HomeMy WebLinkAboutCT 02-06; KIRGIS TENTATIVE MAP; UPDATED GEOTECHNICAL INVESTIGATION; 2011-08-01CHRISTIAN WHEELER
ENGINEERING
UPDATED GEOTECHNICAL INVESTIGATION REPORT
KIRGIS SUBDIVISION
CARLSBAD TRACT 02-06
TWAIN AVENGE
CARLSBAD, CALIFORNIA
SUBMITTED TO
BRIAN AND GAYL HYNEK
PO BOX 401
GILROY, CAUFORNIA 95021-0451
SUBMITTED BY
CHRISTL\N WHEELER ENGINEERING
3980 HOME AVENGE
SAN DIEGO, CALIFORNLA 92105
r
o
o
Ul o
3980 Home Avenue « San Diego, CA 92105 * 61 9-550-1700 <D FAX 619-550-1701
<
CHRISTIAN WHEELER
ENGINEERING
July 6,2011
Brian and Gayl Hynek
P.O. Box 401
Gilroy, Califomia 95021-0451
CWE 2110148.01
SUBJECn": Updated Geotechnical Investigation Report, Kirgis Subdivision,
Carlsbad Tract 02-00, Twain Avenue, Carlsbad, Califomia.
Reference: Report of Preliminary Geotechnical Investigation, Proposed Five-Lot Residential
Project, APN 212-010-03, West of Faraday Road, Carlsbad, Ca.'\i£otmii,prepand by
Christian Wheeler Engineering, CWE Project No. 201.116.01, datedUatch. 14, 2001.
Dear and ^^s. Hjmek:
In accordance with your request, and our proposal and agreement dated -^^^^ 2,2011, Christian
Wheeler Engineering has completed an updated geotechnical investigation report for the subject project.
We are presenting herewith a report of our findings and recommendations.
If you have any questions after reviewing this report, please do not hesitate to contact om office. This
opportunity to be of professional service is sincerely appreciated.
Respectfully submitted,
CHRISTIAN WHEELER ENGINEERING
Charles H. Christian, R.G.E. #00215
CHC:TSW:DBA
Disttibution: (2) Submitted
(1) david@.lmco.net
3980 Home Avenue * San Diego, CA 92105 o 61 9-550-1700 * FAX 619-550-1701
TABLE OF CONTENTS
PAGE
Introduction and Project Description 1
Project Scope 2
Findings 2
Site Description 2
General Geology and Subsurface Conditions 3
Geologic Setting and Soil Description 3
Topsoil 3
Subsoil 3
Slopewash 4
Old Paralic Deposits 4
Santiago Formation 4
Goundwater 4
Conclusions 5
Recommendations 6
Grading and Earthwork 6
General 6
Pre-Grade Meeting 6
Observation of Grading 6
Site Preparation 7
Transition Building Pads 7
Select Grading 7
Cut and Fill Slope Construction 7
Excavation Characteristics 8
Excavation Characteristics 8
Sediment Traps 8
Processing of Fill Areas 8
Compaction and Method of Filling 8
Surface Drainage 8
Grading Plan Review 9
Sbpe Stability 9
General 9
Erosion Control 9
Foundations 10
General 10
Footing Dimensions 10
Bearing Capacity 10
Foundation Reinforcement 10
Post-Tensioned Foundations 11
Lateral Load Resistance 11
Seismic Design Factors 11
Settlement Characteristics 12
Expansive Characteristics 12
Foundation Plan Review 12
Foundation Excavation Observation 13
Soluble Sufates 13
On-Grade Slab 13
General 13
Interior Floor Slab 13
Under-Slab Vapor Retarders 13
Exterior Concrete Slab-On-Grade 14
CWE 2110148.01
Kirgis Subdivision, Carlsbad Tract 802-06
Twain Avenue, Carlsbad, Califomia
Swimming Pools 14
Masonry Earth Retaining Walls 15
Foundations 15
Passive Pressvure 15
Active Pressures 15
Waterproofing And Subdrain 15
Backfill 15
Limitations 16
Review, Observation and Testing. 16
Uniformity of Conditions 16
Change in Scope 16
Time Limitations 17
Professional Standard 17
Client's Responsibility 17
ATTACHMENTS
PLATES
Plate 1
Plate 2
Plate 3
Site Plan & Geotechnical Map
Fill Over Cut Slope DetaU
Retaining Wall Subdrain Detail
TABLES
Table 1 Seismic Design Factors
APPENDICES
Appendix A Data From CWE 201.116 Geotechnical Report
Appendix B References
Appendix C Recommended Grading Specifications — General Provisions
CWE 2110148.01
Kirgis Subdivision, Carlsbad Tract 802-06
Twain Avenue, Carlsbad, Califomia
CHRISTIAN WHEELER
ENGINEERING
UPDATED GEOTECHNICAL ESJVESTIGATION REPORT
KIRGIS SUBDIVISION
CARLSBADS T ACT 02-06
TWAIN AVENUE
CARLSBAD. CALIFO NIA
INTRODUCTION AND PROJECT DESCRIPTION
This report presents an updated geotechnical report for the subject residential subdivision and associated
improvements to be developed at the southem end of Twain Avenue, in the city of Carlsbad, Califomia.
Figure Number 1, presented on the following page, provides a vicinity map showing the location of the
project.
It is our understanding that the subject project will consist of a five-lot residential subdivision with
associated improvements, including a short access street. It is anticipated that the stmctures will be one
and/or two stories high, and of wood-frame constmction. Shallow foundations and conventional
concrete slab-on-grade floor systems are anticipated. However, post-tensioned foundations may be
utilized. Based on the available plans, grading will consist of cuts and fills of up to about 30 feet and 19
feet in depth, respectively. Proposed cut and fill slopes will be graded at a 2:1 (horizontal to vertical) or
flatter inclination, and extend to a maximum height of about 20 feet and 27 feet, respectively.
To aid in the preparation of this report, we were provided with a set of undated grading and erosion plans
prepared by Landmark Consulting. A copy of the grading plan has been used as the base for our Site Plan
and Geotechnical Map, and is included herein as Plate No. 1. In addition, we have reviewed our " eport
R
of Geotechnical Investigation, Proposed Five-Lot Subdivision", dated March 14, 2001. Appropriate data
form this geotechnical report is presented in Appendix A. This data was used in the preparation of this
updated report.
This report has been prepared for the exclusive use of Brian and Gayl Hynek and their design consultants
for specific application to the project described herein. Should the project be changed in any way, the
3980 Home Avenue * San Diego, CA 92105 * 619-550-1700 CP FAX 619-550-1 701
SITE VICINITY MAP
(Adapted from Thomas Brothers Maps)
KIRGIS SUBDIVISrON
CARLSBADS TRACT 02-06
TWAIN AVENUE
CARLSBAD. CALIFORNIA
i
North SITE
CWE 2110148.01 July 2011 Figure 1
CWE 2110148.01 July 6,2011 Page No. 2
modified plans should be submitted to Christian Wheeler Engineering for review to detemiine their
conformance with our recommendations and to detemiine whether any additional subsurface investigation,
laboratory testing and/or recommendations are necessary. Our professional services have been performed,
our findings obtained and our recommendations prepared in accordance with generally accepted
engineering principles and practices. This warranty is in lieu of aU other warranties, express or implied.
PROJECT SCOPE
The scope of our updated report included a surface reconnaissance, and a review of the aforementioned
documents. Our scope of service did not include assessment of hazardous substance contamination,
recommendations to prevent floor slab moisture intmsion or the formation of mold within the
stmctures, evaluation or design of storm water infiltration facilities, or any other services not specifically
described in the scope of services presented below.
More specifically, the intent of this updated report was to:
a) Visit site to provide a surficial reconnaissance of the current site conditions;
b) Review the referenced geotechnical report and grading plans;
c) Provide updated seismic design parameters as required by the 2010 edition of the
Califomia Building Code;
d) Present updated recommendations for the geotechnical aspects of the proposed site
development as presently proposed;
FINDINGS
SITE DESCRIPTION
The subject site is a nearly rectangular-shaped parcel of land approximately 21.9 acres in area, located at
the southem end of Twain Avenue, in the City of Carlsbad, Califomia. The site is ftirther identified as
Assessor's Parcel Number 212-010-03. Undeveloped canyon lands bound the site to the west, south, and
east, while a residential subdivision bounds the site to the north.
CWE 2110148.01 July 6,2011 Page No. 3
The site is primarily undeveloped; however, numerous small "outbuildings" were scattered across the site
at the time of our site reconnaissance and subsurface exploration. The approximate locations of these
"outbuildings" are shown on the site plan attached herewith as Plate No. 1. Additionally, relatively minor
amounts of trash and debris, were observed across the surface of the site. Vegetation on the upper
portions of the site consists of sparse to relatively dense indigenous bmsh and small to medium sized
trees. Within the descending, canyon areas of the site, the on-site vegetation was observed to consist of
moderately dense to very dense indigenous bmsh and small to medium size trees.
