Loading...
HomeMy WebLinkAbout1991-06-04; Municipal Water District; 107; Contract for Jefferson Street Water LineCARLSBAD Ml VCIPAL WATER DISTRICT - AGENDA BILL +‘- (;\ & ./. ,,- AB # /R 7 TITLE: AWARDING THE CONTRACT FOR MTG. b-+ci / CONSTRUCTION OF THE JEFFERSON STREET DEPT. ENG. WATER LINE PROJECT IN THE CITY OF CARLSBAD - CMWD PROJECT NO. 89-101 DEPT. HO. F RECOMMENDED ACTION: Adopt Resolution No. 737 for acceptance, execution and award of contract for The Construction of the Jefferson Street Water Line Project in the City of Carlsbad, CMWD Project No. 89-101. ITEM EXPLANATION: The project will involve replacing of older, substandard water mains in Jefferson Street from Grand Avenue to Laguna Drive and from Buena Vista Way to the I-5 bridge; also in Arbuckle Place, Home and Hope Avenues. Water system reliability, domestic water distribution, and fire flow capability will be improved to meet City/District Standards by awarding this contract. Construction traffic control will be in conformance with City approved traffic control plans. Plans and specifications for discussed project were prepared by the District engineering staff. In accordance with section 3.28.A.20 of the Municipal Code, Notice to Bidders was published. Thirteen responses were received, opened, witnessed and recorded on May 15, 1991. The lowest responsive bidder for the contract was Sun Valley Construction Co., Inc., 13675 Highway 8 Business, El Cajon, California 92021 for $254;244.01. FISCAL IMPACT: Funds in the amount of $500,000 have been appropriated in the 1990-1991 budget for water main yreplacement projects in the downtown area. The engineer's cost estimate for this project was $375,656. Therefore, there are sufficient funds available for this project. EXHIBITS: 1. Location map. 2. Tabulation of Bids - Exhibit tlA1'. 3. Agreement for the Construction of the Jefferson Street Water Line Project in the City of Carlsbad, CMWD 89-101 - Exhibit ltBtr. 4. Resolution No. 737 for acceptance and execution of the agreement for the Construction of the Jefferson Street Water Line Project in the City of Carlsbad, CMWD 89-101. a-.. . I . I L~CATIO~I MAP 1 713 SbN DIEGO PROJECT NAME: PROJECTN3. EXHISIT NO. JEFFERSON STREET PROJECT 89-101 1 c . , EXHIBIT "A" TABULATION OF BIDS CONSTRUCTION OF JEFFERSON STREET WATER LINE PROJECT IN THE CITY OF CARLSBAD CMWD PROJECT NO. 89-101 ENGINEER'S ESTIMATE $375.656.00 BIDDER TOTAL AMOUNT 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Sun Valley Construction Co., Inc. 13675 Highway 8 Business El Cajon, CA 92021 Trenchers West Construction Co., Inc. 1240 Logan, #M Costa Mesa, CA 92626 Gary J. Herman, Inc. 2601 S. Yale Street Santa Ana, CA 92704 Valverde Construction, Inc. 1202 Philadelphia Street Whittier, CA 90601 Dietrich Corp. 1243 Greenfield Dr., #H El Cajon, CA 92021 H.S. Excel Corp. 221 Pawnee Street, Ste. 103 San Marcos, CA 92069 Engineering Enterprises & Construction 8924 White Oak Avenue Northridge, CA 91375 Falcon General Engineering 572 Collyn Street Vista, CA 92083 Don Hubbard Contracting Co. P.O. Box 577 Encinitas, CA 92024 Drainage Construction Co., Inc. 1505 Sycamore Avenue Vista, CA 92083 Miramontes Construction Co., Inc. P.O. Box 90095 City of Carlsbad, CA 91715-0095 $254,244.01 $279,829.00 $292,376.29 $295,615.00 $307,498.00 $307,624.00 $310,980.80 $334,191.00 $337,768.90 $342,346.00 $344,610.00 c . Exhibit "A'* - Jefferson Street Water Line Project Tabulation of Bids - Page 2 12. Lacy Construction Co. P.O. Box 2079 Escondido, CA 92033 13. Duarte 61 Baum, Inc. P.O. Box 9005, #505 La Mesa, CA 91944 $351,208.00 $367,571.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 I.8 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO. 737 A RESOLUTION OF THE BOARD OF DIRECTORS OF THE CARLSBAD MUNICIPAL WATER DISTRICT FOR ACCEPTING A BID AND AUTHORIZING THE EXECUTION OF AN AGREEMENT FOR THE CONSTRUCTION OF THE JEFFERSON STREET WATER LINE PROJECT IN THE CITY OF CARLSBAD, CMWD PROJECT NO. 89-101 WHEREAS, the Board of Directors of the Carlsbad Municipal Water District of Carlsbad, California, as follows: 1. That the bid of Sun Valley Construction Co, Inc., 13675 Highway 8 Business, El Cajon, California 92021, in the amount of $254,244.01 is hereby accepted. 