HomeMy WebLinkAboutLFMP 15; LFMP Zone 15 Amendment; LFMP Zone 15 Amendment; 1998-11-17CITY OF CARLSBAD GROWTH MANAGEMENT PROGRAM LOCAL FACILITIES MANAGEMENT PLAN AMENDMENT ZONE 15 Prepared For: City of Carlsbad Planning Department 1635 Faraday Avenue Carlsbad, California 92008 Prepared By: Hofman Planning Associates Manitou Engineering Urban Systems Associates INDIVIDUALS RESPONSIBLE FOR THE PREPARATION OF THIS PLAN CONSULTANTS : HOFMAN PLANNING ASSOCIATES 5900 Pastour Court Suite 150 Carlsbad, CA 92008 (760) 438-1465 Bill Hofman Stan Weiler Stuart Fisk MANITOU ENGINEERING COMPANY 350 W. 9th Avenue Suite B Escondido, CA 92025 Frank Fitzpatrick Brian Regan URBAN SYSTEMS ASSOCIATES, INC. 4540 Kearny Villa Rd. Suite 106 San Diego, CA 92123 Andy Schlaefli Sam Kab CITY OF CARLSBAD: Don Rideout, Principal Planner Brian Hunter, Senior Planner David Hauser, Assistant City Engineer Ken Quon, Associate Engineer SPONSORING LAND OWNER: Russell Grosse Development 5850 Avenida Encinas, Ste. A Carlsbad, CA 92008 Russell Grosse Local Facilities Management Plan Zone 15 APPROVED BY: Planning Commission Resolution #2972, February 7, 1990 City Council Resolution #90- 10 1, April 10, 1990 **** Local Facilities Management Plan Amendment LFMP 15(A) Boundary Change APPROVED BY: Planning Commission Resolution #4171, September 3, 1997 City Council Resolution 97-647, October 21, 1997 **** Local Facilities Management Plan Amendment LFMP 15(B) Land Use Change APPROVED BY: Planning Commission Resolution #4291, July 1, 1998 City Council Resolution #98-337, November 17,1998 This page left blank TABLE OF CONTENTS I . EXECUTIVE SUMMARY ............................................................................................... 1 I1 . INTRODUCTION ........................................................................................................... 18 I11 . BUILD OUT PROJECTIONS ....................................................................................... 27 IV . PHASING PROJECTIONS ........................................................................................... 39 V . ZONE 15 REQUIREMENTS FOR PUBLIC FACILITIES AND SERVICES ........ 51 CITY ADMINISTRATIVE FACILITIES .................................................................... 52 Performance Standard ........................................................................................... 52 Facility Planning and Adequacy Analysis ............................................................. 52 Mitigation .............................................................................................................. 57 Financing ............................................................................................................... 57 LIBRARY FACILITIES ................................................................................................ 59 Performance Standard ........................................................................................... 59 Facility Planning and Adequacy Analysis ............................................................. 59 Mitigation .............................................................................................................. 64 Financing ............................................................................................................... 64 WASTEWATER TREATMENT CAPACITY ............................................................ 68 Performance Standard ........................................................................................... 68 Facility Planning and Adequacy Analysis ............................................................. 68 Mitigation .............................................................................................................. 73 Financing ............................................................................................................... 73 Facility Planning and Adequacy Analysis ............................................................. 75 Mitigation .............................................................................................................. 81 Potential Additional Sources of Park Acreage ...................................................... 81 Financing ............................................................................................................... 81 DRAINAGE FACILITIES ............................................................................................. 84 Performance Standard ........................................................................................... 84 Facility Planning and Adequacy Analysis ............................................................. 84 Mitigation .............................................................................................................. 90 Financing ............................................................................................................... 93 Facility Planning and Adequacy Analysis ............................................................. 95 Mitigation ............................................................................................................ 112 PARK FACILITIES ....................................................................................................... 75 Performance Standard ........................................................................................... 75 CIRCULATION FACILITIES ........................... .......................................................... 95 Performance Standard ........................................................................................... 95 TABLE OF CONTENTS (continued) FIRE FACILITIES ....................................................................................................... 126 Performance Standard ......................................................................................... 126 Facility Planning and Adequacy Analysis ........................................................... 126 Mitigation ............................................................................................................ 128 Financing ............................................................................................................. 130 Facility Planning and Adequacy Analysis ........................................................... 132 Mitigation ............................................................................................................ 137 Financing ............................................................................................................. 137 Facility Planning and Adequacy Analysis ........................................................... 138 Mitigation ............................................................................................................ 140 Financing ............................................................................................................. 140 Performance Standard ......................................................................................... 141 Facility Planning and Adequacy Analysis ........................................................... 141 Mitigation ............................................................................................................ 150 Financing ............................................................................................................. 151 Performance Standard ......................................................................................... 153 Facility Planning and Adequacy Analysis ........................................................... 153 Mitigation ............................................................................................................ 164 Financing ............................................................................................................. 164 FINANCING .................................................................................................................. 167 Facility Financing Matrix .................................................................................... 167 REFERENCES .............................................................................................................. 177 OPEN SPACE FACILITIES ........................................................................................ 132 Performance Standard ......................................................................................... 132 SCHOOL FACILITIES ................................................................................................ 138 Performance Standard ......................................................................................... 138 SEWER COLLECTION SYSTEM ............................................................................. 141 WATER FACILITIES .................................................................................................. 153 LIST OF EXHIBITS NO . - 1 2 3 4 5 5A 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 TYPE . Map Table Table Table Table Table Map Map Map Map Map Table Table Table Table Table Table Table Table Table Table Table Table Map Table Table Map Table Table Map Table Table Table Map Map Table Table Map Map Map TITLE . PAGE Zone 15 Location Map .................................................................... 3 ZONE 15 Existing Public Facilities Summary Sheet ...................... 4 ZONE 15 Build Out Public Facilities Summary Chart ................... 5 General Conditions for Zone 15 ...................................................... 7 Special Conditions For Zone 15 ...................................................... 9 Major Land Owners ...................................................................... 23 Major Land Owners ....................................................................... 24 General Plan Designations ............................................................ 25 Constraints Map ............................................................................ 29 Development Areas ....................................................................... 22 Zoning ........................................................................................... 26 Build Out Projections .................................................................... 31 Existing Land Use ......................................................................... 32 Developing Land Uses .................................................................. 33 Residential Build Out Projections ................................................. 36 Non-Residential Build Out Projections ......................................... 37 Build Out Population Projections .................................................. 38 AS REQUESTED. EXHIBIT ELIMINATED .............................. 40 AS REQUESTED. EXHIBIT ELIMINATED .............................. 41 Zone 15 Residential Phasing ......................................................... 42 AS REQUESTED, EXHIBIT ELIMINATED .............................. 44 AS REQUESTED, EXHIBIT ELIMINATED .............................. 45 Zone 15 Non-Residential Phasing ................................................. 46 City Administrative Facilities ....................................................... 53 City Administrative Phasing Projections ...................................... 56 City Administrative Financing Matrix .......................................... 58 Library Facilities ........................................................................... 60 Library Phasing Projections .......................................................... 65 Library Financing Matrix .............................................................. 67 Wastewater Facilities .................................................................... 69 Encina WPCF Capacity Analysis .................................................. 68 Carlsbad Sewer Service District Projections ................................. 72 Wastewater Financing Matrix ....................................................... 74 Park Districts ................................................................................. 76 Park Locations ............................................................................... 78 Park Phasing Projections ............................................................... 80 Park Financing Matrix ................................................................... 83 Drainage Basins - Zone 15 ........................................................... 85 Existing and Proposed Drainage Facilities .................................... 87 Drainage Watershed Boundaries ................................................... 92 LIST OF EXHIBITS (continued) 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 TITLE . PAGE Drainage Financing Matrix ........................................................... 94 Existing and Proposed Circulation ................................................ 98 1990 Circulation Trip Distribution ................................................ 99 1991 Circulation Trip Distribution .............................................. 100 1993 Circulation Trip Distribution .............................................. 101 Build Out Circulation Trip Distribution ...................................... 104 Proposed Fire Response Time ..................................................... 129 Fire Financing Matrix .................................................................. 131 1995 Circulation Trip Distribution .............................................. 102 2000 Circulation Trip Distribution .............................................. 103 AS REQUESTED, EXHIBIT ELIMINATED Existing Fire Response Time ...................................................... 127 Open Space Locations ................................................................. 133 Open Space Inventory ................................................................. 134 School District Locations ............................................................ 139 Sewer District Boundaries ........................................................... 142 Major Sewer Facilities Within Zone 15 ...................................... 146 Major Sewer Facilities Outside Zone 15 ..................................... 147 Sewer Financing Matrix .............................................................. 152 Water District Boundaries ........................................................... 155 Water Distribution System .......................................................... 156 Water Financing Matrix .............................................................. 165 Facility Financing Summary ....................................................... 168 I. EXECUTIVE SUMMARY The purpose of this document is to provide a plan for identifying the public facilities that will be needed to accommodate development within the Zone 15 area of the City of Carlsbad, as shown on Exhibit 1 on page 3. The Local Facilities Management Plan (LFMP) for Zone 15 was prepared pursuant to the City's Growth Management Program, as outlined in Chapter 21.90 of the Carlsbad Municipal Code. The plan incorporates and implements the 1986 Citywide Facilities and Improvements Plan.' This document is the first amendment to the Zone 15 LFMP. The original Zone 15 LFMP was adopted by the City of Carlsbad on April 10, 1990. Since the original approval of the Zone 15 LFMP, a number of land use, development and demographic changes have occurred. These changes resulted in inconsistencies between the desired development and the findings and special conditions for parks, drainage and circulation. In order to maintain consistency between the development requirements for Zone 15 and the changing land uses, this LFMP Amendment supersedes the previously approved Zone 15 LFMP. The primary purpose of this amendment is to revise the previous Zone 15 LFMF' special conditions to reflect a General Plan Amendment and Zone Change to accommodate the proposed development of the Terraces at Sunny Creek areas and the commercial site (Development Area l), which are east of El Camino Real and adjacent to both sides of College Boulevard. The Terraces at Sunny Creek project generally decreases the overall impacts to public facilities when compared to the office uses previously approved for this site. This change in land use is the catalyst which warrants the revisions to the LFMP Special Condltions. The revisions also consider the conditions that have been satisfied by other development, those that are no longer applicable due to other land use changes and those for which the timing of need has changed. In addition, a finance plan has been prepared as a part of this LFMP Amendment to provide additional details regarding' the financing of the necessary public facilities within Zone 15. The finance plan will accompany the LFMP Amendment in a separate document. The Introduction chapter provides the details regarding the land use changes and the justification for the preparation of this amendment. Finance Overview During the preparation of the Zone 15 LFMP Amendment it has become clear that no one financing mechanism can satisfy the complex infrastructure requirements of this zone and of the northeast quadrant. However, a combination of financing techniques can ensure conformance of The 1986 CFIP was adopted by City Council on September 23,1986 (CC Resolution No. 8797). 1 Zone 15 LFMP Amendment 1 June 16, 1998 future facilities as development occurs. A common set of goals for the financing of the major facilities can be stated as follows: 1. Provide feasible financing techniques to ensure that all facilities are provided in conformance with the adopted performance standards. 2. Provide for the implementation of financing techniques which consider the financial limitations associated with the high costs of infrastructure construction. 3. Provide for financing options which consider the needs of both the City and the property owners. This plan identifies when future public facilities are needed as growth occurs to ensure compliance with the adopted performance standards. A complete finance plan accompanies this LFMP Amendment which provides a description of the facility improvements to be made, timing of improvements, cost estimates, and funding sources. Zone 15 Requirements For Public Facilities Development assumptions are used to estimate the demand for public facilities generated by development in Zone 15 and are based on the eleven adopted Performance Standards in the Growth Management Program. Exhibit 2 on page 4 shows the current status of each facility with respect to the Performance Standard, given the existing amount of development within the Zone. Because there is currently a limited amount of development within Zone 15, the public facility demands are presently minimal and all Performance Standards are currently being met with the exception of drainage facilities. Exhibit 3 on page 5 provides a summary of public facilities adequacy through build out of Zone 15. Zone 15 LFMP Amendment 2 June 16,1998 Oceanside . 14 1 Existing Roadways 1 :.....a' 1 Zone Boundaries Proposed Roadways Zone 15 Location Map Hofman Planning Associates Exhibit 1 3 This page left blank EXHIBIT 2 ZONE 15 Existing Public Facilities Summary Sheet LFMP 15(B) Facility City Administrative Library Wastewater Treatment Capacity Parks Drainage Circulation Fire Open Space Schools Sewer Collection Water Distribution Conformance With Adopted Performance Standard Yes, existing facilities meet the adopted performance standard. Yes, existing facilities meet the adopted performance standard. Yes, existing facilities meet the adopted performance standard. Yes, Park District 2 (northeast quadrant) currently meets the adopted performance standard. No, existing drainage facilities do not meet the adopted performance standard. Yes, existing circulation facilities meet the adopted performance standard. Yes, existing fire facilities meet the adopted performance standard. Yes, existing open space meets the adopted performance standard. Yes, existing school facilities meet the adopted performance standard. Yes, existing sewer collection facilities meet the adopted performance standard. Yes, existing water distribution facilities meet the adopted performance standard. Zone I5 LFMP Amendment 4 June 16,1998 This page left blank EXHIBIT 3 ZONE 15 Build Out Public Facilities Summary Chart LFMP 15(B) Facility City Administrative Library Wastewater Treatment Facilities Parks Drainage Circulation Fire Open Space Schools Sewer Collection Conformance With Adopted Performance Standard Existing and planned facilities meet the adopted performance standard through build out. Existing and planned facilities meet the adopted performance standard through build out. Existing and planned facilities meet the adopted performance standard through build out. Park District 2 (northeast) will meet the adopted performance standard with the proposed mitigation measures through build out. Drainage facilities will meet the adopted performance standard with the proposed mitigation measures through build out. Circulation facilities will meet the adopted performance standard with the proposed mitigation measures through build out. Existing fire facilities meet the adopted performance standard through build out. Existing open space meets the adopted performance standard for existing and approved projects. An ongoing work program will assure the open space performance standard will be maintained through build out. . Existing and planned school facilities will meet the adopted performance standard through build out. Sewer facilities meet the adopted performance standard with the proposed mitigation measures through build out. Zone 15 LFMP Amendment 5 June 16,1998 Water Distribution Water facilities meet the adopted performance standard with the proposed mitigation measures through build out. Zone IS LFMP Amendment 6 June 16,1998 EXHIBIT 4 General Conditions for Zone 15 LFMP 15@) 1. 2. 3. 4. 5. 6. 7. 8. All development within Zone 15 shall conform to the provisions of Section 21.90 of the Carlsbad Municipal Code and to the provisions and conditions of this Local Facilities Management Plan. All development within Zone 15 shall be required to pay a public facilities fee pursuant to the standards adopted by the City Council on July 28, 1987, and as amended from time to time and all other applicable fees. Development in Zone 15 shall also be responsible for any additional fees to be incorporated into this plan that are found to be necessary to enable facilities to meet the adopted performance standard. The City of Carlsbad shall monitor all facilities in Zone 15 pursuant to Subsections 21.90.130(c), (d) and (e) of the Carlsbad Municipal Code. All development in Zone 15 shall be in conformance with the adopted Citywide Facilities and Improvements Plan as adopted by City Council Resolution 8797 on September 23, 1986. Periodic amendment to the Zone 15 Local Facilities Management Plan is anticipated to incorporate newly acquired data, to amend conditions and upgrade standards as determined through the required monitoring program. Amendment to this Plan may be initiated by action of the Planning Commission, City Council or property owners at any time. If a public facility or service is found not to be in conformance with an adopted performance standard during the yearly monitoring, or at any other time, the matter will be immediately brought before the City Council. If the City Council determines that a non-conformance does exist then no future building or development permits shall be issued unless an amendment to the CFIP or the LFMP for this zone is approved by the City Council which addresses those facility shortfalls and brings those facilities into conformance with the adopted performance standards. After adoption of this Plan by the City Council, no building permits will be allowed unless the performance standards are complied with. Approval of this LFMF' does not constitute prior environmental review for projects within Zone 15. All future projects within Zone 15 shall undergo environmental review per Title 19 of the Carlsbad Municipal Code. Any mitigation measures determined during a project's environmental review shall be complied within their entirety unless findings of overriding consideration are made by the City Council. Zone 15 LFMP Amendment 7 June 16,1998 9. Approval of this plan does not constitute prior discretionary review for projects within Zone 15. All future projects shall undergo review per Title 21 of the Carlsbad Municipal Code. The plan establishes the maximum allowable number of residential units for facilities planning purposes only. The plan does not guarantee any specific residential density. 