HomeMy WebLinkAboutCDP 2020-0044; GIBSON FAMILY RESIDENCE; GEOTECHNICAL GRADING PLAN REVIEW; 2021-03-15~ VINIE & MIDDLETON ENGINEERING, INC.
Ref Job #20-178-P
March 15, 2021
Mr. Curt Gibson
7089 Leeward Street
Carlsbad, CA 92011
2450 Auto P.1rk War
Escondido, California 92029-1229
Phone (760) 743-1214
Fax (760) 739-0343
GEOTECHNICAL GRADING PLAN REVIEW, PROPOSED RESIDENTIAL
DEVELOPMENT, SOUTHWEST CORNER OF PARK DRIVE AND HILLSIDE DRIVE,
CARLSBAD, CALIFORNIA (APN 156-160-15)
The referenced property consists of a vacant lot previously studied by this office in regards
to geotechnical and geologic conditions in support of a single-family residential
development. Our findings, conclusions and development recommendations were provided
in the following technical report:
"Geotechnical Investigation, Proposed Residential Development, Southwest Comer of
Hillside Drive and Park Drive, Carlsbad, California," V & M Job #20-178-P, report dated
August 18, 2020
The preceding report was reviewed in connection with this grading plan review and is on
file with our office. We have received the most recent project Precise Grading Plans,
prepared by bHA Engineering, lnc.(6 sheets -received by email February 2021. A copy of
the grading plan has been reproduced as a Geotechnical Map attached as Plate 1. A
Geologic Cross Section based on the grading plan and our test pits is included as Plate 2.
Based on our review of the Grading Plans, which are substantially similar to the plans
utilized in our Geotechnical Investigation report, they largely represent a feasible design
from a geotechnical engineering viewpoint and are in substantial compliance with the
referenced report.
The following comments should be considered, where appropriate and applicable:
• The referenced report and this review letter should be considered a part of the
project Grading Plans.
• All excavations, grading, earthwork, construction and bearing soil preparation
should be completed in accordance with Chapter 18 (Soils and Foundations) and
Appendix "J" (Grading) of the 2019 California Building Code (CBC), the Standard
Specifications for Public Works Construction, City of Carlsbad Grading Ordinances,
the requirements of the governing agencies, the referenced report and this review
letter.
Mr. Curt Gibson
March 15, 2021
Page2
All grading and bearing soil conditioning should be conducted under the observation
and testing by the project geotechnical engineer. The final building pad and
foundation construction should be inspected, tested as necessary and approved by
the project geotechnical engineer. Geotechnical engineering construction
inspections and test results should be presented in written field and final as-
constructed geotechnical reports. All recommendations should be further field-
verified, confirmed or revised if necessary at that time, based on actual as-graded
soil properties. A Final As-Graded Report should then be issued outlining the
remedial grading and bearing soil preparation activities, test results and confirm (or
revise) foundation and pavement recommendations.
• Compaction procedures remain as outlined in the referenced reports, except where
superceded herein. All recommendations should be further field-verified, confirmed
or revised if necessary at that time.
Based on the project arborists recommendations for protecting the existing Torrey
Pine, there is a 25-foot offset from the trunk of the tree in which no excavations or
undercutting can be done. Outer edges of this offset are adjacent to the retaining
wall associated with the BMP basin, within 1-foot of planned pool/jacuzzi
improvements, and approximately 2 feet from a portion of the planned dwelling.
Removals for surficial compressible soil is anticipated to be on the order of 5 feet
minimum below existing surfaces. With the recommended removals and planned
finish grades, this will equate to approximately 11 to 12 feet of fill (supported on
approved Old Paralic deposits) beneath the planned structure and improvements
adjacent to 6 feet of fill supported on 5 feet of potentially compressible soil. The
Allen Block Wall planned to circumvent the Torrey Pine, and support the toe of a fill
slope ascending to the building pad, will also be supported on potentially
compressible soil. In order to mitigate and minimize the amount of potential surficial
soil consolidation the following recommendations are provided for fill placement and
grading within the 25-foot Torrey Pine offset:
A layer of Tensar BX-1200 geogrid should be placed over the areas of natural
existing ground within the recommended 25-foot offset and overlap a minimum of
5 feet outside of the offset along the building/improvement pad side. An additional
layer of geogrid should be placed after 2 feet of fill in the building pad and pad fill
slope area of the offset (schematically shown on Plate 2).