In general, a gently sloping mesa top that generaUy descends to the south characterizes the uppermost,
northem portion of the site. Moderately steep canyon lands descend to south, east, and west from the
uppermost, mesa top area of the site. The existing on-site elevations within those portions of the site to
receive improvements range from about 330 feet in the northem portion of the site to about 270 feet in
the southwestem portion ofthe site.
GENERAL GEOLOGY AND SUBSURFACE CONDITIONS
GEOLOGIC SETTING AND SOIL DESCRIPTION: The subject site is located in the Coastal Plains
Physiographic Province of San Diego County and is underlain by a relatively minor amount of native
residuum, Quatemary-age old paralic deposits, and Cretaceous-age deposits of the Santiago Formation. The
following provides a discussion, based on our subsurface explorations and our past experience with nearby
projects, of the soU types expected to be encountered beneath the property.
TOPSOIL: Native topsoU was encountered at the surface in most of our exploratory test trenches.
The topsoU layer has an approximate thickness of one foot The topsoU material generaUy consists
of dark brown, sUty sand (SM) that is typicaUy moist and loose in consistency. It shoiUd be noted
that topsoU was not encountered in our test trench T-9, excavated in the northwest portion of the
site. These deposits were judged to have a low potential for expansion (EK50).
SUBSOIL: A layer of native subsoU was encountered within our exploratory test trenches
excavated in the northern, eastern, and southeastem portions of the proposed improvement area.
The subsoU was generaUy noted below the topsoU layer, but was also noted at the surface within the
northeast portion of the site. The thickness of the subsoU layer ranged from approximately one foot
to IV2 feet The subsoU was noted to primarily consist of medium brown, dayey sand (SC). The
subsoU was also noted as being generaUy moist and loose to medium dense. These deposits were
judged to have a moderate potential for expansion (EI between 51-90).
CWE 2110148.01 July 6,2011 Page No. 4
SLXDPEWASH (Qsw) : A layer of slopewash material was noted below the topsoU layer within our
exploratory test trenches excavated in the southwest portion of the proposed improvement area.
The layer had an approximate thickness ranging from VA to 2 feet The materials within the
slopewash layer generaUy consisted of dark brown, sandy clay (CL) that were wet and soft with a
slight amount of gravel and cobble. These deposits were judged to have a moderate potential for
expansion (EI between 51-90).
OLD PARALIC DEPOSITS (Qop): Underlying the topsoU and subsoU layers, a layer of old
paralic deposits manties the northern, eastern, and southeastem portions of the proposed
improvement area. These deposits were identified in the referenced geotechnical report as terrace
deposits. The approximate location of the contact between the old paralic deposits and underiying
Santiago Formation is shown on Plate No. 1. This contact typicaUy occurs at an elevation of 310
feet GeneraUy, the layer of terrace deposits is thickest within the upper areas in the eastem portion
of the improvement area, and thins towards the lower portions. The terrace deposits generaUy
consisted of orangish-brown, clayey sand (SQ that was moist and dense to very dense with some
gravel and cobble. The old paraUc deposits were found to possess a very low expansion potential
(EI=6).
SANTIAGO FORMATION (Tsa): The site is ultimatdy underlain by Tertiary-age deposits of
the Santiago Formation. The formational materials were noted below the terrace deposits in the
northern, eastern, and southeastem portions ofthe proposed improvement area and bdow the
topsoil, subsoil, and slopewash layers in the south-southwestern portions. The materials ofthe
Santiago Formation maiiUy consisted of light brown to light orangish-brown, clayey sand (SQ and
light brown to white, sUty sand (SM). The formational materials also consisted of lesser amounts of
light olive brown, sandy clay (CL). The formational materials were typicaUy moist The sandy
portions of the Santiago Fomiation were dense to very dense \diUe the clayey portions were very
stiff to hard. The sandy portions of the Santiago Formation were judged to have a low expansion
potential (EK50). The clayey portions of the Santiago Formation, which comprise a relativdy smaU
amount of the formational material, were found to possess a medium expansion potential (EI_ 85).
GROUNDWATER: No groundwater or seepage was encountered in any of the areas of the site
investigated. However, it should be recognized that minor groundwater seepage problems may occur
after development of a site even where none were present before development These are usuaUy minor
phenomena and are often the result of an alteration in drainage pattems and/or an increase in irrigation
water. Based on the permeability characteristics of the soU and the antidpated usage and development, it
CWE 2110148.01 July 6,2011 Page No. 5
is our opinion that any seepage problems which may occur wiU be minor in extent. It is fiirther our
opinion that these problems can be most effectivdy corrected on an individual basis if and when they
occur
CONCLUSIONS
In general, our findings indicate that the subject property is suitable for the construction of the proposed
subdivision and associated improvements, provided the recommendations provided herein are foUowed.
The main geotechnical conditions encountered that affect the proposed devdopment are potentiaUy
compressible surficial soUs, expansive soUs, cut/fiU transitions, and fiU thickness differentials. These
conditions are discussed hereinafter. It should be recognized that some of the recommendations provided
hereinafter to mitigate a certain potentiaUy adverse condition may also be applicable to another condition.
• A relativdy thin mantie of compressible topsoU, subsoU, and slopewash ranging between about two
to three feet in thickness caps the site. These materials are considered unsuitable, in their present
condition, for the support of setdement sensitive improvements, and should be removed and
replaced as compacted filL
• A relativdy smaU percentage of the Santiago fomiation deposits encountered in our trenches was
found to be moderatdy expansive (EI=85). It is recommended that sdect grading be performed to
mitigate this condition. It shovUd be realized that Santiago Fomiation deposits are inherentiy highly
heterogeneous, and the relative amounts of different soUs exposed in our trenches may not be
representative of the as-graded conditions. If sdect grading caimot be performed due to the lack of
suffident low expansive soUs, the foundation recommendations contained in this report may have
to be changed.
• Proposed grading for Lot 3 wiU result in a cut/fiU transition. This condition wUl also occur to a
lesser extent in Lots 1 and 2. Stmctures and improvements spanning cut/fiU transitions may
experience detrimental differential settiements due to the different compression characteristics of
native and fiU soUs. In order to mitigate this condition, it is reconimended that the cut portion of
the lot be undercut as described hereinafter. Undercutting the cut portions of the lots wiU also
facilitate fiiture drainage, trenching and landscaping.
• Depending on their locations, fiU thicknesses differentials exceeding ten feet may exist under the
proposed stmctures in Lots 3,4, and 5. In order to mitigate this condition, it may be necessary to
CWE 2110148.01 July 6,2011 Page No. 6
increase the embedment depth and reinforcement of the foundations, and to increase the thickness
and reinforcement of the on-grade floor slabs.
• Temporary sediment traps are proposed adjacent to the top of proposed fiU slopes on aU five lots.
Sediment traps adjacent to the top of slopes are not advised due to the potential for water
infiltration into the underiying fiU soUs. This condition may detrimentaUy affect the soils underlying
the sediment traps and adjacent slopes. If sediment traps must be located as currentiy proposed,
they shoidd be designed, constmcted, and maintained such that no water infiltrates into the
underlying soil It is our understanding that the design, constmction, and maintenance of the
sediment traps wiU be performed by others than Christian Wheder Engineering.
The site is located in an area that is relativdy free of geologic hazards that wiU have a significant effect on
the proposed constmction. The most likdy geologic hazard that could affect the site is ground shaking due
to sdsmic activity along one of the regional active faults. However, constmction in accordance with the
requirements of the 2007 edition of the Califomia BuUding Code and the local govemmental agendes
should provide a levd of life-safety suitable for the type of devdopment proposed.
RECOMMENDATIONS
GRADING AND EARTHWORK
GENERAL: All grading should conform to the guideUnes presented in Appendix J of the Califomia
BuUding Code, the niinimum requirements of the City of Carlsbad, and the Recommended Grading
Specifications and Special Provisions attached hereto, except where specificaUy superseded in the text of
this report.
PRE-GRADE MEETING: It is recommended that a pre-grade meeting, induding the owner's
representative, grading contractor and a representative from Christian Wheder Engineering, take place to
discuss the recommendations of this report and address any issues that may affect grading and
constmction operations.