10. Approval of any discretionary permit within Zone 15 shall be contingent upon the provision of adequate public facilities to satisfy the Public Facilities Element of the General Plan. At this time a Community Facilities District (CFD) has been formed to finance the construction of several Citywide facilities necessary to serve new development. If the subject Zone 15 property is not a participant within that district, the required General Plan consistency finding cannot be made. Therefore, no discretionary approvals, building permits, grading permits, final maps or other development permits will be issued or approved unless the subject property annexes into the CFD or an alternate financing mechanism is provided by the developer and approved by the City Council to finance the facilities legally applicable to Zone 15 that are included in the Community Facilities District. The following activities are exempt from this: grading, minor planning entitlements or minor construction as a part of ongoing agricultural operations, minor subdivisions and lot line adjustments for financing purposes or a Planned Community Master Plan or a Specific Plan. Any exemption is solely at the City's discretion. Zone I5 LFMP Amendment 8 June 16,1998 EXHIBIT 5 Special Conditions For Zone 15 LFMP 15@) The following Special Conditions apply specifically to development in Zone 15 and must be complied with in addition to the General Conditions for Zone 15. The Special Conditions are also listed separately under the analysis discussion of each facility. As previously discussed, the facility requirements have changed for only three facilities - Parks, Drainage and Circulation. The revisions as provided in this LFMP Amendment have not included changes to each facility chapter, except the Circulation chapter. The Circulation chapter was revised to reflect the slowed regional growth, the completion of many improvements and changes to land uses. The special conditions for Circulation facilities were also modified as necessary to ensure that the required level of service for circulation element roadways would be met. City Administrative Facilities No special conditions. Library No special conditions. Wastewater Treatment Capacity The following action shall be pursued jointly by each sewer district to ensure adequate wastewater treatment capacity through build out: A. Monitor Encina treatment plant flows on a monthly basis to determine actual flow rates and to have an early warning of capacity problems. Parks A. All development shall comply with Chapter 20.44 (Dedication of Land for Recreational Facilities) of the Carlsbad Municipal Code for impacts to Park District 2. Drainage A. All future development in Zone 15 will be required to construct specific future Zone 15 storm drain facilities identified in the approved Master Drainage Plan for each watershed basin. Zone I5 LFMP Amendment 9 June 16,1998 B. Prior to the recordation of any final map, for any specific project within Zone 15, the developers of that project are required to pay the appropriate required drainage area fees established in the latest approved Drainage Master Plan. C. Prior to issuance of a building permit within Watershed "B" of Zone 15, the sediment detention basin and restoration of Calavera Lake Creek shall be installed. This facility is identified in the 1997-1998 to Build Out CIP with previous appropriation for $1,120,000 to cover the cost of design and construction. D. WATERSHEDA 1. Prior to the recordation of the first final map, issuance of grading permit or building permit, whichever occurs first within Watershed A of Zone 15, the developers are required to financially guarantee the construction of the following facilities: a. 54" storm drain from northwestern Zone 15 to future Cannon Road. E. WATERSHED B 1. Prior to the recordation of the first final map, issuance of grading permit or building permit, whichever occurs first within Watershed B of Zone 15, the developers are required to financially guarantee the construction of the following facilities: a. 36" storm drain north of future Cannon Road. b. BJ (48") storm drain south of future Cannon Road. c. 78" storm drain along future Cannon Road alignment. F. WATERSHED C No special conditions are required. G. WATERSHEDD 1. Prior to the recordation of the first final map, issuance of grading permit or building permit, whichever occurs first within the following subareas identified within Watershed D of Zone 15, the developers are required to financially guarantee the construction of the following drainage facilities. Zone 15 LFMP Amendment 10 June 16,1998 Development Area 1: a. BL (90" - 78") storm drain along future College Boulevard between El Camino Real and the eastern boundary of Development Area 1. Development Area 2: b. Facility BM, an enhanced natural channel proposed to carry drainage to Agua Hedionda Creek. Development Area 2 and Development Area 4 c. The remaining portions of Facility BL that includes the storm drain along College Boulevard from the eastern boundary of Development Area 1 to Agua Hedionda Creek and the potential for a bridge structure on College Boulevard across Agua Hedionda Creek. The need for a bridge structure versus a box culvert will be determined at the time of proposed development. 2. Prior to drainage improvements within the Rancho Carlsbad Mobile Home Park and prior to the recordation of a final map for any project within Watershed D, a drainage analysis must be conducted that demonstrates to the satisfaction of the City Engineer that any proposed development will not have a greater flooding effect than the existing 100 year flood for downstream facilities. Circulation The format of the special conditions for circulation facilities has been modified to create a better understanding of the intent of this LFMP Amendment. The special conditions have been divided into five categories directly corresponding to the five development areas within Zone 15. These areas are depicted on Exhibit 5A on page 22. A. An ongoing monitoring program shall be established to evaluate the aspects of improvements, development, and demand on circulation facilities. The construction of improvements is based upon the projected demand of development in the zone and the surrounding region. The construction schedule may be modified without amendment to this plan, however, any deletions or additions to the improvements will require amending this local plan. B. Prior to approval of any tentative map adjacent to College Boulevard within Zone 15, outside the boundary of Development Area 1, the specific alignment for College Boulevard between the northerly boundary of Zone 15 and El Camino Real must be established. This shall include the necessary environmental clearances and required Zone 15 LFMP Amendment 11 June 16,1998 C. public hearings so that construction of College Boulevard can accommodate future development. The funding for the construction of College Boulevard will be guaranteed as provided by the Zone 15 Finance Plan. Prior to recordation of the first final map, issuance of grading permit or building permit, whichever occurs first, within each of the specifically identified development areas of Zone 15, a financing program guaranteeing construction of the following circulation improvements shall be approved: 1. DEVELOPMENT AREA 1 a. College Boulevard 1. College Boulevard between El Camino Real and the northern boundary of Development Area 1 shall be constructed to full width arterial standards. b. College Boulevard and Cannon Road 1. Prior to recording a final map or the issuance of a grading permit or building permit, the applicant shall enter into a secured financial agreement in a form acceptable to the City Council that will secure its fair share of the cost of College Boulevard from El Camino Real to the northern boundary of Zone 15 and Reach 3 of Cannon Road. C. El Camino Real 1. Construction of half street improvements for El Camino Real to prime arterial standards including landscaped median along the frontage of the developing property. 2. Construction of meQan from the northwestern boundary of Development Area 1 to the existing improvements south of Rancho Carlsbad Drive. 3. Construction of transition improvements on the east side of El Camino Real from the northwestern boundary of Development Area 1 northerly to a distance determined by the City Engineer. Zone 15 LFMP Amendment 12 June 16,1998 2. DEVELOPMENT AREA 2 a. College Boulevard and Cannon Road 1. Prior to recording a final map or the issuance of a grading permit or building permit, a financial guarantee to the satisfaction of the City Council shall be in place that will provide for a pro-rata share of the cost of College Boulevard from El Camino Real to the northern boundary of Zone 15 and Reach 3 of Cannon Road. 2. Development within this area shall be obligated to construct only those portions of College Boulevard and Cannon Road offsite from the development which are necessary to serve the respective development in accordance with City Standards and to the satisfaction of the City Engineer. b. College Boulevard 1. Construction of half street improvements for College Boulevard to major arterial standards including landscaped median along the property fronting College Boulevard. This condition applies to the frontage of the property being developed, if any. 3. DEVELOPMENT AREA 3 a. College Boulevard and Cannon Road 1. Prior to recording a final map or the issuance of a grading permit or building permit, a financial guarantee to the satisfaction of the City Council shall be in place that will provide for a pro-rata share of the cost of College Boulevard from El Camino Real to the northern boundary of Zone 15 and Reach 3 of Cannon Road. 2. Development within this area shall be obligated to construct only those portions of College Boulevard and Cannon Road offsite from the development which are necessary to serve the respective development in accordance with City Standards and to the satisfaction of the City Engineer. b. Cannon Road 1. Construction of half street improvements for Cannon Road to major arterial standards including landscaped median along any developing property which fronts onto Cannon Road. Zone 15 WMP Amendment 13 June 16,1998 2. Construction of the center two lanes separated by a raised improved median from College Boulevard to the most easterly road constructed to provide access for the developing property. 3. Conditions 3.b.l and 3.b.2 noted above may be omitted when in the opinion of the City Engineer either one or both of the following conditions exist : a. The Development Area 3 property is precluded from access to Cannon Road due to the requirements of the Habitat Management Plan; or, The proposed development of the property does not access Cannon Road and lacks adequate Anexus@ for construction of such improvements in relation to the proposed development . b. 4. DEVELOPMENT AREA 4 a. College Boulevard and Cannon Road 1. Prior to recording a final map or the issuance of a grading permit or building permit, a financial guarantee to the satisfaction of the City Council shall be in place that will provide for a pro-rata share of the cost of College Boulevard from El Camino Real to the northern boundary of Zone 15 and Reach 3 of Cannon Road. 2. Development within this area shall be obligated to construct only those portions of College Boulevard and Cannon Road offsite from the development which are necessary to serve the respective development in accordance with City Standards and to the satisfaction of the City Engineer. b. College Boulevard 1. Construction of half street improvements for College Boulevard to major arterial standards including landscaped median along the property fronting College Boulevard. This condition applies to the frontage of the property being developed, if any. C. El Camino Real 1. Completion of half street improvements for El Camino Real to prime arterial standards including landscaped median from Rancho Carlsbad Drive to the southeastern boundary of Development Area 4. This condition applies to the frontage of the property being developed, if any. Zone 15 LFMP Amendment 14 June 16,1998 5. DEVELOPMENT AREA 5 a. El Camino Real 1. Completion of half street improvements for El Camino Real to prime arterial standards including landscaped median along the frontage of the developing property between Development Area 1 and Cougar Drive. 2. Prior to final map approval or issuance of a building permit the developing property owner shall pay their fair share contribution for the installation of the El Camino Real improvements pursuant to the requirements of the El Camino Real median reimbursement agreement dated May 6, 1988. No special conditions. Open SDace A. All future development within this zone shall be required to show how it contributes to meeting the open space performance standard above and beyond meeting all other City standards and development regulations and that the development does not preclude the provision of performance standard open space at build out of Zone 15. B. Open space compliance will be monitored annually and as individual projects are reviewed within this zone. C. Prior to the approval of any development within this zone, the Planning Director shall be required to find that the development does not preclude the provision of performance standard open space at build out of Zone 15. Schools The special condition for school facilities is as follows: A. Prior to the approval of any final map or the issuance of any permits within Zone 15, the applicant for the final map or permit shall submit evidence to the City that impacts to school facilities have been mitigated in conformance with the City's Growth Management Plan to the extent permitted by applicable state law for legislative approvals. If the mitigation involves a financing scheme such as a Mello-Roos Community Facilities District which is inconsistent with the City's Growth Management Plan including City Council Policy Statement No. 38, the developer shall submit disclosure documents for Zone 15 LFMP Amendment 15 June 16,1998 approval by the City Manager and City Attorney which shall disclose to future owners in the project, the maximum extent possible, the existence of the tax and that the school district is the taxing agency responsible for the financing district. Sewer District The original Zone 15 LFMP required a financial guarantee for the South Agua Hedionda interceptor system. However, there is currently capacity through the North Agua Hedionda (NAH) sewer conveyance system.* The Carlsbad Municipal Water District (CMWD) will consider allowing additional connections to the NAH line as long as adequate capacity remains available. CMWD has agreed in concept to allow Development Area 1 to utilize the NAH line, provided adequate capacity to serve Development Area 1 remains available at the time of development and provided that Development Area 1 pays its proportional share of the cost of constructing SAHI. Written verification should be obtained from the Carlsbad Municipal Water District during the processing of Development Area 1. A. Prior to the recordation of the first final map, issuance of a grading permit or building permit, whichever occurs first, for any development in Zone 15, a financing mechanism guaranteeing the construction of the following sewer facilities shall be provided: 1. 2. 3. 4. 5. Construction of these facilities is not required for the development of Development Area 1. Written verification regarding excess capacity in NM should be obtained from the Carlsbad Municipal Water District during the processing of Development Area 1. SAHl adjacent to Hidden Valley Road. SAH2 adjacent to Hidden Valley Road. Lift Station adjacent to future Cannon Road. SAH3 adjacent to Future Cannon Road. SAH4 adjacent to Future Cannon Road. B. Sewer Basin 15A 1. Prior to the recordation of the first final map, issuance of a grading permit or building permit, whichever occurs first, for any development in Sewer Basin 15A(Exhibit 56 on page 146 of the original Zone 15 LFMP), a financing mechanism guaranteeing the construction of the following sewer facilities shall be provided: a. b. SAHT2A adjacent to Future Cannon Road. SAHT2C adjacent to Future Cannon Road. Bill Plummer, CMWD, February 1996 2 Zone 15 LFMP Amendment 16 June 16,1998 C. Sewer Basin 15B 1. Prior to the recordation of the first final map, issuance of a grading permit or building permit, whichever occurs first, for any development in Basin 15B outside of Development Area 1, a financing mechanism guaranteeing the construction of the following sewer facilities shall be provided: a. b. c. SAHTlD adjacent to Sunny Creek Rd. SAHTlE adjacent to Sunny Creek Rd. SAHTlG adjacent to El Camino Real Water District A. All future development in Zone 15 shall be subject to requirements per the Water Reclamation Master Plan as determined by the City Engineer. Any water reclamation facilities necessary to accommodate future development must be guaranteed prior to the recordation of a final map, issuance of a grading permit or building permit, whichever occurs first for any project in Zone 15. B. Water facilities for Zone 15 shall be provided at the time of development to the satisfaction of CMWD. C. Prior to or commensurate with installation of Zone 15 water facilities, CMWD shall determine that sufficient water facilities are in place to serve Zone 15. D. All development within Zone 15 shall pay the appropriate water fees established by Ch4WD. Zone 15 LFMP Amendment 17 June 16,1998 This page left blank 11. INTRODUCTION This Local Facilities Management Plan completes the second phase of Carlsbad's overall Growth Management Program for Zone 15. Phase One of the Growth Management Program was completed with the adoption of the 1986 Citywide Facilities and Improvements Plan (CFIP 86). For purposes of public facilities analysis the '86 CFIP separated the City into 25 Local Facilities Management Zones as shown on Exhibit 1 on page 3. Zone 15 is divided into several development areas. These development areas include a large Open Space designated area, a Habitat Conservation Area, the Rancho Carlsbad mobile home park, and Development Areas 1 through 5. The Open Space area currently contains a general plan designation of OS (Open Space). This area will remain as open space. The Habitat Conservation Area was formally known as The Highlands and was approved for 740 dwelling units. Due to the expiration of the tentative map and existing environmental issues, this area is now intended to be used for habitat mitigation. The Rancho Carlsbad mobile home park contains 502 units. Development Area 1 proposes to be developed with commercial uses on the northwest corner of College Boulevard and El Camino Real with residential on the northeast corner of College Boulevard and El Camino Real. Future development of the remaining areas has not been determined at this time. However, since the general plan identifies these areas as residential and open space, the Zone 15 LFMP assumes development to occur at the Growth Control Point for these areas. As mentioned in the Executive Summary, this is the first amendment to the Zone 15 LFMP. A General Plan Amendment (GPA) was submitted with a Tentative Map for a residential development within Development Area 1. The land use changes in Development Area 1, in conjunction with slower than anticipated growth citywide and within Zone 15, are the primary reasons prompting the need to review and modify the Zone 15 LFMP. The Zone 15 LFMP Amendment will ensure that the impacts created by the GPA will not result in an increase in the demand for public facilities within Zone 15. The GPA will require the transfer of 229 dwelling units from the dwelling unit bank for the Northeast Quadrant to the residential portion of the Development Area 1. Transferring these units will not increase the development impacts originally anticipated in the Zone 15 LFMP. In fact, the transfer of these units will result in a net decrease in the overall impacts from future development within Zone 15. This decrease of impacts will occur due to the General Plan Amendment that proposes to change the existing high intensity RWC/O land use designation as approved as a part of the Sycamore Creek Specific Plan to RM within the area now identified as the residential portion of the Development Area 1. Therefore, most of the facilities identified in the original LFMP will experience decreased impacts to facilities and none will show an increase in impacts. The revision to the Zone 15 LFMP includes updating the build out projections for residential and nonresidential development within Zone 15. The build out land use designations are based on the General Plan Amendment processed concurrently with this LFMP Amendment. As a part of Zone 15 LFMP Amendment 18 June 16,1998 the build out projections, the LFMP phases or estimates the zone's development on a yearly basis until build out is reached. Phasing is done to predict future facilities= demands. The adequacy of public facilities is analyzed according to this demand. The analysis includes an inventory of existing and proposed facilities, a phasing schedule that establishes the timing for the provision of facilities in relationship to demand, and a financing plan that establishes methods of funding needed facilities. Since the plan is a regulatory document, each facility section contains conditions to ensure that facilities will conform to the adopted performance standards. Mandatory compliance with the plan and conditions will assure the adequacy of facilities within Zone 15. As mentioned previously, the individual facility chapters, except Circulation, have not been revised with this LFMP Amendment. Exhibit 1 on page 8* indicates where Zone 15 is located within the City. Exhibit 2 on page 4* provides a summary of existing public facilities adequacy for Zone 15 and Exhibit 3 on page 5* provides a summary of public facilities adequacy through build out for Zone 15. Development Assumptions The primary growth management consideration with this L;FMp amendment is that the future development will not increase the demand on public facilities beyond that anticipated in the original Zone 15 LFMP. A large portion of Zone 15, known as the Carlsbad Highlands, will not be developed. In fact, this area is now used for habitat mitigation land. Therefore, the impacts from the development of this area will not occur as anticipated. Since the Carlsbad Highlands was approved for 740 dwelling units and this area will be used for habitat mitigation purposes, these units will eventually be added to the Northeast Quadrant dwelling unit bank. At this time, 361 of the 740 dwelling units have been added to the Northeast Quadrant dwelling unit bank. The remaining 379 units are anticipated to be added in the future when the land is officially set aside for habitat mitigation. As indicated previously, the general plan amendment in the residential portion of Development Area 1 requires the transfer of 229 dwelling units from the Northeast Quadrant dwelling unit bank. Although this transfer increases the number of dwelling units beyond that which was originally anticipated for Development Area 1, the overall impacts to Zone 15 area are currently decreased by the impacts that would have been created by the remaining 132 dwelling units (361 dwelling units added to unit bank from Zone 15 subtracted by 229 dwelling units transferred to Development Area 1 equals 132 remaining dwelling units in unit bank from Zone 15). A. PLANOVERVIEW This LFMp Amendment provides a revised list of the special conditions necessary to ensure that public facilities necessary for development within the zone will be provided concurrent with their need. *Page number reflects original pagination for this exhibit-see index for current page number. Zone 15 LFMP Amendment 19 June 16,1998 The plan is divided into seven parts as follows: I- D- III- Iv- v- VI - VD - Executive Summary: Summarizes the plan and highlights all conditions proposed by the plan. Introduction: Provides an introduction to the format and content of the plan. Build Out Projections: Projects the ultimate amount of development in Zone 15, along with itemizing existing, developing, and future land uses. Phasing: Attempts to project how and when development will be phased in Zone 15. Analysis of Public Facilities Requirements: Provides a complete description and analysis of when and how each facility will be provided and financed based on build out projections and phasing assumptions. Finance: Provides a summary of the financial alternatives available to fund each facility and a discussion of the LFMP's