Loading...
HomeMy WebLinkAbout2014-11-18; Municipal Water District; 792; Tri-Cities Agencies Water Transmission PipelineCARLSBAD MUNICIPAL WATER DISTRICT -AGENDA BILL 10 AB# MTG. DEPT. 792 11-18-14 PW-UTIL ADOPTION OF RESOLUTION REJECTING ALL BIDS AND AUTHORIZING THE SECRETARY TO THE BOARD TO RE-ADVERTISE FOR BIDS FOR THE TRI- AGENCIES WATER TRANSMISSION PIPELINE, REACH 2, PHASE 1, LOCATED ON PIRGOS WAY, PROJECT NO. 5008 DEPT. DIRECTOR GEN. COUNSEL CITY MGR. RECOMMENDED AaiON: Adopt Resolution No. 1506 rejecting all bids and authorizing the Secretary to the Board to re- advertise for bids for the Tri-Agencies Water Transmission Pipeline, Reach 2, Phase 1, located on Pirgos Way, Project No. 5008. ITEM EXPLANATION: The Tri-Agencies Water Transmission Pipeline was constructed by the San Diego County Water Authority (SDCWA) in 1978 to supply treated imported water to three agencies including Carlsbad Municipal Water District (CMWD). Reach 2 ofthe Tri-Agencies Transmission Pipeline only serves water to CMWD and was subsequently quitclaimed by the SDCWA to CMWD in 1982. It is one of four major transmission pipelines supplying imported water to CMWD, and is therefore, a critical water supply pipeline. Reach 2 is 21-inches in diameter and begins at the SDCWA's meter vault referred to as "CMWD No. 4 Service Connection" which is located near the intersection of Cannon Road and Wisteria Drive in the City of Oceanside. Reach 2 proceeds westerly terminating near the intersection of College Boulevard and Carlsbad Village Drive in the Calavera Hills area ofthe City of Carlsbad. There have been numerous leaks on Reach 2 caused by severely corroded and partially disintegrated bell and spigot joints. A report prepared on Reach 2 titled "Tri-Agencies Pipeline Alternatives Investigation" provided information on various options to address the pipeline condition. Based on findings in the report, staff has determined that Reach 2 can be downsized to an 18-inch diameter pipeline due to the construction of new water transmission mains on College Boulevard and Cannon Road. The report recommends replacing the water transmission pipeline in two separate construction phases. Phase I ofthe pipeline replacement extends from the "CMWD No. 4 Service Connection" westerly along Pirgos Way to the City limits of Carlsbad, a length of approximately 1,820 feet (refer to Exhibit 1). The Phase I project will also require the replacement of the existing pressure sustaining facility containing control valves designed to sustain the upstream pressure to the meter located at the SDCWA's "CMWD No. 4 Service Connection". The control valves will be installed in a new below grade concrete vault. Phase 2 extends from the west terminus of the Phase 1 project to College Boulevard. DEPARTMENT CONTACT: David Ahles at 760-602-2748 or email david.ahles(5)carlsbadca.gov FOR SECRETARY USE. BOARD ACTION: APPROVED CONTINUED TO DATE SPECIFIC • DENIED • CONTINUED TO DATE UNKNOWN • CONTINUED • RETURNED TO STAFF • WITHDRAWN • OTHER - SEE MINUTES • AMENDED • REPORT RECEIVED • Project No. 5008 November 18, 2014 Page 2 of 3 On August 26, 2014, the Carlsbad Municipal Water District Board of Directors adopted Resolution No. 1498 which approved the plans and specifications and authorized the advertisement for bids for the construction of the Tri-Agencies Water Transmission Pipeline, Reach 2, Phase 1, Project No. 5008. The Engineer's Estimate for the project was $900,000. On October 15, 2014 the Utilities Department received four (4) sealed bids as follows: CONTRACTOR NAME TOTAL BID AMOUNT 1. GRFCO. $1,178,450 2. Metro Builders & Engineers $1,270,144 3. J.R. Filanc $1,465,475 4. Palm Engineering Construction $1,497,040 The four bids received were significantly above the Engineers Estimate. Staff will be reviewing the plans and specifications, to determine whether any cost savings can be achieved. Following this review, staff recommends re-bidding the Tri-Agencies Water Transmission Pipeline Reach 2, Phase 1, Project No. 5008, to provide an opportunity to receive lower bids. FISCAL IMPACT: An Engineer's Estimate of the construction cost of Tri-Agencies Water Transmission Pipeline, Reach 2, Phase 1, Project No. 5008 was prepared by Black & Veatch Corporation and totals $900,000. Reach 2, Phase 1, is part of the larger capital improvement project Tri-Agencies Water Transmission Pipeline, Project No. 5008. As shown in Table 1 the current project appropriation for Tri-Agencies Water Transmission Pipeline, Project No. 5008 is $6,455,000 from the Water Replacement Fund. TABLE 1 - PROJECT CONSTRUCTION COST ESTIMATE Tri-Agencies Water Transmission Pipeline, Project No. 5008 ESTIMATED COSTS Construction Contract (Engineer's Estimate) $900,000 Construction Contingency $100,000 Construction Management, Inspection, and Material Testing $100,000 