Loading...
HomeMy WebLinkAboutMS 13-07; VIASAT BUILDING 10; FINAL SOILS REPORT; 2015-03-05FINAL COMPACTION REPORT VIASAT BUILDING 10 2502 Gateway Road Carlsbad, California for Pivotal 650 California Street, LLC 22885 Savi Ranch Parkway Suite E Yorba Linda California 92887 voice: (714) 685-1115 fax: (714) 685-1118 www.socalgeo.com March 5, 2015 Pivotal 650 California St., LLC 2201 Camelback Road, Suite 650 Phoenix, Arizona 85012 Attention: Mr. Tony Feiter Project No.:14M110-6 Subject:Final Compaction Report ViaSat Building 10 2502 Gateway Road Carlsbad, California References: Geotechnical Investigation, Proposed Commercial/Industrial Development, Bressi Ranch Lots 10-13, NEC of Gateway Road and El Camino Real, Carlsbad, California, prepared by Southern California Geotechnical, Inc. (SCG) for Levine Investments, dated January 23, 2008, SCG Project No. 07G227-1. Rough Grade Compaction Report, Building 10, NEC Gateway Road and El Camino Real, Carlsbad, California, prepared for Pivotal 650 California St., LLC by SCG, dated April 1, 2014, SCG Project No. 14M110-2. Gentlemen: In accordance with your request, Southern California Geotechnical, Inc. (SCG) presents this Final Compaction Report which serves as a summary of the geotechnical observation and testing performed by our personnel during post-grading earthwork operations at the subject site. PROJECT DESCRIPTION The project site is located at the northeast corner of Gateway Road and El Camino Real. The site is bordered to the west by El Camino Real, to the south by Gateway Road, to the east by Campbell Place, and to the north by an office building and the terminus of Campbell Place. The project site is an irregularly-shaped parcel, approximately 8± acres in size. Prior to construction, graded slopes ranging in height from 5 to 7± feet border the site to the north and east. Ground surface cover consisted of exposed soil with moderate grass and weed growth. The eastern half of the overall site was previously sheet-graded and is designated for future development. The ViaSat Building 10 development occupies the western half of the overall site. Building 10 was constructed in the southwest corner of the planned development area. The building is a 3- story structure of tilt-up concrete construction, supported on conventional shallow foundations and a concrete slab-on-grade floor. Two smaller structures identified as the Antenna and Mechanical buildings were constructed to the north of Building 10. The buildings were surrounded by asphaltic concrete pavements, Portland cement concrete flatwork, and new landscaping. A new fill slope was constructed on the northeast perimeter of the site, adjacent Campbell Place. SOUTHERN CALIFORNIA GEOTECHNICAL A Lnl1{cmw1 Cnrpomfim, ViaSat Building 10 – Carlsbad, CA Project No. 14M110-6 Page 2 PREVIOUS STUDIES Southern California Geotechnical, Inc. (SCG) previously conducted a geotechnical investigation for the proposed development. The results of this investigation were presented in the above referenced report. The subsurface exploration conducted for this project consisted of eight (8) borings advanced to depths of 15 to 19½± feet below the existing site grades. A Rough Grade Compaction Report was also prepared for this project by SCG. This report documented remedial grading activities performed within the building pad area. Generally, the building pad area was excavated to depths ranging from 6 to 11± feet below the proposed pad grade. The overexcavation was filled with structural compacted fill up to planned pad grades. SUMMARY OF EARTHWORK OPERATIONS AND TESTING Foundation Subgrade Evaluation SCG evaluated the condition of the foundation bearing soils within the footing excavations for the building. Our evaluations indicated that the foundation excavations were underlain by recently placed compacted structural fill soils. These materials were probed at several random, periodic locations. All of the encountered soils were found to be medium dense to dense and possessed adequate moisture contents. Based on our evaluations, the foundation bearing soils for the buildings are considered suitable for support of foundations designed for a maximum soil bearing pressure of 2,500 lbs/ft2. Fill Slope A new fill slope was constructed along the northeast perimeter of the site, adjacent to Campbell Place. A keyway was excavated at the planned toe of slope. At the proposed toe, the keyway was founded a minimum of 2± feet into competent native materials. The keyway bench was approximately 1 foot deeper at the heel of the key. Prior to filling, subgrade soils at the base of the keyway were scarified to a depth of 12± inches; moisture conditioned, and then recompacted. Benching of the back cut into competent materials was performed during the