impact on City finances. Appendices: Provides the technical materials used in preparation of this plan. The most detailed part of the plan is Part V. This part is divided into eleven separate sections, one for each facility. Each section provides a detailed analysis of the facility. If a facility is not conforming with the adopted performance standard, there will be a discussion describing this situation, a description of mitigation or alternatives, and a financing discussion. Each facility section will conclude with adequacy findings. Adequacy findings summarize whether or not the public facility conforms with the adopted performance standard. B. OVERVIEW OF MANAGEMENT ZONE 15 Management Zone 15 is located in the northeast quadrant of Carlsbad as shown on Exhibit 1 on page 3. It is bounded by Zone 14 to the northhorthwest, El Camino Real to the west, Zones 16 and 5 to the south and the City of Oceanside to the east. Zone 15 is approximately 1,224 net acres in size, Exhibit 6 on page 23 lists the major land owners within Zone 15 and Exhibit 7 on page 24 shows the location of their holdings. Primarily a residential area, Carlsbad's existing General Plan calls for residential land uses ranging in density from Low (0-1.5 dwelling unitdacre) to Medium (4-8 dwelling Zone 15 LFMP Amendment 20 June 16,1998 units/acre). Nonresidential land uses within Zone 15 consist of general plan open space (OS), commercial (C), and planned industrial (PI). The General Plan Amendment processed concurrently with the LFMP Amendment changed the land use categories from high density residential, commercial, and office uses (RWC/O-1 and RWC/O-2) to medium and high density residential uses (RM-2 and RH-1). The General Plan Designations, within Zone 15 are shown on Exhibit 8 on page 25. Two Specific Plans have been approved within Zone 15. The Sunny Creek Specific Plan (SP-191) encompasses approximately 307 acres entirely within Zone 15. This plan established a 2.0 du/acre average density and general guidelines, but did not approve specific development plans. The Sycamore Creek Specific Plan (SP- 190) encompasses approximately 59 acres and provides guidelines for development of a mixed use, commercial, office, residential development. The Sycamore Creek Specific Plan was amended concurrently with the LFMP Amendment. The amended specific plan removed the area north and east of the intersection of College Boulevard and El Camino Real. The land use zoning within Zone 15, is shown on Exhibit 9 on page 26. As Exhibit 9 shows, that the land use zoning in Zone 15 is primarily residential. The zone is comprised of Residential Agricultural with minimum lot size of 10,000 square feet (R-A- lo), Rural Residential Estate (R-E), Residential Mobile Home Park (RMHP), Single Family with minimum lot size of 20,000 square feet (R-1-20), Residential Agricultural with minimum lot size of 2.5 acres (R-A-2.5), and Limited Control (L-C). The L-C zoning will ultimately be amended to be consistent with the general plan. A zoning designation of Residential Density Multiple (RDM) is designated for the residential portion of Development Area 1 to allow for a small lot single family detached development and an affordable housing project. Nonresidential zoning includes Commercial (C-2) and Manufacturing with a Qualified Development Overlay (MQ). The General Plan Land Use designations for Zone 15 are broken down into subarea. These subarea allow easier identification of public facilities demand and supply. These subarea are used consistently throughout this plan. Existing development in Zone 15 consists of a 502-unit mobile home park and 18 single- family dwelling units scattered throughout the zone. Zone 15 LFMP Amendment 21 June 16,1998 Development Areas lm Hofman Planning ._ dmAssoci at es Exhibit 5A 3498 22 ZONE 15 EXHIBIT 6 Property Owners List MAP KEY GROSS NUMBER OWNERSHIP APN CT NUMBER ACREAGE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 29 BARLOW STATE OF CALIFORNIA CANTARlNl COSTA REAL M W D COSTA REAL M W D REGENTS OF U C EBRIGHT GRIBBLE GROSSE HAGAMAN KAT0 HOLLY SPRINGS LTD KELLY WESTERN LAND MANDANA CAL CO MANDANA CAL CO PILSBURY & EVANS REGENTS OF U.C. LUBLINER CANAM PROPERTIES WELAND WESTERN LAND WESTERN LAND WESTERN LAND KELLY BARBER WRISLEY TCHANG 209-060-23 168-050-02 168-050-30 209-070-02 168-050-08 169-011-24 169-230-28 209-040-1 5 209-040-29 168-050-29 209-070-01 169-230-02 209-040-02 209-040-33 209-040-28 209-070-04 209-070-05 209-070-08 168-050-06 168-050-07 168-050-03 168-050-25 168-050-26 209-060-48 209-060-53 209-060-1 1 209-040-27 209-070-07 209-070-03 209-090-1 2 169-230-03 169-230-04 169-230-05 169-230-07 169-230-12 169-230-18 169-230-23 169-230-29 2 0 9 - 0 6 0 - 5 5 209-060-59 209-090-01 209-090-02 209-090-03 209-090-04 209-090-05 209-090-06 209-090-07 209-090-08 209-090-09 209-090-10 209-090-1 1 209-060-54 168-050-23 168-050-24 209-060-03 209-060-06 209-060-10 209-060-14 209-060-58 209-060-56 209-060-57 209-040-35 168-050-31 SP 191 SP 191 SP 191 SP 191 SP 191 SP 191 SP 191 SP 191 SP 191 CT 96-02 (1) CT 96-02 CT 96-02 CT 96-02 CT 96-02 CT 96-02 CT 96-02 CT 96-02 CT 96-02 CT 96-02 CT 96-02 CT 96-02 CT 96-02 (1) (1) (2) 5 00 25 12 57 88 54 63 138 50 3.12 0 11 58.77 51.87 5.51 9.59 4 70 10.79 6.58 5.24 21.23 31.85 20.00 14.10 17.11 57.71 63.45 94.1 1 11.35 0.55 3.56 5.00 186.66 3.84 3.43 48.83 13.41 13.69 5.42 10.63 1 .89 4.22 4.80 22.28 47.27 3.73 3.85 3.59 1.09 2.09 2.45 4.31 2.21 2.91 17.60 0.59 17.63 86.39 2.02 49.89 6.44 6.56 31.48 2.00 1.22 2.71 59.59 2.85 168-050-32 65.90 TOTAL (3) 1522.98 NOTES: (1) A PORTION OF THESE PROPERTIES LIES WITHIN SP 191. (2) APPROX. 20 ACRES OF THE PROPERTY SHOWN ON EXHIBIT 7 IS UNDER 50 YEAR LEASE TO WESTERN LAND. (3) THE TOTAL GROSS ACREAGE DIFFERS IN THIS TABLEWHEN COMPARED TO THE GROSS ACREAGE IN THE CONSTRAINTS TABLE. THE DIFFERENCE IS 8.03 ACRES AND IS DUE TO PLANIMETER MEASUREMENT ERROR OF LESS THAN 0.5%. 23 n 76 I: 24 RLM Low-Medium Density (0-4 du/ac) RM Medium Density (4-8 du/ac) RH High Density 05-23 du/ac) N 0 N-RES I DE NTI A1 os Open Space C Community Commercial PI Planned Industrial MIXED USE RH/C/O High Density/Community CommerciaVOff ice General Plan Designations TW Hofman Planning Exhibit 8 .,mAssoci at es 3498 25 R-A Residential Ag ri cu It u ral R-E Rural Residential Estate R-1 One-Family Residential RMHP Residential Mobile Home Park RDM Residential Density Multiple 1-c limited Control* NON-RES1 DENTIAL c-2 General Commercial MQ Industrial/Qualified Development Overlay Zone os Open Space * Ultimate Zoning to be consistent with General Plan Land Use Zoning 1m Hofman Planning amAssoci at es Exhibit 9 3-4-98 26 This page left blank 111. BUILD OUT PROJECTIONS To properly assess and plan for facilities to serve Zone 15, it is necessary to project the type and intensity of land use as the zone builds out. These build out projections define land use intensity and corresponding facilities= demands. The build out projections for Zone 15 are based on the Sunny Creek Specific Plan (SP 191), the current Carlsbad General Plan. The methodology used in compiling these build out projections is consistent with that used in the 1986 CFIP. The methodology is briefly described as follows: A. GENERAL PLAN LAND USE General Plan Land Use Designations were plotted on a 1" = 200' base map. A reduction of this map is shown on Exhibit 10 on page 29. These designations were divided into subarea to aid in facility analysis. The gross acreage of each subarea was determined by planimeter measurement. Exhibit 11 on page 31 summarizes these acreage calculation^.^ Appendix 1 provides a map of the sub areas at 1'' = 200' scale. B. GENERALIZED CONSTRAINTS ANALYSIS Consistent with adopted City policies and ordinances, development constraints within each subarea were identified. Constraints that may have existed on land that is developed or has land use approvals were not included in this analysis. Constraints fall into two basic categories: 1) full and 2) partial. Fully constrained areas cannot be used to calculate residential density and are considered undevelopable. Fifty percent of partially constrained residential areas can be used in residential density calculations. Since full development constraints occasionally overlap each other, for accounting purposes, constraints are organized in a hierarchy beginning at 'A' - major power line easement and ending in 'J' - slopes between 25% - 40%. When this occurs, only the area of the highest level constraint is calculated for build out projection purposes. It is recognized that underlying constraints exist and that these constraints as well as others will be defined by specific environmental review for individual development projects. The gross acreage calculations per sub-area shown on Exhibit 11 may differ slightly from those shown per parcel on Exhibit 6. This is because the acreage on Exhibit 6 are taken from assessor parcel maps whereas those on Exhibit 11 are determined by planimeter measurement at 200' scale accuracy. Zone 15 LFMP Amendment 27 June 16,1998 Full environmental constraints are as follows: A. B. C. D. E. F. G. H. I. Major (r 69 kv) power-line easements Proposed circulation element roadways Railroad track beds or R-O-W Slopes of 40% or more in grade Significant riparian, or woodland habitats Significant wetlands Floodways Permanent bodies of water Other significant environmental features as Environmental Review process. determined by the Partial Developmental Constraints include: J. Slopes between 25-40% in grade: only 1/2 of the area within slopes between 25-40% in grade can be used in residential density calculations. Also included in the constraints analysis is the programming of: K. Planned school facilities The approximate area and location of school facilities are indicated in the General Plan. The beneficial and efficient provision of these facilities requires a minimum area of land free of development constraints. Consistent with City and school district policy, the minimum acreage identified by the General Plan for school facilities was not used in the applicable subarea's residential density calculations. 28 June 16,1998 Zone 15 LFMP Amendment 29 30 AWtp (1) Gmwal Plm Lnd Uaa Gro*r FULL I PARTIAL ISCHOOLS DanpMtm Aenr ABC D E F G H I Totali J u2I K RL-1 73.08 3.60 3.601 10.5 5.251 - . Net DeMbDabm AEnr 64 23 165 25 22948 231 27 138 59 4640 49 82 10 70 385 121 97 10 83 10 64 2 71 680 174 160 420 3048 31 05 717 73 BB 41 3058 2 18 3.17 17.60 261 11 78 61 95 5077 11250 0.00 0.00 1224.26 ism iies 1068.36' 0.10 4.40 0.30 0.30 2.80 0.20 3.30 0.30 4.20 1.38 1531.011 I 21.54 I 69.761 32.10 I 42.48I l6.W 1290 2470 1235 1650 3520 176C 1460 3150 1725 450 100 050 560 220 110 ow 060 030 220 150 075 280 2010 100s 350 080 040 030 200 100 OW 050 025 520 138 150 020 010 250 300 150 040 080 040 3620 am 2040 'E! oo( 10213 11897 5948 0.00 12267 180.45 80.23 0.10 0.05 1.20 0.00 0.00 0.41 1.30 0.65 5.40 0.30 0.15 73.10 45.80 22.90 0.00 000 000 78.50 46.10 23.05 azo 0.00 202.78 207.05l 103.98 0.M 31 This page left blank C. EXISTING LAND USE Existing land uses within each subarea as of January 1, 1998 were identified. Residential density as well as square footage and type of nonresidential structures were itemized. Exhibit 12 on page 32 provides a detailed breakdown of existing land uses. Residen ti a1 : EXHIBIT 12 Existing Land Use AS OF 1/1/98 General Plan Project Land Use Gross Subarea Acres Proiect Name Proiect # DU's RM- 1 88.4 Rancho Carlsbad N/A 502 In addition to Rancho Carlsbad Mobile Park, there are 18 single family dwelling units scattered throughout the Zone. D. DEVELOPING LAND USE Developing Land Use is a category which defines the status or stage of a land use proposal or project in the development process. The development process begins when a development application is submitted to the City. Various procedures are followed depending on the type of application submitted. In all cases, applications are reviewed to ensure that all City standards are met and there is conformance with all previous discretionary approvals prior to finalizing the projects and issuing building permits. Once the project has received final occupancy, the development process ends and the Land Use is identified as an existing land use. Land use in the developing process was identified by a review of the City of Carlsbad Planning Department development records. A detailed itemization of developing land uses is provided in Exhibit 13 on page 34 (page number reflects original pagination for this exhibit-see index for current page number). After receiving tentative discretionary approval, a land use is considered approved. The approval is valid until the land use is developed and occupied or the tentative approval expires. Zone 15 LFMP Amendment 32 June 16,1998 EXHIBIT 13 ZONE 15 - DEVELOPING LAND USE Genenl Plan SUB ARE4 RL-2 AL kM-1 RLM-2 RLM-2A RLM-3 RLM-3A RLM-4 RLM4 RLM-5 RLM-6 RLM-7 RW RLMBA RLM-9 RLM-9A RLM-10 RLM-1 1 Number 263.58 263.12 195.19 51.40 SP191 1) 56.52 8.80 14.73 11.94 3.56 12.00 , 3.12 3.20 19.08 SP 191 1) 5.00 SP191 11 11.00 SPl9l 1) ' 134.82 SP191 1) (&Of lllllQQ8) Ueveloping Status 01 C Total Exlsbng -1 NOTES: (1) SP 191 is the Sunny Creek Specific Plan. This plan established densities and general guidelines for development but did not approve any dwelling units. (2) This is a part of Development Area 1. (3) RM-2 was previously identified as RHICIO-1 and RHICIO-3. (4) One-third of RHICIO-2 net acreage is used for residential build out projections. (5) Two-thirds of the total RHICIO-2 net acreage is used for non-residential build out projections. (6) C-1 received approval for 175,000 of commercial area during the processing of the Sycamore Creek Specific Pian. (7) SP 190 is the Sycamore Creek Specific Pian. However, the Zone 15 LFMP allows for a maximum of 305,530 square feet. Zone 15 LFMP 33 June 10,lBM E. BUILD OUT PROJECTIONS CALCULATIONS Residential and nonresidential build out projections as of January 1, 1998 for Zone 15 are shown on Exhibit 14 and 15 on pages 37 and 38 (page numbers reflects original pagination for these exhibits-see index for current page numbers). Build out projections are calculated as follows: 1. Residential Build Out Proiections The net developable acreage of each residential land use subarea is multiplied by the adopted Growth Management control point as shown below: General Plan Land Use Designation RL RLM RM RMH RH Growth Management Control point4 1 .o 3.2 6.0 11.5 19.0 The result provides the base residential dwelling unit build out projections for each subarea consistent with the passage of Proposition E on November 4, 1986. Both existing and approved dwelling units are subtracted from this yield to indicate the amount of future residential development in the zone. 2. Non-Residential Build Out Proiections The net developable acreage of each nonresidential land use subarea is multiplied by either .3 or .4 as described below. The resultant figures provide an estimate of ultimate land use intensity as defined by building square footage for each subarea. This estimate is used for facility planning purposes. The Growth Management Program uses the .3 factor to estimate building square footage yields on either 1) unapproved and unimproved, vacant, unconstrained land or on 2) urbanized, underdeveloped, nonresidential sites. These urbanized, under- developed sites typically exhibit significant man-made constraints to development. Primary constraints are: a) compatibility with surrounding land uses and b) proper interfacing with existing infrastructure and public facilities. Dwelling unit per acre of non-constrained land pursuant to Sections 21.53 and 21.90 of the Carlsbad Municipal Code. 4 Zone 15 LFMP Amendment 34 June 16,1998 The .4 factor is used to estimate building square footage yields on unconstrained lots which have approved land use projects and have all infrastructure in place. The area identified as C-1 was previously approved for 175,000 square feet via the Sycamore Creek Specific Plan (SP 190). However, in order to identify the maximum potential development for this site, the net acreage for the Commercial Site of 17.6 acres was multiplied by the .3 factor which resulted in a maximum commercial area of 229,997 square feet. The nonresidential build out projection is 305,530 square feet. Due to the changes to the nonresidential land use designations, the overall nonresidential build out projection has decreased by 529,899 square feet when compared to the nonresidential square footage identified in the Zone 15 LFMP originally approved in 1990. The .3 factor was used to estimate square footage for all other nonresidential areas. F. BUILD OUT POPULATION PROJECTION The build out population projection for Management Zone 15 was determined by applying a population generation rate of 2.3 178 persons/dwelling unit. The build out population projections for Zone 15 are shown on Exhibit 16 on page 39 (page number reflects original pagination for this exhibit-see index for current page number). These build out population projections are used consistently throughout this plan for the purpose of predicting demand for public facilities. June 16, I998 Zone 15 LFMP Amendment 35 EXHIBIT 14 (As of 1/1/98) Zone 15 - LFMP Residential Build Out Projections RLM-12 2) RLM TOTAL General Plan Land Use 31.05 717.73 I RLM-2 RLM.2A 2) RLM-3A 2) RLM-4A 2) RLM-5 RLM-6 RLM-7 RLM-8 RLM-8A RLM-9 RLM-9A 2) RLM-10 2) RLM-11 2) RLM-3 RLM-4 1,847 Net Developable Acres 64.23 165.25 229.48 231.27 138.59 46.40 49.82 10.70 3.85 121.97 10.83 10.64 2.71 6.80 1.74 1.60 15.08 4.20 30.48 I 14 I 0 GMCP 1) 1 .oo 1 .oo 3.20 3.20 2.88 3.20 2.88 3.20 2.88 3.20 3.20 3.20 3.20 3.20 3.20 2.88 2.88 2.88 2.88 RM-2 4) RM TOTAL RH-1 6) TOTAL RES RH/C/O-2 5) os-2 30.58 118.99 2.18 1,068.38 1.06 19.00 61.95 0.00 200 730 50 2,857 20 Base Residential Build Out Projections 64 165 229 379 443 134 159 31 12 351 35 34 9 22 0 5 43 12 88 90 1 503 518 0 1 1 Existing DU's 1 1 1 2 1 2 1 7 Approved DU's I AI 2,877 I 520 I 0 Future DU's 63 165 228 379 443 134 159 31 12 350 35 32 8 20 0 5 43 11 88 83 1,833 28 199 227 50 2,339 19 (11 2.357 Notes: 1) Growth Management Control Point 2) The GMCP for areas within the Sunny Creek Specific Plan (SP 191) are adjusted to provide an overall density of 2.0 du/ac as specific in the plan. 3) This area is the Habitat Conservation Area which was previously known as the Carlsbad Highlands property. This site was originally approved for 740 dwelling units, but is now being utilized for habitat conservation purposes. There are 379 units remaining that are not a part of the Northeast Quadrant dwelling unit bank. single family dwellings units with 28 second units. calculate dwelling unit density. housing units. 4) This area is a part of Development Area 1 and proposes 172 market rate 5) Consistent with the previous Zone 15 LFMP, one third of the net acreage is used to 6) This area is the affordable housing portion of Development Area 1. This area proposes 50 af Zone 15 LFMP 36 June 10,1998 EXHIBIT 15 General Plan Net Designation Acres RHICIO-2 1) 3.17 c-I 2) 17.60 PI 2.61 TOTAL ZONE 23.38 Land Use Developable Zone 15 - LFMP Non-Residential Build Out Projections (As of 1/1/98) tiMP Non- Base Non- Residential Residential Estimated LU Intensity Build Out Existing Approved Future Estimate Projections Sq. Ft. Sq. Ft. Sq.Ft. 30% 41,426 0 0 41,426 30% 229,997 0 175,000 54,997 30% 34,107 0 0 34,107 . 305,530 0 175,000 130,530 Zone 15 LFMP 37 - June 10,1998 EXHIBIT 16 ZONE 15 BUILD OUT POpuunoN PROJECTIONS (As of lHfS8) i nation TOTAL RLMl RLM-2 RLM2A 2) - ROSi&lll*l Build old Pl+dbllS 64 165 229 379 443 134 159 31 12 351 35 34 e 22 0 5 43 12 08 wng DU'r 1 1 1 2 1 2 1 - F- DUs DVa 63 105 228 379 443 134 19 31 12 350 35 32 8 20 0 5 43 11 08 p- Index (2.3178) 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 2.3178 23178 2.3178 0 0 383 2 0 sx 0 0 878 0 0 1021 0 0 31 1 0 0 36# 0 0 11 2 0 81 1 0 0 81 5 0 74 2 0 1s 5 0 4f 0 0 C 0 0 11 0 0 1OC 2 0 2: 0 0 201 0 0 2e Buln out Pqwlabm PlqMaon 149 383 532 818 1027 31 I 369 72 28 81 3 81 79 21 51 0 12 100 27 Notea: 1) Growth Management Control Point 2) The GMCP for areas within the Sunny Creek Spachic Plan (SP 191) are adjusted to provide 3) This area is the Habitat Conservation Area which was previously known as the Carlsbad Highlands property. an overall density of 2.0 du/ac as spedfied in the plan. This site was originally approved for 740 dwelling units, but is now being utilied for habitat conservation purposes. There are 379 units remaining that are not a part of the Northeast Quadrant dwelling unit bank. 4) This area proposes 172 market rate single family dwellings units with 28 second units. 5) Consistent with the previous Zone 15 LFMP. one third of the net acreage is used to calculate 6) This area is the affordable housing portion of Development Area 1. Thki area proposes 50 affordable housing units. dwelling unit density. ZOmlSLFMP 38 This page left blank VI. PHASING PROJECTIONS Phasing projections estimate when, where and how much development will occur in Zone 15 between now and build out. Although difficult to predict exactly, phasing projections begin to make possible advance planning and programming of public facilities to assure adopted performance standards are continually met. Specifically, phasing projections: 1. Project estimated demands for public facilities on a yearly basis until build out. 2. Project and establish thresholds which indicate when and where public facilities improvements are needed. 3. By projecting facility thresholds, allow sufficient lead time for facility programming to assure performance standards are continually met. 4. Through threshold identification, allow the City to implement public facility improvements. A. ZONE 15 LAND USE PHASING 1. Residential The residential phasing projections for Zone 15 are shown on Exhibit 19 on page 43 (page number reflects original pagination for this exhibit-see index for current page number). The projected residential phasing schedule is intended to be used for projecting future need and timing of public facilities. It is a tool to allow the City to anticipate future public facility needs and to budget monies for their improvement. The projected residential phasing schedule is not absolute. The actual number of dwelling units to be built each year will vary depending on economic conditions. Zone I5 LFMP Amendment 39 June 16, 1998 Exhi bit 17 Table AS REQUESTED, EXHIBIT ELIMINATED Zone 15 LFMP Amendment 40 June 16,1998 Exhibit 18 Table AS REQUESTED, EXHIBIT ELIMINATED Zone 15 LFMP Amendment 41 June 16,1998 This page left blank EXHIBIT 19 Zone 15 Resdential Phasing * * * FOR FACILITY PLANNING PURPOSES ONLY * * * 3uild Ou. asof 111 1998 1998 1999 2000 200 1 2002 2003 2004 2005 2006 2007 2008 2009 2010 201 1 2012 2013 2014 201 5 2016 2017 2018 2019 2020 2021 2022 rOTAL Zone 15 520 0 70 70 110 120 180 180 180 180 180 187 150 150 150 150 150 150 0 0 0 0 0 0 0 0 2.877 TOTAL ZONE DU's 520 520 590 660 7 70 890 1070 1250 1430 1610 1790 1977 2127 2277 2427 2577 2727 2877 2877 2877 2877 2877 2877 2877 2877 2877 2,877 - 'OTA L :ONE '0 P U LATl ON 1,205 1,205 1,368 1,530 1,785 2,063 2,480 2,897 3,314 3,732 4,149 4,582 4,930 5,278 5,625 5,973 6,321 6,668 6,668 6,668 6,668 6,668 6,668 6,668 6,668 6,668 6,668 NOTE: Phasing projections for Zone 15 shall be incorporated into the Capital Improvement Program. Zone 15 L FMP 42 June 10,1998 This page left blank 2. Non-Residential The nonresidential phasing projections for Zone 15, are shown on Exhibit 22 on page 47 (page number reflects original pagination for this exhibit-see index for current page number). Similar to residential phasing, the nonresidential projections are estimated for purposes of public facility planning. Comparable to residential phasing projections, this exhibit is provided to facilitate future monitoring of this Local Facilities Management Plan. 3. Phasing Summary Both residential and nonresidential phasing projections are provided in order to plan for public facilities. The plan provides these projections to establish thresholds which indicate the need for additional facilities. The Growth Management Program and the Zone 15 LFMP anticipate that the actual phasing of development in this zone will vary from these projections. In no instance, however, will phasing be modified to the point that the performance standard will not be met. The public facility thresholds established in this plan will ensure that compliance with the adopted performance standards is maintained, or no development will be allowed until compliance is reached. The Capital Improvement Plan phasing projections shall incorporate the phasing projections as provided in the Zone 15 LFMP. Zone 15 LFMP Amendment 43 June 16,1998 Exhibit 20 Table AS REQUESTED, EXHIBIT ELIMINATED Zone 1 S LFMP Amendment 44 June 16,1998 Exhibit 21 Table AS REQUESTED, EXHIBIT ELIMINATED Zone 15 LFMP Amendment 45 June 16,1998 This page left blank Pages 47 - 50 are blank due to Revision of Zone 15 Zone I5 LFMP Amendment 47 June 16, 1998 Pages 47 - 50 are blank due to Revision of Zone 15 Zone 15 LFMP Amendment 48 June 16, I998 Pages 47 - 50 are blank due to Revision of Zone 15 Zone 15 LFMP Amendment 49 June 16,1998 Pages 47 - 50 are blank due to Revision of Zone 15 Zone 15 LFMP Amendment 50 June 14,1998 This page left blank V. ZONE 15 REQUIREMENTS FOR PUBLIC FACILITIES AND SERVICES The Local Facilities Management Plan for Zone 15 addresses eleven separate facilities at three levels of analysis. Each Facility City Admin. Facilities Library Wastewater Treatment Capacity Park Drainage Circulation Fire Open Space Schools Sewer Collection Water Distribution X X X X Zone X X X X X X X of these facilities is evaluated to determine conformance with the adopted performance standard. For each facility analysis the following is provided: a. An illustrative map showing facilities discussed in the section and district boundaries; . b. The adopted service level performance standard which must be complied with at all times as development occurs; c. A detailed facility adequacy and planning analysis; d. A list of conditions necessary to ensure conformance with the adopted performance standard; e. A discussion of mitigation measures and financing mechanisms. Citywide facilities (City Administrative, Library, and Wastewater Treatment) have been analyzed in the 1986 CFIP. Analyses of these facilities are also included in this Local Facilities Management Plan to verify compliance with the 1986 CFTP or to suggest alternatives that assure conformance with the adopted performance standard. This plan shows how each adopted performance standard will be complied with as development occurs within Zone 15. This plan includes financing of all public facilities and services. The plan also includes a complete facility phasing schedule which is linked to public facility demands within the zone. 51 CITY ADMINISTRATIVE FACILITIES I. PERFORMANCE STANDARD 1,500 square feet per 1,000 population must be scheduled for construction within a five year period. 