensional Checks Pressure Ratings Shop Drawings shall be submitted and approved prior to manufacture of pipe. The layout schedule shall indicate the order of installation, the length and location of each pipe section and special, the station and elevation of the pipe invert at all changes in grade, and all data on curves and bends for both horizontal and vertical alignment. B. Submit data used by the Contractor in manufacture and quality control. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15056 - Ductile Iron Pipe and Fittings - 1 of 6 1.4 Pavment A. Payment for the Work in this section shall be included as part of the lump-sum or unit-price bid amount for which such Work is appurtenant thereto. B. Payment by the linear foot shall be for each diameter and for each pipe strength designation measured horizontally over the pipe centerline. PART 2 - MATERIALS 2.1 Pipe Ductile iron pipe and fittings shall be manufactured in accordance with ANSI 21.50, AWWA C150 and ANSI 21 51, AWWA C151, and shall be of the sizes and thickness classes shown on the Plans. Unless otherwise specified, size four inch (4") through six inch (6") DIP shall be thickness Class 52, while size eight inch (8") and larger shall be thickness Class 50. Unless otherwise specified, pressure class pipe may be substituted for thickness class pipe according to the following schedule: Pipe Diameter Under 16-inch 16 to 18-inch 20 to 24-inch 30 to 36-inch 42 to 60-inch Minimum Pressure Class Not Allowed 250 300 250 200 2.2 Coatings All pipe fittings shall be shop coated with one prime coat of asphaltic coating approximately I-mil thick in accordance with ANSI A21.51 , AWWA C151. All pipe and fittings above ground or in vaults shall be painted in accordance with Section 09900, Painting and Coatings. 2.3 Linings Unless otherwise noted on the Plans or elsewhere in the Specifications, all pipe and fittings shall be cement-mortar lined. A. Cement-Mortar Lining: All pipe and fittings shall be double thickness cement-mortar lined in accordance with ANSI A21.4 or AWWA C104. All cement shall be type II unless otherwise specified. a. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15056 - Ductile Iron Pipe and Fittings - 2 of 6 2.4 Joints And Accessories Unless otherwise shown on the Plans, all joints shall be the push-on type joint. Joints and accessories shall conform to the requirements and dimensions specified in ANSI A21.11, AWWA Clll. F 2.5 Concrete Thrust Blocks Concrete thrust blocks shall be placed as shown on the Plans and shall consist of Class B portland cement concrete containing not less than five sacks of portland cement per cubic yard and shall conform to Section 03300, Concrete Construction. Concrete blocks shall be placed between the undisturbed ground and the fittings to be anchored. Quantity of concrete and the bearing area of the pipe and undisturbed soil shall be as shown on the Plans, unless otherwise determined by the Owner's Representative. The concrete shall be placed, unless specifically shown otherwise on the Plans, so that the pipe joints and fittings will be accessible to repairs. 2.6 Restrained Joints The restrained joints shall be a special push-on type joint unless otherwise specified that is designed to provide longitudinal restraint in lieu of a concrete thrust block. Restrained joints are required for fittings larger than 12-inch diameter with a deflection of 1 1 %io or greater and where indicated on plans. The length of the restrained joints shown on the Plans is the minimum required length. The Contractor shall select an approved restrained joint and then use it exclusively for all of the Work. Restrained joints for push-on joint pipe installations shall be U.S. Pipe "TR-FLEX" pipe or approved equal. - Restraint of field cut pipe shall be kept to a minimum. But when necessary, unless otherwise specified, restraint of field cut pipe shall be provided by the use of U.S. Pipe's "TR-FLEX" pipe field weldments, or approved equal. 2.7 Fittings Fittings for ductile iron pipe shall be manufactured in accordance with ANSI A21 .lo, AWWA C110 or C153. They shall be made of ductile iron and the letters "DI" or "DUCTILE" shall be cast on them, unless otherwise specified. Fitting joints shall be in accordance with ANSI A21.11, AWWA C1 1 1 , and shall be of the push-on type. Mechanical joint fittings will not be permitted unless otherwise specified on the Plans. 2.8 Pipe Lenqths Pipe lengths shall be as specified in ANSI A21.51, AWWA C151, except where shorter lengths are required to fit horizontal and vertical alignment. Combined horizontal and vertical deflections at any rubber gasket or flexible coupling joints shall not exceed eighty percent (80%) of the maximum deflection recommended by the manufacturer. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15056 - Ductile Iron Pipe and Fittings - 3 of 6 2.9 Flanqes Flanges shall be ductile iron, Class 125, unless otherwise shown on the Plans, screwed-on type in accordance with ANSI A21.15, AWWA C115, for pipe, and integrally cast for fittings in accordance with ANSI A21.10, AWWA C110 and shall be flat face. Gaskets shall be 1/8-inch thick minimum in accordance with AWWA C115 and shall have a minimum rated working pressure equal to 350 psi at 180°F. Drop-in type gaskets with holes prepunched shall be used where both flanges are flat face. Where adjoining flange is steel, the steel flange shall be flat face. 2.1 0 Bolts and Nuts Bolts and nuts shall be cadmium plated and shall conform to ASTM A307, Grade B. Washers shall be provided for each nut and shall be the same material as each nut. All buried flanges, bolts, and nuts shall be encased in wax tape per Section 09902. All bolt threads shall be lubricated with non-oxide grease. Flange faces shall be wire brushed and cleaned prior to joining each flange. 2.1 1 Warninq Tape Use marking tape consisting of one layer of aluminum foil laminated between two colored layers of inert plastic film. The lamination bond should be strong enough that the layers can not be separated by hand. Tape shall be a minimum of 5 mils thick and 6 inches wide. Elongation shall be a minimum of 600-percent. Tape shall bear a continuous, printed, message every 16 to 36 inches warning of the installation buried below. Tape shall be selected from the District's Approved Materials List. - PART 3 - EXECUTION 3.1 General Ductile iron pipe and fittings shall be assembled in accordance with the applicable sections of AWWA C600, "Installation of Gray and Ductile Cast-Iron Water Mains and Appurtenances" and as specified herein. 3.2 Transportation Transportation shall be by competent haulers and accomplished in a manner that will avoid damage to the pipe, its lining, or coating. The Contractor shall unload by mechanical means, such as a crane or backhoe, or by rope and skids, as recommended by the manufacturer. In using skids, pipes must be prevented from striking other pipe. No dropping of pipe from trucks will be allowed. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15056 - Ductile Iron Pipe and Fittings - 4 of 6 3.3 Earthwork -c Excavation and backfill, including the pipe bedding, shall conform to the provisions of Section 02200, Earthwork. 3.4 General Installation Procedures and Workmanship Prior to laying the pipe, the bottom of the trench shall be graded and prepared to provide uniform bearing throughout the entire length of each joint of pipe. Bell holes of ample dimension shall be dug in the bottom of the trench at the location of each joint to facilitate the joining. The trench shall have a flat or semi-circular bottom conforming to the grade to which the pipe is to be laid. The pipe shall be accurately placed in the trench to within 3 inches horizontally and 1 inch vertically of the lines and grades on the Plans. Fittings shall be supported independently of the pipe. Cutting and machining of the pipe shall be accomplished in accordance with the pipe manufacturer's standard procedures for this operation and in accordance with AWWA C600. Pipe shall not be cut with a cold chisel, standard iron pipe cutter, nor any other method that may fracture the pipe or will produce ragged, uneven edges. Pipe shall be carefully handled to prevent damage to the lining and coating. Cable, rope, or other devices used for lowering fittings into the trench shall be attached around the exterior of the fitting for handling. Under no circumstances shall the cable, rope, or other device be attached through the fitting's interior for handling. -- No joint shall be backfilled until it has been observed by the Owner's Representative. Sufficient trench space shall be left open in the vicinity of each joint to permit visual observation around the entire periphery of the joint. 3.5 Plastic Film Wrap To protect the pipe from corrosion, ductile-iron pipe and fittings buried underground shall be protected with two plastic film wraps in accordance with ANSI A21.5 and AWWA C105. Each wrap shall be a loose 8-mil thick polyethylene tube. All joints between plastic tubes shall be wrapped with 2-inch wide polyethylene adhesive tape, Polyken 900, Scotchrap 50, or approved equal. Installation of plastic film shall conform to AWWA C105. Unless otherwise specified, plastic film wraps shall not be installed on sections of pipe which are to be concrete encased, installed within casings, or through concrete slope anchors. 