OBSERVATION OF GRADING: Observation by die Geotechnical Consultant is essential during the
mass grading operation to confirm conditions antidpated by our investigation, to aUow adjustments in
design criteria to reflect actual fidd conditions exposed, and to detemiine that the grading proceeds in
CWE 2110148.01 July 6,2011 Page No. 7
general accordance with the recommendations contained herein. Continuous or periodic observation shoidd
be provided at the discretion of the (jeotechnical Consultant
SITE PREPARATION: Site preparation should begin with the removal of aU existing improvements
and trash, as weU as any existing vegetation from the areas of the site to be graded. The debris resulting
from this operation should be disposed of off-site. This should indude aU root baUs from trees, aU natural
brush and aU significant root material Existing topsoil, subsoil, and slopewash underlying proposed
settiement-sensitive improvements, including aU proposed fiUs, should be removed in their entirety.
Based on the geotechnical information available, the antidpated removal depths range from about two
feet to three feet. However, deeper removals may be needed in areas not investigated or due to
unforeseen conditions. Actual removal depths wiU be detemiined by our representative. Where necessary
to achieve planned site grades, the removed materials may be replaced as compacted fiU provided they are
thoroughly mixed and moisture conditioned prior to placement
TRANSITION BUILDING PADS: It is recommended tiiat formational soUs underlying die cut
portion of the proposed transition lots be undercut to a minimum depth of four feet (3 feet in previous
report) bdow finish pad grade, or two feet bdow the bottom of footings (one foot below retaining waU
footing keys) whichever is deepest. The undercuts shoidd be performed in such a way that low areas with
impaired drainage are not created. If identified, future swimming pool areas shoidd also be undercut.
Undercut areas should be backfiUed with properly compacted, low expansive fiU (EK50).
SELECT GRADING: Portions of the Santiago Formation were determined to possess a medium
expansive potentiaL Expansive soUs should not be placed within five feet from finish pad grade, and ten
feet from the face of slopes. In addition, expansive soils within five feet from finish pad grade in proposed
cut areas that are undercut, shoidd be removed and replaced with low expansive fiU (EI<50) compacted to
at least 90 percent
CUT AND FILL SLOPE CONSTRUCTION: Cut and fiU slopes may be constmcted at an inclination
of 2:1 or flatter (horizontal to vertical). Compaction of fiU slopes shoidd be performed by back-roUing with
a sheepsfoot compactor at vertical intervals of four feet or less as the fiU is being placed, and track-walking
the face of the slope when the slope is completed. As an altemative, the fiU slopes may be overfiUed by at
least three feet and then cut back to the compacted core at the design Une and grade. Keys shoidd be made
at the toe of fiU slopes in accordance with the recommendations presented under "Compaction and Method
of FiUing." A subdrain is reconimended for transition fiU over cut slopes. A subdrain detaU is provided in
the attached Plate No. 2.
CWE 2110148.01 July 6,2011 Page No. 8
EXCAVATION CHARACTERISTICS: It is antidpated diat the cuts proposed in the aforementioned
grading plans may be achieved with conventional, large heavy-duty grading equipment in good working
order. However, concretions requiring special grading and handling consideration may be encountered
within the Santiago FormatioiL In addition, zones of very dense deposits that are difficult to excavate with
light trenching equipment may be encountered within the Santiago Formation.
SEDIMENT TRAPS: A temporary sediment trap consisting of a smaU detention basin is proposed for
each of the five lots. Design, constmction, and maintenance of the sediment traps wiU be performed by
others than Christian Wheder Engineering. When abandoned, the traps should be backfiUed with low
expansive fiU (EK50) compacted to at least 90 percent
PROCESSING FILL AREAS: Prior to placing any new fiU soils or constmcting any new improvements
in areas that have been deaned out to receive fiU, the exposed soUs shoidd be scarified to a depth of
about 12 inches, moisture-conditioned, and compacted to at least 90 percent relative compaction. In
areas to support fiU slopes, keys should be cut into the competent supporting materials. The keys should
be at least ten feet wide, and be sloped back into the hiUside at least two percent The keys should extend
at least one foot into the competent supporting materials. Where the existing ground has a slope of 5:1
(horizontal to vertical) or steeper, it should be benched into as the fiU extends upward from the keyway.
COMPACTION AND METHOD OF FILLING: AU fiU and backfiU placed at die site should be
compacted to a rdative compaction of at least 90 percent of its maximum dry density as determined by
ASTM Laboratory Test D1557. FiUs should be placed at or sUghtiy above optimum moisture content, in
lifts six to eight inches thick, with each lift compacted by mechanical means. FiUs shoidd consist of
approved earth material, free of trash or debris, roots, vegetation, or other materials determined to be
unsuitable by the (jeotechnical Consultant FiU material should be free of rocks or lumps of soU in excess
of twdve inches in maximum dimension, and free of rocks over six inches in diameter within the upper
three feet of pad grade.
Utility trench backfiU within five feet of the proposed stmctures and beneath driveways, concrete
flatwork, and pavements shoidd be compacted to a minimum of 90 percent of its maximum dry density.
SURFACE DRAINAGE: The drainage around the proposed improvements shoidd be designed to
coUect and direct surface water away from proposed improvements and the top of slopes toward
appropriate drainage facUities. Rain gutters with downspouts that discharge runoff away from the stmctures
into controUed drainage devices are recommended.
CWE 2110148.01 July 6,2011 Page No. 9
The ground around the proposed improvements should be graded so that surface water flows rapidly away
from the improvements without ponding. In general, we recommend that the ground adjacent to stmctures
be sloped away at a minimum gradient of two percent Densdy vegetated areas where runoff can be
impaired should have a minimum gradient of five percent for the first five feet from the stmcture.
Drainage pattems provided at the time of fine grading shoidd be maintained throughout the life ofthe
proposed inprovements. Site irrigation should be limited to the minimum necessary to sustain landscape
growth. Over watering should be avoided. Shoidd excessive irrigation, impaired drainage, or unusuaUy high
rainfaU occur, zones of wet or saturated soU may devdop.
GRADING PIAN REVIEW: The final grading plans should be submitted to this office for review in
order to ascertain that the recommendations of this report have been implemented, and that no additional
recommendations are needed due to changes in the antidpated devdopment plans.
SLOPE STABIUTY
GENERAL: AU slopes at the subject devdopment shoidd be constmcted at a slope ratio of 2.0 horizontal
units to 1.0 vertical unit (2:1) or flatter. Maximum cut and fiU slope heights wiU be less than about 20 feet
and 27 feet, respectivdy. Based on the strength parameters of the on-site soUs in their natural and
mechanicaUy conipacted states, it is our opinion that the proposed slopes wiU be stable in regards to deep-
seated slope faUure and surficial slope faUure. AU fiU slopes shoidd be constructed in accordance with the
grading recommendations presented above.
EROSION CONTROL: The placement of cohesionless soUs at the face of slopes should be avoided.
Slopes should be planted as soon as feasible after grading. Sloughing, deep rilling and slumping of surficial
sods may be antidpated if slopes are left unplanted for a long period of time, espedaUy during the rainy
season. Care should be taken to ensure the proper drainage of aU surface runoff away from the slope face.
Saturation of the slope caused by excessive or improperly chaimded mnoff could detrimentaUy affect the
surficial StabiUty of the slope. Irrigation on and adjacent to slopes shoidd be carefidly monitored to
insure that only the minimum amount necessary to sustain plant life is used. Over-irrigating could not
only be erosive but may significandy increase the chance for slope surficial stability problems and should
be avoided.
CWE 2110148.01 July 6,2011 Page No. 10
FOUNDATIONS
GENERAL: Based on our findings and engineering judgment, the proposed structures may be supported
by conventional continuous and isolated spread footings, provided the site is prepared as reconimended in
this report As an altemative post-tensioned foundations may be utilized. The foUowing recommendations
are considered the minimum based on soU conditions and are not intended to be Ueu of stmctural
considerations. AU foundations should be designed by a qualified stmctural engineer.
FOOTING DIMENSIONS: Spread footings supporting proposed single-and two-story stmctures
shoidd have a minimum embedment depth of 12 inches and 18 inches bdow lowest finish pad grade,
respectivdy. Continuous footings for single-and two-story stmctures should have a minimum width of 12
inches and 15 inches, respectivdy. Isolated footings shoidd have a minimum width of 24 inches.
Minimum dimensions for footings supporting exterior improvements should be 12 inches in depth and
width. Minimum dimensions for footings supporting exterior retaining waUs should be 18 inches in depth
and 24 inches in width. Footings located adjacent to slopes should be extended to a depth such that a
minimum horizontal distance of eight feet exists between the bottom of the footing and the face of the
slope. For retaining waU footings, a ten-foot horizontal setback is recommended. The footing setback
distance from the top of slopes may be modified by using deepened footings. Footing setback is measured
from competent soU and shoidd neglect any loose or soft native soUs that may occur at the top of a natural
slope. Plans for any footings that wiU not comply with the specified setbacks shoidd be submitted to the
Geotechnical Engineer for specific review and approval prior to constmction.
