Loading...
HomeMy WebLinkAbout2021-06-03; Fire Station No. 2 Project Update (District 4); Gomez, Paz\ I To the members of the: CllY COUNCIL Date ~ CA L CC ✓ CM v ACM v DCM{3) ✓ June 3, 2021 Council Memorandum To: Honorable Mayor Hall and Members of the City Council From: Paz Gomez, Deputy City Manager, Public Works Via: Geoff Patnoe, Assistant City Manager@ Re: Fire Station No. 2 Project Update (District 4) {city of Carlsbad Memo ID #2021114 This memorandum provides an update on a previous Council Memorandum dated April 29, 2021, (Attachment A) on the status of the Fire Station No. 2 project, Capital Improvement Program (CIP) Project No. 4060 (project), which will reconstruct the existing Fire Station No. 2 located at 1906 Arena I Road. Background On Nov. 2, 2020, staff issued a notice to proceed to the design-build contractor, Barnhart-Reese Construction, and work on the project commenced. The· duration of the construction contract is 550 calendar days, excluding rain days and change orders that may extend the contract duration. Plans and specifications for the temporary fire station at the Carlsbad City Library parking lot on Dove Lane were submitted to the Building Division for plan check on Jan. 13, 2021. A building permit for the temporary fire station was issued on Feb. 12, 2021. As of the last project update, Barnhart-Reese Construction substantially completed construction of the temporary fire station and permitting ofthe permanent Fire Station No. 2 is ongoing. Discussion Electrical power to the temporary fire station has been established and testing of the temporary fire station is underway. It is anticipated the temporary fire station will be complete and ready for occupancy by June 7, 2021. Design plans and specifications for the permanent Fire Station No. 2 are complete. Building plans were submitted for permitting on April 15, 2021, and the plan check process is ongoing. Grading plans were submitted for review and permitting on April 26, 2021, and a demolition permit application was submitted on May 25, 2021. Next Steps Fire Department personnel started relocating furniture and equipment from the current Fire Station No. 2 into the temporary fire station on June 1, 2021, and began operating out of the Public Works Branch Fleet and Facilities Department 405 Oak Avenue I Carlsbad, CA 92008 I 760-434-2980 t Council Memo -Fire Station No. 2 Project Update (District 4) June 3, 2021 Page 2 temporary fire station beginning the evening of June 2, 2021. Once vacated, the current Fire Station No. 2 will undergo abatement and fumigation. Upon issuance of a demolition building permit, the design-build contractor will demolish the existing Fire Station No. 2, remove debris and begin grading the site. An updated timeline is as follows: June 2021: June 2021: July 2021: July 2022: Completion of temporary fire station construction and relocation of staff Issuance of demolition permits for reconstructing the permanent Fire Station No. 2 Break ground on reconstruction of the permanent Fire Station No. 2, following the hazardous materials abatement, fumigation and demolition Completion of reconstruction of the Fire Station No. 2. Return of staff to newly reconstructed Fire Station No. 2 and removal of temporary fire station, unless delays are experienced and contract duration is extended Attachment: A. Council Memorandum dated April 29, 2021 cc: Scott Chadwick, City Manager Celia Brewer, City Attorney Gary Barberio, Deputy City Manager, Community Services Laura Rocha, Deputy City Manager, Administrative Services Michael Calderwood, Fire Chief Robby Contreras, Assistant City Attorney Jeff Murphy, Community Development Director Suzanne Smithson, Library & Cultural Arts Director John Maashoff, Public Works Manager Steven Stewart, Municipal Projects Manager To the members of the: ~)TY,COUNCIL Date ~ CA 1/ CC ✓ CM ✓ACM .✓ DCM (3),L --' April 29, 2021 ATTACHMENT A Council Memorandum To: From: Honorable Mayor Hall and Members of the City Council Paz Gomez, Deputy City Manager, Public Works Geoff Patnoe, Assistant City Manager @ Via: Re: Fire Station No. 2 Project Update (Dis~ 4) {city of Carlsbad Memo ID #2021089 This memorandum provides an update to a previous memorandum dated Nov. 19, 2020, on the status of the Fire Station No. 2 project, Capital Improvement Program (CIP) Project No. 4060 (project), which will reconstruct the existing Fire Station No. 2 located at 1906 Arena I Road. Background As of the last project update provided in the Council Memorandum dated Nov. 19, 2020, (Attachment A), staff and project consultants have substantially completed their review of the project plans, specifications and design documents required to obtain permits for completing the project. Right-of-way and building permit applications have been submitted and approved for the temporary fire station site. Also, right-of-way and building permit applications