3.6 Warning Tape After the pipe zone and the first 12 inches in the trench zone have been backfilled and compacted, place the marking tape on the compacted backfill and center over the pipe. Run tape continuously along the trench and tie ends of tape together. Wrap marking tape around valve box extension pipes and continue along pipe. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15056 - Ductile Iron Pipe and Fittings - 5 of 6 3.7 At all times when pipe laying is not in progress, the open end of the pipe shall be closed with a tight-fitting cap or plug to prevent the entrance of foreign matter into the pipe. These provisions shall apply during the noon hour as well as overnight. In no event shall the pipeline be used as a drain for removing water which has infiltrated into the trench. The Contractor shall maintain the inside of the pipe free from foreign materials and in a clean and sanitary condition until its acceptance by the Owner's Representative. Preventing Foreign Matter from Entering the Pipe 1. 3.8 Damaqed Pipe or Fittings Damaged pipe or fittings shall be removed upon discovery and without delay from the Project Site. 3.9 Leakaqe Test A. General All pipelines shall be tested in accordance with Section 15040, Testing, Flushing and Disinfection, and the applicable provisions of AWWA C600, except as modified herein. B. Allowable Leakage No pipe installation will be accepted if the leakage is greater than that determined by the following formula: .--.. S D F7 133,200 L= in which L = S = D = P = the allowable leakage, in gallons per hour length of pipe tested, in feet nominal diameter of the pipe, in inches average observed test pressure of the pipe being tested, as is shown on the Plans or specified in Section 0141 0, Testing and Inspection, in pounds per square inch gauge, based on the elevation of the lowest point in the line or section under test and corrected to the elevation of the test gauge. The test pressure shall be 50 psi in excess of the designated working pressure specified for the class of pipe unless the test pressure is shown on the Plans or specified elsewhere in the Specifications. 3.1 0 Disinfection Disinfection shall be in accordance with Section 15040, Testing, Flushing and Disinfection. -- END OF SECTION City of Carlsbad 03/04 (DBE) -. ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15056 - Ductile Iron Pipe and Fittings - 6 of 6 SECTION 15064 POLYVINYL CHLORIDE PRESSURE PIPE AND Fli'TlNGS (AWWA C900) - PART 1 - GENERAL 1.1 Description This section designates the requirements for the manufacture and installation of polyvinyl chloride, abbreviated PVC, pressure pipe, to be furnished and installed by the Contractor, at the location and to the lines and grades shown on the Plans as herein specified for both potable and recycled water. Specifications for related Work are as follows: AWWA C900 PVC Pressure Pipe ANSI A21.10 AWWA C110 AWWA C153 AWWA Manual M23 Ductile Iron and Gray-Iron Fittings Ductile Iron and Gray-Iron Fittings Ductile Iron Compact Fittings Pipe Design and Installation 1.2 Related Work Described Elsewhere The Contractor shall refer to the following Specification section(s) for additional .- requirements: A. Shop Drawing Submittals: 01300 B. Testing and Inspection: 01 41 0 C. Earthwork: 02200 D. Concrete Construction: 03300 E. Testing, Flushing and Disinfection: 15040 1.3 Submittals The Contractor shall furnish submittals in accordance with Section 01 300, Shop Drawing Submittals. Submittals are required for the following: A. Submit Shop Drawings, material lists, manufacturer's literature and catalog cuts and other information. B. Submit an affidavit from the pipe manufacturer that all delivered materials comply with the requirements of AWWA C900, the Plans and Specifications. 1.4 Payment A. Payment for the Work in this section shall be included as part of the lump-sum or unit-price bid amount for which such Work is appurtenant thereto. c B. Payment by the linear foot shall be for each diameter and for each pipe strength designation measured horizontally over the pipe centerline. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15064 - PVC Pressure Pipe and Fittings (AWWA C900) - 1 of 5 PART 2 - MATERIALS -. 2.1 General Material used to produce the pipe shall be made from Class 12454-A or B rigid polyvinyl chloride compounds in accordance with AWWA C900 Section 2.1 (Basic Materials), with an established hydrostatic design basis (HDB) equal to or greater than 4000 psi for water at 73.4 degrees F (23 C). Elastomeric gaskets shall comply with the requirements of AWWA C900 Sections 2.1.5 and 2.1.5.1 (Gaskets and Lubricants). 2.2 Pipe PVC pressure pipe, 4-inch through 12-inch, shall be manufactured in accordance with AWWA C900, and shall be of the sizes and pressure classes shown on the Plans. The pipe shall have integral bell and spigot joints with elastomeric gaskets in accordance with AWWA C900 Section 2.2 (Pipe Requirements). The pipe shall conform with the outside diameter of cast-iron pipe unless otherwise specified and shall conform with the wall thickness of DR series 14, 18, or 25. The pipe shall be manufactured by J.M. Manufacturing Company, Certainteed Corporation, Pacific Western Extruded Plastics Company or approved equal. 2.3 Fittings _-. All fittings for PVC pressure pipe shall be manufactured in accordance with ANSI A21 .I 0, AWWA C110 or C153. All fittings shall be made of ductile iron and the letters "DI" or "DUCTILE" shall be cast on them, unless otherwise specified. Bell size shall be for Class 150 and Class 200 cast-iron equivalent PVC pressure pipe, including the rubber-ring retaining groove. 2.4 Service Saddles Service saddles for PVC pressure pipe shall be made of silicone bronze or brass and shall be double banded or wide single band style. The band(s) and nuts shall be type 304 stainless steel and designed specifically for use with AWWA C900 PVC pipe. Each saddle shall accurately fit the contour of the pipe O.D. without causing distortion of the pipe. The saddle shall be securely held in place with stainless steel bolts and nuts. The service saddle shall have a published working pressure at least equal to the pressure class of the pipe on which it is installed. All saddles shall be provided with torque information and installation instructions. Saddles shall be in accordance with Carlsbad Rules and Regulations for the Construction of Potable Water Mains. 2.5 Warning Tape --L Use marking tape consisting of one layer of aluminum foil laminated between two colored layers of inert plastic film. The lamination bond should be strong enough that the layers can City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15064 - PVC Pressure Pipe and Fittings (AWWA C900) - 2 of 5 not be separated by hand. Tape shall be a minimum of 5 mils thick and 6 inches wide. Elongation shall be a minimum of 600-percent. Tape shall bear a continuous, printed, message every 16 to 36 inches warning of the installation buried below. - For potable water, the tape shall be blue in color with the wording that indicates “Potable Waterline Below” or other appropriate wording as approved by the District. For Reclaimed/Recycled water application, the tape shall be the color purple with the wording that indicates “Reclaimed Waterline below” or other appropriate wording as approved by the Engineer or District. Tape shall be selected from the District’s Approved Materials List. PART 3 - EXECUTION 3.1 Pipe Lenqths Laying lengths shall be 20-feet with the manufacturer’s option to supply up to 15% random (minimum length 1 O-feet) sections. No deflections at bells, fittings or of the pipe will be allowed. The use of deflection collars shall be required. 3.2 Marking Each pipe length shall be marked showing the nominal pipe size, O.D. base, the AWWA pressure class, and AWWA specification designation in accordance with AWWA C900 Section 2.6 (Marking Requirements). - For potable water application, the pipe shall be white or blue in color and for recycled water, the pipe shall be purple in color. The seal of the testing agency that verified the suitability of the material for such service shall be included. 3.3 Earthwork Excavation and backfill, including the pipe bedding, shall conform to the provisions of Section 02200, Earthwork. 3.4 General Installations Procedures and Workmanship PVC pressure pipe and fittings shall be installed per AWWA Manual M23 “PVC Pipe-Design and Installation”, and as herein specified. Proper care shall be used to prevent damage in handling, moving, and placing the pipe. Hoist pipe with fork lift or other handling equipment to prevent major damage or shorten its service life. A cloth belt sling or a continuous fiber rope shall be used to prevent scratching the pipe. The pipe shall be lowered and not dropped from the truck. Dropped pipe will be rejected. - City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15064 - PVC Pressure Pipe and Fittings (AWWA C900) - 3 of 5 Prior to laying the pipe, the bottom of the trench shall be graded and prepared to provide uniform bearing throughout the entire length of each joint of pipe. Bell holes of ample dimension shall be dug in the bottom of the trench at the locations of each joint to facilitate the joining. The trench shall have a flat or semi-circular bottom conforming to the grade to which the pipe is to be laid. - The pipe shall be accurately placed in the trench to the lines and grades on the Plans. Fittings shall be supported independently of the pipe. 3.5 Longitudinal Bendinq No longitudinal bending shall be allowed in the installation of PVC pressure pipe. All deflections shall be accomplished by the use of deflection collars or couplings specifically designed for use with PVC C900 pipe and the deflections as installed shall not exceed the manufacturers written recommendations. 