BEARING CAPACITY: Conventional continuous spread footings with a minimum embedment of 12
inches and width of 12 inches may be designed for an aUowable soU bearing pressure of 2,500 pounds per
square foot This value may be increased by 700 pounds per square foot for each additional foot of
embedment and 400 pounds per square foot for each additional foot of width up to a maximum of 4,000
pounds per square foot The bearing value may also be increased by one-third for combinations of
temporary loads such as those due to wind or sdsmic loads.
FOUNDATION REINFORCEMENT: The project stmctural engineer should provide foundation
reinforcement recommendations. However, based on the antidpated soU conditions, we recommend that
the niinimum reinforcing for continuous footings should consist of at least two No. 5 bars positioned near
the bottom of the footing and two No. 5 bars positioned near the top of the footing.
CWE 2110148.01 July 6,2011 Page No. 11
POST-TENSIONED FOUNDATIONS: Post-Tensioned foundations may be utiUzed for tiie support
of the subject stmctures. We are providing in tabular form bdow the post tension related design parameters
from the Post Tensioning Instimte, 3"* edition.
TABLE I: POST-TENSIONED FOUNDATIONS
Post-Tensioning Institute (PTI) - 3^ Edition
Edge Moistuie Vuution, Cm
Center Lift (ft) 9.0
EdzeUft(ft) 5.4
Di£ktentul S<al Movement, ym
Center Uft (in) .19
EdjieUftdn) .41
A minimum depth of 12 inches bdow adjacent finished grade is recommended for perimeter beams. SoU
bearing values provided in the bearing capadty paragraph are also appUcable for post tensioned
foundations. Footings located adjacent to slopes shoidd be extended to a depth such that a minimum
horizontal distance of eight feet exists between the bottom of the footing and the face of the slope. Footing
setback is measured from competent soU and shoidd neglect any loose or soft native soils that may occur at
the top of a natural slope.
LATERAL LOAD RESISTANCE: Lateral loads against foundations may be resisted by fiiction between
the bottom of the footing and the supporting soil, and by the passive pressure against the footing. The
coeffident of fiiction between concrete and sod may be considered to be 0.35. The passive resistance may
be considered to be equal to an equivalent fluid weight of 350 pounds per cubic foot This assumes the
footings are poured tight against undisturbed soil If a combination of the passive pressure and friction is
used, the friction value should be reduced by one-third. The upper 12 inches of footing embedment should
not be considered when calculating passive pressures, unless the footing abuts a concrete slab-on-grade or a
paved surface.
SEISMIC DESIGN FA(]TORS: Provided below are sdsmic design factors appUcable to the subject
site. The sdsmic design factors were determined in accordance with the 2010 Califomia BuUding Code.
The site coefficients and adjusted maximum considered earthquake spectral response acceleration
parameters are presented here
CWE 2110148.01 July 6,2011 Page No. 12
TABLE II: SEISMIC DESIGN FACTORS
Site Coordinates: Latitude
Longitude
33.138°
-117.299°
Site Class D
Site Coefficient Fa 1.024
Site Coefficient Fy 1.55
Spectral Response Accderation at Short Periods Ss 1.191
Spectral Response Accderation at 1 Second Period Si 0.450
SMS=FaSs 1.219
SMI=FVSI 0.698
SDS=2/3*SMS 0.813
SDI_2/3*SMI 0.465
Probable ground shaking levels at the site could range from sUght to moderate, depending on such
factors as the magnitude of the seismic event and the distance to the epicenter. It is likdy that the site
wiU experience the effects of at least one moderate to large earthquake during the life of the proposed
improvements.
SETTLEMENT CHARACTERISTICS: The antidpated total and differential foundation settiement
is expected to be less than about 1 inch and 1 inch over 40 feet respectively, provided the
recommendations presented in this report are foUowed. It should be recognized that minor cracks
normaUy occur in concrete slabs and foundations due to shrinkage during curing or redistribution of
stresses, therefore some cracks should be antidpated. Such cracks are not necessarily an indication of
excessive vertical movements.
EXPANSIVE CHARACTTERISTICS: Provided that the recommendations contained in this report are
implemented, the prevailing foundation soils are expected to have a low expansive potential (EI < 50).
The recommendations presented in this report reflect this condition.
FOUNDATION PLAN REVIEW: The final foundation plan and accompanying detaUs and notes
should be submitted to this office for review. The intent of our review wiU be to verify that the plans used
for construction reflect the minimum dimensioning and reinforcing criteria presented in this section and
that no additional criteria are required due to changes in the foundation type or layout It is not our intent
to review stmctural plans, notes, details, or calculations to verify that the design engineer has correctiy
appUed the geotechnical design values. It is the responsibiUty of the design engineer to properly
design/specify the foundations and other stmctural elements based on the requirements of the stracture
and considering the information presented in this report.
CWE 2110148.01 July 6,2011 Page No. 13
FOUNDATION EXCAVATION OBSERVATION: AU foundation excavations should be observed
by a representative of this office prior to the placement of forms or reinforcement in order to verify that the
footings have the proper dimensions and that the soU conditions are as antidpated.
SOLUBLE SUFATES
The water soluble sulfate content of foundation soUs shoidd be determined after grading in accordance
with CaUfornia Test Method 417. Nevertheless, Type II modified Portland cement is reconimended for
concrete in contact with soil
ON-GRADE SLABS
GENERAL: It is our understanding that if conventional foundations are utUized for the support of the
proposed stmctures, the floor system for the proposed stmctures wiU consist ofan on-grade concrete slab.
The foUowing recommendations are considered the minimum slab requirements based on the antidpated
soU conditions, are not intended in Ueu of stmctural considerations.
INTERIOR FLOOR SLABS: The niinimum floor slab thickness for Lots 1,2 and 3 should be four
inches (actual), and the floor slab should be reinforced with at least No. 3 reinforcing bars placed at 18
inches on center each way. The minimum floor slab thickness for Lots 4 and 5 should be five inches
(actual), and the floor slab should be rdnforced with at least No. 4 reinforcing bars placed at 12 inches on
center each way. Slab reinforcement should be supported on chairs such that the reinforcing bars are
positioned at mid-hdght in the floor slab. The slab reinforcement shoidd extend kito the perimeter
foundations at least six inches. The garage slab may be constmcted independent of the garage perimeter
footings, but the slab and foundation should have a fdt strip between them. If the garage slab and footings
are constmcted monoUthicaUy, the slab reinforcement should extend into the perimeter foundations at least
six inches.
UNDER-SLAB VAPOR RETARDERS: Steps should be taken to minimize the transmission of
moisture vapor from the subsoU through the interior slabs where it can potentiaUy damage the interior floor
coverings. Local industry standards typicaUy indude the placement of a vapor retarder, such as plastic, in a
layer of coarse sand placed directiy beneath the concrete slab. Two inches of sand and two inches of sand
are typicaUy used above and bdow the plastic, respectivdy. This is the most common under-slab vapor
retarder system used in San Diego County. The vapor retarder shoidd be at least 15-mU plastic with sealed
seams and should extend at least 12 inches down the sides of the interior and perimeter footings. The sand
CWE 2110148.01 July 6,2011 Page No. 14
should have a sand equivalent of at least 30, and contain less than 10% passing the Number 100 sieve and
less than 5% passing the Number 200 sieve. The membrane should be placed in accordance with the
recommendation and consideration of ACI 302, "Guide for Concrete Floor and Slab Constmction" and
ASTM El643, "Standards Practice for Installation of Water Vapor Retarder Used in Contact with Earth or
Granular FUl Under Concrete Slabs".
EXTERIOR CONCRETE SLAB-ON-GRADE
Exterior concrete slabs on grade should have a niinimum thickness of 4 inches and shoidd be reinforced
with at least No 3. bars placed at 18 inches on center each way (ocew). Driveway slabs should have a
minimum thickness of 5 inches and be reinforced with at least No. 4 bars placed at 12 inches ocew.
AU slabs should be provided with weakened plane joints in accordance with the American Concrete
Institote (ACI) guideUnes. Altemative pattems consistent with ACI guideUnes can also be used.
A concrete mix with a 1-inch maximum aggregate size and a water/cement ratio of less tiian 0.6 is
reconimended for exterior slabs. Lower water content wiU decrease the potential for shrinkage cracks.
Consideration should be given to using a concrete mix for the driveway that has a minimum compressive
strength of 3,000 pounds per square inch. This suggestion is meant to address early driveway use prior to
fuU concrete curing. Both coarse and fine a^egate should conform to the latest edition of the "Standard
Specifications for PubUc Works Constmction" ('Greenbook").
Special attention shoidd be paid to the method of concrete curing to reduce the potential for excessive
shrinkage and resultant random cracking. It shoidd be recognized that minor cracks occur normaUy in
concrete slabs due to shrinkage. Some shrinkage cracks should be expected and are not necessarily and
indication of excessive movement or stmctural distress.