were submitted the week of April 12-16, 2021, for the permanent station site. Discussion On Nov. 2, 2020, staff issued a notice to proceed to the design-build contractor, Barnhart-Reese Construction, and work on the proje,ct commenced. The duration of the construction contract is 550 calendar days, excluding rain days and change orders that may extend the contract duration. The design-build contractor submitted plans and specifications for the temporary fire station at the Carlsbad City Library on Dove Lane to the Building Division of the Community Development Department for plan check on Jan. 13, 2021. The city issued a permit on Feb. 12, 2021, and construction is underway. As projected, the temporary station should be complete and ready for occupancy by the end of May 2021. Design and development of the plans and specifications for the permanent station are ongoing. Preliminary design and bridging documents used to bid the project did not include an elevator. During development of the plans, specifications and drawings, the city determined that the current code requirements would require installation of an elevator or exterior lift. Incorporation of an elevator into the project delayed submission of the plans for a building permit by approximately 10 weeks. The design-build contractor submitted revised building plans on April 15, 2021, and the revised date for permit issuance is now anticipated to be June 2021. Public Works Branch Fleet and Facilities Department 405 Oak Avenue I Carlsbad, CA 92008 I 760-434-2980 t Coun'cil Memo -Fire Station No. 2 Project Update (District 4) April 29, 2021 Page 2 The revised completion date for reconstruction of the existing fire station and removal of the temporary fire station is anticipated to be June 2022. Next Steps The design-build contractor will continue constructing the temporary station and revising project plans, specifications and drawings as necessary to address staff and consultant review comments. The revised timeline is as follows: May 2021: June 2021: July 2021: June 2022: Completion of temporary station construction and relocation of staff Issuance of demolition and building permits for reconstructing Fire Station No. 2 Reconstruction of the permanent Fire Station No. 2 starts, following hazardous materials abatement, fumigation and demolition . Completion of reconstruction of Fire Station No. 2. Return of staff to newly reconstructed fire station and removal of temporary fire station at the Carlsbad City Library on Dove Lane, unless delays are experienced and contract duration is extended Attachment: A. Council Memorandum dated Nov. 19, 2020 cc: Scott Chadwick, City Manager Celia Brewer, City Attorney Gary Barberio, Deputy City Manager, Community Services Laura Rocha, Deputy City Manager, Administrative Services Michael Calderwood, Fire Chief Robby Contreras, Assistant City Attorney Jeff Murphy, Community Development Director Suzanne Smithson, Library & Cultural Arts Director John Maashoff, Public Works Manager Steven Stewart, Municipal Projects Manager ATTACHMENT A Council Memorandum Nov.19,2020 To: From: Via: Re: Honorable Mayor Hall and Members of the City Council Paz-Gomez, Deputy City Manager, Public Works Geoff Patnoe, Assistant City Manager /f.j~ Fire Station No. 2 Project Update (DistHt('4) {city of Carlsbad Memo ID #2020253 This memorandum provides an update on the status of Fire Station No. 2, Capital Improvement Program (CIP) Project No. 4060, which will reconstruct the existing Fire Station No. 2 located at 1906 Arenal Road. Background Fire Station No. 2 (fire station) was built in 1969 for one full-time firefighter and a yearly workload off ewer than 250 calls for service. Today, the fire station has a staff of five full-time firefighters who handle approximately 4,000 calls per year. The fire station, which was designed to house fire apparatus built in the 1960s, is too small to house the fire apparatus currently used by public safety staff. The fire station also lacks the fire separation between the fire apparatus parking area, working and living spaces and medical equipment supplies, which is now required by the current California Building Code. Hence, there was a need to replace the existing fire station with a new one. Under a law passed by voters in 1982, the city may not spend more than $1 million in general fund money to purchase or improve city property without first receiving voter approval. A new fire station was estimated to cost more than $1 million, so this law would apply. In November 2016, City of Carlsbad voters approved Measure 0, which authorized the use of general fund money to replace Fire Station No. 2. The fire station will be rebuilt at the station's existing site. During the reconstruction work, the fire station's staff will operate out of temporary facilities in the parking lot area of the Carlsbad City Ubrary located on Dove Lane (referred to as the Dove Library), approximately one mile from the current site. The reconstructed fire station will: • Have enlarged fire apparatus bays to accommodate new, modern fire response vehicles • Be built to current building and seismic codes with consideration for green technologies • Provide gender-specific facilities • Ensure medical supplies and living quarters are not exposed to carcinogens from firefighting equipment Public Works Branch Fleet and Facilities Department 405 Oak Avenue I Carlsbad, CA 92008 I 760-434-2980 t ' t ; Council Memo -Fire Station No. 2 Project Update (District 4) Nov .. 