11. FACILITY PLANNING AND ADEQUACY ANALYSIS This analysis provides an inventory of existing and programmed City Administrative Facilities owned and leased by the City of Carlsbad. These facilities include both permanent and temporary structures. This analysis projects the build out demand for City Administrative Facilities and determines compliance with the adopted performance standard. Exhibit 23 on page 53 shows the location of the existing and future City Administrative Facilities. A. INVENTORY d Build Out Ciw 1. ve De-: .. Citywide projected population comes from the 1986 CFP. Zone 15 projected population comes from Exhibit 16 on page 38. Performance Projected Standard PoDulation Llsmu&m Existing (1/1/89) Citywide Zone 15 Build Out Citywide (2014) Zone 15 (1997) 66,460 99,690 1,285 1,928 134,914 7,433 202,371 11,150 52 Housing. and Rodevoiopmorrt CIvic Cultor NOTE: AN locarions are aooroximare. Scale m MANrrOU EXHIBIT 23 ENGINEERING C0MPM)V City Administrative Facilities -53- Zone 15 .. .. ... 2. bventorv of Exls~itv Adwt ive Fa-: The existing City Administrative Facilities owned and leased by the City of Carlsbad as of January 1, 1989 are: Permanent Temporary Leased BLm GQ-u w City Hall (1200 Carisbad Village Drive) Main Building Finance Modular Purchasing/Personnel Modular Redevelopment (2965 B Rooseveit) Community Development (2075 Las Palmas Drive): 12,899 29700 1,800 3,200 22,627 Public Safety and Service Center (I) (2560 Orion Way): Police and Fire 53,700 Vehicle Maintenance 10,358 TOTAL EXISTING FACILITIES 125,254 Existing City Administrative Facilities as of January 1, 1989 exceed the performance standard. However, 2.6 percent of the total square footage is leased and another 3.6 percent is in temporary modular units. If the leases are terminated or temporary facilities are no longer used, thereby reducing existing City Administrative Facilities, this analysis would need to be redone to assess compliance with the adopted performance standard. If compliance was not being maintained, all residential development in the City would be stopped until the appropriate mitigation could be implemented. 54 .. ... 3. entory of ADDro ved Future Citv Awat ive Faalitles: The adopted 1989-1990 to Build Out Capital Improvement Program (CC Reso. No. 89-210) funds the following City Administrative Facilities for construction within 5 years (1994): Facilitv Square Funding Ea YciK Source Public Safety Center (II): Construction 6ZOOo ’92-’93 $3,955,000 PFF/S5 New City Hall N/A 1999 + s23,100,000 PFF No other City Administrative Facilities are identified within the City’s adopted CIP. Existing City Administrative Facilities plus those scheduled for construction within five years in the adopted 1989-90 to Build Out CIP are as follows: Permanent Temporary Leased G5l-W G!lm fam Existing 117,584 4,500 3,200 B. PHASING The citywide residential phasing projections on Exhibit 17 on page 40 are incorporated into Exhibit 24 on page 56. Exhibit 24 projects the adequacy of City Administrative Facilities on a citywide basis by comparing the projected facility demand with existing and funded facilities. PFF = Public Facilities Fee and S = Sewer Enterprise Fund. 55 EXHIBIT 24 ZONE 15 - PHASING OF CITY ADMINISTRATIVE FACILITIES (1,500 SWARE FEET PER 1,000 POWLAIION) PROJECTED BUILD OUT 1989 I990 I991 1992 1 W3 1 994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 201 1 2012 2013 2014 1,232 2,540 2,716 2,236 1,838 1.296 1,111 1,386 815 742 413 338 237 237 237 227 227 227 227 227 227 227 212 1 IO 101 OLD OUT 0 260 .368 368 400 400 309 3Q3 Ild Out 1,232 2,800 3,m 2,604 2,238 1,696 1,500 1,386 815 742 433 338 237 23 7 237 227 227 227 22 7 227 227 227 212 110 101 BLD OUT 66,460 69.504 76.423 84,041 90.478 96.008 1w.199 103,906 107,330 109,344 1 1 1,178 112,248 113,083 113,648 114,254 114,840 115, 401 115.962 116.522 117,083 117,644 118,205 118,766 119,290 119,562 119,811 99,690 104,256 114,635 126,065 135,717 144,012 150,294 155.B58 160,996 164,016 166.767 168,371 169,624 170,503 171,381 172,260 173,101 173.942 174,784 175,625 176.466 177.308 178.149 178,935 179.343 179,717 125,284 125,284 187,284 187,284 187,284 167,284 187,284 187,284 187,284 187,284 187,284 187,284 187.284 187,284 187,284 187,284 187,284 187,284 187,284 187,284 187,284 187,284 187,284 187,284 187,284 187,284 25.594 2I,028 72,649 61.219 51,567 43.272 36,985 31,426 26,288 23,268 20,517 18,913 17,660 16,781 15,903 15,024 14,183 13,342 12,500 11,659 10.818 9.976 9,135 8.349 7.941 7.567 IOlAL 45,782 I 3,008 I 48,487 I - 56 - C. ADEQUACY FINDINGS Analysis of Zone 15’s demand on City Administrative Fadities as of 1/1/89 indicates no mitigation is needed at this time. The performance standard is currently being conformed to and is projected to conform until build out. The yearly monitoring program will assure that the adopted performance standard is complied with through build out. 111. MITIGATION General Co ndmo nS .. If at any time the adopted City Administrative Facilities performance standard is not being complied with, then residential development in Zone 15 will be stopped until the performance standard is met. SDecial Conditions No special conditions. W. FINANCING The City collects a public facility fee (PFF) which is set at 3.5% of pennit valuation. This fee is paid at time of building permit issuance. In calculating the PFF the following expenditures were projected for City Administrative Facilities: Las Palmas Facility $2,000,000 City Hall - Future s23,100,000 Public Safety Center Phase II $3,455,000 TOTAL -__I-- $29,055,000 In addition to the PFF funds, the adopted 1989-1990 to Build Out CIP indicates the use of sewer funds for part of the public safety center Phase n. Public Facility Fees will continue to be paid by development in the zone. Thus, no special financing mechanism for City Administrative Facilities is required as a condition of development within Zone 15. Exhibit 25 on page 58 shows a facility financing matrix for this facility. This matrix summarizes the individual facility to be financed, its estimated cost and timing of construction, the existing budgeted CIP monies available for the facility and the future funding options. 57 LONE 15 - CllY ADMlNlSlRAllON FACILIIY FINANCING AS OF 1/1/90 - 58 - LIBRARY FACILITIES I. PERFORMANCE STANDARD 800 square feet per 1,OOO population must be scheduled for construction within a five year period. IT. FACILlTy PLANNING AND ADEQUACY ANALYSIS This analysis provides an inventory of existing and approved library facilities owned and leased by the City of Carlsbad. This analysis projects the build out demand for library facilities and determines compliance with the adopted performance standard. Future citywide library facility demand is projected based on the 1989-90 to Build Out Capital Improvement Program, the adopted LFMP's and Zone 15. Exhibit 26 on page 60 shows the location of existing and future library facilities. A. INVENTORY 1. ild Ou t Iibrarv De man& Citywide projected population and Zone 15 projected population comes from Exhibit 16 on page 38. Performance Standard Projected Demand PoDulatlon Existing (1/1/89) Citywide Zone 15 Build Out Citywide (2014) Zone 15 (1997) 66,460 53,168 1,285 1,028 134,9 14 107,931 7,433 5,946 59 Civic Center Library Legend Existing Library 0 Planned Library NOTE: All locations are apDroximate. MANTTOU ENGINEERING COMPLINY EXHIBIT 26 Library Faciiities Zone 15 -60- .. ... 2. bventorv of E- Libram Fa: 3. Existing library facilities owned and leased by the City of Carlsbad as of January 1, 1989 are the following: Facility Owned Leased lam w Civic Center Library (1200 Carlsbad Village Drive) 24,600 Adult Learning Center (1207 Carlsbad Village Drive) La Costa Area Libraxy* (7750 El Camino Real) Warehouse (2075 Cone De Nogal) 300 4,500 2,060 Inventorv of ADD roved Future Libra? Facilities: South Carlsbad Library: A six acre City owned site has been identified and designed for the South Carlsbad Library. This library is projected to be 58,000 square feet in size and to open in 1992. According to City staff, the 6,960 square feet of existing leased library space will expire and be vacated when the South Carlsbad library is constructed. The 1989-90 to Build Out CIP allocates funds for debt financing between 1989-1999 + . The South Carisbad library site was approved by the City Council on July 7, 1987'. The site is near the northwest comer of El Cdno Real and Alga Road as shown on Exhibit 26 on page 60. The existing 6,960 square feet of leased library space will expire when the new South Carlsbad Library is constructed. The staff report for this action is contained in Appendix A-2, Agenda Bill No. 8867. 7 61 North Carlsbad Library Expansion: The 1989-90 to Build Out Capital Improvements program shows funds for construction of the North Carlsbad Library Expansion in 1994-99. This expansion will provide approximately 8,000 square feet of additional library space. Build Out Library: Funds for an additional 17,331 square.feet of Library space for Build Out are shown in 1999+ in the 1989-90 to Build Out Capital Improvements Program. The following is a summary of the 1989-90 to Build Out Capital Improvement Program funding allocation for library facilities: South Carlsbad Library: Descnptioq Cost ('89 dollars) w Funding .. Debt Financing 1989-1999+ $28.1 million TOTAL $28.1 million North Carlsbad Library Expansion: Cost ('89 dollars) Funding Descriptioq w Construction 1994-99 $3.9 million Build Out Library: Funding DescriDtion Year Cost ('89 dollars) Construction 1999 + $5.1 million 62 B. PHASING Existing library facilities plus those budgeted in the adopted 1989-90 to Build Out CIP for construction within 5 years are as follows: 1989: Existing: Civic Center Library Adult Learning Center La Costa Area Library Warehouse S. Carlsbad Library 58,000 Adult Learning Center La Costa Area Library Ware house 1994-99: N. Carlsbad Library Expansion 8.OOO e Feet of Lib ram SD ace Added Subtracted Total 3 1,560 89,560 400 4,500 5060 82,600 90,600 1999+: Build Out Library 17,33 1 107,93 1 To assess when the threshold for future library facilities will be reached, the phasing projections on Exhibit 17 on page 40 are used. These phasing projections are incorporated into Exhibit 27 on page 65. Exhibit 27 projects the adequacy of library facilities on a citywide basis by comparing the projected facility demand with existing and funded facilities. C. ADEQUACY FINDINGS Analysis of Zone 15’s demand on library facilities as of 1/1/89 indicates no mitigation is needed at this time. The performance standard is currently being conformed to and is projected to conform until build out. 63 111. MITIGATION .. General Co- If at any time the adopted Library Facilities performance standard is not being complied with. then residential development in Zone 15 will be stopped until the performance standard is met. .. Special Conditlom No special conditions. W. FINANCING South Carlsbad Library: On July 7, 1987, the City Council took action for the acquisition, grading, design and construction of the 58,000 square foot South Carlsbad Library. Although the City Council has guaranteed the needed funds, the long term financing mechanisms may be modified at some time in the future. The adopted 1989-90 to Build Out CIP has appropriated $25,868,000 for library facilities. Of this total amount $16,860,000 is budgeted for debt financing of the South Carlsbad Library construction. $1,124,000 per year is budgeted for debt service payment which would be payable over the next 20 years. North Carlsbad Library: The 1989-90 to Build Out CIP shows $3,948,000 for construction of the North Carlsbad Library expansion in 1994-99. This will provide an additional 8,000 square feet of library space at the existing library on 1250 Carlsbad Village Drive for a total of 32,600 square feet. Build Out Library: The 1989-90 to Build Out CIP indicates that $5,060,000 for an additional 17,331 square feet of library facilities will be funded in 1999+ to fulfill the demand for libraries at build out. This space will likely be added to existing facilities. The primary source of funding will be Public Facility Fees (3.5% of building permit valuation). This fee is collected at the time building permits are issued for all residential, commercial and industrial developments. 64 €XttlBlr 27 1,232 2,800 3.w 2.604 2,238 1,696 1,500 1,386 815 742 433 338 237 237 237 227 227 227 22 7 227 227 227 212 110 101 , BLD OUT ZONE $5 - PHASING OF LIBRARY FAClLlllES (800 SWARE FEET PER 1,000 POPULATION) I IN TOTAL ADOP 1 ED PLANS I PROJECTED BUILD OUT 1989 lop0 lW1 lW2 1993 1 W4 lW5 1996 1997 1998 1999 2000 2001 2002 2003 2004 200s 2006 2007 2008 2009 2010 201 1 2012 2013 2014 1,232 2.540 2,716 2,236 1,838 1,296 1,111 1.386 815 74 2 435 338 237 237 237 227 227 227 227 227 227 227 212 110 101 BLD OUT 0 260 368 368 400 400 389 303 Bld Out 66,460 69, SO4 76,423 84,044 90,478 96,008 100,199 103,906 107,330 109.346 11 1,178 112,248 113,083 113,640 114,254 114,840 115,401 115,962 116,522 117,083 117,644 118,205 118,766 119,290 119,562 119.811 53,168 55.603 61,138 67,235 72,303 76,807 80,159 83,124 85,864 87,475 00,942 89,798 90,466 90,935 91,403 91,872 92.321 . 92,769 n.2ia 93,667 94,115 94,564 95,013 95,432 95,649 95,849 82,600 82,600 82,600 82,600 82,600 90,600 90,600 90,600 90,600 90,600 107,931 107,931 107,93 1 107,931 107,931 107,931 107,931 107,931 107,931 107,931 107,931 107,931 107,93 1 107,931 107,931 107,931 29,432 26,997 21,462 15,365 10,217 13,793 10,441 7,476 4,756 3,125 18,989 18,133 17,465 16,996 16,528 16,059 15,610 15,162 14,713 14,264 13,816 13,367 12,918 12,4W 12,282 12,082 --____-_____---_------.---------.----------------------------------------------------------------.--------------------------- IOTA1 45.782 I 3,008 I 48,487 I ---_.-_.___------------------.------------------------------------------------------------------------------------------------- NOTES: (1) Dwelling mits In Other Adopted Zone Plans are those projected in the LFMP for Zones 1-9, 11, 12, 19, 20, 22 (2) Source - Exhibit 17. (3) Total adopted dwelling wits include the adopted zones 1-9, 11, 12, 19, 20, 22, 24 along with Zones 14 and 15. (4) Existing cityWide population is the base population used for projecting Adopted Zone Plan Populations. (5) 58,000 square foot Expansion of South Carlsbed Library. Expiration cf lease on 6960 scpare feet. (6) 8,000 square foot Expansion of North Carlsbad Library. (7) 17,331 square feet additional library for build out. wd 24. lhe Zone 14 Plan is udcr technicat revieu and the phasing is included for planning purposes only. I Exhibit 28 on page 67 shows a facility fiancing matrix for this facility. This matrix summarizes the individual facility to be financed, its estimated cost and timing of construction, the existing budgeted CIP monies available for the facility and the future funding options. 66 EW11IBIT 28 ZONE 1s - LIBRARY FAClLlllES FlUAUClllC AS Of 1/1/90 1. Library Remodel I 8,000 sf I S3.941,OOO 1 I 2. Library - For Iulld I I I I 3. Library - Swth I I Out Population I 17,331 rf I S5,060,000 Carlcbad I 58,000 rf I S28,100,000 , 1004-w I I 1999+ I I 1 1989-1999 I I I I I I I I I I ,_____-_---____..------ I I I I I I I I I ____---.--------- I I I I I I I I I -----------.---- I I I I I I I I I ---I This page left blank WASTEWATER TREATMENT CAPACITY I. PERFORMANCE STANDARD Sewer treatment plant capacity is adequate for at least a five year period. 11. FACILITY PLANNING AND ADEQUACY ANALYSIS k INVENTORY Wastewater Treatment in the City of Carlsbad is provided by three independent agencies: The City of Carlsbad Sewer Service District, Leucadia County Water District (LCWD) and Vallecitos Water District as shown on Exhibit 29 on page 69. Wastewater Treatment is provided primarily at the Encina Water Pollution Control Facility (WPCF) and also at satellite treatment facilities. Ownership as well as wastewater treatment capacity of the Encina WPCF is shared on a percentage basis by six independent sewer districts. Exhibit 30 lists the six agencies and their permitted treatment capacity to the Encina WPCF as follows: Exhibit 30 WCMA WrCF CAPAaLy ANALYSIS Satellite Available Remaining I Tmatment Treatment Existing Treatment I 1. Gwty I I. I Ownership Enana WPCF For- Gpaoty GpKlty Flow Capraty I I Agency I (MGD) (MGD) WGD) (MGD) (HGD) ! I I Perrent Gpoty at Adjusted Notes I 30.00 732 7.02 -.- 7.02 5.41 1.61 I 25.40 6.20 6.20 1.20(1) 6.20 4.72 1.48 I Vista I Carisbad I 459 1.12 1.04 1.00 204 204 0.00 1 17.78 4.34 4.34 2.00 6.34 3.90 2.44 1 Buena I Vallecitoc I Lcucadia I 16.67 4.07 459 0.75 5.34 35 1 1.83 I Encinitas I S56 136 1.21 -.- 1.21 1.04 0.17 I I TOTAL 1 100.00 24.a 24.40 4.95 28. Is 20.62 753 I NOTES: 1. Currently not operational. 2 Summary of Leases: 1) Buena to LCWD 0375 MGD 3) Vista to Buena 0.30 MGD: 2) Enanitas to LCWD 0.15 MGD: 3. As of November. 1989. 68 crty of oceansids Calavera Hills Reclamation / . Treatment Faciiity (existing but not operational) .1 \ n ' Faciiity cw of -- NOTE: All locations are amroximate. -69- MANrrOU ENGINEERING COMPPNV EXHIBIT 29 Wastewater Facilities Zone 15 Currently, the Encina WPCF has capacity to treat 24.4 million gallons per day (MGD). Ultimately, this facility will be able to treat up to 45 MGD. As shown below, Carlsbad Sewer Service District owns limited treatment capacity in a smaller localized satellite treatment facility: Percentage of Encina Capacity (25.4%) 6.20 MGD Calavera Hills Treatment Facility' MGD TOTAL AVAILABLE TREATMENT CAPACITY 7.40 MGD Capacity at the Encina WPCF is separated into two categories: Treatment capacity and outfall capacity. This analysis will deal primarily with treatment capacity. The Encina Ocean Outfall is a drainage line that transports the treated sewage (effluent) from the Encina WPCF and satellite facilities and discharges approximately 8,900 feet into the Pacific Ocean. Currently, the Encina Ocean Outfall has a 40.5 million gallons per day (MGD) capacity. The outfall capacity is shared by six sewer districts and is projected to provide sufficient capacity to the year 2000. Outfall capacity just as treatment capacity, is shared on a percentage basis by the six sewer senrice districts. 1. xlst1n.g Facilities: .. The City of Carlsbad has capacity available at two wastewater treatment plant facilities. Primary treatment capacity is provided through Encina WPCF which is a regional facility owned by six member agencies. The current rate of capacity of Encina WPCF is 24.4 MGD of which Carlsbad retains ownership of 25.4 percent or 6.20 MGD. The City of Carlsbad also holds title to the Calavera Hills Wastewater Treatment Plant which has a capacity of 1.2 MGD. The Calavera Hills Facility is not operational at this time and would require approximately $2.33 million to make it operational. Operation at the Calavera Hills Plant is estimated to cost $360,000 per year. Comparable treatment at the Encina WPCF is estimated at $135,000 per year. The Calavera Hills Plant is not economical to operate for treatment capacity except in the absence, of needed capacity at Encina WPCF. B. PHASING Exhibit 31 on page 72 shows the existing and projected demand and treatment capacity for Carlsbad Sewer Service District. Existing demand is 4.72 MGDS with current capacity Currently not in operation. Carlsbad Sewer Service District currently assumes a flow rate of 220 gallons/EDU. 70 at the Encina WPCF at 6.20 MGD. With the addition of Phase IV expansion of Encina WPCF in 1992, Carlsbad's capacity at Encina WPCF will become 9.24 MGD (25.68%). With the addition of Phase IV expansion of Encina, total capacity at Encina will become 36.00 MGD. 1. PhasinP and Service Demand Wastewater treatment senrice area population projections for the Encina WPCF service district is depicted in the following chart: ENCINA WPCF PLAN Year SEWER SERVICE AREA POPULATION Vista Carlsbad Buena Vista '' Vallecitos Leucadia Encinitas 35,300 24,400 5,500 0 20,800 ~,OOo 7,000 49,100 69,000 22,800 6,100 49,000 6 1,000 8,900 TOTAL 118,OOO 265,900 ST700 81,500 24, loo 6,100 53,000 74,000 9,500 300,900 --- C. ADEQUACY FINDMGS Exhibit 31 on page 72 estimates the necessq treatment capacity needed to accommodate growth within the Carlsbad sewer service area to the year 1995. lo Projections approved by Joint Advisory Committee January 28, 1987. Portion of the City of Vista served by Buena Sanitation District. 11 71 EXHIBIT 31 ZQlE 1s URLSOAO SERVICE MEA DEIIAY) Ayo AVAIUBLE WSTTNITER TREATMENT CAPACITY 6.20 6.20 6.20 9.26 9.26 -----..-.-. NOTES: 1. Results of A.D.S. -cered floo JS of 11/1/89. T~bL~l~trd EDU's are canp.rrd to metered flou resulting in m JSS& historical E.O.U. ftou of 180 GAL/EDU. Subrcqwcrt projections uerc derivcd asruning a flou rate of 220 WL/EDU. 2. ' Projected EDU's adjusted for M ass& three-percent V~CJKY rate. 3. M(;D = Millions Of CJllons p.r DJ~. - 72 - I, 111. MITIGATION The following action shall be pursued jointly by each sewer district to ensure adequate wastewater treatment capacity through the year 2000: 1. Monitor Encina treatment plant flows on a monthly basis to determine actual flow rates and to have an early warning of capacity problems. IV. FINANCING Sewer connection fees provide the primary source of funding for both sewer line upgrades and expansion of treatment piant capacity. The timing of sewer facilities upgrades and the mechanism of financing are critical to analysis of the adequacy of funding for piant expansion. Carlsbad Sewer Service District has projected Capital Improvement funds to provide for needed facilities. Exhibit 32 on page 74 shows a facility financing matrix for this facility. This matrix summarizes the individual facility to be financed, its estimated cost and timing of construction, the existing budgeted CIP monies available for the facility and the future funding options. 73 , ZONE 15 - UASlEUAlER FINANCING HAIRIX AS OF 1/1/90 I 1. Encina Outfall Upgrade I $9,685,000 I I I I I I 2. Lncins Phase IV Expansion . I S29.396,OOO I 3. Encina Solids Management I $7,488,000 I IOIAL UASIEUAIER COSIS U6,569,000 ===SE=I===x== 1WC-1999 I Sewer Fees 1989-W* I Seuer Fees 1989-994 I Seuer Fees I I I I I I I I I I I I I I I I I I I I I I I I I I Balance foruard: UOO.000 for Encl~ Sotido Managnnmt. I I I $1,245,715 for Phase IV trpansion ---_--___-_----_________________________-------------------------------------------------------------.------.-.