3.6 Pipe Joint Assembly The spigot and bell shall slide together without displacement of the rubber gasket. The joint shall be dirt free. The best laying practice is with the bell facing in the direction of laying. Insert the rubber ring into the groove making sure the ring is completely seated. Lubrication of the spigot and instruction of use shall be supplied by the pipe manufacturer. The spigot shall be inserted into the bell and forced slowly into position by use of a large bar lever and a wood block across the pipe end. For large pipe, a come-along (with padding that will not scratch the pipe) may be used. - 3.7 Concrete Thrust Blocks Concrete thrust blocks shall be placed as shown on the Plans and shall consist of Class B portland cement concrete containing not less than five sacks of portland cement per cubic yard and shall conform to Section 03300, Concrete Construction. Concrete blocks shall be placed between the undisturbed ground and the fittings to be anchored. Quantity of concrete and the bearing area of the pipe and undisturbed soil shall be as shown on the Plans, unless otherwise determined by the Owner's Representative. The concrete shall be placed, unless specifically shown otherwise on the Plans, so that the pipe joints and fittings will be accessible to repairs. 3.8 Mechanical Thrust Restraint No mechanical thrust restraint devices which transfer forces from fittings to the PVC pipe wall shall be permitted. 3.9 Preventinq Foreiqn Matter from Enterina the Pipe --4 At all times when pipe laying is not in progress, the open end of the pipe shall be closed with a tight-fitting cap or plug to prevent the entrance of foreign matter into the pipe. These provisions shall apply during the noon hour as well as overnight. In no event shall the City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15064 - PVC Pressure Pipe and Fittings (AWWA C900) - 4 of 5 pipeline be used as a drain for removing water which has infiltrated into the trench. The Contractor shall maintain the inside of the pipe free from foreign materials and in a clean and sanitary condition until its acceptance by the Owner’s Representative. - 3.10 Leakaqe Test A. General: All pipelines shall be tested in accordance with Section 15040, Testing, Flushing and Disinfection, except as modified herein. 8. Allowable Leakage: The following table shall be used for allowable leakage for C900 PVC Pressure Pipe: Pipe size (inches) 6 8” 1 0” 1 2” AI Iowa b I e I ea kag e gals/4hrs/lOOO’ of pipe 0.5 0.66 0.83 0.99 Unless otherwise specified on the Plans or in Section 01410, Testing and Inspection, the test pressure shall be 75 psi in excess of the designated working pressure specified for the class of pipe being tested. /c 3.1 1 Disinfection Disinfection shall be in accordance with Section 15040, Testing, Flushing and Disinfection. END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15064 - PVC Pressure Pipe and Fittings (AWWA C900) - 5 of 5 c- SECTION 15066 POLYVINYL CHLORIDE WATER TRANSMISSION PIPE AND FllTlNGS (AWWA C905) PART 1 - GENERAL 1.1 Description This section designates the requirements for the manufacture and installation of polyvinyl chloride, abbreviated PVC, water transmission pipe to be furnished and installed by the Contractor at the location and to the lines and grades shown on the Plans as herein specified. Specifications for related Work are as follows: AWWA C905 ANSI 21.10 AWWA C110 AWWA C153 AWWA Manual M23 PVC Water Transmission Pipe Ductile Iron and Gray Iron Fittings Ductile Iron and Gray Iron Fittings Ductile Iron Compact Fittings PVC Pipe Design and Installation 1.2 Related Work Described Elsewhere - The Contractor shall refer to the following Specification section(s) for additional requirements: A. Shop Drawing Submittals: 01300 B. Earthwork: 02200 C. Concrete Construction: 03300 D. Testing, Flushing and Disinfection: 15040 1.3 Submittals The Contractor shall furnish submittals in accordance with Section 01 300, Shop Drawing Submittals. Submittals are required for the following: A. Submit Shop Drawings, material lists, manufacturer’s literature and catalog cuts and other information. B. Submit an affidavit from the pipe manufacturer that all delivered materials comply with the requirements of AWWA C905, the Plans and Specifications. 1.4 Pavment A. Payment for the Work in this section shall be included as part of the lump-sum or unit-price bid amount for which such Work is appurtenant thereto. B. Payment by the linear foot shall be for each diameter and for each pipe strength designation measured horizontally over the pipe centerline. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15066 - PVC Pressure Pipe and Fittings (AWWA C905) - 1 of 5 PART 2 - MATERIALS -.., 2.1 General Material used to produce the pipe shall be made from Class 12454-A or B rigid polyvinyl chloride compounds in accordance with AWWA C905 Section 2.1 (Basic Materials), with an established hydrostatic design basis (HDB) equal to or greater than 4000 psi for water at 73.4 degrees F (230C). Elastomeric gaskets shall comply with the requirements of AWWA C905 Sections 2.1.3 (Elastomeric Gaskets) and 2.1.4 (Gaskets and Lubricants). 2.2 Pipe PVC water transmission pipe, 14-inch through 30-inch, shall be manufactured in accordance with AWWA C905, and shall be of the sizes and dimension ratios (DR) shown on the Plans. If a pressure class is called for on the Plans, it shall mean the pressure rating (PR) as defined in AWWA C905. The pipe shall have integral bell and spigot joints with elastomeric gaskets in accordance with AWWA C905 Section 3 (Pipe Requirements). The pipe shall conform with the outside diameter of cast-iron pipe unless otherwise specified and shall conform with the wall thickness of DR series 18 or 25 or as shown on the drawings. The pipe shall be manufactured by J.M. Manufacturing Company, Certainteed Corporation, Pacific Western Extruded Plastics Company or approved equal. 2.3 Marking Each pipe length shall be marked showing the nominal pipe size, O.D. base, the AWWA pressure class, and AWWA specification designation in accordance with AWWA C905 Section 4.7 (Marking Requirements). For potable water applications, the pipe shall be white or blue in color and the seal of the testing agency that verified the suitability of the material for potable water service shall be included. For Recycled or Reclaimed water applications, the pipe shall be purple in color and contain the markings of "Caution: Reclaimed Water - Do Not Drink - Peligro Aqua lmpura - No Beber" or other appropriate markings as approved by the Engineer or District. 2.4 Fittinas All fittings for PVC water transmission pipe shall be manufactured in accordance with ANSI A21.10, AWWA C110 or C153. All fittings shall be made of ductile iron and the letters "DI" or "DUCTILE" shall be cast on them, unless otherwise specified. Bell size shall be for Class 165 and Class 235 cast-iron equivalent PVC water transmission pipe, including the rubber-ring retaining groove. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15066 - PVC Pressure Pipe and Fittings (AWWA C905) - 2 of 5 2.5 Service Saddles Service saddles for AWWA C905 PVC water transmission pipe shall not be allowed unless specifically called for on the Plans. ,.- 2.6 Warning Tape Use marking tape consisting of one layer of aluminum foil laminated between two colored layers of inert plastic film. The lamination bond should be strong enough that the layers can not be separated by hand. Tape shall be a minimum of 5 mils thick and 6 inches wide. Elongation shall be a minimum of 600-percent. Tape shall bear a continuous, printed, message every 16 to 36 inches warning of the installation buried below. For Reclaimed/Recycled water application, the tape shall be the color purple with the wording that indicates "Reclaimed Waterline below" or other appropriate wording as approved by the Engineer or District. Tape shall be selected from the District's Approved Materials List. PART 3 - EXECUTION 3.1 Pipe Lengths Laying lengths shall be 20-feet with the manufacturer's option to supply up to 15% random (minimum length 1 0-feet) sections. 3.2 Earthwork rc- Excavation and backfill, including the pipe bedding, shall conform to the provisions of Section 02200, Earthwork, and AWWA C905 Section A6 installation. 