Loading...
HomeMy WebLinkAboutPD 2020-0034; HARBOR POINTE SLOPE REPAIR; FINAL SOILS REPORT; 2021-06-24 As-Built Soils/Compaction Report Harbor Pointe HOA Slope Restoration below 6887 and 6899 Watercourse Drive Project No. PD 2020-0034, Drawing No. 526-9A Carlsbad, California prepared for: Harbor Pointe HOA c/o Ms. Joanne Diaz Curtis Management Company 5050 Avenida Encinas, Suite 160 Carlsbad, CA 92008 by: TerraPacific Consultants, Inc. 4010 Morena Boulevard, Suite 108 San Diego, CA 92117 June 24, 2021 File No. 20-065.1 4010 Morena Boulevard, Suite 108 • San Diego, CA 92117 • (858) 521-1190 • (858) 521-1199 fax • terrapac.net Harbor Pointe HOA June 24, 2021 c/o Ms. Joanne Diaz File No. 20-065.1 Curtis Management Company 5050 Avenida Encinas, Suite 160 Carlsbad, CA 92008 Subject: As-Built Soils/Compaction Report Harbor Pointe HOA Slope Restoration below 6887 and 6899 Watercourse Drive Project No. PD 2020-0034, Drawing No. 526-9A Carlsbad, California Dear Ms. Diaz: TerraPacific Consultants, Inc. (TCI) has completed field observation and testing services for the subject slope restoration. These services included inspection of the keyway and back cuts, observation of geogrid reinforcing layers, compaction testing of engineered fill, and review of the subsurface drainage facilities within the restoration area. Based on our observations and testing, it is our opinion that the geotechnical aspects of the slope restoration have been completed in general conformance with the recommendations provided in our referenced report and the approved plans. Further discussion regarding our site observations, compaction test results, and recommendations are presented in the accompanying report. We appreciate the opportunity to be of service. If you should have any questions, please do not hesitate to contact the undersigned. Sincerely, TerraPacific Consultants, Inc. Dylan J. Thomas, PG 9857 Matthew H. Marquez, PE 70072 Associate Geologist Senior Engineer Distribution: Ms. Joanne Diaz – Curtis Management Co. Mr. Mike Bailey – City of Carlsbad Mr. Brian Saltzman – TSAC Engineering TABLE OF CONTENTS 1.0 INTRODUCTION ............................................................................................................. 1 1.1 Purpose and Scope ............................................................................................ 1 1.2 Site Description .................................................................................................. 1 2.0 GRADING AND COMPACTION ..................................................................................... 2 2.1 General Procedure ............................................................................................. 2 2.2 Site Preparation.................................................................................................. 2 2.3 Slope Keyway ..................................................................................................... 2 2.4 Keyway Drain System ........................................................................................ 3 2.5 Slope Reconstruction ......................................................................................... 3 2.6 Compaction Tests .............................................................................................. 4 2.7 Laboratory Testing ............................................................................................. 4 3.0 CONCLUSIONS AND RECOMMENDATIONS ............................................................... 4 3.1 Conclusions ........................................................................................................ 4 3.2 Planting and Maintenance ................................................................................. 