------------------------------------------ -14- This page left blank PARK FACILITIES I. PERFORMANCE STANDARD Three acres of Community Park or Special Use Area per 1,OOO population within the park district must be scheduled for construction within a five year period. 11. FACILITY PLANNING AND ADEQUACY ANALYSIS Park faciiities are addressed on a park district basis. There are four park districts which correspond to the four quadrants of the City. Zone 15 is located in Park District 2 as shown on Exhibit 33 on page 76. A. INVENTORY .. 1. and Build Out Park Demand: The projected population for Park District 2 comes from Exhibit 16 on page 38. Performance Projected Standard Park District 2 Population Park Dernand(acres1 Existing (1/1/89) Build Out (2014) 10,084 22,343 30.25 67.03 Of this, the Zone 15 existing and projected build out population and demand is: Zone 15 Existing (1/1/89) Build Out (1997) Performance Projected Standard Population Park Demand(acres1 1,285 7,433 3.86 22.30 75 m MANTTOU ENGINEERING COMPL\NY -76- EXHIBIT 33 Park Districts Zone 15 .. ... 2. bventorv of FmtlnP Par- In Pa District 2: The inventory of existing parks listed below was approved on July 17, 1989 by the Parks and Recreation Commission. Larwin Community Park is scheduled and funded for construction within five years and can be used to meet the adopted performance standard. Although the 1989- 90 to Build Out CIP schedules Laxwin Park construction in 1991-92 for $2,530,000, the funds will not be available until 1993-94. Since 1993- 94 is within the five year increment specified in the adopted performance standard, the park can be used to meet the existing demand. These parks are shown on Exhibit 34 on page 78 and are the following: co-ty Parks Calavera Hills Ownership City rn Active Acres 16.16 Larwin Active City 22.26 TOTAL 38.36 Soecial Use Are- m Ownership Acres Safety Center Ballfield Passive City 2.00 Hope Elementary School Active CUSD zsp TOTAL 4.80 TOTAL EXISTING FACILITIES 43.16 3. Inventory o f Projected Future Park Facilities: An inventory of projected parks was approved on July 17, 1989 by the Parks and Recreation Commission. These parks are shown on Exhibit 34 on page 78 and are the following: Communitv Parks Macario12 Owners hip Active City TOTAL PROPOSED FUTURE FACILITIES Acres 25.00 25.00 ----- ’* Macario Canyon Park is shown on Exhibit 34 on page 78. 77 Legend Existing Community Park A Future Community Park 0 Existing Special Use Area 0 Future Special Use Area Note: All locations are approximate. MANrrOU ENGINEERING COM-Y -78- EXHIBIT 34 Park Lo cations Zone 15 4. Projected Bu ild Out Ade-cv of Park FaciIitiG: 43.16 acres of existing park facilities can be applied toward meeting the adopted parks performance standard. The 25.0 acres of projected future park facilities are proposed facilities per the City's adopted Parks Inventory. Macario Park is not scheduled for construction within five years (1999 + ) and thus, cannot be used to meet the adopted performance standard. Assuming the proposed facilities were scheduled and funded for construction prior to build out, the projected build out adequacy/inadequacy of park facilities in Park District 2 is as follows: Existing Facilities Proposed Future Facilities Total Build Out Park Facilities Park District 2 Build Out Demand Projected Park District 2 Adequacy 43.16 25.00 68.16 acres 67.03 1.13 acres B. PHASING Exhibit 35 on page 80 shows Park C:r:-.c. ? -pply and park district demand based on Park District 2 population pqfci~~~. These projections include the projected phasing schedules for Zones 7 and 14 since zone plans for these areas are currently under review by the City of Carlsbad. C. ADEQUACY FMDINGS Park District 2 conforms with the adopted performance standard until 1993. 79 EYHI9II 35 ZONE IS . PHASING OF PARK rrciiiriEs . PARK DISIRICI z PROPOSE0 SUlLO 011 1989 1990 1991 1992 1993 lW4 1995 1996 1997 1998 1999 2000 2001 2002 2003 200s ZOOS 2006 2007 2008 2009 2010 2011 2012 2013 2014 0 DLO w1 0 23 36 36 21 5 DLO WI 291 . 0 0 221 0 260 130 99 ,368 150 115 368 . 150 115 400 150 115 400 140 115 389 DLO a1 115 303 115 DLO WI 115 115 101 DLD CUI 291 481 620 669 70 1 686 649 418 115 115 115 101 0 0 0 0 0 0 0 0 0 0 0 0 0 DLO 011 4,081 4.m 4.853 5.m 6,142 6,843 7,529 8,178 8,596 6,711 8,826 8,941 9,042 9,042 9,042 9,042 9.042 9.042 9,042 9,042 9,042 9,042 9,042 9,042 9,042 DLO all 719 1o.w 1.189 10.803 1,532 11,wz 1,653 13,524 1.732 i5.m 1,695 16.909 1.a 18.601 1,033 20.m 204 21,241 284 2l.525 284 21,w 250 22.093 0 22,343 0 22,343 0 22,343 0 22,343 0 22,343 0 22,343 0 22,343 0 22.343 0 22,343 0 22.343 0 22,343 0 22.343 0 22.343 DLO our 010 our 30.25 32.41 35.97 40.57 45.53 55.81 60.62 63.R t4.57 65.43 66.28 67.03 67.03 67.03 67.03 67.03 67.03 67-03 67.03 67.03 67.03 67-03 67.03 67. 03 5o.n 43.30 13.0 43.30 7.J 43.30 2.7 43.30 (2.2 43.30 (7.1 43.30 (12.5 43.30 (17.3 43.30 (20.4 68.16 3.5 68.16 2.1 68.16 1 .I 68.16 1.1 68.16 1.1 68.16 1.1 68.16 1.1 M.1b 1.1 68.16 1.1 68.16 1.1 68. 16 1.1 68.16 1.1 68.16 1.1 68.16 1.1 td. 16 1.1 68.16 1.1 43.30 10.a -80- 111. MITIGATION al CW .. . A All development shall pay Park-in-Lieu Fees and Public Facility Fees for Park District 2. B. No residential development shall be allowed after 1992 unless actions have been taken by the City to construct additional park facilities. W. POTENTIAL ADDITIONAL SOURCES OF PARK ACREAGE In addition to the community parks and special use areas listed in the existing and projected inventory, the following schools could possibly enter into joint use agreements with the City of Carlsbad when the schools are constructed: Potential Estimated Special Use Area m Qwnershig Acres Zone 7 Elementary School No. 2 Active CUSD 2.5 Zone 14 Junior High School Active CUSD 20.0 Zone 14 Elementary School Active CUSD 2.5 TOTAL 25.0 It is not proposed that these schools be used towards fulfilling the parks requirement in the nonheast quadrant. It is however, acknowledged that these schools, when operational, could become special use areas upon a written agreement between the respective school district and the City of Carlsbad to joint use playground facilities. When a joint use agreement is in effect these facilities may be used towards meeting the parks performance standard so long as the area is not used for temporary classrooms. This LFMP will need to be formally amended when this occurs. V. FINAiVCING The City’s approved Capital Improvements Plan contains the following funding for park facilities in Park District 2: Park Proiect 1991-92 1999 + Larwin S2,530,000 Macario (credit) $7,000,000 81 As shown, the only park facility to be scheduled for construction within a five year period in Park District 2 is Larwin Community Park Although the 1989-90 to Build Out CXP schedules Larwin Park construction in 1991-92 for $2,530,000, the funds will not be available for construction purposes until 1993-94. Since 1993-94 is within the five year increment specified in the adopted performance standard, the park can be used to meet the adopted performance standard. The City estimates this expenditure would allow approximately 22.2 acres of park to be constructed. Exhibit 36 on page 83 shows a facility financing matrix for this facility. This matrix summarizes the individual facility to be financed, its estimated cost and timing of construction, the existing budgeted CIP monies available for the facility and the future funding options. 82 EXHlBll 36 , I -1erwln Perk 22.2 acres 25 ecres $2,530, OW s7,000,000 1993-91 1Wt City - PFF Clty - PFF PFF - Public Frcititieo Fee -8 1- This page left blank DRAINAGE FACILITIES I. PERFORMANCE STANDARD Drainage facilities must be provided as required by the City concurrent with development. 11. FACILITY PLANNING AND ADEQUACY ANALYSIS Zone 15 is located in the Agua Hedionda Lagoon Watershed. The storm water within this watershed flows through man-made channels, storm drains, and ~t~ral drainage courses to Agua Hedionda Creek. Agua Hedionda Creek, in turn, flows into the Agua Hedionda Lagoon. A map of the natural drainage areas and the drainage basins is shown on Exhibit 37 on page 85. The source for the information contained in this report is the Drainage Master Plan entitled "Drainage Master Plan for the City of Carisbad, Califomi&" dated June, 1980, prepared by VTN Southwest. This Master Plan sets forth the comprehensive local drainage systems necessary to meet the long term needs of the City. In addition to the Drainage Master Plan, this analysis references the Hydrology Study for the Northeast Quadrant prepared by Dr. Howard Chang under the direction of the City. The hydrology report provides additional analysis and mitigation measures for a 100-year flood in the northeast quadrant. The Drainage Master Plan and HydroIogy Study establish the requirements for local drainage systems that are necessary to meet the long term needs of the City. The Drainage Master Plan, Hydrology Study for Northeast Carlsbad, and any subsequent updates should be used in planning for future facilities and improvements. Appendix 4 of this pian includes a map with the boundary of Zone 15 delineated on the Drainage Master Plan.. As was indicated in the Citywide Facilities and Improvements Plan, drainage is distinguished from all other public facilities and improvements because by its very nature it is more accurately assessed as specific development plans are finalized. However, certain facilities may be necessary which are larger than those required from a single development project and, therefore, need to be identified so that the proper funding can be collected for the -- construction of these facilities. 84 I LEGEND: - Zone Boundary I - - - - - Drainage Basln Boundary -..-- Nowllne of Malor Creek EXHIBIT 37 Drainage Baslns Local Facilities Management Plan Zone 15 85 k INVENTORY 1. 2. The existing major drainage facilities (30" or larger) that are within Zone 15 are shown on Exhibit 38 on page 87. The existing major drainage facilities within Zone 15 are as follows: 1. Improved Channel 2. Double 3'x 6' Box Culvert Rancho Carlsbad Mobile Home Park El Camino Real 3. 36" Stom Drain El Camino Real 4. Earth Channel Rancho Carlsbad Mobile Home Park The improvement pians for Sycamore Creek I (CI' 83-36, drawing No. 251- 6), propose a 60" to 78" stom drain be constructed along future College Boulevard between El Camino Real and Agua Hedionda Creek. A 30 to 48 storm drain facility in Palmer Way is proposed to connect to the 60 to 78" storm drain in College Boulevard. This storm drain system supercedes the 66" to 84" system proposed in the Drainage Master Plan for the same area. The purpose of this storm drain would be to collect runoff and to extend the storm drain system in College Blvd. as shown on the improvement plans for Koll Development (CT 81-10). Facilitv BY: The Drainage Master Plan proposes a 54" storm drain northerly of Agua . Hedionda Creek. The approximate locations of these systems are shown on Exhibit 38 on page 87. The purpose of these storm drains would be to collect runoff in the northerly drainage basins within Zone 15 and to convey the storm water to the natural drainage channels and to Agua Hedionda Creek and its tributaries. 86 EXISTINO STORM DRAIN --- --- EXISTINO EARTH CHANNEL - EXISTINO BOX CULVERT ==---= PROPOSED STORM DRAIN CITY OF OCEANSIDE PROPOSED DESILTATION BASIN a WITH CAPACITY n loo c.v. --- SUB DRAINAOE BASIN BOUNDARY + DIRECTION OF OVERLAND FLOW FLOW LINE OF CREEK @ EXISTINO FACJLITY -87- aches BH. BT and BJ: ... There are three storm drain systems proposed by the ment Drainage Master Plan in the northern most part of Zone 15. These are idenufied as facilities BH, BI and BJ on the plat showing a pomon of the Drainage Master Plan in Appendix 4. Facilities BH and BI, however, will be replaced by a 54 inch line and 36 inch line, as proposed by the Carlsbad Highlands approved Tentative Map. These facilities are identified on Exhibit 38 on page 87 The specific size and location of these proposed systems is currently being assessed as part of the hydrologic and hydraulic analysis for Carlsbad Highlands (C.T. 82-12). The required drainage facilities within this portion of Zone 15 will be identified in the development plans for C.T. 82-12 and the improvement plans for future Cannon Road. These storm drain facilities shall be provided at the time of development to the satisfaction of the City Engineer to insure conformance with the performance standard. The proposed major storm drain facilities within Zone 15 are based on the Drainage Master Plan and hydrology study prepared by Dr. Howard Chang. These facilities are shown on Exhibit 38 on page 87 and are as follows: 5. 6. 7. 8. 9. 10. 11. 12. 13. BL 60" - 78" storm drain along future College Boulevard benveen El kino Real and Agua Hedionda Creek. 30" to 48 storm drain southerly of Agua Hedionda Creek. BK 54" storm drain northerly of Agua Hedionda Creek. 54" storm drain from northwestern Zone 15 to future Cannon Road. 36" storm drain north of future Cannon Road. BJ (48") storm drain south of future Cannon Road. Sediment detention basin to be located upstream of Rancho Carisbad Mobile Home Park. (Near the future intersection of Cannon Road and College Boulevard.) Restoration or reconstruction of approximately 3,500 feet of Calavera Lake Creek from the proposed detention basin to the El Camin-o Real bridge. 78" storm drain along the future Cannon Road alignment. The Drainage Master Plan does not recommend any improvements to any of the major drainage facilities outside of Zone 15. .88 The location and size of the proposed storm drain facilities have been approximated for the purposes of this plan. The actual locations and sizes will be defined as the surrounding area develops and the storm runoff is analyzed according to current design standards. The City is currently in the process of revising the Drainage Master Plan which is anticipated to be adopted towards the end of 1989. The updated version will analyze the adequacy of the existing storm drain facilities and propose the construction for specific major storm drain facilities so that future development will continue to conform with the adopted performance standard as development occurs. In addition, the revised Master Plan will incorporate the 100-year flood analysis provided in the hydrology report prepared by Dr. Howard Chang. It should be noted that Dr. Chang's study identifies a potential for flooding at the Rancho Carlsbad Mobile Home Park bridge on Agua Hedionda Creek. Although no mitigation is required to meet the performance standard, future development within the Agua Hedionda Creek Basin may be required to provide additional mitigation to the satisfaction of the City Engineer as a result of subsequent hydrology studies. B. PHASING The watershed boundaries are shown on Exhibit 39 on page 92. The approach taken to establishing the watershed boundaries is based on ensuring that needed facilities are in place prior to or commensurate with development. There are 4 separate watersheds (labeled Watershed A through D) in Zone 15. The thresholds for the major drainage facilities within each watershed can be easily established, thereby determining the appropriate mitigation measures. The watershed boundaries allow for the independent review and development of the drainage facilities within each boundary. Improvements outside of the watershed boundaries may be required if deemed necessary to serve development within Zone 15. C. ADEQUACY FMDINGS Existing drainage facilities 'currently do not meet the adopted performance standard for major storm drain facilities. The hydrology report prepared by Dr. Chang has indicated that a potential drainage inadequacy exists in the event of a 100-year flood that will require construction of a detention basin and restoration or reconstruction of Calavera Lake Creek. In addition to the future facilities required by Dr. Chang's Hydrology Study, future development will be required to construct any major drainage facilities identified in the current Master Plan at the time of development as determined by the City Engineer. The revised Drainage Master Plan may also require additional conditions 89 111. at the time of development. The construction of these facilities will be a condition to the.approval of future development in Zone 15 so that conformance with the adopted performance standard will be maintained. MIT~GATION Sped a1 Cond itions k All future development in Zone 15 will be required to construct any future Zone 15 storm drain facilities identified in the current Drainage Master Plan and revised Drainage Master Plan for each watershed basin as determined by the City Engineer. Any facilities necessary to accommodate future development must be guaranteed prior to the recordation of the first final map, issuance of a grading permit or building permit, whichever occurs first in Zone 15. B. Prior to the recordation of any final map, for any specific project within Zone 15, the developers of that project are required to: 1. Pay the required drainage area fees established in the current Drainage lMaster Plan and; 2. Execute an agreement to pay any drainage area fees established in the fonhcoming revised Drainage Master Plan. C. Prior to the recordation of the first final map, issuance of grading permit or building permit, whichever occurs first within Zone 15, the developers are required to financially guarantee Zone 15’s proportional share of the following facilities to the satisfaction of the City Engineer: 1. Sediment detention basin to be installed in Zone 15 upstream of Rancho Carlsbad Mobile Home Park. 2. Restoration or reconstruction of approximately 3,500 feet of Calavera Lake Creek from the proposed detention basin to El Camino Real bridge to the satisfaction of the City Engineer. 3. Provide a mechanism for the maintenance of the sediment detention basin. Prior to issuance of a building permit within Zone 15, the sediment detention basin and restoration of Calavera Lake Creek shall be installed. Financing The cost of the proposed sediment detention basin is estimated to be S86,ZO and the estimated cost for restoration or reconstruction of Calavera Lake Creek is s634,ooo. 90 D. WATERSHEDA 1. Prior to the recordation of the first final map, issuance of grading permit or building permit, whichever occurs first within Watershed A of Zone 15, the developers are required to 6nanciaUy guarantee the construction of the following facilities: a. 54" storm drain from northwestern Zone 15 to future Cannon Road. The estimated cost for 54" storm drain is $ 248,400. E. WATERSHEDB 1. Prior to the recordation of the first final map, issuance of grading permit or building permit, whichever occurs first within Watershed B of Zone 15, the developers are required to financially guarantee the construction of the following facilities: a. 36" storm drain north of future Cannon Road. b. E3.J (48") storm drain south of future Cannon Road. c. 78 storm drain along future Cannon Road alignment. The estimated cost for the 36 storm drain north of future Cannon Road is $131,100. The estimated cost for storm drain BJ is $491,280. The estimated cost for the 78" storm drain is $472,500. These facilities are to be funded by the developer of Watershed B. F. WATERSHEDC No special conditions are required. G. WATERSHEDD 1. Prior to the recordation of the first final map, issuance of grading permit or building permit, whichever occurs first within Watershed D of Zone 15, the developers are required to financially guarantee the construction of the following facilities: a. BL (60" - 78) storm drain along future College Boulevard between El Camino Real and Agua Hedionda Creek. 91 LEGEND: EXISIINO YlOnM UAAlN . . . . - .- __ EXISllNO EARTtl CHANNEL - EKlSrlNQ BOX CULVERT I I - - I PROPOSED STORM DRAIN CllY OF OCEANSIDE PROPOSED DESlLTATlON BASIN WllH CAPACITY x 100 C.Y. --- SUB ORAINAOE BASIN BOUNDARY --+ DIRECTION OF OVERLAND FLOW FLOW LINE OF CREEK ZONE 16 BOUNDARY WATERSHED BOUNDARIES . __...__ APPROXIMATE LOCATION OF @ EXISTINO FACILITY Celavore Creek e00 I200 Watershod Eoundarles Local Facillties Management Plan Zone 15 -91 b. 30" - 48" storm drain south of Agua Hedionda Creek. c. BK (54") storm'drain north of Agua Hedionda Creek. Financlne The cost for the proposed facilities in Watershed D is $453,325. facilities are to be funded by the developer of Watershed D. These IV. FINANCING A large portion of Zone 15 falls within Drainage Master Plan Areas Nos. 9 and 13, the boundaries of which are indicated in Appendix 4. Fees for these drainage areas were established as part of the 1980 Master Plan. The City's Drainage Master Plan is currently being revised. The revised plan should address fee requirements for the areas of Zone 15 not within the existing Drainage Master Plan Areas Nos. 9 and 13. Exhibit 40 on page 94 summarizes the above financing in a facility financing matrix. This matrix summarizes the individual facility to be financed, its estimated cost and timing of construction, the existing budgeted CIP monies available for the facility and the future funding options. 93 LNHlElr 40 ZONE 15 - DRAINAGE FINANCING MAlRlY AS OF 1/1/90 -----_._---_____________________________---------------------------------------.---------------------------------.-------------------------------- Sedinmt Oetcntlon Basin Chml Rccontructlon Uatcrshed A: 5bm 8tOC. drain Uatcrshed 0: 36" storm driln Llne BJ storm drain Uatershed 0: 60y-78u 8tOIU draln 30"-48* storm draln Headwall8 Clcamut Rlp Rap 54'' storm drain tlea&al Is C I eanout a RIP R.p 1-2 acres 3,500 LF 1200 LF 950 LF 1.00 LF 1,350 LF 1,060 LF 412 LF 1 Ea. 5 Ea. 35 CY l.200 Lf 2 EA 1 EA 10 CY S86.250 Wb,OOO S248,400 Sl3I.100 S491.20 1272,500 s200,790 $38,560 $3,300 ~15,000 U.725 s1~,000 %- $3,000 SI, 350 =_EI==ZETEIELE IOlAL DRAINAGE COSIS $2,526,155 concurrent w/ developmi concurrent w/ devalqmi cmcurrent u/ davelapnmi concur r ent w/ developni I Y concurrent u/ developml I 0 0 0 Y I I 0 developer developer davcloper developer Y I developer I I I (I I I I I This page left blank CIRCULATION FACILITIES I. PERFORMANCE STANDARD No road segment or intersection in the zone nor any road segment or intersection out of the zone which is impacted by development in the zone shall be projected to exceed a Service Level C during off-peak hours, nor Service Level D during peak hours. Impacted is when twenty percent or more of the traffic generated by the Local Facilities Management Zone will use the road segment or intersection. 11. FACILITY PLANNING AND ADEQUACY ANALYSIS This analysis determines whether or not the circulation system within Zone 15 conforms to the adopted performance standard. It will also address all circulation element road segments and intersections outside of Zone 15 impacted by twenty percent or more of the traffic generated by Zone 15 to ensure conformance with the adopted performance standard. This section is based on the "Transportation Analysis For Carlsbad Facilities Management Zone 15" report prepared by Urban Systems Associates, Inc., dated August 9,1989. In order to determine the transportation related impacts which are likely to result from land uses within Zone 15 and to develop the off-site transportation improvements phasing plan, Urban Systems obtained and evaluated existing traffic flow data for the area. Projections for future short-term and long-term traffic flow were provided by the San Diego Association of Governments (SANDAG) in their City of Carlsbad Constrained General Plan Use Traffic Forecast of August 29, 1986. The update to the Circulation chapter also incorporates the "Transportation Analysis For Sunny Creek - T.M. 83-36 Amended" report prepared by Urban Systems Associates, Inc., dated February 22, 1996. The project specific transportation analysis is utilized as a supplement to the original Zone 15 transportation analysis. This transportation analysis also identifies the transportation related impacts which are likely to result from the land use changes within Zone 15 and to develop the off-site transportation improvements needed for the development of Development Area 1. Urban Systems obtained and evaluated existing traffic flow data for the area based on data provided by the 1994 SANDAG (San Diego Association of Governments) traffic flow map and the City of Carlsbad Traffic Monitoring Report prepared by JHK & Associates in 1995. Zone 15 LFMP Amendment 95 June 10,1998 A. INVENTORY 1. Circulation Element Roads Within Zone 15 Zone 15 consists of 502 existing mobile homes with access to El Camino Real by Rancho Carlsbad Drive and 18 single family dwelling units scattered throughout the zone with access to public streets by way of private driveways and easements. El Camino Real along the westerly portion of Zone 15 is currently an interim four lane prime arterial that will be improved to six lane prime arterial standards as abutting properties develop or as may be needed to comply with the Growth Management Standards. Circulation element roadways located in Zone 15 include the following: Road Segment Classification Cannon Road Major Arterial College Boulevard to eastern Zone 15 boundary College Boulevard El Camino Real to Cannon Road Major Arterial These roadways are shown on Exhibit 41 on page 98. 