Loading...
HomeMy WebLinkAbout2015-06-23; Municipal Water District; 808; Accept Bids Award Contract to Dick Miller Inc Construction of Tri-Agencies Water Transmission Pipeline Reach 2 Phase 1 Project No 5008CARLSBAD MUNICIPAL WATER DISTRICT -AGENDA BILL 14 AB# MTG. DEPT. 808 06-23-15 PW-UTIL ACCEPT BIDS AND AWARD OF CONTRACT TO DICK MILLER INC. IN THE AMOUNT OF $1,097,197 FOR CONSTRUCTION OF THE TRI- AGENCIES WATER TRANSMISSION PIPELINE, REACH 2, PHASE 1, LOCATED ON PIRGOS WAY, PROJECT NO. 5008 DEPT. DIRECTOR GEN. COUNSEL CITY MGR. RECOMMENDED ACTION: Adopt Resolution No. 1527 accepting bids and awarding a contract to Dick Miller Inc. in the amount of $1,097,197 for construction of the Tri-Agencies Water Transmission Pipeline, Reach 2, Phase 1, located on Pirgos Way, Project No. 5008. ITEM EXPLANATION: The Tri-Agencies Water Transmission Pipeline was constructed by the San Diego County Water Authority (SDCWA) in 1978 to supply treated imported water to three agencies including Carlsbad Municipal Water District (CMWD). Reach 2 ofthe Tri-Agencies Transmission Pipeline only serves water to CMWD and was subsequently quitclaimed by the SDCWA to CMWD in 1982. It is one of four major transmission pipelines supplying imported water to CMWD, and is therefore, a critical water supply pipeline. Reach 2 is 21 inches in diameter and begins at the SDCWA's meter vault referred to as "CMWD No. 4 Service Connection" which is located near the intersection of Cannon Road and Wisteria Drive in the City of Oceanside. Reach 2 proceeds westerly, terminating near the intersection of College Boulevard and Carlsbad Village Drive in the Calavera Hills area of the City of Carlsbad. There have been numerous leaks on Reach 2 caused by severely corroded and partially disintegrated bell and spigot joints. A report prepared on Reach 2 titled "Tri-Agencies Pipeline Alternatives Investigation" provided information on various options to address the pipeline condition. Based on findings in the report, staff has determined that Reach 2 can be downsized to an 18 inch diameter pipeline due to the construction of new water transmission mains on College Boulevard and Cannon Road. The report recommends replacing the water transmission pipeline in 2 separate construction phases. Phase I ofthe pipeline replacement extends from the "CMWD No. 4 Service Connection" westerly along Pirgos Way to the City limits of Carlsbad, a length of approximately 1,820 feet. The Phase I project will also require the replacement of the existing pressure sustaining facility containing control valves designed to sustain the upstream pressure to the meter located at the SDCWA's "CMWD No. 4 Service Connection". The control valves will be installed in a new below grade concrete vault. Phase 2 extends from the west terminus ofthe Phase I project to College Boulevard. DEPARTMENT CONTACT: Mark Biskup 760-603-7352 mark.biskup@carlsbadca.gov f Of? SECRETARY USE. BOARD ACTION: APPROVED CONTINUED TO DATE SPECIFIC • DENIED • CONTINUED TO DATE UNKNOWN • CONTINUED • RETURNED TO STAFF • WITHDRAWN • OTHER - SEE MINUTES • \ AMENDED • REPORT RECEIVED • \ Tri-Citles Water Transmission Pipeline June 23, 2015 Page 2 of 3 On Aug. 26, 2014, the CMWD Board of Directors adopted Resolution No. 1498 which approved the plans and specifications and authorized the advertisement for bids for the construction of the Tri-Agencies Water Transmission Pipeline, Reach 2, Phase 1, Project No. 5008. On Oct. 15, 2014, the Utilities Department received four bids which exceeded the engineer's cost estimate. On Nov. 18, 2014, through the adoption of Resolution No 1506, those bids were rejected and the Board of Directors approved