3.3 General Installations Procedures and Workmanship PVC water transmission pipe and fittings shall be installed per AWWA Manual M23 "PVC Pipe-Design and Installation", and as herein specified. Proper care shall be used to prevent damage in handling, moving, and placing the pipe. Hoist pipe with fork lift or other handling equipment to prevent major damage or shorten its service life. A cloth belt sling or a continuous fiber rope shall be used to prevent scratching the pipe. The pipe shall be lowered and not dropped from the truck. Dropped pipe will be rejected. Prior to laying the pipe, the bottom of the trench shall be graded and prepared to provide uniform bearing throughout the entire length of each joint of pipe. Bell holes of ample dimension shall be dug in the bottom of the trench at the locations of each joint to facilitate the joining. The trench shall have a flat or semi-circular bottom conforming to the grade to which the pipe is to be laid. The pipe shall be accurately placed in the trench to within 3 inches horizontally and 1 inch vertically of the lines and grades on the Plans. Fittings shall be supported independently of the <+ pipe. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15066 - PVC Pressure Pipe and Fittings (AWWA C905) - 3 of 5 3.4 Lonqitudinal Bendinq No longitudinal bending shall be allowed in the installation of PVC water transmission pipe. All deflections shall be accomplished by the use of joints and fittings specifically designed for use with PVC C905 pipe and the deflections as installed shall not exceed the manufacturers written recommendations. -.4 3.5 Pipe Joint Assemblv The spigot and bell shall slide together without displacement of the rubber gasket. The joint shall be dirt free. The best laying practice is with the bell facing in the direction of laying. Insert the rubber ring into the groove making sure the ring is completely seated. Lubrication of the spigot and instruction of use shall be supplied by the pipe manufacturer. The spigot shall be inserted into the bell and forced slowly into position by use of a large bar lever and a wood block across the pipe end. For large pipe, a come-along (with padding that will not scratch the pipe) may be used. Combined horizontal and vertical deflections at PVC pipe joints shall not exceed that recommended by AWWA Manual M23 or published recommendations of the manufacturer (the maximum total deflection allowed shall be one and one-half degrees). 3.6 Concrete Thrust Blocks - Concrete thrust blocks shall be placed as shown on the Plans and shall consist of Class B portland cement concrete containing not less than five sacks of portland cement per cubic yard and shall conform to Section 03300, Concrete Construction. Concrete blocks shall be placed between the undisturbed ground and the fittings to be anchored. Quantity of concrete and the bearing area of the pipe and undisturbed soil shall be as shown on the Plans, unless otherwise determined by the Owner's Representative. The concrete shall be placed, unless specifically shown otherwise on the Plans, so that the pipe joints and fittings will be accessible to repairs. 3.7 Mechanical Thrust Restraint Mechanical thrust restraint devices which transfer forces from fittings to the PVC pipe wall shall only be permitted where piping is greater than 12-inch diameter or where indicated on plans. 3.8 Warninq Tape After the pipe zone and the first 12 inches in the trench zone have been backfilled and compacted, place the marking tape on the compacted backfill and center over the pipe. Run tape continuously along the trench and tie ends of tape together. Wrap marking tape around valve box extension pipes and continue along pipe. 3.9 Preventinq Foreiqn Matter From Enterinq The Pipe - At all times when pipe laying is not in progress, the open end of the pipe shall be closed with a tight-fitting cap or plug to prevent the entrance of foreign matter into the pipe. These provisions City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15066 - PVC Pressure Pipe and Fittings (AWWA C905) - 4 of 5 shall apply during the noon hour as well as overnight. In no event shall the pipeline be used as a drain for removing water which has infiltrated into the trench. The Contractor shall maintain the inside of the pipe free from foreign materials and in a clean and sanitary condition until its acceptance by the Owner. 3.10 Leakage Test A. General: All pipelines shall be tested in accordance with the Section 15040, Testing, Flushing and Disinfection, except as modified herein. B. Allowable Leakage: No pipe installation will be accepted if the leakage is greater than that determined by the following formula: SDfi 148,000 L= c in which L = the allowable leakage, in gallons per hour S = length of pipe tested, in feet D = nominal diameter of the pipe, in inches P = average observed test pressure of the pipe being tested as shown on the Plans or specified in Section 0141 0, Testing and Inspection, in pounds per square inch gauge, based on the elevation of the lowest point in the line or section under test and correction to the elevation of the test gauge. Unless otherwise specified on the Plans or in Section 01410, Testing and Inspection, the test pressure shall be 50 psi in excess of the designated working pressure specified for the class of pipe being tested. 3.1 1 Disinfection Disinfection shall be in accordance with Section 15040, Testing, Flushing and Disinfection. END OF SECTION /-- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15066 - PVC Pressure Pipe and Fittings (AWWA C905) - 5 of 5 SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE - PART 1 - GENERAL 1.1 Description This section designates the requirements for steel pipe fabrication, test in shop, installation of steel pipe, fabrication of steel sheet or plate, mill-manufactured steel pipe, bends, special pipes with outlets, pass holes, flanges and all other fittings. Steel pipe shall conform to the following except as modified by this Specification: AWWA C200 Steel Water Pipe 6-inches and larger AWWA C205 Cement-mortar protective lining and coating AWWA C207 Steel Pipe Flanges AWWA C208 Dimensions for Fabricated Steel Water Pipe Fittings AWWA C209 Cold Applied Tape Coating for the Exterior of Special Sections, Connection and Fittings for Steel Water Pipelines Standard Qualification Procedure for Manual Welding Operators c- AWS ASME Boiler and Pressure Vessel Code AWWA C214 Tape Coatings Systems for the Exterior of Steel Water Pipeline 1.2 Related Work Described Elsewhere The Contractor shall refer to the following Specification section(s) for additional requirements: A. Shop Drawing Submittals: 01300 B. Testing and Inspection: 0141 0 C. Trenching, Backfilling and Compacting: 02223 D. Structural Steel and Miscellaneous Metalwork: 051 00 E. Tape Wrap and Mortar Coating: 09870 *-- F. Painting and Coating: 09900 G. Petrolatum Wax Tape Coating: 09902 City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15076 - Cement-Mortar Lined and Coated Steel Pipe - 1 of 10 H. Cathodic Protection: 131 20 I. General Piping Systems and Appurtenances: 15000 J. Testing, Flushing and Disinfection: 15040 K. Miscellaneous Couplings, Pipe and Appurtenances: 15092 1.3 Submittals The Contractor shall furnish submittals in accordance with Section 01 300, Shop Drawing Submittals. Submittals are required for the following: A. Submit Shop Drawings, material lists, manufacturer's literature and catalog cuts of, but not limited to, the following: Shop Drawings Fabrication Details Layout Diagram and Schedule Manufacturer's tests Protective Coatings Mill Reports or Plant Test Reports Dimensional Checks Welding Rods for Field Welding Shop Drawings shall be submitted and approved prior to manufacture of pipe. The layout schedule shall indicate the order of installation, the length and location of each pipe section and special, the station and elevation of the pipe invert at all changes in grade and horizontal alignment, and all data on curves and bends for both horizontal and vertical alignment. Other items of information to be included in Layout Diagram and Schedule are pipe outside diameter, wall thickness, location of all welded seams, working pressure, locations of bulkheads for field hydrostatic pressure testing, location of closure piece and their lengths, location of all pipes and specials, location of valves and other mechanical equipment, limits of field welded joints, locations and callouts for flanges, reinforcing collars, wrapper plates and crotch plates. Details for joints, butt straps, couplings, flanges, bulkheads and their method of attachment to the pipeline, linings and coatings shall be provided with Layout Diagram and Schedule. - The Layout Diagram and Schedule shall be submitted with a separate statement by the manufacturer certifying that the pipe as represented in the Layout Diagram and Schedule is in accordance with these specifications as well as exterior weld bead requirements the requirements of Section 09870, Part 3.2 D. B. Submit data used by the Manufacturer in manufacture and quality control, including but not limited to affidavit of complance with AWWA C200 and C205, certificate that cement complies with ASTM C150, and wire fabric conformance to ASTM Standards.. -"- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15076 - Cement-Mortar Lined and Coated Steel Pipe - 2 of 10 C. Test reports showing the physical properties of the rubber used in the gaskets shall be submitted. D. Procedure qualification records shall be submitted for each welder who will be performing the field welding and copies of their welder qualification records. 