4 4.0 CLOSURE ....................................................................................................................... 5 4.1 Limitations .......................................................................................................... 5 APPENDICES: Appendix A – Figures Appendix B – Results of Field Density Tests Appendix C – Laboratory Testing Results Harbor Pointe Slope Restoration • 6887 & 6899 Watercourse Drive • File No. 20-065.1 • June 24, 2021 - 1 - 1.0 INTRODUCTION 1.1 Purpose and Scope The purpose of this report is to describe our site observations and present the results of compaction testing during the restoration/earthwork activities for the subject slope, which experienced a surficial failure in April 2020. The restoration, as described in this report, was conducted to reconstruct the slope to the pre-failure configuration approved by the City of Carlsbad. The scope of our work included research of geologic/geo-hazard maps pertinent to the site, review of original development documents available from the City of Carlsbad, on- and off- site meetings, field observations and compaction testing, laboratory analysis of the fill materials, engineering/geologic evaluation, and preparation of this report. 1.2 Site Description The surficial failure area is located behind 6887 to 6899 Watercourse Drive on a west-facing, descending slope situated north of Harbor Point Road. The approximate location of the site is presented on the attached Site Location Map, Figure 1 in Appendix A. From the top, along the rear property lines of Lots 49 through 52, the slope descends a maximum of approximately 35 feet at 2:1 (horizontal: vertical) inclination to the rear property lines of the homes along the toe of slope on Shearwaters Drive (Lots 53 through 55). The surficial failure consisted of two well-defined scarps generally located between the midpoint and top of the slope with associated debris and tension cracks. The larger of the two scarps was located below 6895 Watercourse Drive and roughly measured 30 feet wide by 16 feet long by 1.5-to 2.5 feet deep. The smaller scarp was below 6899 Watercourse Drive and was approximately 10 feet wide by 6 feet wide by 1.5 feet deep. Soil/debris from the failure flowed into the backyards of 6892 and 6896 Shearwaters Drive. The restored failure area also included tension cracks that developed north of the scarps on the slope below the southern portion of 6887 Watercourse Drive and most of 6891 Watercourse Drive. The tension cracks were indicators of impending surficial failure and were generally aligned with the defined head scarps located to the south. Development documents related to the earthwork indicate the lots were graded in the mid- 1980s. Based on the grading plans and the subsurface investigation described in our referenced report dated May 29, 2020, the subject slope is entirely composed of engineered fill. The originally planned grading configuration of the slope was to be engineered fill over cut soil/native bedrock. However, due to seepage conditions reportedly occurring at the bedrock contact during grading, the lower portion of the slope was over-excavated. It replaced as stability fill equipped with a subdrain system, which reportedly discharges near Shearwaters Drive and Bluewater Road. Harbor Pointe Slope Restoration • 6887 & 6899 Watercourse Drive • File No. 20-065.1 • June 24, 2021 - 2 - 2.0 GRADING AND COMPACTION 2.1 General Procedure In general, the slope restoration earthwork consisted of removing vegetation, failure debris, and loose soil, followed by the placement of compacted fill to reconstruct the slope. Removals were made to expose and bench into competent engineered fill with a keyway at the base of the restoration area. Reinforcing geogrid was placed within the