re- advertisement for bids. Subsequent to rejecting the bids, and after further review ofthe plans and specifications, staff adjusted the engineer's estimate to more accurately reflect the current bidding climate and revised the construction cost estimate from $900,000 to $1,200,000. On May 5, 2015, the Utilities Department received seven sealed bids for the construction of this project as shown in the following table. The re- bidding resulted in more contractors bidding, with the lowest responsive bidder being $81,253 lower than the lowest bidder in the previous bid results. CONTRACTOR NAME TOTAL BID AMOUNT Dick Miller Inc. $1,097,197 CCL Contracting Inc. $1,126,030 Universal Pipeline Inc. $1,127,500 Filanc $1,247,777 Ortiz Corporation $1,281,168 GRFCO Inc. $1,362,450 Piperin Corporation $1,578,350 The lowest responsive bidder, Dick Miller Inc., submitted a bid in the amount of $1,097,197. Staff has completed it's review of the contract documents and has determined that Dick Miller Inc. is the confirmed low bidder and their bid documents are responsive. Staff recommends that Dick Miller Inc. be awarded the contract. FISCAL IMPACT: An Engineer's Estimate of the construction cost of Tri-Agencies Water Transmission Pipeline, Reach 2, Phase I, Project No. 5008 was $1,200,000. Reach 2, Phase 1, is part of the larger capital improvement project Tri-Agencies Water Transmission Pipeline, Project No. 5008. As shown in Table 1 the current project appropriation for Tri-Agencies Water Transmission Pipeline, Project No. 5008 is $6,455,000 from the Water Replacement Fund. Tri-Cities Water Transmission Pipeline June 23, 2015 Page 3 of 3 TABLE 1 - PROJECT CONSTRUCTION COST ESTIMATE Tri-Agencies Water Transmission Pipeline, Project No. 5008 ESTIMATED COSTS Construction Contract (Dick Miller Inc.) $1,097,197 Construction Contingency $165,000 Construction Management, Inspection, and Material Testing $110,000 TOTAL ESTIMATED CONSTRUCTION COSTS (Phase 1) $1,372,197 Current Appropriation - Tri-Agencies Pipeline, CIP No. 5008 $6,455,000 Current Expenditures/Encumbrances, CIP No. 5008 (Environmental/Design) $431,153 TOTAL AVAILABLE TRI-AGENCIES PIPELIWi^iHUyH/IWiBWWlMliill^ $6,023,847 ADDITIONAL APPROPRIATION ANTICIPATED FOR CONSTRUCTION None Sufficient funds have been appropriated from the Water Replacement Fund for this project. ENVIRONMENTAL IMPACT: The project was previously evaluated in the Final Program Environmental Impact Report (EIR), dated October 2012, for the City of Carlsbad Sewer Master Plan and the CMWD Water and Recycled Water Master Plan Updates (EIR 12-01). The EIR evaluated the potential environmental effects of the project components described in the CMWD 2012 Water Master Plan Update. This project (Phase I ofthe Water Supply and Transmission Project No. 48) is within the scope ofthe Final Program EIR 12-01, and with the implementation ofthe project's mitigation measures, impacts to biological and cultural resources would be less than significant, therefore, no further California Environmental Quality Act (CEQA) compliance is required. PUBLIC NOTIFICATION None required. EXHIBITS: 1. Resolution No. 1527 accepting bids and awarding the contract to Dick Miller Inc. in the amount of $1,097,197 for the construction ofthe Tri-Agencies Water Transmission Pipeline, Reach 2, Phase 1, located on Pirgos Way, Project No. 5008. Location Map Exhibit 1 1 RESOLUTION NO. 1527 2 A RESOLUTION OF THE BOARD OF DIRECTORS OF CARLSBAD MUNICIPAL WATER DISTRICT (CMWD), ACCEPTING BIDS AND AWARDING A CONTRACT TO DICK MILLER INC. IN THE AMOUNT 4 OF $1,097,197 FOR THE CONSTRUCTION OF THE TRI-AGENCIES WATER TRANSMISSION PIPELINE, REACH 2, PHASE 1, LOCATED 5 ON PIRGOS