fill placement procedures. Utility Trench Backfill Utility trench backfill soils were tested for compaction on an intermittent basis as scheduled by the site superintendent for Ledcor Construction. The utility trenches tested by our field representatives included several interior sewer and electrical, as well as exterior sewer, electrical, fire, water and storm drain lines. The depths of the tested utility trenches generally ranged from 1 to 16± feet as measured to the top of the utility line or shading material. Fill soils were compacted in lifts within the trenches with a backhoe or excavator mounted compaction wheel and hand operated mechanical compactors. Results of compaction tests performed at discrete locations indicated that at least 90 percent of the ASTM D-1557 maximum dry density was achieved at the test locations. Compaction test results within the top 1 foot within the building pad and top 3 feet in pavement areas, indicate that at least 95 percent of the ASTM D- 1557 maximum dry density was achieved at the test locations. SOUTHERN ViaSat Building 10 – Carlsbad, CA Project No. 14M110-6 Page 3 Pavement Subgrade Precise grading activities within the new pavement areas generally consisted of minor cuts and fills of less than 1± foot in order to establish the proposed finish subgrade elevations. The subgrade soils within the new on-site parking/driveway and sidewalk areas (including adjacent curb & gutter and ribbon gutter) were scarified, moisture treated or dried as necessary, and then recompacted. Vibratory rollers, rubber tired loaders, and scrapers were used for compaction. The results of compaction testing performed at discrete locations during fill placement activities indicated that at least 95 percent of the ASTM D-1557 maximum dry density was achieved at the test locations. A base course layer consisting of crushed miscellaneous base was compacted over the approved subgrades within new automobile parking and drive approach areas. The base material was moisture conditioned and then compacted with vibratory smooth drum rollers. The results of compaction testing indicated that at least 95 percent of the ASTM D-1557 maximum dry density was achieved at all test locations for the base course material. Asphaltic Concrete The temperature and loose depth of asphaltic concrete was measured during the paving operations. The asphalt temperatures were noted to be above the minimum required lay down temperature and no temperature related problems were observed during paving. Subsequent to the compaction of the asphalt with steel drum rollers, density tests were performed to determine the relative compaction. Compaction test results indicated that the asphaltic concrete was compacted to at least 95% of the reported Marshall maximum density at all test locations. General Comments Structural fill compaction was tested by the Nuclear Method (ASTM D-6938) and referenced to the maximum dry density values obtained by the Modified Proctor method (ASTM D-1557). Where density tests indicated less than the minimum specified compaction, the soils were moisture treated as necessary and recompacted until the specified compaction was achieved as indicated by retests. The locations of the density tests are indicated on the enclosed Density Test Location Plan, Plate 1. Moisture-density test results are presented on Table 1, enclosed in this report. In addition, data regarding the soil types used as structural fill are presented on Table 2. CONCLUSIONS AND RECOMMENDATIONS The fill soils observed in the footing excavations are expected to provide adequate support for the new structures which utilize a foundation system designed for a maximum allowable soil bearing pressure of 2,500 lbs/ft2. The fill soils placed during site grading operations and utility trench backfilling procedures have been prepared in accordance with recommendations presented in the original geotechnical engineering report. The new pavement subgrades are expected to provide adequate support for the new pavement sections and the anticipated traffic loads. SOUTHERN ViaSat Building 10 – Carlsbad, CA Project No. 14M110-6 Page 4 CLOSURE Test results presented in this report have been accumulated during intermittent observation and random testing by this company, as scheduled by the site superintendent for Ledcor Construction. The test results and observations summarized in this report were found to be in general compliance with current grading codes. However, we cannot be responsible for grading or earthwork activities that were performed during the absence of our personnel. Our professional services have been performed using our understanding of that degree of care and skill ordinarily exercised, under similar circumstances, by reputable geotechnical