SWIMMING POOLS
Swimming pools may be constmcted as part of the proposed development or by future individual
homeowners. If the proposed pool is a settiement sensitive vanishing edge pool or a zero edge pool, it is
recommended that it be founded in the formational soUs underlying the compacted fiU. Depending on
the pool location, this recommendation may necessitate a foundation system consisting of concrete cast-
in-place piers. Appropriate foundation recommendations wiU be provided by this office after the
proposed swimming pool layout is avaUable.
CWE2110148.01 July6,2011 PageNo. 15
EARTH RETAINING WALLS
FOUNDATIONS: Foundations for proposed retaining waUs should be constmcted in accordance with
the recommendations for shaUow foundations presented previously in this report.
PASSIVE PRESSURE: The passive pressure for the design of sUding resistance for the proposed
retaining waU footings may be considered to be 350 pounds per square foot per foot of depth. This
pressure may be increased one-third for seismic loading. The coeffident of fiiction for concrete to soU may
be assumed to be 0.35 for the resistance to lateral movement When combining fiictional and passive
resistance, the fiiction should be reduced by one-third.
ACTIVE PRESSURE: The lateral soU pressure for the design of unrestrained earth retaining stmctures
with level backfiU may be assumed to be equivalent to the pressure of a fluid weighing 35 pounds per
cubic foot (pcf). An additional 13 pcf should be added to the above value for a 2:1 (horizontal to vertical)
sloping backfiU condition. These pressures do not consider any other surcharge. If any are antidpated,
this office should be contacted for the necessary increase in sod pressure. These values are based on a
drained, non-detrimentaUy expansive (EI <50) backfiU condition.
The project stmctural engineer may dedde that some of the proposed retaining waUs shoidd be designed
to resist sdsmic loads. Seismic lateral earth pressures on restrained and unrestrained retaining waUs may
be assumed to equal an inverted triangle starting at the bottom of the waU with the maximum pressure
equal to 7H pounds per square foot (where H = waU height in feet) occurring at the top of the retained
portion of the waU.
WATERPROOFING AND SUBDRAIN: Waterproofing detaUs should be provided by the project
architect. A su^ested waU subdrain detaU is provided on Plate No. 3. We recommend that the
Geotechnical Consultant observe aU retaining waU subdrains to verify their installation.
BACKFILL: AU backfiU soUs should be compacted to at least 90 percent relative compaction. Expansive
or clayey soUs shoidd not be used for backfiU materiaL The waU should not be backfiUed until the masonry
has reached an adequate strength.
CWE 2110148.01 July 6,2011 PageNo. 16
LIMITATIONS
REVIEW, OBSERVATION AND TESTING
The recommendations presented in this report are contingent upon our review of final plans and
specifications. Such plans and spedfications should be made avaUable to the (Jeotechidcal Engineer and
Engmeering Geologist so that they may review and verify their compUance with this report and with the
2007 edition ofthe Califomia BuUding Code.
It is recommended that Christian Wheder Engineering be retained to provide continuous soU engineering
services during the earthwork operations. This is to verify compUance with the design concepts,
specifications or recommendations and to aUow design changes in the event that subsurface conditions
differ from those antidpated prior to start of constmction.
UNIFORMITY OF CONDITIONS
The recommendations and opinions expressed in this report reflect our best estimate of the project
requirements based on an evaluation of the subsurface soU conditions encountered at the subsurface
exploration locations and on the assumption that the soU conditions do not deviate appreciably from those
encountered. It shoidd be recognized that the performance of the foundations and/or cut and fiU slopes
may be influenced by undisdosed or unforeseen variations in the soU conditions that may occur in the
intermediate and unexplored areas. Any unusual conditions not covered in this report that may be
encountered during site devdopment should be brought to the attention of the (jeotechnical Engmeer so
that he may make modifications if necessary.
CHANGE IN SCOPE
This office should be advised of any changes in the project scope or proposed site grading so that we may
determine if the recommendations contained herein are appropriate. It should be verified in writing if the
recommendations are found to be appropriate for the proposed changes or our recommendations should
be modified by a written addendum.
CWE 2110148.01 July 6,2011 PageNo. 17
TIME LIMITATIONS
The findings of this report are vaUd as of this date. Changes in the condition of a property can, however,
occur with the passage of time, whether they are due to natural processes or the work of man on this or
adjacent properties. In addition, changes in the Standards-of-Practice and/or Govemment Codes may
occur. Due to such changes, the findings of this report may be invaUdated whoUy or in part by changes
beyond our controL Therefore, this report should not be reUed upon after a period of two years without a
review by us verifying the suitabiUty of the condusions and recommendations.
PROFESSIONAL STANDARD
In the performance of our professional services, we comply with that level of care and skUl ordinarily
exerdsed by members of our profession currentiy practicing under similar conditions and in the same
locaUty. The dient recognizes that subsurface conditions may vary from those encountered at the locations
where our borings, surveys, and explorations are made, and that our data, interpretations, and
recommendations are based soldy on the information obtained by us. We wiU be responsible for those
data, mterpretations, and recommendations, but shaU not be responsible for the kitetpretations by others of
the information devdoped. Our services consist of professional consultation and observation only, and no
warranty of any kind whatsoever, express or impUed, is made or intended in connection with the work
performed or to be performed by us, or by our proposal for consulting or other services, or by our
furnishing of oral or written reports or findings.
CUENT'S RESPONSIBIUTY
It is the responsibUity of the CUent, or their representatives, to ensure that the information and
recommendations contained herein are brought to the attention ofthe stmctural engineer and architect for
the project and incorporated into the project's plans and specifications. It is fiirther thek responsibUity to
take the necessary measures to insure that the contractor and aU subcontractors carry out such
recommendations during constmction.
Existing Grade
4' Typical Bench Hdgjit
Competent Earth Material
Provide heel drain during gradeing as required per
recommendations of soils engineer. Drain sloped at
minimum of 1% toward and a suitable outlet
Competent
Earth Material Where natural slope gradient is 5:1 or less, benching is not necessary.
However, all compressible or unsuitable materials are to be removed prior to placing fill material.
NO SCALE
FIU SLOPE ABOVE CUT SLOPE DETAIL
KIRGIS SUBDtVISION
CAKLSBAD TRACT 02.M
TWAIN AVENUE
CARLSBAD, GALIFORlvHA w
CHRJSTIAN WHEELER
ENGINEERING
FIU SLOPE ABOVE CUT SLOPE DETAIL DATE; July 6,2011 JOBNO.: 2110148.01 w
CHRJSTIAN WHEELER
ENGINEERING
FIU SLOPE ABOVE CUT SLOPE DETAIL
BY: JDB PLATE NO.: 2
w
CHRJSTIAN WHEELER
ENGINEERING
3/4 inch Crushed Rock or
Miradrain 6000 or Equivalent
Geofabric Between.
Rock and Soil
' 12"
L
E 6-inch Minimum
Waterproof Back of WaU
Per Architect's Specifications
Top of Ground
or Concrete Slab
Minimum
4-inch Diameter
Perforated Pipe
PVC Schedule 40
T 6-inch
Minimum
RETAINING WALL
SUBDRAIN DETAIL
No Scale
CHRISTIAN WHEELER
ENGINEERING
KIRGIS SUBDIVISION
CARLSBAD TRACT 024)6
TWAIN AVENUE, CARLSBAD, CAUFORNIA
CHRISTIAN WHEELER
ENGINEERING BY: MAH DATE: July 6,2011
3980 HOME AVENUE
SAN DIEGO, CALIFORNIA 92105
TEL. (619) 550-1700
FAX. (619) 550-1701 JOB NO.: 2110148.01 PLATE NO.: 3
Appendix A
Data from CWE 201.116 Geotechnical Report
t -
Date Excavated:
Equipment:
Existing Elevation:
LOG OF TEST TRENCH NUMBER T-l
2/15/01 Logged by: DRR
Backhoe Project Manager: CHC
313 feet Depth to Water: N/A
Proposed Elevation: 328 feet Bucket Size: 24 inches
a D
0 o
l-l u
S
i
SUMMARY OF SUBSURFACE CONDITIONS
SAMPLES
is C/J
t-H
o
u
P
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
10
Topsoil: Dark brown, SILTY SAND (SM), moist, loose, fine- to medium-
grained.
Subsoil; Medium brown, CLAYEY SAND (SC), moist, loose to medium
dense, fine- to medium-grained.
• I
in
IS
Terrace Deposits (Ot): Orangish-brown, CLAYEY SAND (SC), moist,
dense, fine- to coarse-grained. CK 7.3
CK 6.4
111.1
115.5
SA
El
MD
DS
Terminated at 8 feet.
CHRISTIAN WHEELER.