engineered fill mass to provide additional stability for the restored slope area. Drainage facilities consisting of a subdrain located at the heel of the keyway and a series of vertical chimney drains along the back cut of the engineered fill mass were also constructed. Groundforce performed earthwork activities and related soil compaction for the slope restoration. Observation and testing during grading operations, as described in this report, were conducted between April 20, 2021, and May 21, 2021. A representative from our office observed removals benching and fill placement operations, including performing field density tests, observation of the drainage facilities constructed, review placement of the geo-grid reinforcement, and inspection of the keyway. Descriptions of the soil materials encountered, grading procedures, and compaction test results are further described in the following sections. 2.2 Site Preparation Prior to placement of the new engineered fill, removals into competent fill soils were performed at the surficial failure area. The removals were conducted near the mid-slope at the base of the failure area. Removal operations continued as the restoration progressed up the slope, which included benching into competent engineered fill. The engineered fill encountered and primarily utilized for fill consisted of reddish-brown clayey sand. The approximate limits of the slope restoration area are presented on the attached Geotechnical Plan, Figure 2 in Appendix A. 2.3 Slope Keyway A keyway for the new engineered fill was excavated into competent existing fill material at the base of the restoration area. The dimensions of the keyway are approximately 8.5 feet wide by 120 feet long. The keyway bottom was inclined at a minimum of 2 percent into the slope. Prior to placement of compacted fill, the exposed surface was scarified, moisture- conditioned to optimum moisture content or slightly above, and compacted in-place to a minimum of 90 percent of the laboratory maximum dry density (ASTM D-1557). The approximate keyway location is shown in Figure 2 in Appendix A. Harbor Pointe Slope Restoration • 6887 & 6899 Watercourse Drive • File No. 20-065.1 • June 24, 2021 - 3 - 2.4 Keyway Drain System A heel drain that consists of a 4-inch diameter perforated pipe surrounded by 3/4-inch gravel and wrapped in filter fabric was installed at the back of the keyway. The heel drain was constructed with high points at the north and south ends with flow toward the center at a minimum 1 percent gradient. The subdrain outlet is located near the toe of the slope and consists of a perforated spreader pipe. In addition to the heel drain, a series of geo-composite chimney drains were installed vertically up the back of the restoration area to help collect potential groundwater seepage that may develop and migrate toward the back of the recompacted fill mass during periods of prolonged rainfall/saturated conditions. The approximate heel drain, outlet pipe, and chimney drains locations are shown on the Geotechnical Plan, Figure 2 in Appendix A. 2.5 Slope Reconstruction Once the slope keyway was constructed, and the heel drain was installed, fill was placed and compacted from the bottom up. The earth materials utilized for compacted fill generally consisted of the existing fill materials encountered during excavation of the site. Processed existing fill material utilized for the slope restoration was previously tested to verify the minimum shear strength requirements specified. Prior to fill placement and compaction, the soil material was moisture-conditioned and blended as needed, placed in loose lifts approximately 6 to 8 inches in thickness, and mechanically compacted with the remote-controlled vibratory sheep foot compactor, ride- along