consultants practicing in this area at this time. No other warranty, express or implied, is made as to the professional services described in this report. This report was prepared exclusively for Pivotal 650 California St., LLC, and should not be used by other parties unfamiliar with its intent. This opportunity to be of continued professional service is sincerely appreciated. Should you have any questions regarding this project, please contact us at your earliest convenience. Respectfully Submitted, SOUTHERN CALIFORNIA GEOTECHNICAL, INC. Ricardo Frias Staff Engineer Robert G. Trazo, GE 2655 Principal Engineer Enclosures: Density Test Location Plan, Plate 1 Summary of Field Density Tests, Table 1 Summary of Moisture-Density Relationships, Table 2 Distribution: (1) Addressee (3) Ledcor Construction, Attn: Robert Rowe SOUTHERN CALIFORNIA GEOTECH !Cff~~ ~ l "" l"'7' 22885 Savi Ranch ParkwaySuite EYorba Linda, CA 92887Phone: (714) 685-1115Fax: (714) 685-1118www.socalgeo.comDENSITY TEST LOCATION PLANVIASAT BUILDING 102502 GATEWAY ROADCARLSBAD, CALIFORNIASCALE: 1" = 30'SCG PROJECT14M110-6DRAWN: RFCHKD: RGTPLATE10146*SoCalGeoGEOTECHNICAL LEGEND APPROXIMATE LOCATION OF IN-PLACE DENSITY TEST APPROXIMATE LIMITS OF OVEREXCAVATION 100 APPROXIMATE ELEVATION AT BOTTOM OF OVEREXCAVATION 50 I 15 '- I ----- 3 689 • 664 • 487 203 202 656 • 68 • 665 • 632 • 270-277 66 627 • , 66 626 • BUILDING 10 199,200 198 177 176 175 241 • 213 214 195 197 182 204 181 194 205 178 179 180 ST AIR WELL 2 l ···!244 ° • 193 • ·242 · • 688 • 495 3 3 ' 11 I I 66 • 48 5 171 668 • • 62 • 66 6 9 • 93 -.- 1881 I > I 189~1 ~250 \ > 139 589 6 4 295 " ' ------118 117 292-------- 635 • 62 • 290,2:1-- " ----------------651 • --\,,--! -~~~-t~=----'c:::::_1 1 -l I ~ ~ ' --~ -~ - \ \ • -- 1310.ol -NOT£: BAS£ MAP PROVIDED BY O'DAY CONSULTANTS, INC. Z< i::::::: -~z ::c:: i::::::: E--0 :=:> E:::: 0 ~ Cl'J< u TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 112 07-Apr-14 -6.0 Storm Drain B 16.5 104.6 91 113 07-Apr-14 -4.0 Storm Drain B 15.9 106.3 92 114 07-Apr-14 -2.0 Storm Drain B 15.7 109.1 95 115 07-Apr-14 SG Storm Drain B 16.3 107.1 93 Fail: 95% Required 116 07-Apr-14 SG Storm Drain B 15.5 109.6 95 Retest #115 117 07-Apr-14 -6.0 Storm Drain B 16.9 105.0 91 118 07-Apr-14 -4.0 Storm Drain B 16.2 106.8 93 119 07-Apr-14 -2.0 Storm Drain B 13.9 108.2 94 Fail: 95% Required 120 07-Apr-14 -2.0 Storm Drain B 15.8 109.3 95 Retest #119 121 08-Apr-14 SG Storm Drain B 15.2 110.3 96 122 08-Apr-14 -10.0 Storm Drain B 16.4 103.8 90 123 08-Apr-14 -8.0 Storm Drain B 16.8 104.4 91 124 08-Apr-14 -6.0 Storm Drain B 16.1 104.8 91 125 08-Apr-14 -4.0 Storm Drain B 15.6 105.5 92 126 08-Apr-14 -2.0 Storm Drain B 15.9 106.4 93 Fail: 95% Required 127 08-Apr-14 -2.0 Storm Drain B 15.4 108.8 95 Retest #126 128 08-Apr-14 SG Storm Drain B 16.0 109.9 96 129 08-Apr-14 -10.0 Storm Drain B 17.2 103.9 90 130 08-Apr-14 -8.0 Storm Drain B 16.6 105.1 91 131 08-Apr-14 -6.0 Storm Drain B 16.9 104.2 91 132 09-Apr-14 -4.0 Storm Drain B 17.3 105.7 92 133 09-Apr-14 -2.0 Storm Drain B 16.6 107.9 94 Fail: 95% Required 134 09-Apr-14 -2.0 Storm Drain B 15.8 109.2 95 Retest #133 135 09-Apr-14 SG Storm Drain B 14.9 110.5 96 136 09-Apr-14 -2.5 Sewer Line B 12.8 107.1 93 Fail: 95% Required 137 09-Apr-14 -2.5 Sewer Line B 15.5 109.3 95 Retest #136 138 09-Apr-14 -1.0 Sewer Line B 15.9 109.7 95 139 09-Apr-14 SG Sewer Line B 15.3 110.1 96 140 09-Apr-14 -1.0 Sewer Line B 15.7 109.6 95 141 10-Apr-14 -3.5 Sewer Line B 16.5 105.1 91 142 10-Apr-14 -1.5 Sewer Line B 16.1 108.9 95 143 10-Apr-14 SG Sewer Line B 15.6 109.5 95 144 10-Apr-14 SG Sewer Line B 14.1 106.4 93 Fail: 95% Required 145 10-Apr-14 SG Sewer Line B 15.7 109.5 95 Retest #144 146 10-Apr-14 -6.0 Storm Drain B 16.9 105.3 92 147 10-Apr-14 -4.0 Storm Drain B 16.5 107.1 93 148 10-Apr-14 -2.0 Storm Drain B 16.0 109.1 95 149 10-Apr-14 SG Storm Drain B 13.7 106.8 93 Fail: 95% Required 14M110-6 Viasat Building 10 -- Carlsbad, California Page 1 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 150 10-Apr-14 SG Storm Drain B 15.1 109.9 96 Retest #149 151 11-Apr-14 -11.0 Storm Drain B 16.9 105.1 91 152 11-Apr-14 -9.0 Storm Drain B 17.3 105.8 92 153 11-Apr-14 -7.0 Storm Drain B 16.2 106.5 93 154 11-Apr-14 -6.0 Storm Drain B 16.5 105.2 91 155 11-Apr-14 -4.0 Storm Drain B 15.6 107.0 93 156 11-Apr-14 -2.0 Storm Drain B 15.4 110.8 96 157 11-Apr-14 -6.0 Storm Drain B 16.8 104.4 91 158 11-Apr-14 -4.0 Storm Drain B 15.5 106.6 93 159 11-Apr-14 -2.0 Storm Drain B 13.1 107.4 93 Fail: 95% Required 160 11-Apr-14 -2.0 Storm Drain B 15.8 109.6 95 Retest #159 161 11-Apr-14 SG Storm Drain B 14.8 110.4 96 162 16-Apr-14 -7.5 Sewer Line A 18.3 105.2 90 163 16-Apr-14 -5.5 Sewer Line A 17.8 107.0 92 164 16-Apr-14 -3.5 Sewer Line A 17.5 107.6 92 165 16-Apr-14 -1.5 Sewer Line