TOTAL ESTIMATED CONSTRUCTION COSTS (Phase 1) $1,100,000 Current Appropriation - Tri-Agencies Pipeline, CIP No. 5008 $6,455,000 Current Expenditures/Encumbrances, CIP No. 5008 (Environmental/Design) $355,000 TOTAL AVAILABLE TRI-AGENCIES PIPELINE PROGRAM, CIP NO. 5008 $6,100,000 ADDITIONAL APPROPRIATION ANTICIPATED FOR CONSTRUCTION None Sufficient funds have been appropriated from the Water Fund for this project. Project No. 5008 November 18, 2014 Page 3 of 3 ENVIRONMENTAL IMPACT: The project was previously evaluated in the Final Program Environmental Impact Report (EIR), dated October 2012, for the City of Carlsbad Sewer Master Plan and the Carlsbad Municipal Water District (CMWD) Water and Recycled Water Master Plan Updates (EIR 12-01). The EIR evaluated the potential environmental effects of the project components described in the CMWD 2012 Water Master Plan Update. This project (Phase I ofthe Water Supply and Transmission Project No. 48) is within the scope of the Final Program EIR 12-01 and no further California Environmental Quality Act (CEQA) compliance is required. PUBLIC NOTIFICATION None required. EXHIBITS: 1. Resolution No. 1506 rejecting all bids and authorizing the Secretary to the Board to re- advertise for bids for the Tri-Agencies Water Transmission Pipeline, Reach 2, Phase 1, located on Pirgos Way, Project No. 5008. 2. Location Map Exhibit 1 1 RESOLUTION NO. 1506 3 2 A RESOLUTION OF THE BOARD OF DIRECTORS OF CARLSBAD MUNICIPAL WATER DISTRICT (CMWD), REJECTING ALL BIDS AND AUTHORIZING THE SECRETARY OF THE BOARD TO RE-ADVERTISE 4 FOR BIDS FOR THE TRI-AGENCIES WATER TRANSMISSION PIPELINE, REACH 2, PHASE 1, LOCATED ON PIRGOS WAY, 5 PROJECT NO. 5008 6 y WHEREAS, the Board of Directors of the Carlsbad Municipal Water District, California 8 has determined it necessary, desirable, and in the public interest to replace the existing 21-inch 9 Tri-Agencies Water Transmission Pipeline with a new 18-inch steel water pipeline and; 10 WHEREAS, on August 26, 2014, the Board of Directors of the Carlsbad Municipal Water ^ ^ District, California adopted Resolution No. 1498, which approved the plans for the construction 12 ofthe Tri-Agencies Water Transmission Pipeline, Project No. 5008; and 13 WHEREAS, an environmental impact assessment was conducted for the Tri-Agencies 14 1^ Pipeline Project, and a Program EIR was approved by the Board through Resolution No. 2012- 16 245, on November 13, 2012; and 17 WHEREAS, four sealed bids were received on October 15, 2014 by the Carlsbad 1^ Municipal Water District for the construction of the Tri-Agencies Water Transmission Pipeline, Project No. 5008; and WHEREAS, the Board of Directors of the Carlsbad Municipal Water District, California, has determined it necessary, desirable, and in the public interest to reject all bids in accordance with California Public Contracts Code, Section 22038, and the Municipal Code Section 3.28.080 19 20 21 22 23 24 and to seek new bids for the Tri-Agencies Water Transmission Pipeline, Project No. 5008; and 25 WHEREAS, the Engineer's estimate for the project cost is $900,000; and WHEREAS, there are sufficient funds available in the Water Replacement Fund to 27 complete the project; and 28 " 1 WHEREAS, under the operating agreement with the City of Carlsbad, Carlsbad Municipal ^ Water District adopted the city's purchasing rules; and NOW, THEREFORE, BE IT RESOLVED by the Carlsbad Municipal Water District Board of the City of Carlsbad, California, as follows: 1. That the above recitations are true and correct. 2. That the four bids submitted for the Tri-Agencies Water Transmission Pipeline, Reach 2, Phase 1, Project No. 5008 are hereby rejected. 3 4 5 6 7 8 9 3. The Secretary to the Board is hereby authorized and directed to publish, in 10 accordance with State law, a Notice to Contractors Inviting Bids for the construction of the Tri- 11 Agencies Water Transmission Pipeline, Reach 2, Phasel, Project No. 5008, in accordance with 12 the plans, specifications, and contract documents referred to herein. 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 // // // // // // // // // // // // // // 6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 PASSED, APPROVED AND ADOPTED at a Special Meeting of the Board of Directors of the Carlsbad Municipal Water District of the City of Carlsbad on the 18th day of November 2014, by the following vote to wit: AYES: NOES: ABSENT: Board Members Hall, Packard, Wood, Schumacher, Blackburn. None. None. MATT HALL, President ATTEST: BARBARA ENGLESON, See'retary till li i LOCATION MAP NOT TO SCALE REACH 2 PHASE 1 an or OCEANSIOC HWHWAY • VICINITY I MAP MOT TO SCAU PROJECT SITE PROJECT NAME TRI-AGENCIES WATER TRANSMISSION PIPELINE REACH 2, PHASE 1 PLOnO) BYi SCOTT EVAHS PLOT DAJE:4/I5/13 PAIHilkMimnes nEP/WTMENTUOMJlW MV>S\90t«Olie PROJECT NUMBER 5005 EXHIBIT