2. That the President of the Board of Directors of the Carlsbad Municipal Water District is hereby‘authorized and directed to execute an agreement, a copy of which is attached hereto marked Exhibit lrBtr for and on behalf of the Carlsbad Municipal Water District. PASSED, APPROVED AND ADOPTED, at a regular meeting of the Carlsbad Municipal Water District held on the 4th day of June I 1991, by the following vote to wit: AYES: Board Members Lewis, Kulchin, Larson, and Nygaard NOES: None ABSENT: Board Member Stanton ATTEST: ALETHA L. RAUTENKRANZ, Seer (SEAL) CMWD 89-101 1 .a. ” SECTION 00530 - AGREEREFIT THIS AGREEMENT, made and entered into this day of 1991, by and between CARLSBAD mEAL WATER DISTRICT, hereinafter referred to as '@Districttt and SUN VALLEY CONSTRUCTION CO., INC., hereinafter referred to as Contractor." WITNESSETH: 1. 2. 3. 4. 5. Contractor shall, under the direction and to the satisfaction of District, furnish all labor, materials, equipment, transportation and services for: CONSTRUCTION OF THE JEFFERSON STREET WATERLINE PROJECT IN TEE CITY OF CARLSBAD. in the principal sum of $254.244.0X in accordance with the plans and contract specifications documents, all of which are incorporated herein by reference and made a part hereof. Contractor shall pay to any laborer, mechanic or apprentice employed, the prevailing rate of hourly wages and rates for legal holidays, overtime work, .and standard apprentice wages as set forth in the Advertisement for Bids and keep adequate records thereof. Contractor shall, accordingly, pay as a penalty to the District the sum of up to One Hundred Dollars ($100.00) for each calendar day or portion thereof for each workman paid less than the prevailing and standard wage under this contract, by Contractor and/or any sub- contractor. Contractor shall commence construction within ten (10) calendar days from receipt of Notice to Proceed and pursue said work in a diligent and workmanlike manner without interruption and complete construction thereof within ninety (90) calendar days as noted in the Notice to Proceed. District agrees to pay and Contractor agrees to accept proportionate payments as Work progresses according to specification, subject to additions and deductions provided therein, all in accordance ,with the applicable provisions of Standard Specifications for Public Works Construction which sums shall be computed for the prices set forth in the bid submitted by the Contractor. The Contractor will commence the work required hereunder when required by the Notice to Proceed, and shall complete the work within the following times thereafter: Ninety (90) Calendar Days -l- 4 The Contractor agrees to pay as liquidated damages, the sum noted in Paragraph SP 6-9 in Section 00800 of these specifications, after the stipulated completion date(s) that the work remains uncompleted. 6. This agreement shall be binding upon all Parties hereto and their respective heirs, executors, administrators, successors, and assigns, but shall not be assigned by either Party without the express written consent of the other. IN WITNESS WHEREOF, the parties hereto have hereunto set their hands and seals the day and year first hereinabove written. CARLSBAD MUNICIPAL WATER DISTRICT BY ATTEST: CLAUDE A. LEWIS, JR., PRESIDENT BOARD OF DIRECTORS CARLSBAD MUNICIPAL WATER DISTRICT , SECRETARY OF THE BOARD OF DIRECTORS CARLSBAD MUNICIPAL WATER.DISTRICT - BY ALETHA L. RAUTENKRANZ SUN VALLEY CONSTRUCTION CO.. INC . CONTRACTOR 13675 Hiahwav 8 Business ADDRESS . . El Caion. California 92021 (619-443-15$& TELEPHONE APPROVED AS TO FORM BY LEGAL COUNSEL BY STEVEN L. VARGAS Title President BY Title (SEAL)