19, 2020 Page 2 • Meet Occupational Safety and Health Administration (OSHA) and National Fire Protection Association (NFPA) standards • 'Follow the architectural design elements of the surrounding community Given the project's challenging site constraints, staff has chosen the design-build project delivery method over the more traditional method of putting the full design of the project out to bid first and using a design-bid-build delivery method. The design-build approach allows a greater level of design and construction creativity. The first step in the design-build project delivery method is to develop project criteria (i.e., preliminary design plans and specifications), which disclose all site conditions and constraints known to the city and convey the city's requirements for the finished project. This project is consistent with the city's Climate Action Plan (CAP) Measures B, G and J, and Council Policy No. 71: • Measure B, Action 1: "Require PV (photovoltaic solar array) on large new non-residential construction." o The project work scope requires a photovoltaic solar array on the roof sized to meet the requirements of City Ordinance CS-347, which was approved by City Council on March 12, 2019 • Measure G, Action 2: "Commission city facilities." o The project work scope requires a commissioning process that tests all newly installed mechanical and electrical systems to ensure operational efficiency • Measure J, Action 2: "Solar water heating and heat pump ordinance for new non-residential construction." o The project work scope requires installation of a solar water heater to meet this requirement • Council Policy No. 71, subparagraph 2(a), on construction of civic facilities: "Whenever practicable and within a reasonable cost/benefit ratio, design and construct mechanical and electrical systems to achieve the maximum energy efficiency achievable with current technology." o The design for this project meets the latestfederal standards, as set forth in Title 24, with compliant heating, ventilation and air conditioning equipment, light- emitting diodes (LED) light fixtures and photovoltaic solar arrays to optimize electrical energy efficiency Additionally, this project will provide two electric vehicle charging stations, which will be available for use by the public. The project will demolish the existing 3,650 SF one-story facility and construct a new 10,782 SF two-story facility. The fire apparatus access has been reconfigured so entrance will be from Arena I I I Council Memo -Fire Station No. 2 Project Update (District 4) Nov.19,2020 Page 3 Road with exit onto El Camino Real. This design necessitates adding traffic signals for a KEEP CLEAR zone on southbound El Camino Real and relocating an existing bus stop on northbound El Camino Real to approximately 20 feet south of the intersection at Arenal Road. On Sept. 25, 2018, the city posted a project information webpage on the city's website. The webpage includes historical information about the project as well as an estimated project timeline. https://www.carlsbadca.gov/services/depts/fire/firestation2.asp The following background timeline is provided (targeted schedule completion dates are shown in parentheses for some activities): November 2016-71% of City of Carlsbad voters approved Measure 0, which authorized the use of general fund money to replace Fire Station No. 2. Under'a law passed by voters in 1982, the city may not spend more than $1 million in general fund money to purchase or improve city property without first receiving voter approval. April 2017 -Staff posted a Request for Qualifications as part of a solicitation process to select a consultant to evaluate site conditions and constraints, and to develop bridging documents for a design-build proposal solicitation. July 11, 2017-The City Council adopted Resolution No. 2017-134, which authorized an agreement with Domusstudio Architecture, Inc. to develop bridging documents and preliminary design plans and specifications for replacement of Fire Station No. 2 and construction of a temporary fire station. (target was August 2017) Oct. 18, 2017-Enhanced stakeholder outreach began in conformance with Council Policy No. 84, Development Project Public Involvement Policy. July 20, 2018 -Preliminary project design