1.4 Inspection and Field Verification A. The District’s Representative or his authorized representative will inspect materials, fabrication, and testing of pipes and specials at the manufacturer’s plant. B. Where new pipelines are to be connected to existing waterlines of the District, the Contractor shall verify in the field the location, elevation, pipe material, pipe outside diameter, and any other characteristics of the existing waterline before proceeding with the pipe fabrication or installation. This field verification shall be performed in the presence of the District’s Representative. Adjust and align the new pipeline as necessary to meet the field conditions and provide all required material, labor and equipment to make the connection. 1.5 Payment A. Payment for the Work in this section shall be included as part of the lump-sum or unit-price bid amount for which such Work is appurtenant thereto. _I B. Payment by the linear foot shall be for each diameter and for each pipe strength designation measured horizontally over the pipe centerline. PART 2 - MATERIALS 2.1 Pipe Design Requirements Pipe lining and coating shall be the product of one company in the business of designing and manufacturing cement-mortar lined, tape wrapped and mortar coated steel pipe. Use of subcontractors or subcontracts to apply the lining and coating of the steel pipe is not allowed. The pipe shall consist of the following components: A welded steel cylinder with joints formed integrally with the steel cylinder or with steel joint rings welded to the ends; A centrifugally-cast cement-mortar lining; A self- centering bell and spigot joint with a circular preformed elastomeric gasket, so designed that the joint will be watertight under all conditions of service; Tape wrapping of the cylinder over a dielectric coating; A dense, concentric, steel reinforced exterior cement-mortar coating. rc‘ The Plans indicate the elevations and alignment of the pipeline, the nominal inside diameter of the lined pipe, and the minimum steel cylinder thickness or design pressure (adjusted to City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic ti Recycled Water Transmission Mains 15076 - Cement-Mortar Lined and Coated Steel Pipe - 3 of 10 satisfy transient conditions). Specifications or, if none is stated, the amount of cover shall be scaled from the Plans. Design soil cover shall be as stated on the Plans or Minimum thickness of the steel cylinder shall be as shown on the Plans or, if not shown on the Plans, as determined by the following formula, except that steel thickness shall not be less than 10 gauge (0.1 345-inch). t= MWhere P = Design pressure, in psi plus 50 psi minimum 2s S = Steel stress at design pressure, Le., 16,500 psi t = Steel cylinder thickness, in inches d = OD of steel cylinder, in inches 2.2 Steel Cylinders Materials used in fabricating steel cylinders shall be hot rolled carbon steel sheets conforming to the requirements of ASTM A53, Grade 6, ASTM A570 Grade 36 or Grade 33, or steel plates conforming to the requirements of ASTM A36. The method of testing shall conform to the requirements of ASTM A570. Full penetration welds will be required. circumferential stress in the steel shall not exceed 16,500 psi at the design pressure. Welds may be straight or spiral seam. The 2.3 Cement Cement for mortar lining and coating shall be Portland Cement Type II and conform to ASTM C150, unless otherwise specified. Admixtures containing chlorides shall not be used. - 2.4 Steel Bar or Wire Reinforcement Circumferential steel bar or wire reinforcement shall conform to ASTM A615, Grade 40, "Specifications for Billet-Steel Bars for Concrete Reinforcement". Wire fabric reinforcing for cement-mortar coatings and linings of fittings shall conform to ASTM A1 85, "Specifications for Welded Steel Wire Fabric," or ASTM A497, "Specifications for Welded Deformed Steel Wire Fabric." Spiral-wire reinforcement for cement-mortar coatings shall conform to ASTM A82. 2.5 Steel for Joint Rinqs Steel for bell rings shall conform to ASTM A575, "Specification for Merchant Quality Hot Rolled Carbon Steel Bars." Steel for spigot rings shall conform to ASTM A576, "Specification for Special Quality Hot-Rolled Carbon Steel Bars." 2.6 Dimensions The steel pipe sizes shown on the Plans or otherwise referred to shall be the nominal inside diameter. Unless otherwise specified, the nominal diameter shown on the Plans shall be considered to be the inside diameter after lining. __ City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15076 - Cement-Mortar Lined and Coated Steel Pipe - 4 of 10 2.7 Manufacturer's Tests Each steel cylinder with joint rings attached and cylinders for specials shall be hydrostatically tested to a circumferential stress of at least 22,000 psi, but not more than 25,000 psi. If leaks develop during testing, the cylinder shall be repaired by welding and retested until all leaks are eliminated. - The seams in short radius bends and special fittings shall be tested by the air-soap method using air at a pressure of 5 psi or by the dye-check method. However, if the fitting is fabricated from cylinders which have been previously hydrostatically tested, no further test will be required on seams so tested. Hydrostatic testing of fittings to 150% of the design pressure may replace the tests described above. Any defects revealed by any of the alternate test methods shall be repaired by welding and the fitting retested until all defects have been eliminated. 2.8 Fabrication Details Each special and each length of straight pipe shall be plainly marked at the bell end to identify the design pressure and the proper location of the pipe or special by reference to I ayou t sc hed u le. Exposed portion of joint rings shall be protected from corrosion by the manufacturer's - standard coating. The pipe shall be fitted with devices shown on the Plans to permit continuous electrical bonding of the various joints following field installation. 2.9 Protective Coatings and Linings All exposed metal surfaces shall be painted or coated as specified in Section 09900, Painting and Coating, except where painting is specified elsewhere and in this section. All steel pipe and fittings for underground service shall be cement-mortar lined, taped wrapped and cement-mortar coated in accordance with AWWA C205 and C602 unless otherwise specified on the Plans. Tape wrap shall be in accordance with Section 09870. Linings shall be in accordance with the table below. For the following nominal inside diameters, the lining thickness and minimum cement-mortar coating thickness shall be as follows: LINING COATING Nominal Pipe Size Thickness Tolerance Thickness Tolerance (inches) (inches) (inches) (inches) (inches) 4- 10 12-18 20 - 44 45 - 58 60 and over City of Carlsbad 03/04 (DBE) 1 I4 - 1 /32+ 1 I32 318 -1 I1 6+1 I8 1 12 -1 I1 6+1 I8 314 -1 I1 6+1 I8 314 -1 I1 6+1 I8 1 12 518 314 1 1 114 +1 I8 +1 I8 +1 I8 +1 I8 +1 I8 ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15076 - Cement-Mortar Lined and Coated Steel Pipe - 5 of 10 2.1 0 Cement-Mortar Curing The pipe shall be cured by water curing, steam curing or a combination of both. Water curing and steam curing may be used interchangeably on a time ratio basis of four hours water curing to one hour of steam curing. Where steam curing is used, the pipe shall be kept in steam maintained at a temperature of 100 F to 150 F for the specified period and, where water curing is used, the pipe shall be kept continually moist by spraying or other means for the specified periods. The pipe shall not be allowed to dry either on the inside or outside surfaces during the curing period. Where water curing is used, the pipe shall be kept continuously moist for seven days at a temperature of not less than 40 F before being moved to the trench site. Cement-mortar lining and coating of special pipe and fittings may be cured in accordance with the above provisions or by prompt application of a white-pigmented sealing compound conforming to ASTM C309. Sealing compound shall not be applied at joint ends where compound will interfere with the bond of joint mortar. 2.1 1 Special Pipe and Fittings The manufacturer shall furnish all fittings and special pieces required for closures, curves, bends, branches, manholes, outlets, connections for mainline valves, and other appurtenances required by the Plans. 1 Special fittings shall be fabricated of welded steel sheet or plate, lined and coated with cement-mortar of the same type as the adjoining pipe and applied as specified for lining and coating of specials in AWWA C205 and as modified herein. Butt welding shall be used, unless otherwise indicated on the Plans. Minimum centerline radius of an elbow or bend shall be as follows. The maximum deflection at a mitered girth seam shall be 22-1/2 degrees. Pipe Size (Inches) Minimum Centerline Radius 30 - 48 51 - 60 Over 60 2-112 times ID 1 0-feet 2 times ID The circumferential stress in the sheet or plate shall not exceed 13,500 psi at the design pressure. The minimum thickness of sheet or plate shall be as follows: Fittina Diameter Ranae (Inches) 18 and under 20 - 24 26 - 36 38 - 45 48 - 54 57 - 60 63 - 72 75 - 84 City of Carlsbad 03/04 (DBE) Minimum Thickness of Sheet or Plate 10 gauge 311 6" or 7 gauge 114" 511 6 318" 711 6" 1/2" 518" ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15076 - Cement-Mortar Lined and Coated Steel Pipe - 6 of 10 4 ...