A 18.6 108.3 93 Fail: 95% Required 166 16-Apr-14 -1.5 Sewer Line A 17.3 111.4 96 Retest #165 167 16-Apr-14 SG Sewer Line B 15.2 110.9 96 168 16-Apr-14 -4.0 Sewer Line B 16.4 106.3 92 169 16-Apr-14 -2.0 Sewer Line B 15.1 109.6 95 170 16-Apr-14 SG Sewer Line B 15.7 110.5 96 171 16-Apr-14 -6.0 Sewer Line B 16.2 106.1 92 172 16-Apr-14 -4.0 Sewer Line B 16.5 107.5 93 173 16-Apr-14 -2.0 Sewer Line B 15.3 109.2 95 174 16-Apr-14 SG Sewer Line B 14.9 110.1 96 175 16-Apr-14 SG Interior Sewer A 18.1 106.6 92 176 16-Apr-14 -1.0 Interior Sewer A 18.8 105.8 91 177 16-Apr-14 SG Interior Sewer A 18.5 107.4 92 178 17-Apr-14 SG Interior Sewer A 17.2 107.8 93 179 17-Apr-14 -1.0 Interior Sewer A 17.5 105.5 91 180 17-Apr-14 SG Interior Sewer B 16.0 105.9 92 181 17-Apr-14 -2.0 Interior Sewer B 15.4 103.1 90 182 17-Apr-14 -1.0 Interior Sewer A 17.6 106.3 91 183 17-Apr-14 SG Interior Sewer A 17.4 108.2 93 184 18-Apr-14 -6.0 Sewer Line B 15.8 105.8 92 185 18-Apr-14 -4.0 Sewer Line B 15.1 106.6 93 186 18-Apr-14 -2.0 Sewer Line B 15.4 108.9 95 187 18-Apr-14 SG Sewer Line B 15.7 110.5 96 14M110-6 Viasat Building 10 -- Carlsbad, California Page 2 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 188 18-Apr-14 -6.0 Sewer Line A 18.3 105.1 90 189 18-Apr-14 -4.0 Sewer Line A 17.9 106.1 91 190 18-Apr-14 -2.0 Sewer Line A 13.9 106.6 92 Fail: 95% Required 191 18-Apr-14 -2.0 Sewer Line A 17.1 110.9 95 Retest #190 192 18-Apr-14 SG Sewer Line A 17.8 110.4 95 193 18-Apr-14 SG Interior Sewer A 17.5 105.5 91 194 18-Apr-14 -2.0 Interior Sewer A 16.6 104.3 90 195 18-Apr-14 -1.0 Interior Sewer A 16.9 104.7 90 196 18-Apr-14 SG Interior Sewer A 17.2 106.0 91 197 21-Apr-14 -1.5 Interior Sewer B 16.6 105.1 91 198 21-Apr-14 SG Interior Sewer B 16.1 105.6 92 199 21-Apr-14 -1.5 Interior Sewer B 16.5 102.1 89 Fail: 90% Required 200 21-Apr-14 -1.5 Interior Sewer B 15.8 106.8 93 Retest #199 201 21-Apr-14 SG Interior Sewer A 16.7 108.1 93 202 21-Apr-14 -1.0 Interior Sewer A 18.2 105.3 90 203 21-Apr-14 SG Interior Sewer A 17.6 106.9 92 204 21-Apr-14 SG Interior Electrical A 18.0 107.4 92 205 21-Apr-14 SG Interior Electrical B 15.5 105.4 92 206 22-Apr-14 -4.0 Sewer Line A 18.8 108.4 93 207 22-Apr-14 -2.0 Sewer Line A 17.4 110.6 95 208 22-Apr-14 SG Sewer Line B 13.2 102.2 89 Fail: 95% Required 209 22-Apr-14 SG Sewer Line B 14.8 108.8 95 Retest #208 210 22-Apr-14 SG Storm Drain B 15.2 109.3 95 211 22-Apr-14 -1.0 Storm Drain A 17.4 110.1 95 212 22-Apr-14 SG Storm Drain A 16.8 111.3 96 213 23-Apr-14 SG Interior Electrical A 17.3 105.8 91 214 23-Apr-14 -5.0 Interior Electrical A 16.6 105.1 90 215 23-Apr-14 SG Interior Electrical A 16.9 106.5 91 216 24-Apr-14 -2.0 Storm Drain B 16.6 109.4 95 217 24-Apr-14 -1.0 Storm Drain B 15.5 109.7 95 218 24-Apr-14 SG Storm Drain B 14.8 110.8 96 219 24-Apr-14 -2.0 Storm Drain B 16.3 109.9 96 220 24-Apr-14 -1.0 Storm Drain A 17.1 110.4 95 221 24-Apr-14 SG Storm Drain A 17.4 111.6 96 222 24-Apr-14 -0.5 Storm Drain A 17.2 112.0 96 223 25-Apr-14 -1.0 Storm Drain B 15.6 109.2 95 224 25-Apr-14 SG Storm Drain B 15.1 109.5 95 225 25-Apr-14 -1.0 Storm Drain B 15.8 108.9 95 14M110-6 Viasat Building 10 -- Carlsbad, California Page 3 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 226 25-Apr-14 SG Storm Drain B 14.5 110.3 96 227 03-May-14 296.0 Site Fill A 15.8 104.3 90 228 03-May-14 299.0 Site Fill B 14.2 103.9 90 229 03-May-14 301.0 Site Fill B 14.6 104.7 91 230 03-May-14 30.0 Site Fill B 14.1 105.4 92 231 03-May-14 302.0 Site Fill B 13.9 103.6 90 232 03-May-14 303.0 Site Fill A 15.7 104.6 90 233 03-May-14 302.5 Site Fill B 14.5 104.0 90 234 03-May-14 303.5 Site Fill B 13.8 105.5 92 235 03-May-14 304.5 Site Fill B 14.2 104.8 91 236 05-May-14 -3.0 Water Line B 13.3 109.6 95 237 05-May-14 -2.5 Water Line B 13.1 110.2 96 238 05-May-14 -2.5 Water Line B 12.9 108.8 95 239 05-May-14 -1.0 Water Line A 15.1 110.5 95 240 05-May-14 -1.0 Water Line B 13.3 109.2 95 241 05-May-14 304.5 Site Fill B 14.6 104.7 91 242 05-May-14 304.5 Site Fill B 14.9 103.5 90 243 05-May-14 305.0 Site Fill B 14.2 105.8 92 244 05-May-14 305.0 Site Fill B 14.0 106.0 92 245 06-May-14 -3.0 Water Line B 15.3 104.3 91 Fail: 95% Required 246 06-May-14 -2.0 Water Line B 14.6 108.7 95 Retest #245 247 06-May-14 -3.0 Water Line B 13.9 109.6 95 248 06-May-14 -2.0 Water Line A 15.1 110.3 95 249 06-May-14 -1.0 Water Line B 14.2 108.9 95 250 06-May-14 -2.0 Water Line B 13.2 110.6 96 251 06-May-14 -3.0 Water Line A 15.1 111.1 95 252 06-May-14 -2.0 Water Line A 15.3 110.2 95 253 08-May-14 -2.0 Water Line B 15.3 110.0 96 254 08-May-14 -1.5 Water Line B 15.2 110.1 96 255 08-May-14 -1.0 Water Line B 15.0 109.4 95 256 08-May-14 -0.5 Water Line B 15.1 109.4 95 257 08-May-14 -1.0 Water Line B 15.5 109.2 95 258 09-May-14 -0.5 Storm Drain B 14.8 110.6 96 259 09-May-14 -0.5 Storm Drain