HomeMy WebLinkAbout2015-01-27; Municipal Water District; 800; Recycled Water Phase III Pipeline ExpansionCARLSBAD MUNICIPAL WATER DISTRICT-AGENDA BILL 11 AB# 800 DATE 01-27-15 DEPT. PW-UTIL ADOPTION OF RESOLUTION APPROVING THE PLANS AND SPECIFICATIONS AND AUTHORIZING THE SECRETARY TO THE BOARD TO ADVERTISE FOR BIDS FORTHE RECYCLED WATER PHASE III PIPEUNE EXPANSION SEGMENT lA & 7, PROJECT NO. 5208 DEPT. DIRECTOR GEN. COUNSEL CITY MGR. RECOMMENDED AaiON: Adopt Resolution No. 1515 approving the plans and specifications and authorizing the Secretary to the Board to advertise for bids for the Recycled Water Phase III Pipeline Expansion Segment lA and 7, located within the Palomar Airport Business Park, The Villas of Calaveras Hills Home Owners Association and Hope Elementary School Site, Project No. 5208. ITEM EXPLANATION: Pipeline Expansion Segments lA and 7 are part ofthe Phase HI Recycled Water Project. These two pipeline segments are being constructed separately as part ofthe region's Round 3 Proposition 84 IRWM Grant. Pipeline Expansion Segment No. lA is located within the Palomar Airport Business Park along Las Palmas Rive, Corte Del Nogal, Corte Del Abeto, Yarrow Drive, Corte De La Pina, Corte Del Cedro, and Cosmos Court. Pipeline Expansion Segment No. 7 is located within The Villas of Calaveras Hills Home Owners Association and Hope Elementary School Site along Carlsbad Village Drive, Tamarack Avenue and Chatham Road. This project includes the construction of approximately 4,150 linear feet of 8-inch diameter, 6,600 linear feet of 6-inch diameter, and 3,400 linear feet of 4-inch diameter polyvinyl chloride (PVC) pipeline and 58 recycled water services. Recycled water in these pipeline segments will be used for landscape irrigation. Staff recommends approving the plans and specifications and authorizing the Secretary to the Board to advertise for bids for the construction of Recycled Water Phase 111 Pipeline Expansion Segment lA and 7, Project No. 5208. DEPARTMENT CONTACT: David Ahles at 760-602-2748 or by email davidahles@carlsbadca.gov FOR SECRETARY USE. BOARD ACTION: APPROVED CONTINUED TO DATE SPECIFIC • DENIED • CONTINUED TO DATE UNKNOWN • CONTINUED • RETURNED TO STAFF • WITHDRAWN • OTHER - SEE MINUTES • AMENDED • REPORT RECEIVED • Recycled Water Phase I January 27, 2015 Page 2 of 2 FISCAL IMPACT: An Engineer's Estimate of the construction cost of Recycled Water Phase 111 Pipeline Expansion Segment lA and 7, Project No. 5208 was prepared and totals $2,900,000. The project's construction contract will be with CMWD. A summary of estimated construction costs and available funds is shown in Table 1. TABLE 1 - PROJECT CONSTRUCTION COST ESTIMATE Recycled Water Phase III Pipeline Expansion Segment 18, Project No. 5208 \ ESTIMATED COSTS Construction Contract (Engineer's Estimate) $2,900,000 Construction Contingency $250,000 Construction Management, Inspection, and Material Testing $250,000 TOTAL ESTIMATED CONSTRUCTION COSTS (Segment 18) $3,400,000 Current Appropriation-Phase III Pipelines, CIP No. 5208 $10,000,000 Current Expenditures/Encumbrances-Phase III Pipelines, CIP No. 5208 $280,000 TOTAL AVAILABLE PHASE 111 PIPELINE PROGRAM, CIP NO. 5208 $9,720,000 ADDITIONAL APPROPRIATION ANTICIPATED FOR CONSTRUCTION None Sufficient funds have been appropriated from the Recycled Water Fund to fund this project. ENVIRONMENTAL IMPACT: An environmental impact assessment was conducted for the Phase 111 Recycled Water Project, and a Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program was approved by the Board through Resolution No. 1455, on November 27, 2012. PUBLIC NOTIFICATION: None required. EXHIBITS: 1. Resolution No. 1515 approving the plans and specifications and authorizing the Secretary ofthe Board to advertise for bids for the Recycled Water Phase III Pipeline Expansion Segment lA and 7, located within the Palomar Airport Business Park, The Villas of Calaveras Hills Home Owners Association and Hope Elementary School Site, Project No. 5208. 