-_ Outlets at special fittings shall be reinforced with collars or crotch plates. If collar reinforcement is used, the outlet diameter shall not exceed 69% of the ID of the fitting. The diameter of outlets reinforced with crotch plates may equal the fitting diameter. The effective shoulder width "W" of collars from the inside surface of the steel outlet to the outside edge of the collar measured on the surface of the cylinder shall be not less than one- third or more than one-half the ID of steel outlet. The thickness of the collar shall be not less than "T" as determined by: Pw x ID cvl. x ID outlet T= 36,000 x W where Pw is the design pressure in pounds per square inch, and all other dimensions are in inches. Collars may be oval in shape or rectangular with well-rounded corners. Outlets 3-inches in diameter and smaller may be installed without collars. The design of crotch plates shall be based upon the paper by Swanson, Chapton, Wilkinson, King, and Nelson, originally published in June 1955 issue of the Journal of the American Water Works Association. 2.12 Insulating Flange Kits See Section 131 20 of these specifications. 2.13 Handling and Shipment ZL Pipe and special fittings shall be handled carefully, and blocking and holddowns used during shipment shall prevent movement or shifting. Both ends of pipe and fittings on trucks or rail cars shall be bulkheaded or covered in order to prevent excessive drying of the interior lining. 2.14 Warninq Tape Use marking tape consisting of one layer of aluminum foil laminated between two colored layers of inert plastic film. The lamination bond should be strong enough that the layers can not be separated by hand. Tape shall be a minimum of 5 mills thick and 6 inches wide. Elongation shall be a minimum of 600-percent. Tape shall bear a continuous, printed message every 16 to 36 inches warning of the installation buried below. For potable water applications, the tape shall be blue in color with the wording that indicates "Potable Waterline below" or other appropriate wording as approved by the Engineer or District. For reclaimed/recycled water applications, the tape shall be the color purple with the wording that indicates "Reclaimed Waterline below" or other appropriate wording as approved by the Engineer or District. Tape shall be selected from the District's Approved Materials List. c City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15076 - Cement-Mortar Lined and Coated Steel Pipe - 7 of 10 PART 3 - EXECUTION - 3.1 Installation A. Trench Preparation: Earthwork shall be carried out in accordance with Section 02200, Earthwork. Pipe laying shall be scheduled so that the bell end of the pipe faces in the direction of laying. Pipe installation on slopes steeper than 20% shall be laid in an uphill direction. Prior to laying the pipe, the bottom of the trench shall be graded and prepared to provide uniform bearing throughout the entire length of each joint of pipe. Suitable bell holes shall be excavated at each joint and a shallow lateral depression shall be scooped out half a pipe length from the last pipe laid to allow for easy removal of the belt pipe sling and thus avoid any movement of the pipe after it is placed on proper line and grade. B. Joints: All field joints shall be welded joints. The pipe should be picked up well balanced, then lowered into the trench so that the spigot end may be entered into the bell end of the last pipe laid. Metal or wooden spacers shall be placed against the inside shoulder of the bell of 24-inch and larger pipe to provide the proper space between abutting ends of the pipe. For pipe sizes smaller than 24-inches, where joints have not been pre-fabricated, butt straps shall be used at all joint, unless indicated otherwise on the plans. The pipe interior shall be inspected by a closed circuit television camera, to assure quality of internal mortar. -~ For pipe sizes 24-inches and larger, the joint recess shall be pointed from the inside with cement mortar after the backfill has been placed and compacted and the pipe permitted to take any normal settlement. The mortar shall be mixed of one part cement to one and one-half parts of sand and pointing accomplished in two or more lifts and finished off flush by troweling. Pipe shall be inspected visually by work persons within the pipe, to assure internal mortar quality. The outside joint recess shall be grouted with cement mortar after a diaper has first been placed around the joint and tightened securely to prevent leakage while the mortar is being poured. The diaper shall be made of moisture resisting paper or heavy duty sail cloth of sufficiently close weave to prevent cement loss from the mortar. The diapers shall be hemmed on each edge and shall contain a metal strap within each hem sufficiently longer than the circumference of the pipe to allow a secure attachment of the diaper to the pipe. The diaper width will depend upon pipe size and design and shall be the width recommended by the manufacturer. Following installation of the diapers, the joints shall be poured and rodded from one side only until the mortar comes up to the top of the diaper on the opposite side. Approximately one hour subsequent to the pouring of the joint, the joint shall be rechecked and, if any settlement, leakage or shrinkage has taken place, the joint shall be refilled with mortar. - Outside joints may be grouted before or after the placement of bedding and backfill materials if those materials are to be mechanically compacted. If bedding and backfill materials are to be hydraulically densified, grout shall be poured and City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15076 - Cement-Mortar Lined and Coated Steel Pipe - 8 of 10 "I _- allowed to set before applying water. In any case, joints shall be grouted before backfill is placed over the top of the pipe. C. Butt-Strap Closure Joints: Butt-strap closure joints shall be completed in the trench after the pipe has been laid to the alignment and grade shown on the Plans. They should be field welded by full-circumferential fillet welds or one of the edges may be shop welded and the other field welded. Welding shall be done in the same manner as specified for welded joints. The interior of the joints shall be filled with stiff plastic mortar and finished off smoothly with the inside of the pipe. Clean the inside steel surfaces by wire brushing or power brushing. Wire mesh, 2" x 4" x No. 13 gauge, clean, and free from rust, shall be applied to the interior of the joints so that the wires on the 2- inch spacing run circumferentially around the pipe. The wires on the 4-inch spacing shall be crimped in such a manner that the mesh will be held 3/8-inch from the metal joint surface. The mesh shall be lapped a minimum of 8-inches and shall be securely wired in position. Pack the cement mortar into the recess of the joint and steel trowel finish to match the adjoining pipes. The joint exterior shall be coated with mortar to a minimum thickness of 1%-inches. Immediately prior to applying mortar to the interior or exterior of the joints, a cement wash shall be applied to the metal to be coated. D. Welded Joints: Welded joints shall be completed after the pipe is in final position. Welded joints shall be either a welded Carnegie joint or a lap-welded slip joint as shown on the Plans. Any recess between the bell and spigot shall be caulked with a rod to facilitate the welding. Pipe of 30-inches in diameter or more may be welded from the inside. Welders assigned to the Work shall be qualified under the AWS standard qualification procedure. Joints to be welded shall be cleaned, preferably prior to placing the pipe in the trench, of all loose scale, heavy rust, paint, cement, and grease. At least a 1 /2-inch recess shall be provided between adjacent mortar-covered surfaces to place the weld. In all hand welding, the metal shall be deposited in successive layers and the minimum number of passes or beads in the completed weld shall be as follows: Steel Cylinder Thickness (Inches) Fillet Weld Minimum Number of Passes Smaller than 311 6 1 311 6 and 114 2 511 6 3 318 3 After the joints have been welded, the joint shall be grouted with cement mortar in the same manner as specified for rubber-ring joints. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15076 - Cement-Mortar Lined and Coated Steel Pipe - 9 of 10 3.2 At all times when pipe laying is not in progress, the open end of the pipe shall be closed with a tight-fitting cap or plug to prevent the entrance of foreign matter into the pipe. These provisions shall apply during the noon hour as well as overnight. In no event shall the pipeline be used as a drain for removing water which has infiltrated into the trench. The Contractor shall maintain the inside of the pipe free from foreign materials and in a clean and sanitary condition until its acceptance by the Owner's Representative. Preventing Foreiqn Matter from Entering the Pipe & 3.3 Leakaae Test A. General: All pipelines shall be tested in accordance with Section 15040, Testing, Flushing and Disinfection, and the applicable provisions of AWWA C600, except as modified herein. B. Allowable Leakage: No leakage will be allowed for welded joints. The length of pipe with welded joints will be deducted from the total length in computing the allowable leakage. All visible leaks must be repaired regardless of the results of the leakage allowance measurements. 