B 15.3 109.3 95 260 09-May-14 -1.0 Storm Drain B 15.0 109.9 96 261 09-May-14 -1.0 Storm Drain B 15.1 109.5 95 262 09-May-14 -1.5 Storm Drain B 15.6 109.7 95 263 09-May-14 -1.0 Storm Drain B 15.8 110.1 96 14M110-6 Viasat Building 10 -- Carlsbad, California Page 4 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 264 09-May-14 -0.5 Storm Drain B 15.2 109.2 95 270 21-May-14 -3.5 Interior Electrical A 16.8 107.2 92 271 21-May-14 -3.0 Interior Electrical A 17.0 108.1 93 272 21-May-14 -2.5 Interior Electrical A 17.1 107.6 92 273 21-May-14 -2.0 Interior Electrical A 16.7 107.9 93 274 22-May-14 -2.0 Interior Electrical A 17.3 108.4 93 275 22-May-14 -1.0 Interior Electrical A 17.1 109.2 94 276 22-May-14 SG Interior Electrical A 17.0 110.4 95 277 22-May-14 SG Interior Electrical A 17.2 110.7 95 290 13-Jun-14 -1.0 Water Line B 12.5 106.0 92 Fail: 95% Required 291 13-Jun-14 -1.0 Water Line B 14.1 109.4 95 Retest #290 292 13-Jun-14 -1.0 Water Line B 15.4 110.0 96 293 13-Jun-14 -1.5 Water Line B 16.0 109.0 95 294 13-Jun-14 -0.5 Water Line B 15.2 109.7 95 295 13-Jun-14 -0.5 Water Line B 14.9 109.4 95 296 19-Jun-14 -4.0 Electrical Line A 18.0 107.0 92 297 19-Jun-14 -5.0 Electrical Line A 18.2 106.2 91 298 19-Jun-14 -2.5 Electrical Line B 15.2 109.4 95 299 19-Jun-14 -1.5 Electrical Line B 14.0 110.0 96 300 19-Jun-14 -7.0 Electrical Line B 16.0 104.0 90 301 19-Jun-14 -6.5 Electrical Line B 17.0 103.4 90 302 19-Jun-14 -5.0 Electrical Line B 16.1 105.5 92 303 19-Jun-14 -4.5 Electrical Line B 15.8 104.9 91 304 19-Jun-14 -3.0 Electrical Line B 14.4 109.0 95 305 19-Jun-14 -1.0 Electrical Line B 14.0 108.8 95 306 19-Jun-14 -0.5 Electrical Line B 14.2 109.4 95 307 20-Jun-14 -4.0 Electrical Line B 18.0 101.5 88 Fail: 90% Required 308 20-Jun-14 -4.0 Electrical Line B 16.9 103.7 90 Retest #307 309 20-Jun-14 -2.5 Electrical Line B 15.9 109.0 95 310 20-Jun-14 -2.0 Electrical Line B 15.1 109.5 95 311 20-Jun-14 -1.0 Electrical Line B 15.5 109.2 95 312 20-Jun-14 -0.5 Electrical Line B 16.0 109.0 95 313 26-Jun-14 -1.0 Electrical Line B 15.8 102.6 89 Fail: 95% Required 314 26-Jun-14 -1.0 Electrical Line B 15.2 108.7 95 Retest #313 315 26-Jun-14 -0.5 Electrical Line B 15.4 109.1 95 316 27-Jun-14 -0.5 Electrical Line B 15.9 109.4 95 317 27-Jun-14 -1.5 Electrical Line B 15.4 109.6 95 318 27-Jun-14 -0.5 Electrical Line B 15.3 109.3 95 14M110-6 Viasat Building 10 -- Carlsbad, California Page 5 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 319 27-Jun-14 -4.0 Sewer Line B 14.7 108.5 94 320 27-Jun-14 -2.5 Sewer Line B 14.9 108.9 95 321 27-Jun-14 -1.0 Sewer Line B 14.9 109.0 95 322 27-Jun-14 -1.5 Sewer Line B 15.0 109.5 95 323 27-Jun-14 -0.5 Water Line B 15.1 109.2 95 324 08-Jul-14 -2.0 Electrical Line B 16.9 107.3 93 Fail: 95% Required 325 08-Jul-14 -2.0 Electrical Line B 15.8 109.9 96 Retest #324 326 08-Jul-14 -1.0 Electrical Line B 15.5 109.1 95 327 08-Jul-14 SG Electrical Line B 15.2 109.6 95 328 08-Jul-14 -2.0 Electrical Line B 15.7 109.3 95 329 08-Jul-14 -1.0 Electrical Line B 14.9 109.8 95 330 08-Jul-14 SG Electrical Line B 15.4 110.0 96 331 09-Jul-14 -3.0 Fire Line B 14.7 109.2 95 332 09-Jul-14 -1.5 Fire Line B 16.0 108.9 95 333 09-Jul-14 SG Fire Line B 15.1 110.4 96 334 09-Jul-14 -1.0 Water Line B 15.8 109.3 95 335 09-Jul-14 SG Water Line B 14.9 109.4 95 336 09-Jul-14 -1.0 Water Line B 15.6 109.2 95 337 09-Jul-14 SG Water Line B 15.3 110.6 96 338 09-Jul-14 -3.0 Water Line B 15.8 108.8 95 339 09-Jul-14 -2.0 Water Line B 11.8 107.1 93 Fail: 95% Required 340 09-Jul-14 -2.0 Water Line B 14.5 109.1 95 Retest #339 341 10-Jul-14 -1.0 Water Line B 15.5 108.7 95 342 10-Jul-14 SG Water Line B 15.9 109.5 95 343 10-Jul-14 -1.0 Water Line B 14.8 109.3 95 344 10-Jul-14 SG Water Line B 15.4 110.8 96 345 10-Jul-14 -3.0 Interior Water B 16.8 103.8 90 346 10-Jul-14 -1.0 Interior Water B 16.2 104.9 91 347 10-Jul-14 SG Interior Water B 15.7 108.7 95 348 15-Jul-14 -1.5 Electrical Line B 14.1 110.7 96 349 15-Jul-14 -1.5 Electrical Line B 13.2 106.0 92 Fail: 95% Required 350 15-Jul-14 -1.5 Electrical Line B 14.6 109.3 95 Retest #349 351 15-Jul-14 -1.5 Electrical Line B 15.1 110.5 96 352 15-Jul-14 -1.5 Electrical Line B 15.2 109.4 95 353 30-Jul-14 -2.0 Electrical Line A 15.7 111.3 96 354 30-Jul-14 SG Electrical Line A 16.0 110.9 95 355 30-Jul-14 -1.5 Electrical Line A 17.0 113.0 97 356 30-Jul-14 -1.0 Electrical Line A 17.2 110.4 95 14M110-6 Viasat Building 10 -- Carlsbad, California Page 6 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 357 30-Jul-14 SG Electrical Line A 15.9 112.6 97 358 30-Jul-14 SG Electrical Line A 15.5 111.2 95 359 31-Jul-14 -2.0 Electrical Line B 15.2 110.2 96 360 31-Jul-14 -1.0 Electrical Line B 15.0 109.7 95 361 31-Jul-14 -1.5 Electrical Line B 15.0 109.7 95 362 31-Jul-14 -3.0 Electrical Line B 15.2 110.0 96 363 31-Jul-14 -2.0 Electrical Line B 14.8 109.8 95 364 31-Jul-14 -1.0 Electrical Line B 15.1 109.6 95 365 01-Aug-14 -1.0 Electrical Line B 14.8 109.4 95 366 01-Aug-14 -3.0 Electrical Line B 15.2 110.1 96 367 01-Aug-14 -1.5 Electrical Line B 15.0 109.3 95 368 01-Aug-14 -2.0 Electrical Line B 15.3 110.4 96 369 01-Aug-14 -1.0 Electrical Line B 15.2 109.7 95 370 01-Aug-14 -0.5 Electrical Line B 14.7 109.2 95 371 19-Aug-14 -1.0 Electrical Line C 15.9 102.3 90 Fail: 95% Required 372 19-Aug-14 -1.0 Electrical Line C 14.8 108.2 95 Retest #371 373 19-Aug-14 -1.5 Electrical Line C 15.2 101.3 89 Fail: 95% Required 374 19-Aug-14 -1.5 Electrical Line C 15.0 108.5 95 Retest #373 375 19-Aug-14 -2.0 Electrical Line C 15.5 101.0 89 Fail: 95% Required 376 19-Aug-14 -2.0 Electrical Line C 14.5 109.2 96 Retest #375 377 19-Aug-14 -3.0 Electrical Line C 14.7 108.7 95 378 19-Aug-14 -2.0 Electrical Line C 14.1 109.1 96 379 21-Aug-14 -2.0 Electrical Line C 18.3 102.1 90 Fail: 95% Required 380 21-Aug-14 -2.0 Electrical Line C 14.5 108.3 95 Retest #379 381 21-Aug-14 -1.5 Electrical Line C 21.0 99.3 87 Fail: 95% Required 382 21-Aug-14 -1.5 Electrical Line C 13.7 108.5 95 Retest #381 383 21-Aug-14 -2.0 Electrical Line C 16.4 99.1 87 Fail: 95% Required 384 21-Aug-14 -2.0 Electrical Line C 15.0 108.2 95 Retest #383 385 22-Aug-14 -1.5 Electrical Line C 15.6 100.9 89 Fail: 95% Required 386 22-Aug-14 -1.5 Electrical Line C 15.1 108.4 95 Retest #385 387 22-Aug-14 -2.0 Electrical Line C 16.4 99.8 88 Fail: 95% Required 388 22-Aug-14 -2.0 Electrical Line C 15.8 108.2 95 Retest #387 389 22-Aug-14 -1.5 Electrical Line C 15.4 104.2 91 Fail: 95% Required 390 22-Aug-14 -1.5 Electrical Line C 15.0 108.7 95 Retest #389 391 22-Aug-14 -1.5 Electrical Line C 14.1 108.3 95 392 22-Aug-14 -1.0 Electrical Line C 14.0 108.6 95 393 18-Sep-14 316.0 Slope Fill A 14.4 101.3 87 Fail: 90% Required 394 18-Sep-14 317.0 Slope Fill A 15.1 98.6 85 Fail: 90% Required 14M110-6 Viasat Building 10 -- Carlsbad, California Page 7 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 395 18-Sep-14 312.5 Slope Fill B 14.2 107.2 93 396 18-Sep-14 311.0 Slope Fill A 14.7 108.3 93 397 18-Sep-14 311.0 Slope Fill A 15.4 108.8 93 398 18-Sep-14 315.0 Slope Fill A 16.1 105.1 90 Retest #393 399 18-Sep-14 315.5 Slope Fill B 14.8 107.2 93 Retest #394 400 18-Sep-14 316.0 Slope Fill B 14.2 104.4 91 401 18-Sep-14 317.0 Slope Fill A 16.2 107.8 93 402 18-Sep-14 318.0 Slope Fill B 14.3 104.8 91 403 18-Sep-14 317.5 Slope Fill A 16.2 105.6 91 404 18-Sep-14 -4.0 Electrical Line A 15.6 105.2 90 405 18-Sep-14 -4.0 Electrical Line A 15.4 106.3 91 406 18-Sep-14 -4.0 Electrical Line B 15.0 104.3 91 407 19-Sep-14 310.0 Slope Fill A 16.4 107.8 93 B.O.X. 408 19-Sep-14 317.5 Slope Fill B 14.5 104.3 91 B.O.X. 409 19-Sep-14 317.0 Slope Fill A 15.6 105.2 90 B.O.X. 410 19-Sep-14 315.0 Slope Fill A 16.1 106.1 91 B.O.X. 411 19-Sep-14 298.0 Slope Fill B 14.7 103.6 90 412 19-Sep-14 300.0 Slope Fill A 16.1 105.3 90 413 19-Sep-14 301.0 Slope Fill A 15.5 107.0 92 414 19-Sep-14 301.5 Slope Fill B 14.2 104.4 91 415 19-Sep-14 302.0 Slope Fill A 15.7 105.7 91 416 22-Sep-14 319.5 Slope Fill B 11.3 101.7 88 Fail: 90% Required 417 22-Sep-14 320.0 Slope Fill B 12.5 102.7 89 Fail: 90% Required 418 22-Sep-14 319.5 Slope Fill B 14.3 103.5 90 Retest #416 419 22-Sep-14 320.0 Slope Fill B 13.9 104.5 91 Retest #417 420 22-Sep-14 323.0 Slope Fill B 14.0 104.8 91 421 22-Sep-14 320.0 Slope Fill B 14.2 103.9 90 422 22-Sep-14 321.0 Slope Fill B 13.8 104.2 91 423 24-Sep-14 320.0 Slope Fill B 10.3 101.5 88 Fail: 90% Required 424 24-Sep-14 322.0 Slope Fill B 11.5 102.6 89 Fail: 90% Required 425 24-Sep-14 320.0 Slope Fill B 12.2 100.3 87 Fail: 90% Required 426 24-Sep-14 319.0 Slope Fill B 12.5 101.8 89 Fail: 90% Required 427 24-Sep-14 320.0 Slope Fill B 14.2 103.7 90 Retest #423 428 24-Sep-14 322.0 Slope Fill B 13.5 104.8 91 Retest #424 429 24-Sep-14 320.0 Slope Fill B 13.7 103.9 90 Retest #425 430 24-Sep-14 319.0 Slope Fill B 14.0 104.2 91 Retest #426 431 25-Sep-14 317.0 Slope Fill B 12.0 101.2 88 Fail: 90% Required 432 25-Sep-14 320.0 Slope Fill B 12.5 102.5 89 Fail: 90% Required 14M110-6 Viasat Building 10 -- Carlsbad, California Page 8 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 433 25-Sep-14 321.0 Slope Fill B 11.7 101.5 88 Fail: 90% Required 434 25-Sep-14 317.0 Slope Fill B 13.5 104.8 91 Retest #431 435 25-Sep-14 320.0 Slope Fill B 13.9 105.2 91 Retest #432 436 25-Sep-14 321.0 Slope Fill B 13.2 103.9 90 Retest #433 437 25-Sep-14 323.0 Slope Fill A 15.5 107.3 92 438 25-Sep-14 323.0 Slope Fill A 15.7 106.5 91 439 26-Sep-14 325.0 Slope Fill B 12.3 101.5 88 Fail: 90% Required 440 26-Sep-14 326.0 Slope Fill B 12.7 101.7 88 Fail: 90% Required 442 26-Sep-14 327.0 Slope Fill A 14.5 102.7 88 Fail: 90% Required 443 26-Sep-14 325.0 Slope Fill