vibratory sheep foot compactor, and/or mechanical tamper to at least 90 percent relative compaction per the maximum dry density value determined in accordance with the ASTM D- 1557 test method (see Section 2.6 of this report). Each succeeding fill lift was treated similarly. As the fill was brought up, the slope backcut was benched into competent fill, and geogrid reinforcement layers were placed within the fill mass at an approximate vertical spacing of 24 inches. The type of geogrid reinforcement used was Tencate Miragrid 3XT. Upon completion of fill placement, the slope face within the repair area was trimmed back with a Komatsu excavator, wheeled with the compaction wheel, and further compacted by track walking. Harbor Pointe Slope Restoration • 6887 & 6899 Watercourse Drive • File No. 20-065.1 • June 24, 2021 - 4 - 2.6 Compaction Tests Based upon our testing and observations, the fill placed for the subject repair was compacted to a minimum of 90 percent of the laboratory maximum dry density (ASTM D-1557), as required. Compaction testing was conducted utilizing the sand cone test method (ASTM D- 1556) and Campbell Pacific Nuclear Test Gauges (ASTM D-2922 and D-3017). The compacted fill was tested periodically as construction progressed. Testing was conducted at approximately 12-inch to 24-inch vertical intervals. In general, the testing indicates the fill construction met the minimum compaction standards required for the project. The results of our field density tests are tabulated in Table 1 in Appendix B. Approximate locations of the tests are indicated on the Geotechnical Plan, Figure 2 in Appendix A. The test locations and elevations are approximate, based on our interpretation of the available plans. It should be mentioned that the compaction test results are considered to be representative of the conditions where the test was performed. Compaction levels beyond the locations tested may vary. 2.7 Laboratory Testing Supplemental laboratory tests were performed to support the construction monitoring and provide a basis for our evaluation of compacted fill. The laboratory program included determining the maximum dry density and optimum moisture content of soils utilized as fill. The testing was performed in accordance with the ASTM D-1557 test procedure (modified Proctor). All testing phases were conducted in general accordance with applicable ASTM specifications and/or other accepted test methods. A summary of the laboratory test results are available in Appendix C. 3.0 CONCLUSIONS AND RECOMMENDATIONS 3.1 Conclusions Based on our observation and testing results, it is our opinion that the described earthwork has been completed in general conformance with the recommendations contained in our May 29, 2020 report, the referenced plans, and the intentions of this office. If required, a formal survey of the repair area may be completed by others to prepare the as-built grading plan. 3.2 Planting and Maintenance The subject slope area is considered surficially and grossly stable and anticipated to remain so under normal conditions, provided that erosion control measures are implemented as soon as possible, i.e., erosion control mat, planting, etc. It is recommended that deep- rooting, drought-tolerant trees, shrubs, and ground cover be used. Harbor Pointe Slope Restoration • 6887 & 6899 Watercourse Drive • File No. 20-065.1 • June 24, 2021 - 5 - Some routine maintenance should be anticipated during the life of this project. This should include maintaining grades, particularly along the top of the slope, so that water runoff is not directed toward the slope. The responsible party should consider improving the surface drainage conditions along the rear property line of Lot 53 (6896 Shearwaters Drive), e.g., install