3.4 Disinfection Disinfection shall be in accordance with Section 15040, Testing, Flushing and Disinfection. -- END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic 8, Recycled Water Transmission Mains 15076 - Cement-Mortar Lined and Coated Steel Pipe - 10 of 10 SECTION 15092 MISCELLANEOUS COUPLINGS, PIPE AND APPURTENANCES - PART 1 - GENERAL 1.1 Description All valves, couplings, and appurtenances shall conform to requirements of the standard dimensions and pressure classification of the immediately adjacent pipe, valve or appurtenance as specified. 1.2 Related Work Described Elsewhere The Contractor shall refer to the following Specification section(s) for additional requirements: A. Shop Drawing Submittals: 01300 B. Painting and Coating: 09900 C. Petrolatum Wax Tape Coating: 09902 1.3 Submittals Contractor shall furnish submittals in accordance with the requirements of Section 01 300, Shop Drawing Submittals. The following submittals are required: A. Submit Shop Drawings for all miscellaneous couplings, pipe and appurtenances. Shop Drawings shall include listing of materials of construction, with ASTM reference and grade, including lining and paint coating intended for use, with lining and coating manufacturers' and paint numbers listed. 1.4 Payment Payment for the Work in this section shall be included as part of the lump-sum or unit-price bid amount for which such Work is appurtenant thereto. PART 2 - MATERIALS 2.1 Gaskets, Nuts, and Bolts Gaskets for flanged joints shall be fullface, compressed non-asbestos composition sheet packing, graphited on both sides, "drop-in" type, boltholes prepunched, conforming to the requirements of ANSI B16.21, 1/8-inch thick and shall be as manufactured by Crane Co., Garlock or approved equal. Bolts and studs shall be cadmium plated and shall conform to ASTM A307, Grade B, "Steel Machine Bolts and Nuts and Tap Holes," when a ring gasket is used and shall conform to either ASTM A261, "Heat-Treated Carbon Steel Bolting Material" or ASTM AI 93, "Alloy-Steel Bolting Material for High Temperature Service," when a full-face gasket is used. Bolts and nuts shall be heavy hexagon series. Nuts shall conform to ASTM A194, "Carbon and Alloy Steel Nuts for Bolts for High Pressure and High Temperature Service" either in Grade 1, 2 or 2H. The fit shall be ANSI B1 .l, "Unified Screw Threads," Class 2, except that Class 3 fit shall be used in holes .t City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15092 - Miscellaneous Couplings, Pipe and Appurtenances - 1 of 2 tapped for studs. Threads may be made by either cutting or cold forming. Between 1/4-inch and 3/8-inch shall project through the nut when drawn tight. Washers shall be provided for each nut and shall be the same material as each nut. All buried flanges, including bolts, nuts and washers, shall be encased in wax tape per Section 09902. __ All bolt threads shall be lubricated with non-oxide grease. Flanged faces shall be wire brushed and cleaned prior to joining each flange. 2.2 Wax Tape Encasement Unless otherwise specified on the Plans, all couplings and appurtenances for underground installation shall be encased in wax tape per Section 09902. 2.3 Paintina and Coatinq All miscellaneous couplings, pipe and appurtenances referenced in this section shall be painted and coated, interior and exterior, in accordance with Section 09900, Painting and Coating. 2.4 Flexible Couplings Joints for which flexible couplings are required, shall be made with Baker, Smith-Blair, or approved equal, flexible couplings. Gaskets shall be plain rubber gaskets. Threads on bolts or compression collars shall be lubricated with non-oxide grease before assembling the coupling. For cast-iron, ductile-iron or asbestos cement pipe sizes 2-inches through 16-inches, use Baker Series 228, Smith-Blair Series 41 3, or approved equal. - Transition couplings shall be Baker Series 21 2, Smith-Blair Series 41 3, or approved equal. Flanged coupling adapters for cast iron or ductile iron pipe sizes 3-inches through 12-inches shall be Baker Series 601, Smith-Blair Series 912, or approved equal. Flanged coupling adaptors for cast or ductile iron pipe greater than 12-inches shall be Baker Series 602 or Smith- Blair Series 91 3. Flanged coupling adapters for steel pipe sizes 3-inches through 24-inches shall be Baker Series 602, Smith-Blair Series 91 3, or approved equal. 2.5 Pipe Unions Screw unions may be employed on pipelines 2-1/2-inches in diameter and smaller. Pipes and fittings made of non-ferrous metals shall be isolated from ferrous metals by nylon insulating pipe bushings, unions or couplings manufactured by Smith-Blair, Pipe Seal and Insulator Co. or approved equal. PART 3 - EXECUTION (Not Applicable) City of Carlsbad 03/04 (DBE) END OF SECTION ECR (PAR to Cassia) Domestic 8, Recycled Water Transmission Mains 15092 - Miscellaneous Couplings, Pipe and Appurtenances - 2 of 2 SECTION 151 00 VALVES PART 1 - GENERAL 1.1 Description This section includes materials, testing, and installation of manually operated valves, check valves, air and vacuum valves, air-release valves, and combination air-release valves. 1.2 Related Work Described Elsewhere The Contractor shall refer to the following Specification section(s) for additional requirements: A. Shop Drawing Submittals: 01300 B. Painting and Coating: 09900 C. Petrolatum Wax Tape Coating: 09902 D. Testing, Flushing and Disinfection: 15040 1.3 Submittals Contractor shall furnish submittals in accordance with the requirements of Section 01 300, Shop Drawing Submittals. The following submittals are required: c. A. Submit Shop Drawings, manufacturer's catalog data and detail construction sheets showing all valve parts and describing material of construction by material and specification (such as AISI, ASTM, SAE, or CDA). Submittal shall include valve dimensions including laying lengths, dimensions and orientation of valve operators, as installed on the valves. Submittals shall also indicate valve linings and coatings with manufacturer's and paint numbers listed. B. For valves requiring certified tests, submit certified test results. 1.4 Pavment Payment for the Work in this section shall be included as part of the lump-sum or unit-price bid amount for which such Work is appurtenant thereto. PART 2 - MATERIALS 2.1 General All valves shall be new and of current manufacture. Valves shall be furnished and installed by the Contractor at the location and in accordance with the type of ends as shown on the Plans and as herein specified. Valves shall be provided with stem extension if depth of valve nut exceeds 5-feet. Valve extensions shall be pinned to the valve operating nut. - City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15100 -Valves - 1 of 6 The manufacturer shall have manufactured tight-closing valves of the valve type intended for use for a period of at least five years. The Contractor shall furnish and install each specific type of valve from a single manufacturer and use it throughout the Work. All valves shall have a rated working pressure of at least 150 psi. All valves shall be certified to meet the test pressure as specified and shall have a rated working pressure that exceeds the full working pressure specified. - A. B. C. D. Connections: Valves shall have flanged, hub, screwed, or special connector ends as shown on the Plans. Where not indicated, the valves shall have the same type of connection as the pipeline in which valves are to be installed and conform to the Specifications. Bolts, Nuts and Washers: Bolts, nuts and washers for aboveground and buried installations shall be cadmium plated and shall conform to ASTM A307, Grade B, "Steel Machine Bolts and Nuts and Tap Holes," when a ring gasket is used, bolts, nuts, and washers shall conform to either ASTM A261, "Heat-Treated Carbon Steel Bolting Material" or ASTM A1 93, "Alloy-Steel Bolting Material for High Temperature Service". Bolts and nuts shall be heavy hexagon series. Nuts shall conform to ASTM A194, "Carbon and Alloy Steel Nuts for Bolts for High Pressure and High Temperature Service" either in Grade 1,2, or 2H. The fit shall be ANSI B1.l, "Unified Screw Threads," Class 2, except that Class 3 fit shall be used in holes tapped for studs. Threads may be made by either cutting or cold forming. Between 1/4-inch and 3/8-inch shall project through the nut when drawn tight. -. Bolts, nuts and washers for underground installations including below ground structures shall be type 316 stainless steel. All buried bolts shall be completely coated with non-oxide grease, or approved equal. All aboveground bolt threads shall be lubricated with graphite and oil. Flanged faces shall be wire brushed and cleaned prior to joining each flange. Polyethylene Encasement: Unless otherwise specified on the Plans, all valves for underground installation shall be encased in two layers of 8 mil polyethylene wrap in accordance with AWWA C105. Painting and Coating: All valves referenced in this section shall be painted and coated, interior and exterior, in accordance with Section 09900, Painting and Coating. 