2. Identification of ImDacted Road Sepments and Intersections As stated in the performance standard, impacted road segments and intersections are those that have 20% or more of the Zone 15 traffic using them. Exhibits 42 and 47 on pages 99 and 104 shows the directional distribution percentage of traffic leaving Zone 15 from Development Area 1 and build out. The road segments and intersections that are impacted by Zone 15 and the development of Development Area 1 are as follows: Road Segments Classification El Camino Real Carlsbad Village Drive - Palomar Airport Road Prime Arterial Palomar Airport Road (PAR) College Blvd. - 1-5 Prime Arterial Zone 15 LFMP Amendment 96 June 10,1998 College Boulevard Palomar Airport Road - El Camino Real El Camino Real - Cannon Road Cannon Road City Limit - El Camino Real El Camino Real - 1-5 Intersections El Camino ReaVCarlsbad Village Drive El Camino ReaVChestnut Avenue El Camino Real/Tamarack Avenue El Camino RealKelly Drive El Camino ReaVCannon Road El Camino ReaVCollege Blvd. El Camino RealRaraday Avenue El Camino RealPalomar Airport Road Palomar Airport RoadCollege Boulevard Palomar Airport RoadPaseo Del Norte Palomar Airport Roam-5 Northbound Off Ramp Palomar Airport Roam-5 Southbound Off Ramp College BoulevardFaraday Avenue Cannon RoadCollege Boulevard Cannon Roawaraday Avenue Cannon RoadKelly Drive Cannon RoadPaseo Del Norte Cannon Roam-5 Northbound Off Ramp Cannon Roam-5 Southbound Off Ramp Major Arterial Major Arterial Zone 15 LFMP Amendment 97 June 10,1998 This page left blank LEGEND: Existing Roadwey ----- Proposed Roadway 10% I LEGEM) NO SCALE DIRECTIONAL DISTRIBUTION PERCENTAGES ONTO EXISTING STREETS Exhibit 43 EXHIBITELIMINATED Zone 15 LFMP Amendment 100 June 10,1998 Exhibit 44 EXHIBIT ELIMINATED Zone 15 LFMP Amendment 101 June 10,1998 Exhibit 45 EXHIBITELIMINATED Zone 15 LFMP Amendment 102 June 10,1998 Exhibit 46 EXHIBIT ELIMINATED Zone 15 LFMP Amendment 103 June ZO, 1998 BUILDOUT CIRCULATION - TRIP DISTRIBUTION EXHIBIT 47 Zone 15 This page left blank B. PHASING The previously estimated timing for the required improvements (i.e., 1990,1995,2000) has been revised to follow a more realistic approach. The timing for the required improvements is based on the impacts created by development at the time development occurs within Development Areas 1 through 5. If future traffic analysis or the City’s monitoring program indicate that additional or different improvements are needed, the required improvements identified in this LFMP may be adjusted to guarantee conformance with the adopted performance standards . The purpose of this analysis is to evaluate impacted road segments and intersections serving Zone 15 and to propose a mitigation plan if these facilities are determined to operate below the adopted performance standard. The phasing of development and analysis of traffic impacts will be monitored on an annual basis. However, for the purpose of this amendment, the timing of the necessary improvements will be presented in the following increments: Improvements needed for Development Area 1 Improvements needed prior to development within Development Area 2 Improvements needed prior to development within Development Area 3 Improvements needed prior to development within Development Area 4 Improvements needed prior to development within Development Area 5 One of the primary road segments impacted by development within Zone 15 is Cannon Road. Construction of this segment has been a concern for not only Zone 15, but Zone 7 and Zone 14 as well. This LFMP amendment addresses some appropriate measures to ensure that Cannon Road shall be constructed as needed. Cannon Road east of El Camino Real to the east city limit is divided into two segments identified as Reach 3 and Reach 4. Reach 3 of Cannon Road is the segment between El Camino Real and future College Boulevard. Reach 4 of Cannon Road is the segment between future College Boulevard and the east city limit. Due to land use changes and habitat conservation efforts, the area identified as Habitat Conservation Area will not be developed. Therefore, the need for Reach 4 of Cannon Road has significantly decreased. Along with a decrease in need is also a decrease in the number of dwelling units that would have contributed to the financing for the construction of this segment. It has been acknowledged by the City Engineer that due to the land use changes and the decrease in the number of dwelling units in this portion of Zone 15, Reach 4 may never be constructed or may be identified as a regional roadway, thereby relinquishing Reach 4 as a circulation facility requirement for Zone 15. The City Engineer’s decisions to consider Reach 4 as a regional roadway is based on the understanding that the property owners within Zone 15 agree to contributing their pro-rata share of the financing and construction of Reach 3 of Cannon Road. This agreement can be integrated into the facility fee program identified in the circulation mitigation requirements and the Zone 15 Finance Plan for the required improvements to College Boulevard and Cannon Road. In the event that the Zone 15 Zone 15 LFMP Amendment 105 June 10,1998 property owners present evidence that Reach 3 is not necessary for development within Zone 15, the City Engineer may reconsider reinstating Reach 4 as a Zone 15 circulation facility requirement. Additionally, if the property owners within Development Area 3 request approval for development within Development Area 3, then frontage improvements and adequate access may be required. The improvement requirements for Development Area 3 are described in the circulation mitigation requirements provided in this chapter as well as in the Zone 15 Finance Plan. Finally, prior to the recordation of a final map within Zone 15 outside of Development Area 1, a new fully updated Local Facilities Management Plan is to be approved by the City Council. At that time, the property owners within Zone 15 will be more knowledgeable regarding the actual development that should occur within Zone 15. A new LFMP will reflect this future development and provide a more accurate level of analysis for impacts and improvement requirements. C. ADEQUACY FINDINGS Traffic conditions for the impacts created by the future development have been analyzed. In accordance with the adopted performance standard, the existing and proposed traffic facilities within and surrounding Zone 15 will be identified by an evaluated level of service. The Zone 15 traffic report and the Transportation Analysis for Sunny Creek indicate that all existing facilities impacted by the zone currently meet the adopted performance standard. The recommended circulation improvements needed for each of the above Development Areas are identified and are discussed later in this analysis. The City of Carlsbad utilizes a two-tier evaluation to analyze the level of service for road segments. The two methods utilized are as follows: 1. Daily Capacity 2. Peak Hour Volumes The first level of analysis determines an approximate off peak level of service using a ratio of existing Average Daily Traffic (ADT) to an assumed average roadway capacity. This volume to capacity ratio provides an indication of level of service (A-F) for the road segments. This method is a very generalized approach in determining levels of service and is used as an indicator of the off peak level of service. Zone 15 LFMP Amendment 106 June IO, I998 According to the adopted performance standard, no road segment or intersection impacted by traffic generated from Zone 15 shall exceed a Level of Service C during off peak hours or a Level of Service D during peak hours. The daily capacity method, as described above, analyzes a road segment for a daily average volume and is not an indicator of peak hour volumes. Therefore, in conjunction with the performance standard, the evaluated levels of service utilizing the daily capacity method is indicative of off peak operating levels and a Level of Service C will not be exceeded. The second level of review for road segments analyzes peak hour capacities. This is a more detailed analysis and is performed when it can be shown that the road segment is functioning at a capacity greater than the assumed capacity. This method utilizes traffic counts during peak hours to determine the appropriate level of service. This detailed analysis is used to more accurately project timing of failure of the road segment. This allows the needed improvements to be scheduled so that conformance with the adopted performance standard will be maintained. Zone 15 LFMP Amendment 107 June 10,1998 1. LOS for Development Area 1 with Existing ADT The level of service for roadways impacted by Zone 15 upon the development of Development Area lare as follows': Roadway Capacity Volume V/C LOS El Camino Real Carlsbad Village Dr. - Chestnut 50.0 26.1 .52 A Chestnut - Tamarack 40.0 24.1 .60 A Tamarack - College 40.0 28.0 .70 B College - Faraday 40.0 22.9 .57 A Faraday - Palomar Airport Rd. 40.0 26.9 .67 A College Blvd. El Camino Real - Faraday Avenue Faraday Avenue - Palomar Airport Road Palomar Airport Road College - Paseo Paseo Del Norte to 1-5 Del Norte 20.0 7.3 .36 A 20.0 11.3 .56 A 50.0 41.3 .83 B 50.0 46.8 .94 c Source: Urban Systems Associates, Inc. - Transportation Analysis for Sycamore Creek I (pg. 19), February 22,1996 Zone 15 LFMP Amendment 108 June 10,1998 The level of service for intersections impacted by Development Areal are as follows2: Intersection El Camino RedCarlsbad Village Drive El Camino Real/Tamarack El Camino ReaVCollege Blvd. El Camino ReaVFaraday Ave. El Camino ReaVPalomar Airport Rd. Palomar Airport Rd./College Blvd. Palomar Airport Rd./Paseo Del Norte Palomar Airport Rd./I-5 Northbound Palomar Airport Rd./I-5 Southbound College BoulevarcUFaraday Avenue Off Ramp Off Ramp AM Peak PMPeak A B A A B A B B A A A B B C D C B D A A Cannon Road from 1-5 to the easterly City limit (Reaches 1,2,3 and 4) must be constructed to full major arterial standards prior to any connection with Cannon Road in the City of Oceanside. 2. LOS at Build Out Prior to development within Development Areas 2, 3, 4 and 5, an updated LOS analysis shall be conducted to determine the build out conditions of the identified road segments and intersections. Future long-term traffic volumes at build out of the City were provided by SANDAG in their “City of Carlsbad Fully Constrained General Plan Land Use Traffic Forecast,” August 29,1986. The Build Out projected roadway volumes and capacity of impacted road segments are the following: Source: Urban Systems Associates, Inc. - Transportation Analysis for Sycamore Creek I (pg. 20), February 22,1996 Zone 15 LFMP Amendment 109 June 10,1998 Roadway El Camino Real Tamarack - Kelly Kelly - Cannon Cannon - College College - Faraday Faraday - Palomar Airport Rd. College Blvd. El Camino Real - Sycamore Creek Rd. Sycamore Creek Rd. Cannon Rd. 44.5 Cannon Road City Limit - College College - El Camino Real El Camino Real - Faraday Faraday - Paseo Del Norte Paseo Del Norte - 1-5 Capacity 44.5 44.5 66.7 66.7 66.7 44.5 24.9 44.5 44.5 44.5 44.5 50.0 Volume VIC LOS 29.7 29.7 29.9 38.6 49.5 37.3 .56 15.7 14.4 13.5 18.7 30.3 .67 -67 .45 .58 .74 .84 A .35 .32 .30 .42 .6 1 B B A A C D A A A A B Zone 15 LFMP Amendment 110 June 10,1998 The level of service for intersections impacted by Zone 15 at build out are the following: Intersection El Camino ReaVChestnut El Camino Reawamarack El Camino ReaVKelly Drive El Camino ReaVCannon Rd. El Camino ReaVCollege Blvd. El Camino ReaVFaraday Ave. El Camino ReaVPalomar Airport Rd. Cannon RoadEaradayA Cannon RoadKelly Cannon Roamaseo Cannon Roam-5 Cannon Roam-5 Del Norte Northbound Off Ramp Southbound Off Ramp AM Peak PM Peak A B A B C D C C A C B A A B A C C C C A D B B Analysis of College Boulevard from El Camino Real to Sycamore Creek Road indicates that the road segment may operate at an unacceptable Level of Service at build out. In accordance with the City's "Guidelines and Instructions for the Preparation of Local Facilities Management Transportation Studies," a peak hour analysis is necessary for College Boulevard from El Camino Real to Sycamore Creek Road. The results are as follows: Roadwav College Boulevard El Camino Real - Sycamore Creek Rd. D From Method 2 analysis, this road segment is projected to operate at an acceptable level (see Method 2 worksheet in Appendix 5). Therefore, all impacted roadways and intersections are operating at adequate level of service at build out to meet the adopted performance standard. Zone 15 LFMP Amendment 111 June 10,1998 This page left blank 111. MITIGATION Special Conditions The proposed mitigation is divided into the categories established under the phasing portion of this section. Since a finance plan accompanies this LFMP Amendment, all cost references have been removed and are now located in the Zone 15 Finance Plan. It should be understood that all cost estimates presented in the finance plan are preliminary in nature and will need further refinement as the actual scope of work, utility needs, environmental mitigation requirements and right-of-way dedications are determined. A. An ongoing monitoring program shall be established to evaluate the aspects of improvements, development, and demand on circulation facilities. The construction of improvements is based upon the projected demand of development in the zone and the surrounding region. The construction schedule may be modified without amendment to this plan, however, any deletions or additions to the improvements will require amending this local plan. B. Prior to approval of any tentative map adjacent to College Boulevard within Zone 15, outside the boundary of Development Area 1, the specific alignment for College Boulevard between the northerly boundary of Zone 15 and El Camino Real must be established. This shall include the necessary environmental clearances and required public hearings so that construction of College Boulevard can accommodate future development. The funding for the construction of College Boulevard will be guaranteed as provided by the Zone 15 Finance Plan. C. Prior to recordation of the first final map, issuance of grading permit or building permit, whichever occurs first, within each of the specifically identified development areas of Zone 15, a financing program guaranteeing construction of the following circulation improvements shall be approved: 1. DEVELOPMENT AREA 1 a. College Boulevard 1. College Boulevard between El Camino Real and the northern boundary of Development Area 1 shall be constructed to full width arterial standards. Zone 15 LFMP Amendment 112 June 10,1998 b. College Boulevard and Cannon Road (Reach) 1. Prior to recording a final map or the issuance of a grading permit or building permit, the applicant shall enter into a secured financial agreement in a form acceptable to the City Council that will secure its fair share of the cost of College Boulevard from El Camino Real to the northern boundary of Zone 15 and Reach 3 of Cannon Road. C. El Camino Real 1. Construction of half street improvements for El Camino Real to prime arterial standards including landscaped median along the frontage of the developing property. 2. Construction of median from the northwestern boundary of Development Area 1 to the existing improvements south of Rancho Carlsbad Drive. 3. Construction of transition improvements on the east side of El Camino Real from the northwestern boundary of Development Area 1 northerly to a distance determined by the City Engineer. 2. DEVELOPMENT AREA 2 a. College Boulevard and Cannon Road 1. Prior to recording a final map or the issuance of a grading permit or building permit, a financial guarantee to the satisfaction of the City Council shall be in place that will provide for a pro-rata share of the cost of College Boulevard from El Camino Real to the northern boundary of Zone 15 and Reach 3 of Cannon Road. 2. Development within this area shall be obligated to construct only those portions of College Boulevard and Cannon Road offsite from the development which are necessary to serve the respective development in accordance with City Standards and to the satisfaction of the City Engineer. Zone 15 LFMP Amendment 113 June ZO, 1998 b. College Boulevard 1. Construction of half street improvements for College Boulevard to major arterial standards including landscaped median along the property fronting College Boulevard. This condition applies to the frontage of the property being developed, if any. 3. DEVELOPMENT AREA 3 a. College Boulevard and Cannon Road 1. Prior to recording a final map or the issuance of a grading permit or building permit, a financial guarantee to the satisfaction of the City Council shall be in place that will provide for a pro-rata share of the cost of College Boulevard from El Camino Real to the northern boundary of Zone 15 and Reach 3 of Cannon Road. 2. Development within this area shall be obligated to construct only those portions of College Boulevard and Cannon Road offsite from the development which are necessary to serve the respective development in accordance with City Standards and to the satisfaction of the City Engineer. b. Cannon Road 1. Construction of half street improvements for Cannon Road to major arterial standards including landscaped median along any developing property which fronts onto Cannon Road. 2. Construction of the center two lanes separated by a raised improved median from College Boulevard to the most easterly road constructed to provide access for the developing property. 3. Conditions 3.b.l and 3.b.2 noted above may be omitted when in the opinion of the City Engineer either one or both of the following conditions exist: a) The Development Area 3 property is precluded from access to Cannon Road due to the requirements of the Habitat Management Plan; or, The proposed development of the property does not access Cannon Road and lacks adequate “nexus” for construction of such improvements in relation to the proposed development. b) Zone 15 LFMP Amendment 114 June 10,1998 4. DEVELOPMENT AREA 4 a. College Boulevard and Cannon Road 5. 1. Prior to recording a final map or the issuance of a grading permit or building permit, a financial guarantee to the satisfaction of the City Council shall be in place that will provide for a pro-rata share of the cost of College Boulevard from El Camino Real to the northern boundary of Zone 15 and Reach 3 of Cannon Road. 2. Development within this area shall be obligated to construct only those portions of College Boulevard and Cannon Road offsite from the development which are necessary to serve the respective development in accordance with City Standards and to the satisfaction of the City Engineer. b. College Boulevard 1. Construction of half street improvements for College Boulevard to major arterial standards including landscaped median along the property fronting College Boulevard. This condition applies to the frontage of the property being developed, if any. C. El Camino Real 1. Completion of half street improvements for El Camino Real to prime arterial standards including landscaped median from Rancho Carlsbad Drive to the southeastern boundary of Development Area 4. This condition applies to the frontage of the property being developed, if any. DEVELOPMENT AREA 5 a. El Camino Real 1. Completion of half street improvements for El Camino Real to prime arterial standards including landscaped median along the frontage of the developing property between Development Area 1 and Cougar Drive. Zone 15 LFMP Amendment 115 June 10,1998 2. Prior to final map approval or issuance of a building permit the developing property owner shall pay their fair share contribution for the installation of the El Camino Real improvements pursuant to the requirements of the El Camino Real median reimbursement agreement dated May 6, 1988. Zone 15 LFMP Amendment 116 June 10,1998 This page left blank Pages 117 - 125 are blank due to Revision of Zone 15 This page left blank FIRE FACILITIES I. PERFORMANCE STANDARD No more than 1500 dwelling units outside of a five minute response time. 11. FACILITY PLANNING AND ADEQUACY ANALYSIS k INVENTORY 1. Inventow of E xistinn Demand: A total of 127 existing dwelling units in Zones 7, 8, 14, 15 and 24 are presently outside a five minute response time. from Fire Stations No. 3 and No. 5. The existing developments outside the five minute response time are itemized in Appendix 6. A summary of fire demand is as follows: Existing Units Outside Five Minute Response 127 Performance Standard Unit Limit 1.5oQ Dwelling Units Allowed Above Performance Standard 1,373 2. Inventory o f Existinp Fire Facilities: At the present time, Fire Stations Nos. 3 and 5 serve Zone 15. Fire Station No. 3 is located at 3701 Catalina Drive. Fire Station No. 5 is located in the City Safety Center. Both stations are shown on Exhibit 49 on page 127. This exhibit also shows the five minute fire response time within this area. A 30 mph average driving rate is used to determine the five minute response time. The five minute response time begins when the fire truck leaves the fire station. This is equivalent to a 2.5 mile driving distance from the fire station. 126 126 CLU’s Outside Of Response nine In Zone 7 111 MANrrOU ENGINEERING COMMY EXHIBK 49 Existing Fife Response 77me -127- . Zone 15 .. . 3. -oved Fa-- Fire Station No. 3 will be relocated eastward from its current location to an area adjacent to Carlsbad Village Drive and Tamarack within Zone 7. The City's five year Capital Improvement Program (CIP) has scheduled funding for the relocation during 1992-1993. B. PHASING Fire Stations No. 3 and No. 5 will provide fire support to Zone 15. The specific timing for relocation of Fire Station No. 3 will depend on: 1) the rate of development within the northeast quadrant and 2) the amount of development outside the five-minute response time of Fire Station No. 3. Per the performance standard for fire facilities, no more than 1500 dwelling units may exist outside the five minute response time of a fire station. Exhibit 50 on page 129 shows the five minute response time after relocation of Fire Station No. 3 in addition to Fire Station No. 5. As shown on this exhibit. no dwelling units will be outside the five minute response time of Fire Stations No. 3 and No. 5 within the northeast quadrant at build out. C. ADEQUACY FINDINGS Zone 15 currently meets the adopted performance standard and will continue to meet the performance standard until build out. 111. MITIGATION SDecial Conditions No special conditions. 128 LEGEND Gisting fire Station - ha Wthin The 'Five Minute Response Tme" Far ES#3 11-1)- Area Within The '%e Minute Response Tme" Ru ESUS 1111 MANrrOU ENGINEERING COMPANY EXHlBlT 50 Proposed Ere Response Time Zone 15 -129- N. FINANCING The City of Carlsbad's 1989-90 to Build Out CTP schedules $451,000.00 for the design and construction of the relocated Fire Station No. 3. This station will be a 3,500 square foot facility of the same design as Stations No. 4 and No. 6. After the relocation, the existing Fire Station No. 3 building and site will be sold. Exhibit 51 on page 131 shows a facility financing matrix for this facility. This matrix summarizes the individual facility to be financed, its estimated cost and timing of construction, the existing budgeted CIP monies available for the facility and the future funding options. 130 EWHl8ll 51 ZWE 15 - FIRE FINANCING MATRIX AS OF 1/1/90 I 1. flre station YO. 3 I I I I 1. I I I I I I I -relocation I I I US1,oM) I 1992-93 IClIV - Pff 1=1.c..1...