Loading...
HomeMy WebLinkAbout2018-10-16; Municipal Water District; ; Acceptance of bids and award of contract to Ferreira Coastal Construction Co. for construction of the Recycled Water Phase Ill Pipeline Expansion Segment 5 Project and the Miscellaneous Pipeline Replacements ProjectCA Review lfa'V' 9 MUNICIPAL WATER DISTRICT . Staff Report . Meeting Date: To: From: Staff Contact: Subject Oct. 16, 2018 President and Board Members Scott Chadwick, Executive Manager Lindsay Leahy, Associate Engineer Lindsay.leahy@carlsbadca.gov or 760-603-7325 Acceptance of bids and award of contract to Ferreira Coastal Construction Co . for construction of the Recycled Water Phase Ill Pipeline Expansion Segment 5 Project and the Miscellaneous Pipeline Replacements Project. Recommended Action Adopt a Resolution accepting bids and awarding a contract to Ferreira Coastal Construction Co. for an amount not to exceed $9,487,655 for construction of the Recycled Water Phase Ill Pipeline Expansion Segment 5, Project No. 5208-B, and the Miscellaneous Pipeline Replacements, Project No. 3904 (Project). Executive Summary The Project is part of the Carlsbad Municipal Water District's (CMWD) $37 million Phase Ill Recycled Water Program (Program). The majority of the Project will provide recycled water to customers along El Camino Real, north of Chestnut Avenue, Tamarack Avenue, Marron Road, and Cannon Road (Recycled Water Project, Project No. 5208-B). Additionally, the Project includes replacement of potable water mains (Potable Water Project, Project No. 3904) within the Carlsbad Palisades and Flower Fields Homeowners Associations to meet current CMWD standards. These water mains will be replaced under the Miscellaneous Pipeline Replacements, Capital Improvement Program (CIP) No. 3904. Carlsbad Municipal Code subsections 3.28.080(C) and (G) require City Council approval to award Public Works contracts when the value exceeds $175,000. The bid amount for this Project is $9,487,655. Staff recommends accepting bids and awarding a contract to Ferreira Coastal Construction Co. Discussion CMWD started its Recycled Water Program in 1990 with Phase I. The Carlsbad Water Recycling Facility (CWRF) was constructed beginning in 2002 as part of Phase II expansion. In 2008, at the completion of Phase II, recycled water production was approximately 4 million gallons per day (mgd). In 2012, Phase Ill began with preparation of a feasibility study, which recommended an expansion of the CWRF to 7 mgd, 18 miles of new pipeline, and construction of a 1.5-million- gallon storage tank. Currently, only the storage tank and 6 miles of pipeline remain to be constructed. October 16, 2018 Item #6 Page 1 of 8 The Recycled Water Project includes construction of approximately 29,500 linear feet of 6-inch diameter polyvinyl chloride (PVC) recycled water pipeline and services. This work includes installation of pipelines along Tamarack Avenue from Skyline Road to Kirkwall Avenue, Kelly Drive, Marron Road, Haymar Drive, and El Camino Real from Chestnut Avenue to Haymar Drive. In addition to the work on Segment 5, the Recycled Water Project includes approximately 1,400 linear feet of 8-inch diameter and 500 linear feet of 6-inch diameter PVC recycled water pipeline and services along Cannon Road for Segment 2 and a reach of Segment 7 in the Calavera Hills area. Recycled water served from these pipeline segments will be used for landscape irrigation. The Potable Water Project includes construction of approximately 1,850 linear feet of 8-inch diameter and 4,100 linear feet of 6-inch diameter PVC potable water pipeline and services. The water main improvements will be completed in the vicinity of the Segment 5 recycled water work and will be included in this Project to minimize construction impacts to residents and capitalize on construction savings due to economies of scale. The improvements will be completed within the Carlsbad Palisades development near Tamarack Avenue and El Camino Real, and throughout the development on Flower Fields Way off Avenida de Anita. On July 17, 2017, through the adoption of Resolution No. 1601, the CMWD Board approved plans and specifications and authorized the secretary of the Board to advertise to receive bids for the Project. On Aug. 29, 2018, 11 sealed bids were received for construction of this Project as shown in the following table: RECYCLED WATER PHASE HI PJPELINE EXPANSION SEGMENT 5, PROJECT NO. 5208-B CONTRACTOR .. · TOTAL BID 1. Ferreira Coastal Construction Co. $9,487,655 2. Cucamonga MNR Construction, Inc. $9,787,370 3. Big Ben, Inc. $10,992,700 4. Capriati Construction Corp. $11,385,993 5 Vido Artukorich & Son, Inc. $11,443,640 6 TC Construction Company, Inc. $11,619,600 7 E.J. Meyer Company $12,662,222 8 Orion Construction Corp. $12,963,000 9 Burtech Pipeline Incorporated $14,700,000 10 Colich & Sons LP. $14,859,600 11 Sukut Construction $15,654,900 October 16, 2018 Item #6 Page 2 of 8 Ferreira Coastal Construction Co. submitted the lowest bid in the amount of $9,487,655. The engineer's estimate of the construction cost of the Project was $10,100,000. A summary of the bid schedules is shown in the table below: RECYCLED WATER PHASE Ill PIPELINE EXPANSION SEGMENT 5, PROJECT NO. 5208-B BID SCHEDULE A -Recycled Water Project $7,330,816 B -Potable Water Project $2,156,839 TOTAL BID AMOUNT $9,487,655 The construction contract contains general performance standards, referenced technical specifications, and includes a one-year warranty period. A five percent retention will be withheld from each progress payment until final acceptance of the Project. The construction contract includes liquidated damages which may be assessed in the amount of $3,000 per day for each day in excess of the time specified for completion of the work. Staff has completed review of the bid documents and has determined that Ferreira Coastal Construction Co. is the confirmed low bidder. Ferreira Coastal Construction Co. submitted a list of similar projects to show their capabilities and qualifications to perform the specified work. Staff recommends that Ferreira Coastal Construction Co. be awarded the contract. Fiscal Analysis The estimated total cost of the Recycled Water Project is $9,281,658 and it will be funded by the Clean Water State Revolving Fund (SRF) via Recycled Water Ill Pipelines Program, CIP No. 5208. The estimated total cost of the Potable Water Project is $2,817,763 and it will be funded by the Miscellaneous Pipeline Replacements Program, CIP No. 3904. The total estimated cost of the Project is $12,099,421 and includes the following: construction contract, contingency for change order management, construction management and inspection, engineering support for contractor shop drawings, requests for information and meetings, and community outreach. A summary of the available funds and estimated construction costs are shown in the tables below: RECYCLED WATER PHASE 111 - PIPELINES, CIP NO. 5208 Current Appropriation $21,197,529 Current Expenditures/Encumbrances $7,461,034 TOTAL AVAILABLE RECYCLED WATER PHASE Ill -PIPELINES,_CIP NO. 5208 $13,736,495 RECYLCED WATER PHASE Ill PIPELINE EXPANSION SEGMENT 5, PROJECT NO. 5208-B {RECYCLED WATER PROJECT) Construction Contract (Ferreira Coastal Construction Co.) $7,330,816 Construction Contingency (estimated) $733,082 Construction Management, Inspection, and Material Testing (estimated) $1,150,000 Engineering Construction Support, Contingency, Staff and Consultant $53,900 Community Outreach (estimated) $13,860 TOTAL ESTIMATED CONSTRUCTION COSTS $9,281,658 REMAINING BALANCE AFTER PROJECT NO. 5208-B $4,454,837 ADDITIONAL APPROPRIATION NEEDED $0 October 16, 2018 Item #6 Page 3 of 8 MISCELLANEOUS PIPELINE REPLACEMENTS, CIP NO. 3904 Current Appropriation $3,933,000 Current Expenditures/Encumbrances $730,309 TOTAL AVAILABLE MISCELLANEOUS PIPELINE REPLACEMENTS, CIP NO. 3904 $3,202,691 RECYLCED WATER PHASE Ill PIPELINE EXPANSION SEGMENT 5, PROJECT NO. 5208-B (POTABLE WATER PROJECT} Construction Contract (estimated) $2,156,839 Construction Contingency (estimated) $215,684 Construction Management, Inspection, and Material Testing (estimated) $425,000 Engineering Support During Construction and Contingency, Staff and $16,100 Consultant Community Outreach (Estimated) $4,140 TOTAL ESTIMATED CONSTRUCTION COSTS $2,817,763 REMAINING BALANCE AFTER PROJECT NO. 5208-B $384,928 ADDITIONAL APPROPRIATION NEEDED $0 RECYCLED WATER PHASE III PIPELINE EXPANSION SEGMENT 5, PROJECT NO. 5208-B Recycled Water Phase Ill $9,281,658 Miscellaneous Pipeline Replacements, CIP No. 3904 $2,817,763 TOTAL ESTIMATED CONSTRUCTION COSTS $12,099,421 Next Steps Once contract documents are fully executed and a purchase order is issued, staff will schedule a pre-construction meeting with Ferreira Coastal Construction Co. and a Notice-to-Proceed will be issued. The consultant cultural monitors for the Project have indicated that additional monitoring may be required which could impact the construction schedule. The duration ofthe construction contract is 375 working days, exclusive of rain days and change orders that may extend the contract duration. Upon successful completion of the Project, staff will record a Notice of Completion to release bonds. Environmental Evaluation (CEQA) On Nov. 27, 2012, CMWD adopted Resolution No. 1455 approving a Mitigated Negative Declaration (MND) and Mitigation Monitoring and Reporting Program (MMRP) for the Phase Ill Recycled Water Project (EIA 12-02). This Project is a sub-component (ES 5) of the Phase Ill Recycled Water Project and is subject to the Mitigation Measures (MM) that are identified in the MMRP. On July 17, 2018, CMWD adopted Resolution No. 