2.2 Combination Air Valves Air and vacuum release valves shall be of the combination type. The combination unit shall serve the function of allowing air to enter or exit the pipe to alleviate excess air or vacuum conditions in the pipe. The inlet/outlet vent shall have a 20 mesh stainless steel screen secured with stainless steel band. The tap for the valve shall be made in a level section of pipe no closer - City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15100 -Valves - 2 of 6 than 18-inches to a bell, coupling, joint, or fitting. No tap shall be permitted in any machined - section of A.C.P. The Buna-N seat must be fastened to the valve cover, without distortion, for drip-tight shutoff. The floats shall be heavy stainless steel, hermetically sealed; designed to withstand 1,000 psi. The top plug or float shall be center guided through hex bushings for positive shutoff. All materials of construction shall be in writing to conform to ASTM Specifications as follows: Body & Cover Cast Iron ASTM A126 GR.B Float Stainless Steel ASTM A240 Needle & Seat Buna-N Plug Bronze ASTM B1 24 Leverage Frame DeIrin/Cast Iron ASTM D2133/ASTM A1 26 GR.B A. Approved Manufacturer and Model: Combination air valves shall be APCO Models 143C, 145C, 147C, 149C, 150C, ,151 C, or approved equal. 2.3 Butterflv Valves All butterfly valves shall be of the tight-closing, rubber-seat type, with rubber seats which are recess mounted and securely fastened to the valve body and in full compliance with AWWA C504. Valves shall be bubble tight at rated pressures and shall be satisfactory for applications involving valve operation after long periods of inactivity. Valve discs shall rotate 90 degrees from the full open position to the tight shut position. Valves shall meet the full structural requirements of the applicable classes of AWWA C504. Valve bodies shall be constructed of cast-iron ASTM A1 26, Class B unless otherwise specified on the Plans. Flange drilling shall be in accordance with ANSI B 16.1 standard for cast-iron flanges. Two trunnions for shaft bearings shall be integral with each valve body. Body thickness shall be strictly in accordance with AWWA C504. All valve discs shall be constructed of Ni-Resist Type I or high-strength cast iron in accordance with ASTM A48, Class 40. All disc seating edges shall be smooth and polished. Shafts of all valves shall be turned, ground, and polished. Valve shafts shall be constructed of 18-8, Type 304 stainless steel. Valve seats shall be of a continuous natural rubber or a synthetic rubber compound mounted on the body and a stainless steel seat mounted on the disc. Bonded-in seats must be simultaneously molded-in, vulcanized, and bonded to the body and the seat bond must withstand 75-pound pull under test pressure in accordance with ASTM D429, Method B, or seats may be mechanically retained on the disc by 18-8 Type 304 fasteners. Valve seats on valves 24-inches and larger shall be field adjustable and replaceable without dismantling operator, disc, or shaft and without removing the valve from the line. Valves employing a complete rubber liner will not be acceptable in any size. Each valve shall be provided with one or more thrust bearings in accordance with AWWA C504. Thrust bearings which utilize a ferrous metal bearing surface in direct rubbing contact with an opposing ferrous metal surface will not be acceptable. @-- City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15100 -Valves - 3 of 6 Valves shall be fitted with sleeve-type bearings. Bearings shall be corrosion resistant and self-lubricating. Bearing load shall not exceed 2,500 psi. - The use of a stop or lug cast integrally with or mechanically secured to the body for the purpose of limiting disc travel by means of direct contact or interference with the valve disc in either the open or closed position will not be acceptable. Valve operators shall be designed to hold the valve in any intermediate position between fully opened and fully closed without creeping or fluttering. For buried service operation, valve operators shall be of the enclosed gear or screwed rod type. Valve shall open with a counterclockwise rotation of the operator. A. Approved Manufacturer and Model: Butterfly valves shall be Henry Pratt Company Groundhog for buried service, M & H Model 4500, or approved equal. Manual operator shall be Pratt MDT or approved equal. Ductile iron body butterfly valves shall be DeZurik BAW with M-Series handwheel actuator or approved equal. 2.4 The flanges of valves shall be flat faced per AWWA C207-86. Flanges of valves designed for a working pressure of 200 psi or less shall be faced and drilled to a 125-pound American Standard dimension. Flanges of all valves designed for a working pressure of greater than 200 psi shall be faced and drilled to 250-pound American Standard dimensions. Gate Valves and Tapping Valves .-_ Each valve body shall be tested under a test pressure equal to twice its design water working pressure, in accordance with AWWA (2509-87. All interior parts of valves manufactured of bronze or brass, except valve stems, shall conform to the requirements of ASTM 862. Gate valve stems shall be Everdur 1012, NiVee, or Silnic, having a minimum tensile strength of 70,000 psi, a yield strength of 40,000 psi, and elongation of at least 15 percent in 2-inches. The stem is to be visibly marked so that it meets this requirement . All valves connecting to mains shall be flanged on the main side, unless otherwise specified. A. Gate Valves: Gate valves shall conform to AWWA C509-87. Gate Valves shall be designed for a water working pressure of 200 psi and shall be iron bodied, resilient seated, non-rising stem opening to the left, and provided with O-ring stem seal, and a 2-inch square operating nut for buried service and handwheel for above ground service. All interior parts of gate valves, not including valve stems, shall be constructed of bronze conforming to the requirements of ASTM B62. After the valves are assembled and tested, the manufacturer's name or symbol, the size of the valve, the year of manufacture, and the working water pressure shall be cast in the bonnet City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15100 -Valves - 4 of 6 or body of the valve. Gate valves shall be furnished with ends as specified on the Plans or by the Owner’s Representative. .- B. Approved Manufacturer and Model: Gate valves shall be American Flow Control, American AVK, or approved equal. C. Tapping Valves and Sleeves: Tapping valves shall conform to and be tested in accordance with AWWA C500 with the exception of the ends and the seat rings. The valves shall be designed for 150 psi water working pressure, and shall be iron bodied, bottom wedging, ABlP double-disc with parallel seats, opening to the left, provided with a 2-inch square operating nut, non-rising stem, and O-ring stem seal. The ends shall be flanged. The flange on one end shall have slotted bolt holes to fit all standard tapping machines. Seat rings shall be oversized to permit the use of full- size cutters. The cast-iron tapping sleeves may be provided with mechanical joints. D. Approved Manufacturer and Model: The tapping valve and sleeve shall be Mueller H-600 Series for AC pipe, Romac SST with stainless steel flange or Ford ‘Fast’ with stainless steel flange. For PVC pipe, the tapping valve shall be American Flow Control, American AVK, or approved equal. 2.5 Miscellaneous Valves A. Corporation Stops: Corporation stops shall be manufactured of bronze conforming to ASTM B62. Use Ford FB700, Jones J1929, Mueller B2505 or approved equal. The inlet fitting shall be a male iron pipe thread when used with a saddle and the outlet connection shall be a flare type unless otherwise specified. B. Angle Valves: Angle valves shall be all brass valves of the sizes shown on the Plans and shall be, FordBA23-444W, FV23-777W, Jones J1964W, J1973W, or Mueller B- 24255, or approved equal. 2” ball valves should not be used on manual air release or blow-off applications. PART 3 - EXECUTION 3.1 Installation A. Flanges shall be cleaned by wire brushing before installing flanged valves. Flange bolts and nuts shall be cleaned by wire brushing, and threads coated with non-oxide grease after tightening nuts and bolts. Flange to be double wrapped with 8 MIL polyethylene film. Nuts shall be tightened uniformly and progressively. If flanges leak under pressure testing, nuts and bolts shall be loosened or removed, the gasket reseated or replaced, the bolts and nuts reinstalled or retightened, and joints retested. Joints shall be watertight. B. Threaded joints shall be cleaned by wire brushing or swabbing. Teflon joint compound or Teflon tape shall be applied to pipe threads before installing threaded valves. Joints shall be watertight. City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 15100 -Valves - 5 of 6 3.2. Valve Pressure Testing Valves shall be tested at the same time that the connecting pipelines are pressure tested and in accordance with Section 15040, Testing, Flushing and Disinfection. Any parts of valves, operators, or control and instrumentation systems whose pressure rating is less than the test pressure shall be isolated and protected. -Lc END OF SECTION City of Carlsbad 03/04 (DBE) ECR (PAR to Cassia) Domestic & Recycled Water Transmission Mains 151 00 - Valves: - 6 of 6