Loading...
HomeMy WebLinkAbout2007-12-18; Public Financing Authority; 33; Crossings Golf Course Project ConstructionCARLSBAD PUBLIC FINANCING AUTHORITY - AGENDA BILL AB# 33 MTG. 12/18/07 DEPT. CM APPROVAL OF AMENDMENT NO. 2 TO CONTRACT FOR FINAL BUILDING AND ARCHITECTURAL CONSTRUCTION PHASE SERVICES FOR THE CROSSINGS AT CARLSBAD GOLF COURSE PROJECT DEPT. HEAD t CITYATTY. . CITY MGR. \J\ '}<ML_ RECOMMENDED ACTION: It is recommended the Board of Directors of the Carlsbad Public Financing Authority, hereafter the "Authority," ADOPT RESOLUTION NO. 41 approving Amendment No. 2 to an existing agreement with Douglas Fredrikson Architects for final building and architectural construction phase services for The Crossings at Carlsbad Golf Course Project. ITEM EXPLANATION: On January 3, 2006, the Authority approved an agreement with design architect Douglas Fredrikson Architects to provide building and architectural construction phase services required to support the construction of the several buildings, including the clubhouse, on The Crossings at Carlsbad Golf Course Project. On April 3, 2007, the Authority approved Amendment No. 1 to the agreement primarily to provide additional architectural construction phase services to support the expansion of the dining room and kitchen facility in the clubhouse that occurred during the construction of the building. The attached Amendment No. 2 provides for all final building and architectural construction phase services required to close-out the construction of all of the buildings on the site, including the clubhouse. The additional architectural support services include finalizing interior design and finish details, final architectural inspection of the various buildings, close-out of all submittals, coordination of final furnishings details, and review of the contractor's as-built drawings which will become the record drawings for the buildings. This Amendment No. 2 will conclude all work required of the design architects for the building construction. Staff recommends approval of attached Amendment No. 2. ENVIRONMENTAL IMPACT: The providing of architectural professional services is not a "project" as defined by the California Environmental Quality Act nor the environmental policies and procedures of the City of Carlsbad and, therefore, an assessment of environmental impacts is not required. FISCAL IMPACT: The recommended final building and architectural phase services of Amendment No. 2 total $57,000 and will conclude all architectural services for the project's buildings. There are adequate funds within the project's existing construction contingency to approve Amendment No. 2 without requiring an additional appropriation at this time. EXHIBITS: 1. 2. 41 approving Amendment No. 2.Resolution No. _ Amendment No. 2 to agreement with Douglas Fredrikson Architects. Department Contact: Skip Hammann, 760-434-2856, sharn@ci.carlsbad.ca.us or John Cahill, 760-602-2726, icahi@ci.carlsbad.ca.us FOR CITY CLERK'S USE ONL Y. , BOARD ACTION:APPROVED DENIED CONTINUED WITHDRAWN AMENDED W D D D D CONTINUED TO DATE SPECIFIC CONTINUED TO DATE UNKNOWN RETURNED TO STAFF OTHER -SEE MINUTES D D D D Exhibit 1 RESOLUTION NO.41 A RESOLUTION OF THE BOARD OF DIRECTORS OF THE CARLSBAD PUBLIC FINANCING AUTHORITY APPROVING AMENDMENT NO. 2 TO AN AGREEMENT FOR BUILDING AND ARCHITECTURAL CONSTRUCURAL PHASE SERVICES FOR THE CROSSINGS AT CARLSBAD GOLF COURSE PROJECT WHEREAS, the Carlsbad Public Financing Authority, hereafter the "Authority," has previously approved an agreement to provide building and architectural construction phase services for The Crossings at Carlsbad Golf Course, hereafter the "Project;" and WHEREAS, the parties to said agreement desire to expand the scope of services; and WHEREAS, an amendment to said agreement has been prepared for review by the Authority. NOW, THEREFORE, BE IT RESOLVED by the Board of Directors of the Carlsbad Public Financing Authority of the City of Carlsbad, California, as follows: 1. That the above recitations are true and correct. 