additional surface drainage facilities and/or a short retaining wall with a freeboard to direct water around the lot as the original design of the project intended. Disturbed grades due to burrowing animal activity or the uncontrolled action of water should be restored as soon as possible to avoid channeling concentrated water into the slope. Additionally, regular maintenance of the site drainage and irrigation systems for the slope should be conducted to avoid any leakage due to disrepair. Adjust irrigation schedules as needed seasonally with climatic conditions to prevent excessive drying or wetting of slope. 4.0 CLOSURE 4.1 Limitations It is our opinion, within the scope of work defined for us by our client, that we have exercised a degree of care which equals or exceeds that presently maintained by other professionals in the field of geotechnical engineering and engineering geology; and, to the best of our ability, have performed sufficient observations and testing to provide a rational basis for our opinion that grading at this site was performed in general accordance with the recommendations and provisions of the project specifications. No warranties are expressed nor implied. In reviewing the data, opinions, conclusions, and recommendations presented in this report, it should be recognized that our services do not constitute a guarantee that the grading contractor has performed his work in strict accordance with the recommendations and/or specifications. In addition, no representations are made as to the quality or extent of materials not observed by us, for any subsequent change to this site, or the failure of others to properly repair damages by the uncontrolled actions of water. * * * TerraPacific Consultants, Inc. * * * APPENDIX A Figures SITE LOCATION SITE LOCATION 5 5 5 78 Paseo Del NortePaseo Del NorteCarlsba rd B lvd Poinsettia Lane Carlsbad REFERENCE: Google Maps NSite Location Plan Figure 1 LOCATION:6887-6899 Watercourse Drive Carlsbad, CA 4010 Morena BoulevardSuite 108San Diego CA 92117858-521-1190 Harbor Pointe File No. 20-065.1 June 2021 WATERCOURSE DRIVESHEARWATERS DRIVET-3 T-4 T-1 T-2 P-104.2 P-104.0 P-136.2 P-137.8 6895 (LOT 52) 6891 (LOT 51) 6887 (LOT 50) 6892 (LOT 55) 6888 (LOT 56) A ' (Qop2-4)Qcf (Td)Qls/Qcf Approximate location of slope restoration. Approximate location of keyway for slope restoration Tightline subdrain to spreader pipe discharge Approximate location of subdrain system for slope restoration Approximate location of drainage panels along back cut Approximate location of compaction test LEGEND 0 2010 APPROX. SCALE IN FEET KEYWAY N27 REFERENCE:Grading Plan for Harbor Pointe Slope Repair,Sheet 2, prepared by TSAC Engineering Geotechnical Plan4010 Morena BoulevardSuite 108San Diego CA 92117858-521-1190 Figure 2Harbor Pointe Construction File No. 20-065.1June 2021 28 18 3131R 2323R 32 29 5 7 82 4 1 6 35 21 30 20 3 13 15 10 11 17 19 27 33 12 149 34 24 26 25 22 32R APPENDIX B Table Field Density (PCF) Field Moisture (%) Max. Dry Density (lbs/cu. ft.) Opt. Moisture (%) Relative Compaction (%) Pass/Fail 1 4/21/2021 118.0 117.2 9.4 A 127.5 9.5 92%Pass 2 4/21/2021 118.0 115.0 9.8 A 127.5 9.5 90%Pass 3 4/22/2021 120.0 116.8 9.6 A 127.5 9.5 92%Pass 4 4/22/2021 120.0 115.5 10.4 A 127.5 9.5 91%Pass 5 4/26/2021 122.0 114.6 9.8 A 127.5 9.5 90%Pass 6 4/26/2021 122.0 115.1 10.7 A 127.5 9.5 90%Pass 7 4/27/2021 124.0 115.0 9.9 A 127.5 9.5 90%Pass 8 4/27/2021 124.0 115.6 10.5 A 127.5 9.5 91%Pass 9 4/29/2021 118.0 116.4 9.7 A 127.5 9.5 91%Pass 10 4/29/2021 118.0 115.8 9.6 A 127.5 9.5 91%Pass 11 5/3/2021 120.0 118.6 9.7 A 127.5 9.5 93%Pass 12 5/3/2021 120.0 119.3 10.2 A 127.5 9.5 94%Pass 13 5/3/2021 120.0 115.2 9.6 A 127.5 9.5 90%Pass 14 5/4/2021 122.0 114.8 9.5 A 127.5 9.5 90%Pass 15 5/4/2021 122.0 