2. Location Map. 1 RESOLUTION NO. 1515 2 A RESOLUTION OF THE BOARD OF DIRECTORS OF CARLSBAD MUNICIPAL WATER DISTRICT (CMWD), APPROVING THE PLANS ^ AND SPECIFICATIONS AND AUTHORIZING THE SECRETARY OF 4 THE BOARD TO ADVERTISE FOR BIDS FOR RECYCLED WATER PHASE 111 PIPELINE EXPANSION SEGMENT lA AND 7, LOCATED 5 WITHIN THE PALOMAR BUSINESS PARK, THE VILLAS OF CALAVERAS HILL HOME OWNERS ASSOCIATION AND HOPE ^ ELEMENTARY SCHOOL SITE, PROJECT NO. 5208 7 10 11 12 13 14 15 16 8 WHEREAS, the Board of Directors of the Carlsbad Municipal Water District, California 9 has determined it necessary, desirable, and in the public interest to install approximately 4,150 linear feet of 8-inch diameter, 6,600 linear feet of 6-inch diameter, and 3,400 linear feet of 4- inch diameter polyvinyl chloride (PVC) pipeline and 58 recycled water services.; and WHEREAS, the plans and specifications for furnishing of all labor, materials, tools, equipment, transportation, and other expenses necessary or incidental of said project have been prepared and are on file in the Utilities Department of the City of Carlsbad and are incorporated by reference herein; and WHEREAS, an environmental impact assessment was conducted for the Phase III 18 Recycled Water Project, and a Mitigated Negative Declaration and Mitigation Monitoring and 19 Reporting Program was approved by the Board through Resolution No. 1455, on November 27, 2012;and WHEREAS, the Engineer's estimate for the project cost is $2,900,000; and WHEREAS, sufficient funds exist in the Recycled Water Fund. NOW, THEREFORE, BE IT RESOLVED by the Carlsbad Municipal Water District Board of the City of Carlsbad, California, as follows: 1. That the above recitations are true and correct. 20 21 22 23 24 25 26 27 28 3 1 2. That the plans, specifications and contract documents for the Recycled Water Phase 2 III Pipeline Expansion Segment lA and 7, Project No. 5208 are on file in the Utilities Department 3 of the City of Carlsbad and are hereby approved. 4 3. The Secretary to the Board is hereby authorized and directed to publish, in ^ accordance with State law, a Notice to Contractors Inviting Bids for the construction of the Recycled Water Phase III Pipeline Expansion Segment lA and 7, Project No. 5208, in accordance with the plans, specifications, and contract documents referred to herein. 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 // // // // // // // // // // // // // // // // // // // 4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 PASSED, APPROVED AND ADOPTED at a Special Meeting ofthe Board of Directors ofthe Carlsbad Municipal Water District of the City of Carlsbad on the 27th day of January 2015, by the following vote to wit: AYES: NOES: ABSENT: Board Members Hall, Blackburn, Schumacher, Wood, Packard. None. None. MATT HALL, President ATTEST: BARBARA ENGLESOlt; Secretary O\AO^ \ /^^•••.»HH04|EAt^^ LOCATION MAP PIPELINE SEGMENT 7 PIPELINE SEGMENTS PIPELINE SEGMENT 18 PIPELINE SEGMENT 1A PIPELINE SEGMENT2 CWRF ^ EXPANSION PIPELINE SEGMENTS PIPELINE SEGMENTS PROJECT NAME PH>^SE /// RECYCLED WATER PROJECT NUMBER 5208 EXHIBIT 2 PLOTIED BY: SCOTT EVANS PLOT DA JF: 12/17/14 PA7H:D: \UT1UT1ES DEPARTMENT\DESIGN DIVISION\AHLES\5208 AU SEOIENTSDWC