=. I - 131- OPEN SPACE FACILITIES I. PERFORMANCE STANDARD 11. Fifteen percent of the total land area in the zone exclusive of environmentally constrained non-developable land must be set aside for permanent open space and must be available concurrent with development. FACILITY PLANNING AND ADEQUACY ANALYSIS Mibit 52 on page 133 shows graphically the existing, approved and future performance standard open space within Zone 15. Performance standard open space consists of 1) developed open space areas within existing and approved projects and 2) unconstrained, undeveloped open space throughout the remainder of the zone. Unconstrained, undeveloped open space is land that will remain as permanent open space and is free of environmental constraints. Environmental constraints include: beaches, permanent bodies of water, floodways, slopes greater than 40%, simcant wetlands, sigmficant riparian habitats, significant woodland habitats, major power line easements, railroad track beds, and other significant environmental features as determined by the environmental review process. Slopes 2540% and major powerline easements that are improved for open space purposes can count for performance standard open space. A. INVENTORY 1. Inventory of Open Soace Demand. .. The performance standard open space required to be provided for Zone 15 is 15 percent of the total land area that is exclusive of environmentally constrained non-developable land. The total land area within Zone 15 that falls under this definition is 1,227.13 acresm. Zone 15’s build out performance standard requirement for open space, therefore, is 184.07 acres. The existing, approved and future performance standard open space demand and supply is itemized in detail on Exhibit 53 on page 134. See Exhibit 11 on page 30. 132 LEGEND: Performance Standard Open Space -1 Exlstlng Approved EXHIBIT 53 -1 34- As mentioned in the Build Out section, there are 520 existing single family dwelling units located throughout Zone 15. Eighteen of these units are located on large lots, of which the majority of the land is in its natural state. Also, it is anticipated that these lots will be developed at a higher intensity in the future. For purposes of this analysis, therefore, these units are not considered to generate any existing open space demand. Currently, the existing and approved performance standard open space demand is as follows: Acres of Required Developed/ Performance Approved Standard Acres - Existing Approved 88.4 1 13.26 277.84 41.68 366.25 54.94 The performance standard open space demand created by existing projects and approved projects in Zone 15 is 54.94 acres. 2. Inventory of E xist inp and Approved Open Space S- 1: An inventory of the existing and approved performance standard open space supply is also shown on Exhibit 53 on page 134 and is summarized as follows: Acres of Performance Standard - Existing . 111.12 Approved 29.1Q TOTAL 140.22 The total existing and approved performance standard open space supply is 140.22 acres. The existing and approved performance standard open space demand is 54.94 acres. Therefore, 85.28 acres of open space are existing in Zone 15 in excess of the demand generated by existing and approved 135 developments. The open space performance standard in Zone 15, therefore, is currently being met for existing and approved projects. 3. Adequacy Analysis at Build Out: As shown on Exhibit 53 on page 134, in addition to existing and approved performance standard open space supply, 43.05 acres will be required to be supplied by future development within Zone 15. This future open space, when added to existing and approved open space provides 184.07 acres of performance standard open space at build out. The build out demand for open space is 184.07 acres, therefore, the performance standard open space is projected to meet demand at build out. Since Zone 15 is largely undeveloped, many areas of the zone do not have specific development plans available to identify the exact location for future open space. Therefore, all future development will be required to show how it contributes to meeting the above open space requirement above and beyond meeting the other City standards and development regulations. It must also show that the development does not preclude the provision of performance standard open space at build out of Zone 15. B. PHASING Since the Zone 15 phasing schedule does not address the yearly amount of acres developed within Zone 15, no phasing of open space facilities demand can be projected at this time. As part of the annual monitoring program the preparers of this zone plan will provide evidence to assure the open space performance standard is met. C. ADEQUACY FINDINGS As of 1/1/90, Zone 15 has sufficient permanent performance standard open space to meet the adopted performance standard for existing and approved development. In addition, future development within Zone 15 will be required to show how it contributes to meeting the build out open space demand. 136 111. MITIGATION k All future development within this zone shall be required to show how it contributes to meeting the open space performance standard above and beyond meeting the other City standards and development regulations. It must also show that the development does not preclude the provision of performance standard open space at build out of Zone 15. B. Open space compliance will be monitored annually and as individual projects are reviewed within this zone. C. Prior to the approval of any development within this zone, the Planning Director shall be required to find that the development does not preclude the provision of performance standard open space at build out of Zone 15. IV. FINANCING Funding for performance standard open space will be provided by the property owners of Zone 15. Affected property owners or the Homeowners Associations will be responsible for maintaining open space facilities within their development. Unconstrained open space that is not developed will not require maintenance. If unconstrained open space is developed, the funding will be provided by the developer of that open space. 137 SCHOOL FACILITIES I. PERFORMANCE STANDARD School capacity to meet projected enrollment within the zone as 'determined by the appropriate school district must be provided prior to projected occupancy. 11. FACILITY PLANNING AND ADEQUACY ANALYSIS Management Zone 15 is located within the jurisdiction of the Carlsbad Unified School District (CUSD) as shown on Exhibit 54 on page 139. Existing development consists of a 502 unit mobile home park and 18 single family dwelling units. The mobile home park does not generate any students because it is an adult only park. The students generated from the existing singe family dwelling units currently attend Kelly Elementary, Valley Junior High and Carlsbad High School. A. INVENTORY 1. Zone 15 is totally within the boundaries of Carlsbad Unified School District. There are no schools located within Zone 15. The northwest quadrant of the City contains most of the existing schools within the District. At this time, there are five (5) elementary schools, one junior high, one continuation high school, and on high school, all of which are at capacity. 138 ncpe Eiementarj Scnooi. K-8 SchoolI i LEGEND: Existlng SC~OO/ CIty ol Enclnitat 0 Proposed ~choo/ m MANTTOU EXHIBIT 54 ENGINEERING COMPMlY School District Locations Zone 15 -139- The Carlsbad Unified School District recently adopted a new school location plan. The location plan indicates that three (3) elementary school sites will be needed in the northeast quadrant in the future. One site has been identified in Local Facilities Management Zone 7 and two sites in Zone 14. The City of Carlsbad is in the process of revising the City's General Plan to reflect the new school locations selected by the CUSD. B. ADEQUACY FINDINGS For the purposes of long range planning, Carlsbad Unified School District considers all existing facilities at capacity. The smallest increment of demand area used by the District for facility analysis is the quadrant. Although additional sites have been identified in the northeast quadrant, any additional demand generated from Zone 15 development prior to the construction of new schools will necessitate the use of temporary classrooms and relocatables on existing sites. 111. MITIGATION Con- .. A. Conformance with the adopted school performance standard will be a prerequisite of any development within the zone. All development within Zone 15 will be conditioned to pay school fees in accordance with the requirement of the Carlsbad Unified School District. B. ' If Carlsbad Unified School District determines development in Zone 15 will generate student demand prior to construction of new school facilities, financial provision for temporary facilities on existing school sites will be required. IV. FINANCING Financial requirements for school facilities in Zone 15 are comprised of school fee payment and those costs of providing temporary facilities for student demand generated in advance of permanent accommodations if necessary. 140 This page left blank SEWER FACILITIES I. PERFORMANCE STANDARO Trunk-line capacity to meet demand as determined by the appropriate sewer district must be provided concunent with development. 11. FACILITY PLANNING AND ADEQUACY ANALYSIS Sewer service in the City of Carlsbad is provided by three independent agencies: Carlsbad Sewer Service District, Leucadia County Water District (LCWD), and Vallecitos Water District. Zone 15 is entirely within the Carisbad Sewer Service District, as shown on Exhibit 55 on page 142. The information contained in this plan was obtained from the "City of Carlsbad Master Plan of Sewerage" prepared by Wilson Engineering, December, 1987. A. INVENTORY 1. The Rancho Carisbad Mobile Home Park is sewered by an 8 main which flows north to Hidden Valley Road to the existing trunk main which runs along the north side of Agua Hedionda Lagoon. This main is the North Agua Hedionda Interceptor. As shown on Exhibit 57 on page 147, the major sewer interceptors that serve Zone 15 are as follows: a. b. Vista/Carlsbad Interceptor (V/C I) North Agua Hedionda Interceptor (NAHI) In conjunction with these interceptors, a number of lift stations are required to collect the sewage and convey it to the Encina Water Pollution Control Facility (WPCF). a. North Aeua Hedionda Interceptor The North Agua Hedionda Interceptor was constructed in 1966. The interceptor starts at El Camino Real and flows westerly along the north shores of the Agua Hedionda Lagoon to the Foxes Landing Lift Station. The Foxes Landing Lift Station pumps the sewage up and across 1-5 into a short gravity interceptor which flows to the 14 1 . CALAVERA HlLLS RECLAMATION/ TREATMENT FACLJW (Existing But Not Operational) city of VIS;. cm of Son Martos Water District_/ FNER WASTEWATER RECLAMATION FACILITY Ctty at Enctnft8s- NOTE: All locations are aooroximale. EWER DISTRICT BOUNDARY: aJSeak! WASTEWA TER TREA TMENT PLANT-EXISTING EXHIBIT 55 ENGINEERING COMPPNV Sewer District Boundaries -142- Zone 15 MANlTOU Vista/Carlsbad Interceptor. The North Agua Hedionda Interceptor enters the Vista/Carlsbad Interceptor just upstream of the Agua Hedionda Pump Station. The North Agua Hedionda Interceptor is entirely owned by the City of Carlsbad and conveys only the City of Carlsbad’s sewage. Existing Peak Reach Sue Flows (inches) NAHl 21 0.33 NAH2 24 0.55 NAH3 24 1.96 NAH4 Siphons 1.96 NAH5 24 238 NAH6= - - NAH7 18 2.38 Analysis of the above Future Peak Full Pipe Flows Capacityl (MGW - 6.14 034 4.62 1.94 4.62 1.94 6.29 2.45 5.66 1.62 6.79 I -- able shows that the North A~I Existing (MGD)~ Full Pipe Available Capaciw 5.81 4.07 2.66 4.33 3.28 4.4 1 - a Hediond 1 Interceptor system currently has sufficient capacity to serve existing development in Zone 15. Future development within Zone 15 will be served by the South Agua Hedionda Interceptor, discussed later in this section. b. Vista Carlsbad Interceptoi The Vista/Carlsbad Interceptor is jointly owned by the City of Vista and the City of Carlsbad. The City of Carlsbad ownership rights in the interceptor increase throughout the interceptor reaching greater than 50 percent ownership in the downstream reaches of the interceptor. The following table provides a description of the gravity portions of this interceptor: 21 City of Carlsbad retains 100% ownership of ail reaches. Available pipe capacity as of January 1, 1988. 23 NAH6 is the force main from Foxes Landing Lift Station. 143 VISTA/CARLSBAD INTERCEPTOR Description of Pipe Reach Minimum Minimum Length . Capacity Carlsbad Capacity percent Size(in.) Slope( %) (ft.) (MGD) ownership (MGD) VC 13 42 .10 3,520 205 5 1.7 10.6 VC 14 42 .10 5,080 205 5 1.7 10.6 VC 15 42 .12 1,760 22.8 51.7 11.8 VC 16 54 .28 3 10 67.2 45.24 30.4 Existing reaches VC 13, VC 14, and VC 15 will require upgrading. These improvements will be funded through connection fees from both the City of Carlsbad and the City of Vista (See appendix A-9 for timing, cost, and proposed sizes for Vista/ Carls bad Interceptor improvements). ... 2. Proposed Build Out FaaU a. Sewer Basins The South Aqua Hedionda Interceptor is proposed to serve Zone 15 at build out. As shown on Exhibit 56 on page 146, Zone 15 consists of two sewer basins. The basin to the north is known as Sewer Basin 15A and one to the south is known as Sewer Basin 15B. These basins are shown on Exhibit 56 on page 146. Both flow in a westerly direction and come together and end at the intersection of El Camino Real and future Cannon Road. Together the basins comprise a portion of the South Agua Hedionda Sewer Basin. The requirements for the South Agua Hedionda Sewer Basin are taken from the Carlsbad Master Plan of Sewerage. b. Facilities Within Zone 15 At Build Out, wastewater from Sewer Basin 15A will utilize the South Agua Hedionda Interceptor. This will require the construction of new trunk sewers as shown on Exhibit 56 and as follows: Reach Locatlon SkLenmh (in.) (feet) SAHT2A Future Cannon Road 10 6,300 SAHT2C Future Cannon Road 15 3,500 144 For Sewer Basin 15B, the requirements consist of the following: Reach Locatio_n WLenmh (in.) (feet) SAHTlD Sunny Creek 15 3,500 SAHTlE SUMY Creek 15 4,540 SAHTlF Sunny Creek 8 zoo0 SAHTlG El Camino Real 18 2,500 C. Facilities Outside Zone 15 Sputh Aeua Hed ionda In terceD tot The South Agua Hedionda Interceptor is composed of four reaches of pipe and a pump station. The first reach (SAH1) flows west from El Camino Real. along the alignment of future Cannon Road and connects to the second reach (SAH2). SAH2 continues along Cannon to the proposed pump station where the effluent is pumped via the third reach (SAH3) to a connection with the fourth reach (SAH 4). This final reach gravity flows to the future connection with the Vista/Carlsbad Interceptor where it will proceed to the Encina Water Pollution Control Facility for treatment. The following South Agua Hedionda Interceptor facilities, as shown on Exhibit 57 on page 147, will serve future development in Zone 15: Reach Locatlon hLenmh (in.) (feet) SAHl Hidden Valley Road 21 2,320 sAH2 Hidden Valley Road 21 2,200 Lift Station . Future Cannon Road -- -- sAH3 Future Cannon Road 24 2,400 sAH4 Future Cannon Road 21 3,500 145 ,I LEGEND: ............. ----- \c Malor Sewer Facllllles Wlthln Zone 16 I\ Local Facilities Management Pian MNEERINO C- Zone 15 Local Facilities Management Plan EXHIBIT 57 ENOlNEERWUG coMFsMcy Zone 15 Malor Sewer Facllilles Outolde Zone 16 LEGEND: ri LJ 0 EXISTINO MAJOR SEWER LINE EXISTINO PUMP STATION PROPOSED MAJOR SEWER LINE PROPOSED PUMP STATION 0 000 1200 m -147- 3. . Md Out Asswptioq Square footage is based upon the analysis contained in the build out section of this plan. Ultimate build out projections in Zone 15 are from the City of Carlsbad Master Plan of Sewerage. ll&wLus Total Build Out P r oiectiow Residential 3,008 DU Commercial/ Office 835,429 Sq.Ft. Open Space 234 Acres 4. Technical Ass- 5. 6. Sewer Generation Rates as specified in the Carlsbad Master Plan of Sewerage used to project average peak sewer flows are as follows: Lliiauk 1 Jnit Flows Residential 220 GPD/DU Commercial 1,800 Sq.Ft./EDU Office 1,800 GPD/AC Open Space -0- The existing sewer demand being serviced in Zone 15 is 502 dwelling units. These units lie entirely within Sewer Basin 15A. Carlsbad's current sewer Master Plan establishes 220 GPD/DU as the unit flow generation factor as a basis for projecting the average sewer flows for residential use. By multiplying the number of existing units on sewer service by the flow factor and a peaking factor of 2.5 the existing demand for Zone 15 is -28 MGD. Proiected Bu ild Out De man4 The ultimate average sewer flows can be determined for Zone 15 by using the build out projections and the average unit flows. 'The following chart depicts the yearly build out projections for Zone 15: 148 Resid. Cumulative Non- Cumulative Yearly Resid. Resid. Non-Resid. Sewage Flow Year w units EDU EDU h!!aumQ Exist2* 1990 199 1 1992 1993 1994 1995 1996 1997 1998 502 260 368 368 400 400 389 321 502 762 1,130 1,498 1,898 2298 2,687 3,008 3,008 3,008 0 76 43 38 31 25 81 75 59 36 0 76 119 157 188 213 294 369 428 464 .28 .46 .69 .9 1 1.15 1.39 1.65 1.86 1.90 1.91 NOTES: (1) Peak Flow = Average Flow x 25 7. W The City of Carlsbad's Master Plan of Sewerage specifies the future use of reclaimed water for the irrigation of open space and recreational park areas within Zone 15. This reclaimed water could be processed through the Lake Calavera Hills Water Reclamation Plan within Village H in Zone 7. A more detailed discussion of this issue is contained in the Water section of this plan on page 162. B. PHASING . The approach taken to establishing sewer basin boundaries is based on ensuring that the needed facilities are in place prior to or commensurate with development. Sewer basin boundaries are shown on Exhibit 56 and correlate with the natural sewer drainage areas. Thresholds for the major sewer facilities within each sewer basin can be established from information contained within this plan. Although 520 residential units currently exist within Zone 15, only 502 units use the sewer system, with the remaining 18 currently on a septic system. These units.are assumed to use the sewer system at build out. Therefore, the demand has been added in 1996 at residential build out of Zone 15. 24 149 C. ADEQUACY FINDINGS The existing sewer system serving development in Zone 15 currently meets the adopted performance standard however; at the present time, there are no trunk sewerage facilities within Zone 15. Major sewer facilities will be a condition to the approval of future development in Zone 15 as required by the City, so that conformance with the adopted performance standard will be maintained. 111. MITIGATION Con- .. k Prior to the recordation of the first final map, issuance of a grading pennit or building pennit, whichever occurs first, for any development in Zone 15, a f5nanci.n~ mechanism guaranteeing the constru&on of ihe following sewer facilities shall be provided: a. b. c. d. e. SAHl adjacent to Hidden Valley Road. SAH2 adjacent to Hidden Valley Road. Lift Station adjacent to future Cannon Road. SAH3 adjacent to Future Cannon Road. SAH4 adjacent to Future Cannon Road. The estimated cost for the above facilities is $1,932,500. facilities will be funded by the developers of Zone 15. These B. Sewer Basin 1Sq 1. Prior to the recordation of the first final map, issuance of a grading permit or building permit, whichever occurs first, for any development in Sewer Basin 15& a financing mechanism guaranteeing the construction of the following sewer facilities shall be provided: a. b. - SAHl2A adjacent to Future Cannon Road. SAH?zC adjacent to Future Cannon Road. Financing The estimated cost for the facilities within Sewer Basin 15A is $839,500. These facilities will be funded by the developers of Sewer Basin A. 150 C. Sewer Rw 15B 1. Prior to the recordation of the first final map, issuance of a grading permit or building permit, whichever occurs first, for any development in Basin 15B, a financing mechanism guaranteeing the construction of the following sewer facilities shall be provided: a. b. c. d. SAHTlD adjacent to Sunny Creek Rd. SAHTlE adjacent to Sunny Creek Rd. SAHTlF adjacent to future College Boulevard SAHTlG adjacent to El Camino Real. The estimated cost for facilities within Sewer Basin 15B is $1,274,200. These facilities are anticipated to be funded by the developers of Sewer Basin B. IV. FINALVCING Exhibit 58 on page 152 shows a facility financing matrix for this facility. This matrix . summarizes the individual facility to be financed, its estimated cost and timing of construction, the existing budgeted CIP monies available for the facility and the future funding options. 15 1 SAHl Wlddtn Valley iod SAW2 Hlddcn Valley Rod So. Agua Hedlond. Llft Eta. Stage 1 SAW3 future Ciunon mod SAH4 future Cmar Rod SEVER BASIN 1% SAHlU future Cunon Rod SAHl2C future Cmar Rod SEUER BASIN 1%: SAHrlO Smny Creek Rod SAWrlE Smy Creek SAHrlf El Cuino Real SAHllG El Cmim Red 2321 Lf 2200 Lf 1 Ea. 2400 Lf 3500 Lf 6300 Lf 3500 Lf 3500 Lf 4540 Lf 2000 Lf 2500 Lf $313,200 $297, 000 1514,000 1336,000 UR.100 $472,000 $367,100 Concurrent u/ Developmt I Y Y N Concurrent u/ Development I Concurrent u/ Developmt I I I Developer Developer Developer Developer Developer Developer Developer Developer Developer Developer Developer Arrcrrmt Dlrtrlct I Y I Y I I Hello Roor Hello Roor Hello Roo. kllo Roor Hello Roor Hello RO(N kllo Roor I - 152- WATER FACILITIES I. PERFORMANCE STANDARD Line capacity to meet demand as determined by the Carisbad Municipal Water District must be provided concurrent with development. A minimum 10-day average storage capacity must be provided prior to any development. 11. FACILITY PLANNING AND ADEQUACY ANALYSIS Water service in the City of Carlsbad is provided by three independent agencies: Carlsbad Municipal Water District (CMWD), Vallecitos Water District, and the Olivenhain Municipal Water District. Water senrice for Zone 15 is provided entirely by the Carlsbad Municipal Water District (CMWD) as shown on Exhibit 59 on page 155. CMWD uses a Master Plan to evaluate the water systems within their district and formulate long range plans that will provide for future improvements. The information contained in this plan was extracted from the Master Plans of the Carlsbad Municipal Water District. The report prepared for CMWD is entitled "Costa Red Municipal Water District, Master Plan for Public Water System" dated February, 1985, prepared by Woodside, Kubota and Associates, Inc. This Master Plan, according to CMWD, should be used as a tool in planning for future improvements in Zone 15. A. INVENTORY 1. The existing major water facilities for CMWD that are in place within Zone 15 are shown on Exhibit 60 on page 156. The facilities are as follows: No Facility Location 1. 200 MG Squires Dam I NE Comer Zone 15 2. 27 line Southeasterly Portion Zone 15 3. 20" line El Camino Real 4. 1 MG "C' Reservoir North of future Cannon Rd. 5. 14" line In/Out Parallel future Cannon Rd. 6. 21" lines Northeasterly Portion Zone 15 T.A.P. lines 153 2. Id Out As- The section entitled, “Build Out Projections” on page 28 presents the ultimate build out projections €or Management Zone 15. llfamuk Residential High Density Residential Commercial/Office Planned Industrial Open Space 2,968 DU 122 Rooms 40 DU 52 Net Acres 8 Net Acres 132.5 Net Acres 154 Clt y of Vlsta Son Morcos City of Enclnit8s NOTE: All locations are aooroximate. MANrrOU -155- ENGINEERING COMPANY OMScak! EXHIBIT 59 Water District Boundaries Zone 75 EXHIBIT 60 Water Dlstrlbutlon System Local Facllltles Management Plan Zone 15 I 156 a. Average Unit Demand The District's Master Plan has established dwelling unit demand factors as a basis for determining projected average water demands. The following shows the average dwelling unit demands as determined in the CMWD report: RL - Low Density Residential (0-15 DU/Acre) I Jnit Demand 2s 1,400 GPD/DU RLM - Low-Med Density Residential 625 GPD/DU (0-4.0 DU/Acre) RM - Medium Density Residential (4-8.0 DU/Acre) RH - High Density Residential (15-23 DU/Acre) 400 GPD/DU 210 GPD/DU Commercial 3,000 GPD/ACRE IAlnsUk Office/Professional Unit Demand 3,000 GPD/ACRE 26 Planned Industrial 3,000 GPD/ACRE Open Space ---- b. Fire Flow Requirements me master plan for CMWD uses the following fire flow demands to analyze their water systems: 25 The Average Unit Demand for residential land use extrapolated from Plate I, entitled "Residential Water Demand Based on Density of Dwellings," in Costa Real's Master Plan. 26 The Average Unit Demand €or residential land use extrapolated from Plate I, entitled "Residential Water Demand Based on Density of Dwellings," in Costa Real's Master Plan. 157 FIRE FLOW REQUIREMENTSn RL Low Density Residential 0-1 5 RLM Low/Med Resid. 1.5- 4 RM Med Resid. 4 - 10 RMH Med/High Resid 10 - 20 RH High Resid. 20 - 30 N - Neighborhood Commercial c - community Commercial PI - Industrial RRI - Intensive Regional Retail Fire Flow Demand in Gallons/M inute 1500 - 1750 1,750 2500 3,500 3,500 3,000 - 4,000 3,000 - 4,000 3,000 - 4,000 6,000 4. Proiected Build Out Demand: The build out average water demands can be projected for Management Zone 15 by multiplying the build out projection established in this Plan to the average unit demand factors obtained from CMWD’s Master Plan. Projected Average Projected Build Out Build Out X Unit Demand = Average Water Demand The projected average water demand for the build out of Management Zone 15 is as follows: *’ ’Fire Flow recommendations from City of Carlsbad Fire Department. 