B 13.5 103.8 90 Retest #439 444 26-Sep-14 326.0 Slope Fill B 14.0 104.0 90 Retest #440 445 26-Sep-14 327.0 Slope Fill A 15.5 104.9 90 Retest #442 446 26-Sep-14 324.0 Slope Fill A 15.8 106.3 91 447 26-Sep-14 324.0 Slope Fill A 16.0 105.3 90 448 29-Sep-14 321.0 Slope Fill A 15.2 104.8 90 449 29-Sep-14 327.0 Slope Fill A 15.0 104.9 90 450 29-Sep-14 329.0 Slope Fill A 15.3 105.2 90 451 29-Sep-14 33.0 Slope Fill A 15.1 105.0 90 452 29-Sep-14 328.0 Slope Fill B 13.2 103.5 90 453 29-Sep-14 329.0 Slope Fill B 13.0 104.6 91 454 29-Sep-14 326.0 Slope Fill B 13.3 103.7 90 455 29-Sep-14 322.0 Slope Fill B 13.4 103.5 90 456 29-Sep-14 318.0 Slope Fill B 13.1 103.6 90 462 01-Oct-14 -0.5 Water Line D 16.1 112.3 95 463 13-Oct-14 SG Curb and Gutter Subgrade B 11.6 105.7 92 Fail: 95% Required 464 13-Oct-14 SG Curb and Gutter Subgrade B 17.1 107.1 93 Fail: 95% Required 465 13-Oct-14 SG Curb and Gutter Subgrade B 12.2 103.8 90 Fail: 95% Required 466 13-Oct-14 SG Pavement Subgrade B 16.4 110.6 96 467 13-Oct-14 SG Pavement Subgrade B 15.2 111.2 97 468 14-Oct-14 SG Curb and Gutter Subgrade B 15.6 111.1 97 Retest #463 469 14-Oct-14 SG Curb and Gutter Subgrade B 16.1 109.2 95 Retest #464 470 14-Oct-14 SG Curb and Gutter Subgrade B 15.8 110.1 96 Retest #465 471 14-Oct-14 SG Pavement Subgrade B 15.1 112.5 98 472 14-Oct-14 SG Pavement Subgrade B 16.7 110.3 96 473 15-Oct-14 SG Curb and Gutter Subgrade B 15.6 111.3 97 474 15-Oct-14 SG Curb and Gutter Subgrade B 17.1 109.1 95 475 15-Oct-14 SG Curb and Gutter Subgrade B 15.9 110.5 96 476 15-Oct-14 SG Curb and Gutter Subgrade B 15.4 110.8 96 14M110-6 Viasat Building 10 -- Carlsbad, California Page 9 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 477 15-Oct-14 SG Curb and Gutter Subgrade B 16.1 109.7 95 478 17-Oct-14 SG Pavement Subgrade B 16.2 108.9 95 479 17-Oct-14 SG Curb and Gutter Subgrade B 15.4 109.6 95 480 17-Oct-14 SG Curb and Gutter Subgrade A 17.4 110.4 95 481 17-Oct-14 SG Curb and Gutter Subgrade A 18.1 110.1 95 482 17-Oct-14 SG Curb and Gutter Subgrade A 17.8 111.2 95 483 17-Oct-14 BG Pavement Base G 15.6 111.5 91 Fail: 95% Required 484 17-Oct-14 BG Pavement Base G 11.9 115.8 95 485 20-Oct-14 SG Curb and Gutter Subgrade A 11.3 104.7 90 Fail: 95% Required 486 20-Oct-14 SG Curb and Gutter Subgrade A 11.8 103.8 89 Fail: 95% Required 487 20-Oct-14 SG Curb and Gutter Subgrade A 18.6 111.4 96 488 20-Oct-14 SG Curb and Gutter Subgrade A 18.3 110.8 95 489 20-Oct-14 SG Curb and Gutter Subgrade A 17.1 113.1 97 490 20-Oct-14 SG Curb and Gutter Subgrade A 17.5 111.2 95 491 20-Oct-14 SG Curb and Gutter Subgrade A 17.0 112.2 96 492 20-Oct-14 BG Pavement Base G 12.7 116.7 96 Retest #483 493 21-Oct-14 SG Curb and Gutter Subgrade A 17.5 111.7 96 Retest #485 494 21-Oct-14 SG Curb and Gutter Subgrade A 18.1 110.9 95 Retest #486 495 23-Oct-14 SG Pavement Subgrade A 17.6 110.9 95 496 23-Oct-14 SG Pavement Subgrade A 17.1 110.7 95 497 23-Oct-14 SG Curb and Gutter Subgrade A 17.9 111.5 96 498 23-Oct-14 306.0 Slope Fill A 17.3 106.8 92 499 23-Oct-14 309.0 Slope Fill A 16.8 105.7 91 500 28-Oct-14 SG Curb and Gutter Subgrade A 15.6 110.4 95 501 28-Oct-14 SG Curb and Gutter Subgrade A 15.1 108.2 93 Fail: 95% Required 502 28-Oct-14 SG Curb and Gutter Subgrade B 14.8 109.1 95 503 28-Oct-14 SG Curb and Gutter Subgrade A 16.2 110.1 95 504 28-Oct-14 SG Curb and Gutter Subgrade A 16.3 110.6 95 Retest #501 505 28-Oct-14 SG Curb and Gutter Subgrade A 14.5 109.1 94 Fail: 95% Required 506 29-Oct-14 SG Curb and Gutter Subgrade C 14.6 108.3 95 507 29-Oct-14 SG Curb and Gutter Subgrade B 14.2 109.6 95 508 29-Oct-14 SG Curb and Gutter Subgrade A 16.3 110.2 95 Retest #505 509 29-Oct-14 SG Curb and Gutter Subgrade A 15.5 111.3 96 510 29-Oct-14 SG Curb and Gutter Subgrade B 14.5 110.3 96 511 29-Oct-14 SG Curb and Gutter Subgrade B 14.7 109.1 95 588 13-Nov-14 -2.0 Electrical Line B 13.3 110.5 96 589 13-Nov-14 -1.0 Electrical Line B 13.2 109.4 95 590 13-Nov-14 -1.0 Electrical Line B 13.7 110.4 96 14M110-6 Viasat Building 10 -- Carlsbad, California Page 10 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 590A 20-Nov-14 SG Pavement Subgrade A 16.2 110.9 95 591 20-Nov-14 SG Pavement Subgrade A 16.3 110.8 95 592 20-Nov-14 BG Pavement Subgrade G 14.5 108.7 89 Fail: 95% Required 593 20-Nov-14 BG Pavement Subgrade G 11.2 116.2 95 594 20-Nov-14 BG Pavement Subgrade G 12.2 115.9 95 600 21-Nov-14 BG Pavement Subgrade G 11.0 116.3 95 Retest #592 601 21-Nov-14 -2.0 Electrical Line A 15.5 110.9 95 602 21-Nov-14 -2.0 Electrical Line B 14.0 109.3 95 603 21-Nov-14 -1.0 Electrical Line A 15.7 111.0 95 604 21-Nov-14 SG Electrical Line B 14.2 109.7 95 612 24-Nov-14 SG Pavement Subgrade D 14.2 112.2 95 613 24-Nov-14 SG Pavement Subgrade D 14.7 112.5 95 614 24-Nov-14 SG Pavement Subgrade D 13.9 112.3 95 615 24-Nov-14 SG Pavement