2. That Amendment No. 2 is hereby approved and the Chairman of the Board is authorized to execute said amendment. Following the Chairman's execution of said amendment, the Secretary to the Board is directed to forward copies of this resolution and the executed amendment to the Public Works Department, Construction Management and Inspection Division. PASSED, APPROVED AND ADOPTED at a Special Meeting of the Board of Directors of the Carlsbad Public Financing Authority on the 18tb day of December , 2007 by the following vote, to wit: AYES: Board Members Lewis, Kulcbin, Hall, Packard and Nyga^ard. NOES: None. ABSENT: None. Board //''/unit1 AMENDMENT NO. 2 TO AGREEMENT FOR BUILDING ARCHITECTURE CONSTRUCTION PHASE SERVICES FOR THE CARLSBAD CITY GOLF COURSE PROJECT, CITY PROJECT NUMBER 39721-3 DOUGLAS FREDRIKSON ARCHITECTS Q This Amendment No. 2 is entered into and effective as of the /*? day of ? *j/rxJajn*J 2007, amending the agreement dated January 4, 2006 (the "Agreement") by and between the CARLSBAD PUBLIC FINANCING AUTHORITY, a joint powers authority, ("CPFA"), and DOUGLAS FREDRIKSON ARCHITECTS, an Arizona corporation ("Contractor") (collectively, the "Parties") for building and architectural construction phase services for the Carlsbad City Golf Course Project, hereafter the "Project." RECITALS A. On April 9, 2007, the Parties executed Amendment No. 1 to the Agreement to provide additional construction phase architectural services for the Project; and B. The Parties desire to alter the Agreement's scope of work to provide final and complete construction phase architectural services required for the Project; and C. The Parties have negotiated and agreed to a final and complete scope of services and fee. NOW, THEREFORE, in consideration of these recitals and the mutual covenants contained herein, CPFA and Contractor agree as follows: 1. In addition to those services contained in the Agreement, as may have been amended from time to time, Contractor will provide final and complete construction phase architecture services required by CPFA for the Project, 2. City will pay Contractor for all work associated with said additional services on a total fixed price basis of fifty-seven thousand dollars ($57,000). The Parties hereby agree this Amendment No. 2 shall comprise the final and complete scope of work and compensation for all construction phase architecture services for the Project. 3. Contractor will complete all additional work prior to January 4, 2008. 4. All other provisions of the Agreement, as may have been amended from time to time, will remain in full force and effect. 5. All requisite insurance policies to be maintained by Contractor pursuant to the Agreement, as may have been amended from time to time, will include coverage for this Amendment. 6. The individuals executing this Amendment and the instruments referenced in it on behalf of Contractor each represent and warrant that they have the legal power, right and actual authority to bind Contractor to the terms and conditions of this Amendment. City Attorney Approved Version #05.22.01 CONTRACTOR *B CARLSBAD PUBLIC FINANCING AUTHORIj&Y, a Joint Povye/s Ayth^rity (print name/title) CPFA Cha i rrnan" 6 ATTEST: (--(e-mail address) M.WOOD Secretary (print name/title) &***&?il address) .Contractor shall provide a proper notarial acknowledgmeji Contractor. If a Corporation, this Amendment must b< each of the following two groups. '<*• CoetftMtisEdU *' FLOYD R. ADAMS NOTARY PUBLICJSTATE OF ARIZONA t by the "Group A. Chairman, President, or Vice-President **Group B. Secretary, OFFICIAL SEALFLOYD R. ADAMS ™LICOSTATE OF ARIZONAMARICOPA COUNTYMy comm. Expires May 4,2010 Assistant Secretary, CFO or Assistant Treasurer Otherwise, the corporation must attach a resolution certified by the secretary or assistant secretary under corporate seal empowering the officer(s) signing to bind the corporation. APPROVED AS TO FORM: RONALD R. BALL, Counsel to the Board By:. Counsel REV. 10/29/2007