ENCINEER.ING
PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, Califomia
BY: SCC
|OB NO. 201.116
DATE: February 27, 2001
PLATE NO.:
LOG OF TEST TRENCH NUMBER T-2
Date Excavated: 2/15/01 Lo^edby: DRR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 325 feet Depth to Water: N/A
Proposed Elevation: 328 feet Bucket Size: 24 inches
C3
SUMMARY OF SUBSURFACE CONDITIONS
SAMPLES
o
2
u
fc
P
SB
Topsoil: Dark brown, SILTY SAND (SM), moist, loose, fine- to medium-
grained.
- 2
- 4
- 5
- 7
- 8
- 9
10
Subsoil: Medium brown, CLAYEY S7\ND (SC), moist, loose to medium
dense, fine- to medium-grained.
Santiago Formation (Tsa): Light brown, CLAYEY SAND (SC), moist,
dense, fine- to medium-grained. CK
Light brown to olive brown, S.ANDY CLAY (CL), moist, very hard.
CK
Terminated at 6 feet.
7.6
19.1
116.5
101.1 SA
w CHRISTIAN WHEELER
ENG1NEER.ING
PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, Califomia
BY: SCC
IOB NO.: 201.116
DATE: February 27, 2001
PLATE NO.:
LOG OF TEST TRENCH NUMBER T-3
Date Excavated:
Equipment:
Existing Elevation:
2/15/01
Backhoe
317 feet
Lo^d by: DRR
Project Manager: CHC
Depth to Water: N/A
Proposed Elevation: 314 feet Bucket Size: 24 inches
SUMMARY OF SUBSURFACE CONDITIONS
SAMPLES
tLl O
C/3 HH
Q
u
fc
p
o
:S ft
PQ
- 1
- 2
- 3
- 4
Topsoil: Dark brown, SILTY SAND (SM), moist, loose, fine- to medium-
grained.
Subsoil: Medium brown, CLAYEY SAND (SC), moist, loose to medium
dense, fine- to medium-grained.
Terrace Deposits (Ot): Orangish-brown, CLAYEY SAND (SC), moist,
dense to very dense, fine- to coarse-grained with occasional 3 inch cobble.
CK
- 6
- 8
- 9
Sanriaeo Formation (Tsa): Light brown to white, SILTY SAND (SM),
moist, dense to very dense, fine- to medium-grained.
CK 11.0 111.9
Terminated at 10 feet.
CHRISTIAN WHEELER
ENGINEER.1NG
PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, Califomia
BY: SCC
IOB NO. 201.116
DATE: February 27,2001
PLATE NO.:
LOG OF TEST TRENCH NUMBER T-4
Date Excavated: 2/15/01 Logged by: DRR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 317 feet Depth to Water: N/A
Proposed Elevation: 314 feet Bucket Size: 24 inches
P
O
u
s
0
SUMMARY OF SUBSURFACE CONDITIONS
SAMPLES
z I
p 2
o
z ^
H o
c/3
l-H
o
fc
p
is
T
MP)
-1 m
Topsoil: Dark brown, SILTY SAND (SM), moist, loose, fine- to medium-
grained.
- 2
- 4
- 6
- 7
- 8
- 9
I- 10
Subsoil: Medium brown, CLAYEY SAND (SC), moist, loose to medium
dense, fine- to medium-grained.
Terrace Deposits (Ot): Orangish-brown, CLAYEY SAND/SILTY SAND
(SC/SM), moist, dense to very dense, occasional gravel and cobble.
CK
Terminated at 7 feet.
CHRISTIAN WHEELER
ENGINEER.1NG
PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, Califomia
BY: SCC
TOB NO.: 201.116
DATE: February 27, 2001
PLATE NO.:
LOG OF TEST TRENCH NUMBER T-5
Date Excavated: 2/15/01 Logged by: DRR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 290 feet Depth to Water: N/A
Proposed Elevation: 306 feet Bucket Size: 24 inches
PH
P
SUMMARY OF SUBSURFACE CONDITIONS
SAMPLES
z u
Q P
P
*S c/3
SB
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
1- 10
Hi t
Topsoil: Dark brown, SILTY SAND (SM), moist, loose, fine- to medium-
grained.
4^
A I
Ml
Slopewash (Osw): Dark brown, S.ANDY CLAY (CL), wet, soft,
slight amount of gravel and cobble.
Sanriapn Formation (Tsa): Light brown to light orangish-brown,
CLAYEY S.AND (SC), moist, medium dense to dense.
Becomes very dense.
CK
CK 11.2 114.3
Trench log continued on Plate 7.
CHRISTIAN WHEELER
ENGINEER.ING
PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, Califorma
BY: SCC
JOB NO. 201.116
DATE: Febmary 27,2001
PLATE NO.:
Date Excavated:
Equipment:
Existing Elevation:
Proposed Elevation:
LOG OF TEST TRENCH NUMBER T-5 (Continued)
2/15/01 Lo^d by: DRR
Backhoe Project Manager: CHC
290 feet Depth to Water: N/A
306 feet Bucket Size: 24 inches
W P
SUMMARY OF SUBSURFACE CONDITIONS
SAMPLES
z ^ c I P 2
< o
z %
[i] o
CO
o
u
fc
P
^ ft
- 11
12
- 13
- 14
15
- 16
- 17
18
- 19
I- 20
m
sr.
i.
Santiago Formation (Tsa): Light brown to light orangish-brown,
CLAYEY SAND (SC), moist, very dense.
CK 15.5 113.2
Terminated at 15 feet.
w PROPOSED 5-LOT RESIDENTIAL PROJECT w West of Faraday Road, Carlsbad, Califomia
CHRISTIAN WHEELER BY: SCC DATE: February 27, 2001
ENGINEERING TOB NO.: 201.116 PLATE NO.: 7
Date Excavated: 2/15/01
Equipment: Backhoe
Existing Elevation: 313 feet
Proposed Elevation: 300/306 feet
LOG OF TEST TRENCH NUMBER T-6
Lo^ed by: DRR
Project Manager: CHC
Deptii to Water: N/A
Bucket Size: 24 inches
PH a p
o
u
E
i
SUMMARY OF SUBSURFACE CONDITIONS
SAMPLES
z ^ c I p 2 IS °
11] o
C/3 t-H
s
u
fc
p
c/3
is
-1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
••It--la
Topsoil: Dark brown, SILTY SAND (SM), moist, loose, fine- to medium-
grained.
Slopewash ^Osw;>: Dark brown, SANDY CLAY (CL), wet, soft,
slight amount of gravel and cobble.
Santiago Formation (Tsa): Light brown to light orangish-brown,
S-ANDY CLAY (CL), moist, very stiff
Becomes hard.
CK 15.4 110.4
SA
EI
MD
DS
l_ 10 UBI 1
Trench log continued on Plate 9.
w
CHRISTIAN WHEELER
ENGINEERING
PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, Califomia w
CHRISTIAN WHEELER
ENGINEERING
BY: SCC DATE: February 27, 2001 w
CHRISTIAN WHEELER
ENGINEERING IOB NO.: 201.116 PLATE NO.: 8
LOG OF TEST TRENCH NUMBER T-6 (Continued)
Date Excavated: 2/15/01 Logged by: DRR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 313 feet Depth to Water: N/A
Proposed Elevation: 300/306 feet Bucket Size: 24 inches
PH a p
- 15
- 16
- 17
- 18
- 19
I- 20
o
l-l u
S
PH
SUMMARY OF SUBSURFACE CONDITIONS
Santiago Formation (Tsa): Light brown to light orangish-brown,
SANDY CLAY (CL), moist, hard.
Terminated at 14 feet.
SAMPLES
CK
z ^
< o
Z P
tn O
1^ e
o
18.0
fc
fe P
108.6
fe
:S ft
is
CHRISTIAN WHEELER
ENGINEER.ING
PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, California
BY: SCC
IOB NO.: 201.116
DATE: February 27, 2001
PLATE NO.:
Date Excavated:
Equipment:
Existing Elevation:
LOG OF TEST TRENCH NUMBER T-7
2/15/01 Lo^d by: DRR
Backhoe Project Manager: CHC
275 feet Depth to Water: N/A
Proposed Elevation: 315 feet Bucket Size: 24 inches
2
u E
i
0
SUMMARY OF SUBSURFACE CONDITIONS
SAMPLES
rt z ^
p -
§1
(1] o
^ 5.
c/1
HH
o
u
fc
D fe P
fe
c/3
s
- 3
- 4
- 5
- 6 • •• .* fr. i
- 7 ' ! i
Topsoil: Dark brown, SILTY SAND/CLAYEY SAND (SM/SC), moist,
loose, fine- to medium-grained.
Slopewash ^Osw^: Dark brown, SANDY CLAY (CL), wet, soft
to medium stiff, slight amount of gravel and cobble.
gj^ntiagn Formation fTsa^: Light oUve brown to light orangish-brown,
CLAYEY SAND (SC), moist, dense to very dense, fine- to medium-grained. CK 16.3
CK 16.8
109.3
110.0
Practical refusal at 9 feet.
PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, Califomia
CHRISTIAN WHEELER BY: SCC DATE: February 27, 2001
ENGINEER.ING IOB NO.: 201.116 PLATE NO.: 10
LOG OF TEST TRENCH NUMBER T-8
Date Excavated: 2/15/01 Lo^d by: DRR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 314 feet Depdi to Water: N/A
Proposed Elevation: 315 feet Bucket Size: 24 inches
P
o
u
E
s
SUMMARY OF SUBSURFACE CONDITIONS
SAMPLES
rt z U
z ^
ll] O
c/) t—t
o
u
fc /?
fe P
fe
c/3
^s
- 1
Topsoih Dark brown, SILTY SAND (SM), moist, loose, fine- to medium-
grained.
M
2 rv >
3 i\ It
4 h I
.8
Subsoil; Medium brown, CLAYEY SAND (SC), moist, loose to medium
dense, fine- to medium-grained.
- 5
- fi ^
- 7
- 8
- 9
10
Terrace Deposits (Ot); Orangish-brown, CLAYEY SAND (SC), moist,
dense to very dense, fine- to coarse-grained, occasional 2V2 inch gravel.
CK
CK
6.0 113.0
Tenninated at 7 feet.
PROPOSED 5-LOT RESIDENTIAL PROJECT
West of Faraday Road, Carlsbad, Califomia
CHRISTIAN WHEELER BY: SCC DATE: February 27,2001
ENGINEER-ING IOB NO.: 201.116 PLATE NO.: 11
LOG OF TEST TRENCH NUMBER T-9
Date Excavated: 2/15/01 Lo^ed by: DRR
Equipment: Backhoe Project Manager: CHC
Existing Elevation: 314 feet Deptii to Water: N/A
Proposed Elevation: - Bucket Size: 24 inches
PH a P
o o
l-l
u
E
i
SUMMARY OF SUBSURFACE CONDITIONS
SAMPLES
w z ^ c I
p 2
^ o
M \ z ^ ca o
c/3 I—I
o
u
fc
Z P
Pi p
- 1
- 2
- 3
- 4
- 5
- 6
M
Subsoil: Medium brown, CLAYEY S7\ND (SC), moist, loose to medium
dense, fine- to medium-grained.
- 7
- 9
i
M
i
I- 10
Terrace Deposits fOt^: Orangish-brown, CLAYEY SAND (SC), moist,
very dense, fine- to coarse-grained, abundant gravel and cobble. CK 5.7
Santiago Fotmarion fTsa^: Light olive brown, CLAYEY SAND (SC),
moist, dense to very dense, fine- to medium-grained.
CK 15.8
CK
CKI
122.8
111.0
Terminated at 10 feet.
w PROPOSED 5-LOT RESIDENTIAL PROJECT w West of Faraday Road, Carlsbad, Califomia
CHRISTIAN WHEELER BY: SCC DATE: February 27, 2001
ENGINEER.ING IOB NO.: 201.116 PLATE NO.: 12
LABORATORY TEST RESULTS
PROPOSED FIVE-LOT RESIDENTIAL PROTECT
WEST QF FARADAY ROAD
POWAY. CALIFORNLV
MAXIMUM DENSITY/ OPTIMUM MOISTURE CONTENT
Sample Nuniber
Description
Maximuni Density
Optimum Moisture Content
Trench T-l @2'-8'
Orangish-brown, clayey sand (SC)
127.1 pcf
8.5 percent
Trench T-6 @3'-12'
Brown, sandy clay (CL)
106.0 pcf
18.5 pcf
DIRECT SHEAR TEST
Sample Number
Description
Angle of Internal Friction
Apparent Cohesion
Trench T-l @2'-8'
Remolded To 90 Percent
33 degrees
100 psf
Trench T-6 @3'-12'
Remolded to 90 Percent
21 degrees
300 psf
GRAIN SIZE DISTRIBUTION
Sample Number T-l @ 2'-8' T-2 @ 4'-6' T-6 @ 3'-12'
Sieve Size Percent Passing Percent Passing Percent Passing
#4 100
#8 93 100 100
#15 78 99 699
#30 59 98 98
#50 37 97 96
#100 22 87 84
#200 19 70 69
0.05 mm 18 60 55
0.005 mm 11 27 21
0.001 mm 8 18 7
Classification SC CL CL
EXPANSION INDEX TESTS
Sample Number:
Iiutial Moisture:
Iiutial Dry Density:
Final Moisture:
Expansion Index:
Trench T-8 @2'-8'
8.0 percent
108.3 pcf
17.7 percent
6 (very low)
Trench T-6 @3'-l 2'
13.7 percent
101.4 pcf
29.5 percent
85 (medium)
CWE 201.116.1 March 14,2001 Plate No. 13
SLOPE STABIUTY ANALYSIS - FILL SLOPES
Propsed Five-Lot Residential Project
West of Faraday Road
Carlsbad. Califomia
Five-Lot Project CWE 201,116
Ten Most Critical. Ai5LnTriLL.PLT By; SCC 03-12-01 li50pn
380
360
rs a a.29
to 2,30
c 2,31
d 2.32
e 2.32
f 2,33
. 9 2.35
h 2.35
i 2.36
J 2.36
340
Elev.
(ft)
320
300
,9 f
Proposed 2:1
Slope
Fill (Qaf)
Terrace Deposits (Qt)
Santiago Formation (Tsa)
J' 20 40 60 80 100
STABL6H FSnln= =2,29 X-Axis (ft)
Soil Total Saturated Cohesion Friction Pore Pressure
Type Unit Wt, Unit Wt, Intercept Angle Pressure Constant
No, Label <pcf> <pcf> (psf) (deg) Paran, (psf)
1 Tsa UO 130 500 28 0 0
2 Qt 115 135 200 35 0 0
3 nil 115 135 350 32 0 0
120 140
Piez,
Surface
No.
CHRISTIAN WHEELER
ENGINEERING Plate 14
SLOPE STABILITY ANALYSIS - CUT SLOPES
Propsed Five-Lot Residential Project
West of Faraday Road
Carlsbad. Califomia
Five-Lot Project CWE 201,116
Ten Most Critical AiSLDTCUT.PLT Byi SCC 03-12-01 l:56pn
33t>
310
# FS
a 3.05
b 3,06
c 3,07
d 3.08
e 3,08
- f 3,09
g 3,10
h 3.11
i 3,14
J 3,14
Elev,
(ft) 300-
29C-
28C-
27(>
0
Proposed 2:1
Slope
Santiago Fomiation (Tsa)
Soil
Type
No, Label
1 TSQ
30 40 50 60
STABL6H FSnin=3.05 X-Axis (ft)
Total Saturated Cohesion Friction Pore
Unit Wt. Unit Wt. Intercept Angle Pressure
(pcf) (pcf) (psf) (deg) Poran,
110 130 500 28 0
Pressure
Constant
(psf)
0
80
Piez.
Surface
No,
90
CHRISTIAN WHEELER
ENGINEERING
Plate 15
Appendix B
References
CWE 2110148.01 July 6,2011 Appendbc B, Page B-l
REFERENCES
Uiuted Stated Geologic Survey, Seismic Design Values for Buildings, Java Ground Motion Calculator
Version 5.1.0.
Appendix C
Recommended Grading Specifications -
General Provisions
CWE 2110148.01 July 6,2011 Appendix C, Page C-1
RECOMMENDED GRADING SPECIFICATIONS - GENERAL PROVISIONS
KIRGIS SUBDIVISION
CJMILSBAD TRACT 02-06
TWAIN AVENUE
CARLSBAD. CALIFORNIA
GENERAL INTENT
The intent of these specifications is to establish procedures for clearing, compacting natural ground,
preparing areas to be filled, and placing and compacting fill soils to the lines and grades shown on the
accepted plans. The recommendations contained in the preliminary geotechnical investigation report and/or
the attached Special Provisions are a part of the Recommended Grading Specifications and shall supersede
the provisions contained hereinafter in the case of conflict. These specifications shall only be used in
conjunction with the geotechnical report for which they are a part. No deviation from these specifications
will be allowed, except where specified in the geotechnical report or in other written communication signed
by the Geotechnical Engineer.
OBSERVATION AND TESTING
Christian Wheeler Engineering shall be retained as the Geotechnical Engineer to observe and test the
earthwork in accordance with these specifications. It will be necessary that the Geotechnical Engineer or his
representative provide adequate observation so that he may provide his opiiuon as to whether or not the
work was accomplished as specified. It shall be the responsibility of the contractor to assist the Geotechnical
Engineer and to keep him apprised of work schedules, changes and new infonnation and data so that he may
provide these opiiuons. In the event that any unusual conditions not covered by the special provisions or
preliminary geotechnical report are encountered during the grading operations, the Geotechnical Engineer
shall be contacted for fiirther recommendations.