158 Average Unit LaluUk ed B/O Demand RLM 2,236 DU 625 GPD/DU FU 229 DU 1,400 GPD/DU RM 502 DU 400 GPD/DU RH 162 DU 210 GPD/DU c/o 52 ACRES 3,000 GPD/AC PI 8 ACRES 3,000 GPD/AC TOTAL 159 Projected B/O Average Water Demand 1.40 MGD 032 MGD 020 MGD 0.03 MGD 0.15 MGD 0.02 MGD The following chart depicts the yearly build out demand projected for Zone 15, which is served by Carlsbad Municipal Water District. Cumulative Yearly Yearly Yearly Yearly Yearly Average Average URL RM RH Aaes Demand Demand mw w Ul Ul Bau Mm. MGD 1989 17 502 21 21 1990 260 I22 88 21 .42 1991 368 4.7 24 .66 1992 368 13 23 .89 1993 400 3.6 26 1-15 1994 392 8. 3.1 .26 1.41 199s 249 140 9.4 37 1.78 19% 182 81 40 9.4 .26 204 1997 1998 6.8 .02 2.06 4.7 .01 2.07 The projected build out average water demand, as determined by this plan, is lower than projected in the Master Plans. Therefore, the Master Plans for the district can be used as a tool for determining the proposed major water facilities for this zone, and conformance with the adopted performance standard will be assured through build out of Zone 15. 5. Prouosed Build Out The CMWD proposes the following major water facilities as shown on Exhibit 60 on page 156, to serve the ultimate build out of Zone 15: 160 A Squires Expansion 10 MG tank and pipelines B 42" transmission main C 36 transmission main D Pressure reducing station E 10" line F 16" line G lo" line H Pressure reducing station I Pressure reducing station J 16" line K 12" line L Pressure reducing station M 10 line N 14" line 0 Pressure reducing and 0 cogeneration station P Pressure reducing/meter station and 10 line Q Pressure reducing station Location Northeasterly comer Zone 15 Northeasterly to southeasterly comer Zone 15 El Camino Real Northeasterly comer Zone 15 From Map Key D to 0 running north to south Secondary feed from east (S.F.II Reservoir) Across northeasterly Parcel to Res. "C" Before Res. "C' On existing 14" line out of Res. "C" From southeasterly to northwesterly corners Zone 15 S.outheasterly portion Zone 15 Off 42" line easterly portion Northeast comer of Rancho Carlsbad Mobile Home Park From College Blvd. to Rancho Carlsbad Drive Off TAP. line northeasterly portion of Zone 15 Oceanside intertie in Cannon Rd. at City .limits At El Camino Real and Cannon Rd. in the Sycamore Creek subdivision 28 See Exhibit 60, on page 156. 161 R 10" line S 14" line Most northerly portion of Zone 15 In Cannon Rd. - relocation of existing 14" line on northwest side of Rancho Carlsbad Mobile Home Park T 10" line Stubbed to northern limits of Zone 15 U 10" line Stubbed to west at El Camino Real and Cannon Rd The location and sizes of the proposed water lines have been approximated for the purpose of this plan. Exhibit 60 on page 156 shows the proposed lines. The actual locations and sizes will be determined as individual projects within Zone 15 develop. 6. Potential Areas fo r Reclaimed Water; On March 21, 1989, the City of Carlsbad adopted an interim Reclaimed Water Use Policy for new land use development. This policy specifies that all new development within the City of Carlsbad shall use reclaimed water if it can be reasonably determined by the Utilities and Maintenance District and the City Engineer that reclaimed water is available to serve the project. The interim policy further indicates that installation of dual irrigation systems and connections to reclaimed water sources may be required subject to the terms and conditions of the forthcoming Water Reclamation Master Plan. The City of Carlsbad is currently in the process of preparing a Water Reclamation Master Plan which will indicate availability of reclaimed water to new development within the City. Areas identified by this plan for reclaimed water use will be subject to the interim Reclaimed Water Use Policy and consequent requirements from the Utilities and Maintenance District and the City Engineer as specified above. There are approximately 234 acres of open space within Zone 15 that could potentially benefit from the future use of reclaimed water. In addition, the median in College Boulevard could potentially use reclaimed water. 7. Averaee Ten-Dav Storape - Cauac iR According to the District Engineer of CMWD, the storage capacity in the CMWD system currently exceeds the City's 10-day storage standard. The District also indicated that CMWD's goal is to maintain the average 10-day storage capacity when the area within the district is at ultimate build out. 162 STORAGE CAPACITY Current- 1988 Projected- 1 993a Storage Capacity 168.0 MG 2535 MG Average Daily Demand 13.1 MG 18.0 MG Days of Storage 12.9 DAYS 14.1 DAYS Status ADEQUATE ADEQUATE B. PHASING The approach to phasing taken by this Local Facilities Management Plan is based on ensuring that needed facilities are in place prior to or commensurate with development. Due to the fact Zone 15 lies within 3 pressure zones, phasing should not be determined in relationship to water service. The phasing boundaries allow for independent review and development for the water facilities within each boundary. Development within one phase is independent of the improvement requirements of another phase. However, the water district may require improvements outside of the phase boundaries if deemed necessary to serve development. C. ADEQUACY FINDINGS The water distribution system for Zone 15 currently conforms to the adopted performance standard. The development review process established by CMWD will ensure that Zone 15 will remain in conformance with the adopted performance standard through build out of this Zone. In the high pressure zone, i.e. that area above the 300' elevation level, service will be required to be taken from the tri-agency pipeline. CMWD presently has planned to convert this line with the introduction of a pressure regulating and pump station located at Carlsbad Village Drive and College Boulevard and a regulating station located at Cannon Rd. in Oceanside. In the event these stations have not been built prior to development in this zone, these facilities would need to be addressed. Development in the Middle Zone, elevations 170'-300', will use as its source the flow from Squires Dam. In the event the 42" connection has not been made at that the, it will need to be installed or provisions be made for it. Due to its proximity to Squires Dam residual chlorine will be of concern. Detention time may be required Estimated expansion project cost: S7,000,000. 29 163 in order to mitigate this item. Depending on the location of the development, inter- connection with future Low Zone water may serve as a solution. In the Low Zone adequate supply is available with construction of pressure reducing stations and mains. Distribution mains should loop through the zone. One notable item is that all mains have been sized in the Master Plan assuming an ultimate system because this assumes the ability for flow from multiple directions. In the event multidirectional flows cannot be achieved, offsite improvements or the upsizing of onsite mains may be required. 111. MITIGATION A. All future development in Zone 15 shall be subject to requirements per the future Water Reclamation Master Plan as determined by the City Engineer. Any water reclamation facilities necessary to accommodate future development must be guaranteed prior to the recordation of a final map, issuance of a grading permit or building pennit, whichever occurs first for any project in Zone 15. B. . Water facilities for Zone 15 shall be provided at the time of development to the satisfaction of CMWD. C. Prior to or commensurate with installation of Zone 15 water facilities, CMWD shall determine that sufficient water facilities are in place to serve Zone 15. D. All development within Zone 15 shall pay the appropriate water fees established by CMWD. IV. FINAVCING The major water facilities and improvements within Zone 15 will be financed by the water districts capital improvement fund. Revenue for that budget is funded from development fees. Other improvements as noted in Appendix 10 are not included in the CIP and will be required to be funded by individual developers as needed. Exhibit 61 on page 165 shows a facility financing matrix for this facility. This matrix summarizes the individual facility to be financed, its estimated cost and timing of construction, the existing budgeted CIP monies available for the facility and the future funding options. 164 1 8700 LF sioo LF 2700 LF MOO LF 3900 LF 3400 LF 1EA 1 EA 10200 LF 7200 LF CWI) - C.I.P. #I m CJW-Csr1b.d mniclpml Voter Dtstrlct ------.------.-- I -165- Pressure R&lng Statlm (11 loH Line (MI ICy Line (HI Pressure R&lng d (0) Cogener8tlm Statlon Pressure R&lng Meter (P) Presiura R&ing Statlm (a1 lo* 1Ine (R) 14" Llrw (5) 10" Line (1) 10" Llrw (U) St8t hl 1 EA 9500 LF 2400 LF 1 1 1 2700 LF 6000 LF (11 300 LF 30 LF IOTA1 UAIER COS18 $50,000 $150.000 ~120,Ooo $100,oO0 SOO,O00 $225.000 $102,600 ~246,000 $11.400 $1,140 .Ell===icSS.: t17,5%.140 Concurrent u/Developnent 1w2+ Concur r ent U/D8Vdopmt Concurrent u/Devet-t I Devcl opr 00 - C.I.P. Developer Ocvclopr I QU)-Carlrbmd hlcip.1 Uater 0lrtrlct Note: ( I denotes locmtian reference m Exhiblt 60 m page 156. (1) 5400 Lf Recycled, 600 LF Yeu. I - 166- FACILITY FINANCING MATRXX The financing section of this Local Facilities Management Plan completes the analysis by providing financing mechanisms available to fund these public facilities. A facility financing matrix is present on Exhibit 62 beginning on page 168. This matrix supplies the following: 1. Fad&. The identification of each facility inciudes both the actual facility and land acquisition and operation where appropriate. 2. m. The area in acres (ac), lineal feet (LF) or number of units of a particular facility. 3. ed Cost. The cost estimate for each facility is based on the most accurate information as of the writing of this plan. The costs are in 1987-88 dollars and will be updated as yearly monitoring takes place. 4. Tim. The projected date the facility will be constructed. 5. Fundin9 Opt ion. The funding sources are listed in priority order and include City sources, developer sources and public financing sources. In many cases, a combination of sources are proposed. At the end of each facility summary is a list of projects that are currently budgeted in the City's approved 1987- 1992 Capital Improvement Program. Various financing options are summarized in the Executive Summary of this repon on page 1. 167 - 168- Clty - PFF I -169- Sedlnmt oetention Baain Chml Reccmstructiocr Uatershcd A: 54* storm drain Uatershcd E: 36* storm drain Llne BJ 7OY atom drain Uaterched 0: 60°*-781) atom draln 30'-48' rtorm draln He.dwol I I Cleanart Rip R.p S4* atorm draln He&ol ls Cl canart s Rip Rap 1-2 acres 3,500 LF 1200 LF 950 LF 1.800 LF 1,350 LC 1,060 LF 412 LF 1 E.. 5 La. 35 CY 1,200 LF 2 EA 1 LA 10 CY $06,250 w4,Ooo $248,400 $131,100 $491.280 W72,SW s200.790 $38,560 s3.300 $11,000 U.725 s180,OOo u6.m $3.000 $1.350 .xI..CD.aa=a: IOIAL ORAIYACE COSIS S2,526,855 concurrent W/ developent concurrent u/ ckvelopmt cawurrent u/ develapmt concurrent u/ developant 1) concurrent u/ develapmt 1) 1) 1) 1) 1) I I I developer developer developer developer m (I developer 1) (I (I 1) (I (I m 1) I IMPROVEMENIS NEEDED DY 1990: Camon frm Carlsbad Hlghluds to €1 C8dM Real IMPROVEMENIS NEEDED DV 1991: Camon fra El Cadno Real to Paseo del Yorte Traffic Slgnrlr at Camon/l-S nd Caman/Paseo Del Yorte College fra cumon Rod to El Cvino Real IMPRWEMEYIS YEEDEO DY 1993: Camm fra El Caaino Real to Ocemlde IMPROVEMENIS NEEDED DV 1995: El Canino Real/ Palollur Alrport Rod Intersect Im El Canlno Real/ Chestnut Ave. cm Road/ 1-5 Yorthboud off rerp 2 Luws 4 Lwrl 3 1s 2 1-s 4 Lues 2 1nCs left lurn IuwS 1 thru LnC turn lene U,lS4,150 $18,473.lPO $310,000 $1,16(,3OO $942. OOO $51,000 SlS,OOo $9,000 1990 1991 1991 1991 1993 1995 1995 l99S Developer Developer city CIP Developr Developer Developer Developer Developer Assessment DIrtriCt Assessment Dirtrict Developer Assessment District Mello Roos Mello Roos Mello Room Mello ROOS -171- _________---------- IIIPROVEMENTS NEEDED BY 1995: cam Road/ 1-5 Swthboud off rwrp El Cmino Real fra Camon Road to College Blvd Cam Rod frar Paseo Del Yorte to 1-5 IMPROVEMENTS NEEDED BY 1997: El Cmino Real fr/ College Blvd. to Palocur Airport Rod IwuovEnEnis WEEDED BY 2000: El Canlno Real/ Tamarack Ave El Cmlno Real/ faraday Ave. El Canino Real/ Palocur Alrport Rod Cm Road/l-5 Northband on rvlp Camon Road/I-S Southbard on rwp College Boulevard fror El Cmino Real to cam Rod . 1OlAL CIRCULAI turn lm 6 Lanes 5 LaneB 6 tones 1 Lme lurn Lane lurn Lute lurn Lane lurn Lene b Lanes I COSTS s10,000 $301,300 $25, 000 s337,100 $9,000 $9,000 $9,000 $9,000 s9.000 -.000 1995 1w5 1w5 lWT 2000 2000 2000 2000 2000 2000 Developer Developer Oevaloper Developer Developer Developer Developer Developer Developer Developer Assessment District Assessawnt District Assessent Dlrtrict Assessment Dlstrict Assessment Dlstrlct Hello ROO~ Hello Roos Metlo ROOS nello ROOS Hello Roos -1 77- EXHlUlr 62 (Page 6 of 9) I I I I I I I IOIAL FIRE COWS nsi,ooo I I I I IClIY - PFF I I I I I I I I I I I I PFF = Ptblic I I I Fwllltles Fee I ,_______..._-_______--------------------.-..-.---.- I -173- SAW1 Hiddm Valley Rod SAHZ Hldden Valley Rod So. Agua Hedionb Llft Sta. Stage 1 SAH3 Future Cumon Rod SAH4 Future tunon Rod SEHR BASIN 15A: SAHIU Future Cunm Rod SAHIZC Future Cunon Rod SEER BASIN 150: SAHllD Suny Creek Rod SAHllE Sumy Creek SAHllF El Culm Real SAHllG €1 Cvino Real 2321 LF 2200 LF 1 E.. 2400 LF 3500 LF 6300 LF 3500 LF 3500 LF 4540 LF zwo LF 2500 LF I IOIAL SEWER COSTS $113,200 $297,000 S514.000 $336,000 un,soo UR,000 $367. 500 Concurrent u/ Develcpent Concurrent u/ Developnt m Concurrent u/ Developnt Developer Developer Ocvel opr Develqxr Dcve I oper Develqm Developer Devel opr Developer Developer Developer Assessment Olstrict m N m m m Hello Roos Hello Roos Hello Roos Hello Roo. Hello Roor Mello loor Hello Roor I - 114- i Squirer II (A) 42* (0) 36* Line (C) zo* Llne (C) Prercure Rmbclng Statlon (Dl lo* Line (E) 16* Line (F) lo* Line (GI Prearure Rcbclng Statlon (Nl Pressure Rcbclng Strtlm (I] 16* Llne (J) 12* Line (K) 1 8700 LF 1100 LF 2700 LF &WO LF 3900 LF 3400 LF 1 EA 1 EA 10200 LF 7200 LF SUBlOTAL UAIER COSTS $10,OOO,000 $3,300. OOO t1,000,000 $700.000 t50,000 $220,000 $100,000 $85,000 -,m -,000 $500,000 $195.000 I..=t¶t.=I=.. S16,510,oM) 1989- 1992 1w2+ 1989- 1 W2 1989- 1992 Cmcurrent w/Devel-t #I 19924 Concurrent w/Devel -t #I Concur rent w/Develqnent #I Note: ( ) dcnoter tocatlon reference on Exhlblt 60 an pee 116. 00 - C.I.P. #I #I #I Developer 00 - C.I.P. Developer 00 - C.I.P. #I Dcvelapr I cmn-C.rllMd thlcipl Water Dlrtrlct I -175- Pressure Reduclng Stcltlon (1 10" Linc (M) ICu Line (N) Pressure Rcbclng and (0) Cogenercltlon Statlan Pressure Rcbclng Meter (P) station Pressure Reduclng Strtlon (a: IOu llnc 0) 14" llm (t) 1090 iinc (11 10' line (U) 1 EA 4500 LF 2400 LF I 1 1 2700 Lf 6ooo 1F (11 300 1F 30 LF TOTAL UAIER COSIS ts0,000 $150,000 $120,000 s1oo,o0O $225, OOO $102.600 S246,OOO $11,400 $1,140 Concurrent u/Oevtlopmt 1w2+ Cancur r ent w/Oeve I opmt Cancurrant w/Ocvelopnt n n W n n Developer CIM - C.I.P. Oeveloper Developer --Car l abd )lunlclp.l Uater Dlrtrict I ' -176- REFERENCES “Master Drainage Plan For The City of Carlsbad, California,” VTN Southwest, June, 1980. “Capital Improvement Program,” 1989-1990 to Build Out. “Citywide Facilities and Improvements Plan,” City of Carlsbad, Revised September 29, 1986. “Master Plan for Public Water System,” Costa Real Municipal Water District, February, 1985. “Guidelines and Instructions for the Preparation of Local Facilities Management Plan Transportation Impact Studies,” Engineering and Planning Departments, City of Carlsbad, February 9, 1988. “Carlsbad Sewer Master Plan,” Wilson Engineering, December, 1987. “Transportation Analysis for Sunny Creek T.M. 83-36 Amended”, Prepared for Russell Grosse Development Company, Urban Systems Associates, Inc., February 22, 1996. 177 This page left blank I 'IS - ---- I ;:;i~~r,.;,.~,i iii = cmllr ,iy ,llA - :poc id I (1s~. I ed ,F!k - Spec id I Resource Area = future Development et = Future Acquisition ~UtIERSHI P = City Owned JD = Scnool District ;T = State ' = Privately Owned -- = Lease3 5 H LCll I1Y AU!CIIY I = Lighted = Group Sicnic Facility 1 tI uuu IRL HFT I IH NUP GLU 1R PIP 0-0 ous LSI E C 1 5 Li,t E A 1<. 1 - I hi1 SCA SNY I1 VCA P AP CIRA RER EAA T U S I A 1 I 0 ti P E li 1 t C 0 L P R E S E R V LO LU AN SI SR IS fH I CP 1 NU 1IC:IOAV 2 NU LAGUN& RlVlERk jl IN H&C 1 NU H3S? GROVE ..I 1 I HACARIO (25 ACRC CREOII EA. QUAO.) Nu -+6 NU Plltf SCHOOL/ACQUIS111011 5.Bb 4.03 2. IO 21.55 25.00 -5.20 US!: - 61 Yf H 11 NN AI 5s I Ut WO U R 1 5 EXISTING COHH = 39 58 AC tl NU CANNON LAKE 6.81 SUA C a n. 8 NU PI0 PIC0 0.16 SUA C 9 NU OAK 0.40 SUA C m nn n 10 NU HAXTON BROUN .91 SUA C an a I1 NU ROIARY 1.00 SUA 1 12 NU BUENA VISTA ELEMENTARY SCHOOL 2.30 SUA SD n 13 NU CARLSBAO HIGH SCHOOL TENNIS COURTS 1.10 SUA SO n 14 NU SUIH COMPLEX 3.79 SUA C an m ATSF *n i 0 0, I4 RIIfO 0-FII us-- PlSP 110 HETY E EE EP R TAP NKRO GIKA I4 I I RGIII 0 GI 0 G H IRAB m-8 n - ti I K 1 R C - I n 0 R S E 5 ti 0 E C 0 U R T 5 - 1 I T 'I 3 i hh UN fD f LV B OC A0 RU OR ST S EB 'IOIAL ACQU~SIIION Of 1 AC. 10 INCLUDE PINE ELEHENIARY SCIIOM PARK (2 AC) REVISE0 4/21/89 City hned : School District = State - Privately bnned - Lt!dSed I1 L OB' EOC CRU OOR us1 R 1 5. I ITV Autt:IIY. = Lroup Ficnic Facility - Lighred A0 S 0 N f 1 LIU I CHASE FIELO NU I HidOltiG STREEl COHHUNIIY CLWlLR 1UU 1RH IP -0 us SE C 1 5 PL P R E 5 c li \' NU I lo JEFfERSOll ELEHENTARY SCHOOL PARK 'I so DD LB L LD -8 LD NU PILE ELEHENIARY SCHOOL PARK NU VALLEY JUNIOR HlGtI SCHOOL PARK NU CAC COUIURY NU PIN! SENIOR CENTER NU NU CANNNON NU MION BRWN fXlENSlOH MAGIIOL 1A ELEHENIARY SCHOOL PARK " .. L COf OHEP USTA R IA 1 NK 5 GI W RG 0 0 I 'I ! D D D** 8 2.00 SUA 1.50 SUA .8b SUA 3.31 SUA 4.10 SUA 1.70 SUA 1.15 SUA NU NU NU NU NU NOW-CITY OUNEO 25.10 (CUSD - 22.4 AC) REVISE0 4/21/89 AGUA HEOIONDA LAGOON 254.00 SRA 8UENA VISTA LAGOON 202.00 SRA BEACHES (28.3 AC CREDIT LA. QUO) 28.30 SRA MACAR10 (47 AC CREDIT EA, QUAO) 47.00 SRA HUB 92.00 SRA 101111111~ ! I ) !mucic I use Ar - Speciai kesoui red f utore bevelopment = Future Acquislt ion NI Hi HnCAAlO (25 AC. CREOll ALL QUAD.) LGiiJlY Ni NE 8 I I 2*oo I SUA cI n8 SAFEIY CENIER 6ALLFlELO HOFi ELEHENIARY SCHOOL PARK 2.60 SUA SD 1 P I’ 1; I L ” Fih 0 F F S I 1 E P A R K I N G - a - - I, 0 tI P 0 U E R B 0 A T I N G - - - i 0 U f R B 0 A 1 I H G - - - lJ II S I 1 E P A R K I N G - 8 - 1 f ti N 1 5 C 0 U R 1 S - ‘1 - n I 5 T R 0 0 H S - s - u Y H N A S I U H - . - - u R 0 U P H E E T I n G R 0 0 H - - tl 0 R S f 5 H 0 E C 0 U R 1 S - 3 I 2 E 16.16 25.00 22.20 63.36 > H U F F L E B 0 A R 0 S - U 1 1 I P U R P 0 S E C 1 5 U R f H U L 1 I U 5 E 1 A 5 5 I f I C A 1 I 0 N - COH COH COH - - E 1; I E C 0 1 P R E 5 E R V c I H H I N G P 0 0 L - - C N I C A R E A - 8 - - Y A P P A R A 1 U S - 8 - I - D V B C 0 U A 1 J - - - HSlllP = C it y Owned - = School DIstrict - State - Privately Owned - Ledsed I IIV A”EIll1Y woup +icnic fdci lity = 1 ighied - i’ I - I 1- - IOlAL : €€ EXISTING COHH 4 tlf BEACHES (28.3 CREOll ALL QUAO) 28.30 NE HACARIO (41 AC CREDll ALL QUAD) 47.00 111 LAKi CALAVERA 252.00 TOTAL : 327.30 1 WON-CITY OWNED 2.8 AC REVISE0 4/21/89 36 SU - 5 SU -j7 SU I I ALIA HIAA/CIIY - SAMIS ACQ. KXARIO (25 At. CREDIT EA. OUAO. J AVlkRk PROPERTIES fX1SIT HG COHH = 0 AC 1 !11ll111ll11111111ll 1 29 SW 39 SU HXARIO (4? AC CREDIT fA. QUAO) 47.00 SRA C BAIlQUlTOS LAGOON 4B4.00 SRA C/SI U R S E S H 0 E C 0 U R I S d d I L ; S I 1 E P A R K I N G - - - - h II 0 U 0 C 0 U R T S - - - " N P 0 U E R B 0 A T I N G - - - S 1 R 0 0 n S - - I 1. 0 U P H E E I I N G R 0 0 H - - - - h S 5 I f I C A I I 0 N - COM Cot! COH - - - ,,,,, - dp~r~~~ r ibI: nird + = future be wnent = Future Acqulslt ion z E - 41.00 25.00 24.25 91.25 A - - - I H H I N G P 0 0 L - - - R f H U L 1 1 U S f - . ti / i C 0 1 P R I S i R v A Y A P P A R A I U S L 1 I P U R P 0 5 E C T S - - - S I 1 c P A R K I N G - c I bUI 1 E R 5 tap C = City Gwned SD = School Dlstrlct 51 = State P = Privately Owned 1 = Leased CCIl IIY APf1111Y C- = Group Ficnic facility 'I = Lighted _. EXlST(HG SUA L 0 AC EXISTING BCACHES (28.3 AC CREOII EA. QUAD) I 28.30 I SRA Sl/P IOlAL NON-CIIY OWNEO = 6 AC REVISfD 4/21/89 I, I;,, :: ".-.I[ ir:-ir ---A . (111 = CmtunII I :,ilk Special Use Area SRA = Special Resource Area t = future Development it = future Acquisition 5 I z E 1 ~WIIF R Sll I P - = City Owned LO LU A I SI SR IS f 'H 'I I CP A. I I 0 H $0 = Schbol Dlstrlct 31 = Stdte 3 i Privately Owned = Leased 401 SE ;I Si *;Z SL -43 SE 53 Sf -. . 5 SE -xi1 IIY AW;IIY :.I = broup Picnic facility '1 = Llghtrd .. LA COSTA CANYON SIAGECOACH ALGA NORTi FUlURL CkRRlLLO RAfICH CkRPlLLO ACQUlSlllON HkCARlO (25 AC CREOll ALL OUAO) 8. C 3.60 I I I 44 SE fUERTE 44 SE fUERTE ELEMENTARY SCHOOL PARK 45 SE LEVANIE ELEHENlARY SCHOOL PARK 46 SE CAOENCIA 2.00 SUA SO 8 8. 88 2.00 SUA C 8 8 .... 8 ItvJ4 I CoH I 28.00 I cor: I 35.00 I cor! I 1 I b.50 I con I 2z!zLL 119.12 XC 28 SE BEACHES (28.3 AC CRfOII EA. OUAO) 28.30 SRA ST/P 29 SE HACARIO (47 AC CREOIT EA. QUAD) 47.00 SRA C ' - - Cr PA IS HS iI EV cc 0 LA R PE RA E S E R V t - 'I' I I 'I' - -r - 8. 8. - P L A Y A P P A R A T U S - . - 8 - - - - 1 - 6 R 0 U P H E t 1 I N G R 0 0 H L - 8 - - I1 I F DO rl: PA 0 UB EO Rk 1 BI OH AG T I I G I 1 - I I - - h - - i5 HA UN FO f LV E8 B oc A0 RU OR ST S REVISED 1/21/89 IOTA1 NON-CITY WNtO 7.4 AC . SRA SRA SRA "(20,454) IC) I SUA) TOlAL SRA 63.11 12.62 75.73 63.11 24.70 4.94 29.64 24.70 30.20 6.04 36.24 30.20 51.14 L__ 10.23 61.37 51.14 169.14 33.83 202.97 169.14 , ,* . ., L 39.58 38.48 78.06 623.30 16.16 4.80 20.96 327.30 -0- -0- 650.55 -0- 40.34 13.00 53.34 75.30 96.08 56.28 152.36 1,676.45 I ( 23. d~) i 25.86 t 2.33 t560.19 ( 8.54) 1 .I42 ( 8.68) t302.60 .- (30.20) J 6.041 (36.24) t619.80 (10.80) -I 2.77 ( 8.03) t24.16 (73.07) t22.45 ( 50.62.) t1,507.31 ( 20,843) ( 31,775) ( 42,817) (134,914) 19.74 118.44 98.70 52.11 10.42 62.53 52.11 79.44 15.89 9s. 33 79.44 107.04 21.41 128.45 107.04 337.29 67.45 404.75 337.29 II I Ul(t 30.20 8.02 38.22 .o 47.20 .o 47.20 .o 91.25 6.00 97.25 .o 78.78 .o 78.78 .o 247.43 14.02 261.45 .o 10 I - 69. I8 46.50 116.28 623.30 63.36 4.80 68.16 327.30 91.25 6.00 97.25 650.55 119.12 .13.oo 132.12 75.30 343.51 70.30 413.81 1,676.45 LL ( 28 -t 26 12 t524 -. - . t 11. 15 +5 t379. -- - t 11. l-2- + 1. +571. - t 12. u + 3. ( 31. t 6. -- -t2 t 9. t1,339. - MNDSCAPEU AREA CITY HALL/LIBRARY SAFETY CENTER PALOMAR TRIANGLE TAMARACK TRIANGLE POINSETTIA BRIDGE BIENVENIDA CIRCLE 405 OAK FIRE STATIONS (5) LAS FLORES TRIANGLE REDEVELOPMENT AREA CAROL PLACE POLLY LANE BEACH ACCESSES 1166 CARLSBAO VILLAGE ORIVE SPINNAKER HILLS BANK TAMARACK SEWER PLANT SANTA FE CORRIDORS ELM BANKS (EAST OF EL CAMINO) ELM CRIBWALL 18.0 3.5 3.0 .5 .2 .1 2.0 .2 2.5 .1 .1 .s 2.2 4.0 4.0 .2 2.0 - 1.2 TOTAL: 48.3 OPEH SPACE AREAS SPINNAKER POINT EASEMENT WOOOH IN€ BANKS CAOENCIA (REAR LOT) LEVANTE CANYON HOSP GROVE SAN MARCOS CANYON LAGUNA RIVIERA BANK RIGHT OF WAYS: RIGHT OF WAYS MEDIANS LANOSCAPED 1 CAR COUNTRY POINSETTIA AV EN IDA ENC INAS PALOMAR AIRPORT RD. COLLEGE Et CAMINO (NORTH/SOUTH) ALGA RD. ALT I SMA MELROSE RANCHO SANTE FE ACRES 4.0 TOTAL: . TOTAL: TOTAL GRAND TOTAL: - ACRES 10.00 14.00 3 .OO 13.00 49.55 20.00 -- 3.00 112.55 - ACRES 121.2 - ACRES E ..J 1.9 .8 1 .o 4.0 6.0 4.0 .2 1 .o - 2.0 20.4 302.55 - -- MILES 72 MILES .26 1 .oo .56 3.12 .4a 2.08 2.08 .. 11 5 .52 1.04 11.25 PARKS & RECREATIOP CITY OF CARLSBAI GENERAL PLAN END AMJMlY PARK 7 COMkUMTY PARK --J USE AREh JRE SPECIAL USE AREA =IAL AESOURCE AREA -..I----- - - - .- - - ... I , --. PORTION OF PLATE 2 FROM 'MASTER DRAINAGE PLAN" JUNE 1980 Scale COST ESTIMATE ZONE 15 DRAINAGE FACILITIES FACILITY QUANTITY UNIT PRICE TOTAL COST WATER SHED .................................................................... A-D A B B B Sediment Detention Basin 1-2 acres N/A $86 , 250 Dredging Calavera Lake Creek N/A $644 , 000 54" Storm Drain 1,200 LF $207/LF $248 , 400 36" Storm Drain Line BJ 78" Storm Drain D 60tt-78tt Storm Drain D 3Ota-48!@ Storm Drain D Headwalls D Cleanouts D Rip Rap D 54" Storm Drain D Headwall s D Cleanouts D Rip Rap 950 LF $138/LF $13 1 , 100 1,800 LF $273/LF $491,280 1,350 LF $350/LF $472 , 500 Total Watershed B $1,094,880 -------------- 1,060 412 1 5 35 1,200 2 1 10 LF LF EA EA CY LF EA EA CY N/A $200 , 790 N/A $38,560 $3 , 300/EA $3,300 $3 , 000/EA $15 , 000 $135/CY $4 , 725 $150/LF $180,000 $6 , 600 $3 , 000 $135/CY $1,350 $3 , 300/EA $3 , 000/EA -------------- Total Watershed D .. $453 , 325 Total Zone 15 $2,526,855 -----==P===PI=