115.4 9.7 A 127.5 9.5 91%Pass 16 5/4/2021 122.0 114.5 9.9 A 127.5 9.5 90%Pass 17 5/5/2021 124.0 117.0 10.3 A 127.5 9.5 92%Pass 18 5/5/2021 124.0 114.9 9.8 A 127.5 9.5 90%Pass 19 5/10/2021 126.0 114.7 9.2 A 127.5 9.5 90%Pass 20 5/10/2021 126.0 115.6 9.5 A 127.5 9.5 91%Pass 21 5/10/2021 126.0 115.1 9.8 A 127.5 9.5 90%Pass 22 5/10/2021 110.0 115.2 10.2 A 127.5 9.5 90%Pass 23 5/10/2021 112.0 113.4 10.1 A 127.5 9.5 89%Fail 23R 5/10/2021 112.0 114.8 9.7 A 127.5 9.5 90%Pass 24 5/11/2021 114.0 115.5 10.3 A 127.5 9.5 91%Pass 25 5/11/2021 113.0 114.9 10.6 A 127.5 9.5 90%Pass 26 5/12/2021 116.0 115.2 10.2 A 127.5 9.5 90%Pass 27 5/12/2021 128.0 111.8 11.0 Import A 122.0 10.5 92%Pass 28 5/12/2021 128.0 112.3 11.6 Import A 122.0 10.5 92%Pass 29 5/12/2021 128.0 110.4 11.2 Import A 122.0 10.5 90%Pass 30 5/12/2021 128.0 110.1 10.5 Import A 122.0 10.5 90%Pass 31 5/19/2021 130.0 109.0 11.3 Import A 122.0 10.5 89%Fail 31R 5/21/2021 130.0 110.3 10.7 Import A 122.0 10.5 90%Pass 32 5/19/2021 130.0 104.7 11.5 Import A 122.0 10.5 86%Fail 32R 5/21/2021 130.0 110.7 11.2 Import A 122.0 10.5 91%Pass 33SL 5/21/2021 124.0 117.8 9.6 A 127.5 9.5 92%Pass 34SL 5/21/2021 122.0 119.0 9.3 A 127.5 9.5 93%Pass 35SL 5/21/2021 128.0 120.2 9.0 A 127.5 9.5 94%Pass I.D. R SL Max A Import A 122.0 pcf @ 10.5 Re-test 127.5 pcf @ 9.5 Legend Slope Test ASTMD-1557 Results Table 1 Results of Field Compaction Tests Harbor Pointe Slope Repair FN 20-065.1 Test No.Date Tested Elevation (ft.) ASTM D-6938 / D-1556 Soil Type APPENDIX C Laboratory Test Results Project Name:Harbor Pointe Project No. :20-065.1 Boring No.:Import Technician:JMS Date:5/11/2021 Visual Sample Description: Light Brown Silty Sand X Manual Ram Ram Weight 10 LBS Drop 18 inches TEST NO.1 2 3 4 5 6 A Wt. Comp. Soil + Mold (gm.)3736.00 3821.00 3857.00 3810.00 B Wt. of Mold (gm.)1794.00 1794.00 1794.00 1794.00 C Net Wt. of Soil (gm.)A - B 1942.00 2027.00 2063.00 2016.00 D Wet Wt. of Soil + Cont. (gm.)1848.5 1760.9 1804.8 1774.5 E Dry Wt. of Soil + Cont. (gm.)1724.7 1626.4 1643.9 1603.5 F Wt. of Container (gm.)302.7 241.8 298.9 301.2 G Moisture Content (%)[(D-F)-(E-F)]/(E- F)8.7 9.7 12.0 13.1 H Wet Density (pcf)C*29.76 /453.6 127.4 133.0 135.4 132.3 I Dry Density (pcf)H/(1+G/100)117.2 121.2 120.9 116.9 Maximum Dry Density (pcf)122.0 10.5 PROCEDURE USED Procedure COMPACTION TEST ASTM D 1557 Modified Proctor TerraPacific Consultants, Inc. 4010 Morena Boulevard, Suite 108, San Diego, CA 92117 / Phone: (858) 521-1190 Fax: (858) 521-1199 95.0 100.0 105.0 110.0 115.0 120.0 125.0 130.0 135.0 140.0 145.0 150.0 0.0 5.0 10.0 15.0 20.0Dry Density (pcf)Moisture Content (%) SP. GR. = 2.65 SP. GR. = 2.70 SP. GR. = 2.75 Project Name:Harbor Pointe Project No. :20-065 Boring No.:T-1 @ 0-2' Technician:JS Date:5/7/20 Visual Sample Description: Light Brown Silty Sand X Manual Ram Ram Weight 10 LBS Drop 18 inches TEST NO.1 2 3 4 5 6 A Wt. Comp. Soil + Mold (gm.)3659.00 3783.00 3902.00 3928.00 B Wt. of Mold (gm.)1794.00 1794.00 1794.00 1794.00 C Net Wt. of Soil (gm.)A - B 1865.00 1989.00 2108.00 2134.00 D Wet Wt. of Soil + Cont. (gm.)1486.8 1733.9 1649.3 906.5 E Dry Wt. of Soil + Cont. (gm.)1425.1 1636.7 1543.1 835.1 F Wt. of Container (gm.)193.1 187.6 302.3 187.7 G Moisture Content (%)[(D-F)-(E-F)]/(E- F)5.0 6.7 8.6 11.0 H Wet Density (pcf)C*29.76 /453.6 122.4 130.5 138.3 140.0 I Dry Density (pcf)H/(1+G/100)116.5 122.3 127.4 126.1 Maximum Dry Density (pcf)127.8 9.5 PROCEDURE USED Procedure COMPACTION TEST ASTM D 1557 Modified Proctor TerraPacific Consultants, Inc. 4010 Morena Boulevard, Suite 108, San Diego, CA 92117 / Phone: (858) 521-1190 Fax: (858) 521-1199 95.0 100.0 105.0 110.0 115.0 120.0 125.0 130.0 135.0 140.0 145.0 150.0 0.0 5.0 10.0 15.0 20.0Dry Density (pcf)Moisture Content (%) SP. GR. = 2.65 SP. GR. = 2.70 SP. GR. = 2.75