If, in the opiiuon of the Geotechnical Engineer, substandard conditions are encountered, such as
questionable or unsuitable soil, unacceptable moisture content, inadequate compaction, adverse weather, etc.,
construction should be stopped until the conditions are remedied or corrected or he shall recommend
rejection of this work.
CWE 2110148.01 July 6,2011 Appendix C, Page C-2
Tests used to determine the degree of compaction should be performed in accordance with the following
American Society for Testing and Materials test methods:
Maximum Density & Optimum Moisture Content - ASTM D-1557
Density of Soil In-Place - ASTM D-1556 or ASTM D-6938
All densities shall be expressed in terms of Relative Compaction as detemiined by the foregoing ASTM
testing procedures.
PREPARATION OF AREAS TO RECEIVE FILL
All vegetation, brush and debris derived from clearing operations shall be removed, and legally disposed of.
All areas disturbed by site grading should be left in a neat and finished appearance, free from unsightiy debris.
After clearing or benching the natural ground, the areas to be filled shall be scarified to a depth of 6 inches,
brought to the proper moisture content, compacted and tested for the specified minimum degree of
compaction. All loose soils in excess of 6 inches thick should be removed to firm natural ground which is
defined as natural soil which possesses an in-situ density of at least 90 percent of its maximum dry density.
When tiie slope of the natural ground receiving fill exceeds 20 percent (5 horizontal units to 1 vertical unit),
the original grovmd shall be stepped or benched. Benches shall be cut to a firm competent formational soil.
The lower bench shall be at least 10 feet wide or 1-1/2 times the equipment widtii, whichever is greater, and
shall be sloped back into the hillside at a gradient of not less than two (2) percent M other benches should
be at least 6 feet wide. The horizontal portion of each bench shall be compacted prior to receiving fill as
specified herein for compacted natural ground. Ground slopes flatter tiian 20 percent shall be benched when
considered necessary by the Geotechnical Engineer.
Any abandoned buried structures encountered during grading operations must be totally removed. All
undergroimd utilities to be abandoned beneath any proposed stmcture should be removed from within 10
feet of the structure and properly capped off. The resulting depressions from the above described procedure
should be backfilled with acceptable soil that is compacted to the requirements of die Geotechnical Engineer.
This includes, but is not limited to, septic tanks, fuel tanks, sewer lines or leach lines, storm drains and water
lines. Any buried structures or utilities not to be abandoned should be brought to the attention of the
Geotechnical Engineer so tiiat he may determine if any special recommendation will be necessary.
All water wells which will be abandoned should be backfilled and capped in accordance to the requirements
set forth by tiie Geotechnical Engineer. The top of the cap should be at least 4 feet below finish grade or 3
CWE 2110148.01 July 6, 2011 Appendix C, Page C-3
feet below the bottom of footing whichever is greater. The type of cap will depend on the diameter of the
well and should be determined by the Geotechnical Engineer and/or a qualified Stmctural Engineer.
FILL MATERIAL
Materials to be placed in the fill shall be approved by the Geotechnical Engineer and shall be free of
vegetable matter and other deleterious substances. Granular soil shall contain sufficient fine material to fill
the voids. The defiiution and disposition of oversized rocks and expansive or detrimental soils are covered
in the geotechnical report or Special Provisions. Expansive soils, soils of poor gradation, or soils with low
strength characteristics may be thoroughly mked with otiier soils to provide satisfactory fill material, but only
with the explicit consent of tiie Geotechnical Engineer. Any import material shall be approved by die
Geotechnical Engineer before being brought to the site.
PLACING AND COMPACTION OF FILL
Approved fill material shall be placed in areas prepared to receive fill in layers not to exceed 6 inches in
compacted thickness. Each layer shall have a uniform moisture content in the range that will allow the
compaction effort to be efficientiy applied to achieve the specified degree of compaction. Each layer shall be
uniformly compacted to the specified minimum degree of compaction with equipment of adequate size to
economically compact the layer. Compaction equipment should either be specifically designed for soil
compaction or of proven reliability. The minimum degree of compaction to be achieved is specified in either
the Special Provisions or the recommendations contained in the preliminary geotechnical investigation
report.
When the stmctural fill material includes rocks, no rocks will be allowed to nest and all voids must be
carefully filled with soil such tiiat the minimum degree of compaction recommended in the Special
Provisions is achieved. The maximum size and spacing of rock permitted in structural fills and in non-
structural fills is discussed in the geotechnical report, when applicable.
Field observation and compaction tests to estimate tiie degree of compaction of the fill will be taken by the
Geotechnical Engineer or his representative. The location and frequency of die tests shall be at the
Geotechnical Engineer's discretion. When the compaction test indicates that a particular layer is at less than
the required degree of compaction, the layer shall be reworked to the satisfaction of the Geotechnical
Engineer and until the desired relative compaction has been obtained.
CWE 2110148.01 July 6, 2011 Appendix C, Page C-4
Fill slopes shall be compacted by means of sheepsfoot rollers or other suitable equipment Compaction by
sheepsfoot roller shall be at vertical intervals of not greater than four feet In addition, fill slopes at a ratio of
two horizontal to one vertical or flatter, should be trackroUed. Steeper fill slopes shall be over-built and cut-
back to finish contours after the slope has been constmcted. Slope compaction operations shall result in all
fill material six. or more inches inward from the finished face of the slope having a relative compaction of at
least 90 percent of maximum dry density or the degree of compaction specified in the Special Provisions
section of this specification. The compaction operation on the slopes shall be continued until the
Geotechnical Engineer is of the opinion that the slopes will be surficially stable.
Density tests in the slopes will be made by the Geotechnical Engineer during construction of die slopes to
determine if the required compaction is being achieved. Where failing tests occur or other field problems
arise, the Contractor will be notified tiiat day of such conditions by written communication from the
Geotechnical Engineer or his representative in the form of a daily field report.
If the method of achieving the required slope compaction selected by the Contractor fails to produce the
necessary results, the Contractor shall rework or rebuild such slopes until the required degree of compaction
is obtained, at no cost to the Owner or Geotechnical Engineer.
CUT SLOPES
The Engineering Geologist shall inspect cut slopes excavated in rock or lithified formational material during
the grading operations at intervals determined at his discretion. If any conditions not anticipated in the
preliminary report such as perched water, seepage, lenticular or confined strata of a potentially adverse
nature, unfavorably inclined bedding, joints or fault planes are encountered during grading, these conditions
shall be analyzed by tiie Engineering Geologist and Geotechnical Engineer to determine if mitigating
measures are necessary.
Unless otherwise specified in the geotechnical report, no cut slopes shall be excavated higher or steeper than
that allowed by the ordinances of the controlling govemmental agency.
ENGINEERING OBSERVATION
Field observation by the Geotechnical Engineer or his representative shall be made during the filling and
compaction operations so tiiat he can express his opinion regarding die conformance of the grading with
acceptable standards of practice. Neither tiie presence of die Geotechnical Engineer or his representative or
CWE 2110148.01 July 6, 2011 Appendix C, Page C-5
the observation and testing shall release the Grading Contractor from his duty to compact all fill material to
the specified degree of compaction.
SEASON UMITS
Fill shall not be placed during unfavorable weather conditions. When work is intermpted by heavy rain,
filling operations shall not be resumed until the proper moisture content and density of the fill niaterials can
be achieved. Damaged site conditions resulting from weather or acts of God shall be repaired before
acceptance of work.
RECOMMENDED GRADING SPECIFICATIONS - SPECIAL PROVISIONS
RELATIVE COMPACTION: The minimum degree of compaction to be obtained in compacted natural
ground, compacted fill, and compacted backfill shall be at least 90 percent For street and parking lot
subgrade, the upper six inches should be compacted to at least 95 percent relative compaction.
EXPANSIVE SOILS: Detrimentally expansive soil is defined as clayey soil which has an expansion index of
50 or greater when tested in accordance with ASTM D 4829.
OVERSIZED MATERIAL: Oversized fill material is generaUy defined herein as rocks or lumps of soil
over 6 inches in diameter. Oversized niaterials should not be placed in fiU unless recommendations of
placement of such material is provided by the Geotechnical Engineer. At least 40 percent of the fiU soils
shaU pass through a No. 4 U.S. Standard Sieve.
TRANSITION LOTS: Where transitions between cut and fiU occur within die proposed building pad, tiie
cut portion should be undercut a minimum of one foot below the base of the proposed footings and
recompacted as stmctural backfiU. In certain cases that would be addressed in the geotechnical report,
special footing reinforcement or a combination of special footing reinforcement and undercutting may be
required.