plans arid specifications were completed. A conditional use permit, special use permit and variance applications were submitted to the city for. discretionary permitting review. (target was May 2018) Oct. 31, 2018 - A Public Outreach Report; which detailed the public notification process and two informal and two formal community outreach meetings, was completed and submitted in accordance with Council Policy No. 84. October 2019 -Plans and specifications for the temporary fire station at the Dove Library location were submitted to the city for discretionary permitting review. Nov. 26, 2019 -Staff completed review of the permit applications and submitted the documents to the State of California, as required by the California Environmental Quality Act (CEQA) Chapter 2.6, Section 21091(8), for public review. (target was February 2019) ! Council Memo -Fire Station No. 2 Project Update (District 4) Nov. 19, 2020 Page4 The permit application review process took approximately 16 months (from July 2018 to November 2019) instead of the targeted nine months (from May 2018 to February 2019) due to the complexity of the design, number of exceptions to the standards, resolving project questions on code compliance using the design-build methodology and CEQA documentation. Feb. 19, 2020-The Planning Commission adopted Resolution No. 7360, which approved the conditional use permit, special use permit and variance required for the new fire station, and Resolution No. 7361, which approved the conditional use permit and coastal development permit for the temporary fire station. April 21, 2020 -The City Council adopted Resolution No. 2020-065 approving the preliminary design plans and specifications and authorizing the city clerk to advertise for a design-build proposal solicitation. (target was February 2019) Sept. 22, 2020-The City Council adopted Resolution No. 2020-193 authorizing award of a design-build contract to Barnhart-Reese Construction, Inc. (Contractor), to provide design-build services for the Fire Station No. 2 Replacement Project in an amount not to exceed $11,222,472. (target was June 2019) Discussion On Nov. 2, 2020, the Contractor was issued a notice to proceed, which was approximately 14 months later than previously anticipated. The delays can be attributed to a delay in submitting the application packet and the permit application review and approval processes taking longer than previously expected, as explained above. The duration of the construction contract is 550 calendar days, excluding rain days and change orders that may extend the contract duration. The. estimated construction completion date is May 2022. Upon award of the contract, the Contractor contacted the temporary housing trailer manufacturer identified in the contract documents to procure the required trailers. The manufacturer notified the Contractor that due to a housing demand driven by this year's unprecedented wildfires, trailers are back-ordered by approximately six months, which could delay the overall project schedule. The Contractor is currently finalizing design of the project construction drawings and specifications as required for issuance of a building permit. It is anticipated that the building permit will be ready to issue in January 2021 for the temporary fire station, and that the building permit to reconstruct Fire Station No. 2 will be ready to issue in spring 2021. Council Memo -Fire Station No. 2 Project Update (District 4) Nov. 19, 2020 Page 5 Construction of the temporary fire station at the Dove Library is anticipated to be completed and ready for occupancy in spring 2021. Once completed, Fire Department personnel will operate from the temporary fire station until the existing fire station is reconstructed. Reconstruction of the existing fire station and removal of the temporary fire station are anticipated to be completed by May 2022. Next Steps The Contractor will continue to work on acquiring a trailer for the temporary fire station and finalizing t he project design. Timeline is as follows: January 2021: Issuance of building permit for temporary fire station Spring 2021: Issuance of building permit for reconstructing the fire station Spring 2021: Completion of temporary station construction and relocation of staff May 2022: Completion of reconstruction of the fire station, return of staff to newly reconstructed fire station and removal of temporary fire station, unless delays are experienced and contract duration is extended cc: Scott Chadwick, City Manager Celia Brewer, City Attorney Gary Barberio, Deputy City Manager,-Community Services Laura Rocha, Deputy City Manager, Administrative Services Michael Calderwood, Fire Chief Robby Contreras, Assistant City Attorney Jeff Murphy, Community Development Director Suzanne Smithson, Library & Cultural Arts Director John Maashoff, Public Works Manager Steven Stewart, Municipal Projects Manager