WAY, PROJECT NO. 5008 6 y WHEREAS, the Board of Directors of the Carlsbad Municipal Water District, California 8 has determined it necessary, desirable, and in the public interest to replace the existing 21 inch 9 Tri-Agencies Water Transmission Pipeline with a new 18 inch steel water pipeline and; WHEREAS, an environmental impact assessment was conducted for the Tri-Agencies Pipeline Project and a Program EIR was approved on Nov. 13, 2012, by the Board of Directors of the Carlsbad Municipal Water District, California by adopted Resolution No. 2012-245; and WHEREAS, on Aug. 26, 2014, the Board of Directors of the Carlsbad Municipal Water District, California adopted Resolution No. 1498, which approved the plans forthe construction 10 11 12 13 14 15 25 of the Tri-Agencies Water Transmission Pipeline, Project No. 5008; and 17 WHEREAS, on Oct. 15, 2014, four sealed bids were received by the Carlsbad Municipal Water District for the construction ofthe Tri-Agencies Water Transmission Pipeline, Project No. 5008 and WHEREAS, on Nov. 18, 2014, the Board of Directors of the Carlsbad Municipal Water District, California adopted Resolution No. 1506, rejecting all bids and authorizing the Secretary 18 19 20 21 22 23 to the Board to re-advertise for bids for the construction of the Tri-Agencies Water 24 Transmission Pipeline, Project No. 5008; and WHEREAS, seven sealed bids were received on April 21, 2015, by the Carlsbad Municipal Water District for the construction ofthe Tri-Agencies Water Transmission Pipeline, Project No. 5008; and , \ 25 26 27 28 1 WHEREAS, the lowest responsive and responsible bid to construct said project was 2 submitted by Dick Miller Inc. in the amount of $1,097,197; and ^ WHEREAS, the Engineer's estimate for the project cost is $1,200,000; and 4 WHEREAS, there are sufficient funds available in the Water Replacement Fund to 5 complete the project; and 6 ' J WHEREAS, under the operating agreement with the City of Carlsbad, Carlsbad Municipal 8 Water District adopted the city's purchasing rules. 9 NOW, THEREFORE, BE IT RESOLVED by the Carlsbad Municipal Water District Board of the City of Carlsbad, California, as follows: 1. That the above recitations are true and correct. 2. That the low bid of $1,097,197 submitted by Dick Miller Inc. for the construction of the Tri-Agencies Water Transmission Pipeline, Reach 2, Phase 1, Project No. 5008 is accepted and the President is hereby authorized to execute a contract for this project. 11 12 13 14 15 25 3. That the Executive Manager is hereby authorized to approve construction change 17 orders up to $165,000 ^8 4. That the award of this contract is contingent upon the bidder submitting the lowest responsible bid executing the required contract and submitting the required bonds and insurance policies, as described in the contract, within 20 days of adoption of this resolution. The Executive Manager may grant reasonable extensions of time. 19 20 21 22 23 24 25 26 27 // // // // 28 y 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 PASSED, APPROVED AND ADOPTED at a Special Meeting ofthe Board of Directors ofthe Carlsbad Municipal Water District of the City of Carlsbad on the 23^*^ day of June, 2015, by the following vote to wit: AYES: NOES: ABSENT: Board Members Hall, Blackburn, Schumacher, Wood, Packard. None. None. MATT HALL, President ATTEST: BARBARA ENGLESdN, Secretary (SEAL) 2:55 = "y^C/ >^s'> LOCATION MAP REACH 2 PHASE 1 VICINITY MAP NOT TO SCALE PROJECT SITE NOT TO SCALE PROJECT NAME j^,^^,,ciES WATER TRANSMISSION PIPELINE REACH 2, PHASE 1 PROJECT NUMBER 5008 EXHIBIT 2 PLOTTED ey; SCOTT EVANS PLOT DATE: 4/15/13 PATH:D:\UTnJTIES DEPARTUENT\LOCATION UAPS\5008.DWG 1