APPROVE RECYCLED WATER CONNECTION FEE CREDITS
TO MCMILUN DEVELOPMENT FOR CONSTRUCTION OF
OFFSITE RECYCLED WATER PIPEUNE EXPANSION
SEGMENT 7, PROJECT NO 5208
DEPT. DIRECTOR
CITY ATTORNEY
CITY MANAGER
RECOiVIMENDED ACTION:
Adopt Resolution No. 1485 approving Recycled Water Connection Fee credit to McMillin
Development for construction of offsite Recycled Water Pipeline Expansion Segment 1, Project No. 5208.
ITEM EXPLANATION:
On November 13, 2012, the Board of Directors adopted Resolution No. 1450 approving the 2012 Recycled
Water Master Plan, which established the pipelines to be constructed as part of the Carlsbad Municipal
Water District's (CMWD) Phase III Recycled Water Project. The fiscal year 2013-14 Recycled Water Capital
Improvement Program includes the recycled water pipelines as part ofthe Phase III Recycled Water Project.
The pipelines were grouped into eighteen expansion segments which are to be phased in over time, based
on cost effectiveness. Pipeline Expansion Segment 7, located in Tamarack Avenue, will provide service to
the Quarry Creek II Development Project.
McMillin Development will construct Pipeline Expansion Segment 7, to provide recycling water to the
Quarry Creek II Development project, but requested that they receive a credit for the estimated cost to
construct Pipeline Expansion Segment 7 not to exceed $411,000 in lieu of paying the Recycled Water
Connection Fees.
Staff recommends to the Board that the recycled water connection credit be approved in the amount
requested by McMillin Development for consideration to construct Pipeline Expansion Segment 7.
ENVIRONIVIENTAL ilVIPACT:
On November 27, 2012, the Board of Directors adopted Resolution No. 1455, adopting the Mitigated
Negative Declaration and Mitigation Monitoring and Reporting Program for the Phase III Recycled Water
Project, Case No. EIA 12-02, Project 5022.
DEPARTMENT CONTACT: David Ahles 760-602-2748 David.AhlesOCarlsbadca.gov
FOR CITY CLERKS USE ONLY
BOARD ACTION: APPROVED CONTINUED TO DATE SPECIFIC •
DENIED • CONTINUED TO DATE UNKNOWN •
CONTINUED • RETURNED TO STAFF •
WITHDRAWN • OTHER-SEE MINUTES •
AMENDED •
FISCAL iiVIPAa:
The total estimated cost to construct the Recycled Water Pipeline Expansion Segment 7 in Tamarack
Avenue, Project No. 5208, is shown in Table 1. McMillin Development would be provided a credit towards
the Recycled Water Meter Connection Fee for the Quarry Creek II Development not to exceed $411,000,
which is the estimated cost of the pipeline.
TABLE 1 -PROJECT COST ESTIMATE
Recyded Pipeline Expansion Segment 7 in Tamaracl< Ave., Project No. 5208 ESTIMATED COSTS
Design $34,000
Construction Contract $343,000
Construction Contingencies $34,000
TOTAL ESTIMATED CONSTRUaiON COST $411,000
EXHIBITS:
1. Resolution No. 1485 approving a credit for Recycled Water Meter Fees to McMillin
Development for the Quarry Creek II Development Project to offset the cost to construct the
Recycled Water Pipeline Expansion Segment 7, Project No. 5208.
2. Location map.
23
24
25
26
27
28
RESOLUTION NO. 1485
1
2 „
A RESOLUTION OF THE BOARD OF DIRECTORS OF CARLSBAD
3 MUNICIPAL WATER DISTRICT (CMWD), APPROVING A CREDIT FOR
RECYCLED WATER CONNECTION FEES TO McMILUN DEVELOPMENT
FOR THE QUARRY CREEK II PROJECT TO OFFSET THE COST OF
CONSTRUCTING RECYCLED WATER PIPEUNE EXPANSION SEGMENT 7,
PROJEa NO. 5208
WHEREAS, on November 13, 2012, the Board of Directors of the Carlsbad Municipal Water
District, Carlsbad, California, through Resolution No. 1450, approved the 2012 Recycled Water Master
Plan; and
WHEREAS, Recycled Water Pipeline Expansion Segment 7 is part of the Recycled Water
11 Master Plan, and
12 WHEREAS, McMillin Development has requested a Recycling Water Connection Fee credit to
be applied toward the cost of constructing Pipeline Expansion Segment 7; and
WHEREAS, the estimated cost to construct Pipeline Expansion 7 is $411,000.
NOW, THEREFORE, BE IT RESOLVED by the Carlsbad Municipal Water District Board ofthe City
of Carlsbad, California, as follows:
1. That the above recitations are true and correct.
2. That the Executive Manager is hereby authorized to approve a credit for Recycled
13
14
15
16
17
18
19
20 Water Connection Fees to McMillin Development for the Quarry Creek II Project to offset the cost to
21 construct Recycled Water Pipeline Expansion Segment 7, Project No. 5208, up to the amount of
22 $411,000.
///
///
///
///
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
PASSED, APPROVED AND ADOPTED at a Special Meeting ofthe Board of Directors ofthe
Carlsbad Municipai Water District ofthe City of Carisbad on the 19**^ day of November, 2013, by
the following vote to wit:
AYES: Board Members Hail, Packard, Wood, Blackburn and Douglas.
NOES: None.
ABSENT: None.
ATTEST:
BARBARA ENGLESON, Setretary
LOCATION MAP
nr\T
PROJECT
PROJECT
LEGEND:
EXISVNG RECYCLED WATERLINES
RECYCLED WATER PIPELINE EXTENSION
QUARRY CREEK ON-SITE SYSTEM
PROJECT NAME RECYCLED WATER PIPELINE EXTENSION TO QUARRY CREEK
PROJECT
NUMBER
5205
EXHIBIT
PLOTTED BY: SCOTT EVANS PLOT DATE:11/6/13 PATH:D:\UT1UTIES DEPAR^klENT\DESI&^ DIVISI0N\AHLES\5208.DWG 6