All fill placed within the 25-foot offset circle within the fill slope/building pad side
should be compacted to a minimum of 95% of its corresponding maximum dry
density. Elsewhere, 90% minimum compaction will be required.
V1NJI: & MmDLldON ENGINl.b!UNG, I Ne • 2450 Auto Park War• Escondido, Gilifornia 92029-1229 • Phone (760) 743-1214
Mr. Curt Gibson
March 15, 2021
Page3
All preliminary foundation and slab-on-grade recommendations, as well as soil design
parameters and seismic ground motion values, will remain the same as specified in the
referenced Geotechnical Investigation report dated August 18, 2020. Final foundation
and slab-on-grade recommendations will be provided in the As-Graded Compaction
Report (issued after completion of grading) and will be based upon the characteristics
of the imported soil required to complete grading and achieve design grades.
Additional foundation/construction recommendations for structures and improvements
within the influence of the Torrey Pine 25-foot offset may also be warranted and
provided in the As-Graded Report.
A minimum of 2% gradient should be maintained away from all foundations. Roof
gutters and downspouts should be installed with all discharge water from the
downspouts directed away from the foundations and slab to a suitable location. Area
drains should be installed in the yards to collect surface water.
Planter areas adjacent to foundations should be provided with water proofing, using an
impermeable liner against the footings, if determined appropriate.
It should be noted that shallow groundwater conditions may still develop in areas where
no such conditions existed prior to site development. This can be contributed to by
substantial increases of surface water infiltration resulting from landscape irrigation,
which was not present before the development of the site. It is almost impossible to
absolutely prevent the possibility of shallow groundwater on the entire site. Therefore,
we recommend that shallow groundwater conditions be remedied if and when they
develop.
The property owner should be made aware that altering drainage patterns, landscaping,
the addition of patios, planters, and other improvements, as well as over irrigation and
variations in seasonal rainfall, all affect subsurface moisture conditions, which in tum
affect structural performance.
VtN/1: & MmDttl ON ENulNU.IUNu, IN<.:. • 2450 Auto Park Way• Escondido, California 92029-1229 • Phone (760) 743-1214
Mr. Curt Gibson
March 15, 2021
Page4
LIMITATIONS This geotechnical plan review is not a "Plan Check Review'' and does not
relieve the responsibility of the project design consultant(s) and contractor(s) to get
completely familiarized with the requirements of the project soil report(s) and fully
incorporate their recommendations into the project design, plans and construction work,
where appropriate and as applicable. Our review, corrections, and comments are for
general geotechnical conformance of the project plans with the intent of the project soil
report and design recommendations. Review of structural and civil engineering
calculations, architectural intent, structural and civil engineering design modeling and basis,
verification of setback requirements, easements, and right-of-ways, as well as code, city,
and county compliance are beyond geotechnical engineering services. It is the owner's
or his (her) representative's responsibility to provide copies of all pertinent soil report(s),
updates, addendum letters and plan review letters to respective design consultant(s),
general contractor and his (her) subcontractor(s) for full compliance.
This opportunity to be of service again is sincerely appreciated. If you have any questions
or need clarification, please do not hesitate to contact the undersigned. Reference to our
Job #20-178-P will help to expedite our response to your inquiries.
VINJE & MIDDLETON ENGINEER! G, INC.
Ste
CEG #2362
V1NJE & MmDI 1:·10N ENGINFrRING, ]Ne.• 2450 Auto Park Way• Escondido, Califorma 92029-1229 • Phone (760) 743-1214