1601 approving an Addendum to the MND and Supplemental Environmental Package which included extensions to Segment 5, the Segment 7 reach and the Potable Water Project that were not originally analyzed in the MND prepared for the Program. October 16, 2018 Item #6 Page 4 of 8 The Project is within the scope of the prior environmental documents and no further environmental documentation is required per CEQA Guidelines Section 15162. All applicable mitigation measures contained in the prior environmental document have been incorporated into the construction documents. Public Notification This item was noticed in accordance with the Ralph M. Brown Act and was available for public viewing and review at least 72 hours prior to the scheduled meeting date. Prior to the start of construction, the public will be notified of the construction activities using media methods such as signage, email, website and other city c9mmunication channels. The construction contractor will also be required to notify the public of construction activities via changeable message signs, door hangers, letters to property owners, and/or "NO PARKING" signs, as applicable. Exhibits 1. CMWD Board Resolution. 2. Location Map. October 16, 2018 Item #6 Page 5 of 8 RESOLUTION NO. 1606 A RESOLUTION OF THE BOARD OF DIRECTORS OF THE CARLSBAD MUNICIPAL WATER DISTRICT BOARD (CMWD), ACCEPTING BIDS AND AWARDING A CONTRACT TO FERREIRA COASTAL CONSTRUCTION CO. FOR AN AMOUNT NOTTO EXCEED $9,487,655 FOR THE RECYCLED WATER PHASE 111 PIPELINE EXPANSION SEGMENT 5, PROJECT NO. 5208-B. EXHIBIT 1 WHEREAS, the Carlsbad Municipal Water District (CMWD) Board of Directors of the City of Carlsbad, California has determined it necessary, desirable, and in the public interest to install approximately 1,400 linear feet of 8-inch diameter and 30,000 linear feet of 6-inch diameter polyvinyl chloride (PVC) recycled water pipeline and 1,850 linear feet of 8-inch diameter and 4,100 linear feet of 6-inch PVC potable water pipeline; and WHEREAS, on Nov. 27, 2012, CMWD Board Resolution No. 1455 approved an environmental impact assessment that was conducted for the Phase Ill Recycled Water Program, and a Mitigated Negative Declaration (MND) and Mitigation Monitoring and Reporting; and WHEREAS, on May 16, 2018, Planning Commission Resolution No. 7296 approved a Coastal Development Permit and Special Use Permit to construct the Project; and WHEREAS, on June 11, 2018, California Coastal Commission issued a Coastal Development Waiver (6-18-0345-W) to construct the Project; and WHEREAS, on July 17, 2018, CMWD Board Resolution No. 1601 approved plans and specifications, and authorized the secretary to the Board to advertise to receive bids for the construction of the Recycled Water Phase Ill Pipeline Expansion Segment 5, Project No. 5208-B (Project); and WHEREAS, on July 17, 2018, CMWD Board Resolution No. 1601 also approved an Addendum to the MND and Supplemental Environmental Package; and WHEREAS, on Aug. 29, 2018, 11 sealed bids were received by CMWD for construction of the Project; and WHEREAS, the lowest responsible bid was submitted by Ferreira Coastal Construction Co. in the amount of $9,487,655; and WHEREAS, funds have been appropriated from the Recycled Water Phase Ill -Pipelines, CIP No. 5208 and Miscellaneous Pipeline Replacements, CIP No. 3904 and are sufficient for completion of this Project; and October 16, 2018 Item #6 Page 6 of 8 WHEREAS, subsection 3.28.040(()(5) of the Carlsbad Municipal Code authorizes the executive manager to approve change orders in the amount equal to the contingency set at the time of project award. NOW, THEREFORE, BE IT RESOLVED by the CMWD Board of the City of Carlsbad, California, as follows: 1. That the above recitations are true and correct. 2. That the bid in the amount of $9,487,655 submitted by Ferreira Coastal Construction Co. for construction of the Recycled Water Phase Ill Pipeline Expansion Segment 5, Project No. 5208-B, is accepted and the president of the Board is hereby authorized to execute a contract with Ferreira Coastal Construction Co. 3. That the executive manager or designee is hereby authorized to approve construction change orders up to $948,766. 4. That the award of this contract is contingent upon the bidder submitting the lowest responsible bid, executing the required contract and submitting the required bonds and insurance policies, as described in the contract, within 20 days of adoption of this Resolution. The executive manager may grant reasonable extensions of time. PASSED, APPROVED AND ADOPTED at a Special Meeting of the Carlsbad Municipal Water District of the City of Carlsbad on the 16th day of October, 2018, by the following vote, to wit: AYES: NOES: ABSENT: M. Hall, K. Blackburn, M. Schumacher, C. Schumacher, M. Packard. None. None. (SEAL) October 16, 2018 Item #6 Page 7 of 8