Subgrade D 14.2 112.7 96 620 25-Nov-14 SG Pavement Subgrade D 14.9 112.3 95 621 25-Nov-14 SG Pavement Subgrade D 14.5 112.5 95 622 25-Nov-14 SG Pavement Subgrade D 14.2 113.3 96 623 25-Nov-14 SG Pavement Subgrade D 14.5 113.9 97 624 25-Nov-14 SG Pavement Subgrade A 15.7 111.9 96 625 25-Nov-14 SG Pavement Subgrade A 16.0 111.0 95 626 25-Nov-14 SG Pavement Subgrade A 15.9 111.3 96 627 25-Nov-14 SG Pavement Subgrade A 16.3 112.3 96 628 25-Nov-14 SG Pavement Subgrade B 14.2 109.3 95 629 25-Nov-14 SG Pavement Subgrade B 14.0 110.0 96 630 08-Dec-14 BG Pavement Base I 11.3 117.1 95 631 08-Dec-14 BG Pavement Base I 10.9 117.2 95 632 08-Dec-14 BG Pavement Base I 10.8 117.5 95 633 08-Dec-14 BG Pavement Base I 11.2 117.5 95 634 08-Dec-14 BG Pavement Base I 11.4 120.1 97 635 08-Dec-14 BG Pavement Base I 11.0 117.6 95 636 08-Dec-14 BG Pavement Base I 11.3 118.4 96 637 08-Dec-14 BG Pavement Base I 11.1 118.8 96 638 09-Dec-14 BG Pavement Base I 10.7 120.2 97 639 09-Dec-14 BG Pavement Base I 11.0 117.8 95 640 09-Dec-14 BG Pavement Base I 11.3 119.4 97 641 09-Dec-14 BG Pavement Base I 11.0 118.1 96 642 09-Dec-14 BG Pavement Base I 10.6 118.7 96 643 09-Dec-14 BG Pavement Base I 10.7 117.9 95 14M110-6 Viasat Building 10 -- Carlsbad, California Page 11 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 644 10-Dec-14 AC Pavement Asphalt J N/A 138.5 96 645 10-Dec-14 AC Pavement Asphalt J N/A 137.4 95 646 10-Dec-14 AC Pavement Asphalt J N/A 137.1 95 647 10-Dec-14 AC Pavement Asphalt J N/A 138.1 96 648 10-Dec-14 AC Pavement Asphalt J N/A 136.3 95 649 10-Dec-14 AC Pavement Asphalt J N/A 136.9 95 650 10-Dec-14 AC Pavement Asphalt J N/A 136.5 95 651 10-Dec-14 AC Pavement Asphalt J N/A 137.9 96 652 11-Dec-14 AC Pavement Asphalt J N/A 137.1 95 653 11-Dec-14 AC Pavement Asphalt J N/A 136.6 95 654 11-Dec-14 AC Pavement Asphalt J N/A 138.2 96 655 11-Dec-14 AC Pavement Asphalt J N/A 137.5 95 656 11-Dec-14 AC Pavement Asphalt J N/A 137.2 95 657 11-Dec-14 AC Pavement Asphalt J N/A 137.7 96 658 11-Dec-14 AC Pavement Asphalt J N/A 138.3 96 659 11-Dec-14 AC Pavement Asphalt J N/A 136.2 95 661 11-Dec-14 SG Pavement Subgrade B 16.1 109.3 95 662 15-Jan-15 SG Pavement Subgrade A 17.1 110.5 95 663 15-Jan-15 SG Pavement Subgrade A 17.4 111.8 96 664 15-Jan-15 BG Pavement Base I 10.8 117.2 95 665 15-Jan-15 BG Pavement Base I 10.4 118.5 96 666 15-Jan-15 BG Pavement Base I 9.1 114.9 93 Fail: 95% Required 667 15-Jan-15 BG Pavement Base I 10.7 117.5 95 Retest #666 668 15-Jan-15 BG Pavement Base I 10.5 117.9 95 669 15-Jan-15 BG Pavement Base I 10.1 117.1 95 670 15-Jan-15 BG Pavement Base I 9.7 118.2 96 671 15-Jan-15 BG Pavement Base I 10.8 118.8 96 687 22-Jan-15 AC Pavement Asphalt J N/A 139.0 97 688 22-Jan-15 AC Pavement Asphalt J N/A 137.5 95 689 22-Jan-15 AC Pavement Asphalt J N/A 138.3 96 690 22-Jan-15 AC Pavement Asphalt J N/A 137.8 96 691 22-Jan-15 AC Pavement Asphalt J N/A 138.7 96 692 22-Jan-15 AC Pavement Asphalt J N/A 138.0 96 697 28-Jan-15 SG Slope Fill B 13.9 103.6 90 698 28-Jan-15 SG Slope Fill B 14.3 104.2 91 699 28-Jan-15 SG Slope Fill B 14.4 103.9 90 700 28-Jan-15 SG Slope Fill B 13.7 103.8 90 725 13-Feb-15 SG Sidewalk Subgrade B 13.2 109.2 95 14M110-6 Viasat Building 10 -- Carlsbad, California Page 12 TABLE 1 SUMMARY OF FIELD DENSITY TESTS Test No. Date Elev.Test Soil Moisture Dry Density Relative (ft)Location Type Content (pcf) Compaction (%)(%) 726 13-Feb-15 SG Sidewalk Subgrade B 14.3 109.3 95 727 13-Feb-15 SG Sidewalk Subgrade B 14.3 109.4 95 728 13-Feb-15 SG Sidewalk Subgrade B 13.9 109.3 95 729 13-Feb-15 SG Sidewalk Subgrade B 14.2 109.4 95 NOTES: Elevations Referenced To Grade Stakes Set In Field By Others Negative Elevations Reference to SG SG = Finished Subgrade Elevation BG = Base Grade AC = Finished Surface Asphaltic Concrete B.O.X. = Bottom of Overexcavation Retests Performed After Recompaction All Tests Performed by Nuclear Method (ASTM D-6938) 14M110-6 Viasat Building 10 -- Carlsbad, California Page 13 TABLE 2 SUMMARY OF MOISTURE-DENSITY RELATIONSHIPS Soil Type Soil Description Maximum Dry Density (pcf) Optimum Moisture (%) A Yellow Brown Silty Clay, trace fine Sand 116.5 15 B Yellow Brown fine Sand, little silt 115 13 C Light Gray Brown silty fine Sand 114 13.5 D Yellow Brown fine Sandy Silt, trace Clay 118 13.5 E Crushed Aggregate Base 137.5 7.5 F 3/4" Asphaltic Concrete 146 N/A G Crushed Miscellaneous Base 122 10.5 H Light Brown fine Sandy Clay to Clayey fine Sand, trace Silt, trace Gravel 121 11.5 I Crushed Miscellaneous Base 123.5 8.5 J 1/2" Asphaltic Concrete 144 N/A K Gray Brown Clayey fine to coarse Sand, some fine Gravel 129 8.5 L 1/2" Asphaltic Concrete 142 N/A Notes: All Moisture-Density Relationships determined per ASTM D-1557 (Modified Proctor) 14M110-6 Viasat Building 10 -- Carlsbad, California Page 14