Loading...
HomeMy WebLinkAboutCDP 04-56; WESELOH HUMMER IMPROVEMENTS; FINAL SOILS REPORT; 2007-05-11Weseloh Hummer Dealership Carlsbad, California Job No. 03-8538 Page 3 maximum dry density determined per ASTM D1557. Areas of backfill and subgrade and base material that were found to be under-compacted were pointed out to the contractor for corrective work. Those areas were approved a~er corrective work was provided and satisfactory passing test results were obtained. A list of test results is presented on Figure No. IIIs. 8. Excavators or backhoes (JD 410 C) with attached compaction wheels were used to compact the trench backfill up to -1 foot below the top of the trench. From there, a Bob Cat, mechanical hand tampers, and a smooth steel wheel roller were used to compact the backfill. 9. The pavement section approved by the City consisted of 4 inches of asphalt concrete over 6 inches of Class II Base Material over properly compacted subgrade in the street area. In the driveway and parking area the required pavement was 3 inches of asphalt concrete on 4 inches of Class II base. 10. Field density tests were performed at the approximate locations shown in the attached Plot Plan, Figure No II. LIMITATIONS The findings, opinions, and conclusions presented herein have been made in accordance with generally accepted principles and practice in the field of geotechnical engineering in the City of Carlsbad. No warranty either expressed or implied is made. at Project No. 03-8638 TABLE A-SUMMARY OF FIELD DENSITY JBTa(ESULTS (ASTM D1666-90 and/or ASTM D2922-91, ASTM D3017-88) Approximate Water Dry Degree of Test Elevation Content Density Compaction Compaction ...NQ,_ Date of Test !!!st Location !FEET} _lliL ~ _lliL Curve No. Remarks 1 12/22/05 Building Pad 368.8 7.0 122.9 91 1 Previously Reported 2 12/22/05 Building Pad 368.8 7.9 121 .3 90 1 Previously Reported 3 12/22/05 Building Pad 368.8 7.7 121.2 90 1 Previously Reported 4 12/23/05 Building Pad 368.8 5.8 121 .1 90 1 Previously Reported 5 12/27/05 Building Pad 370.5 6.5 121.9 92 2 Previously Reported 6 12/27/05 Building Pad 370.5 6.3 119.1 90 2 Previously Reported 7 12/27/05 Building Pad 370.5 5.4 119.7 90 2 Previously Reported 8 12129/05 Building Pad 370.0 5.7 122.9 91 1 Previously Reported 9 1/6/06 Building Pad 370.0 6.1 122.7 91 1 Previously Reported 10 1/6/06 Building Pad 371.8(FSG) 7.9 119.7 90 2 Previously Reported 11 1/6/06 Building Pad 371 .8(FSG) 8.1 124.4 94 2 Previously Reported 12 1/6/06 Building Pad 371 .8(FSG) 8.0 123.9 93 2 Previously Reported 13 1/6/06 Building Pad 371 .8(FSG) 9.4 121.5 91 2 Previously Reported 14 1/6/06 Building Pad 371.6(FSG) 8.7 121 .8 92 2 Previously Reported 15 11/30/06 Waterline-Paseo del Norte FSG -2.5 6 111.1 87 3 Test failed, see#16 16 11/30/06 Retest of # 15 -2.5 8 114.6 90 3 17 11/30/06 Waterline-Paseo del Norte -1.5 6 121.0 95 3 18 11/30/06 Waterline-Paseo del Norte FSG-3.0 8 118.8 93 3 19 1211/06 Waterline-Paseo del Norte FSG-1 7 122.9 94 4 20 1211/06 Waterline-Paseo del Norte FSG 8 124.5 95 4 21 1211/06 Waterline-Paseo del Norte FSG-1 7 121.4 93 4 22 1211/06 Waterline-Paseo del Norte FSG-2.0 5 114.8 90 3 23 1211/06 Waterline-Paseo del Norte FSG-1 9 118.2 90 4 24 1211/06 Waterline-Paseo del Norte FSG 6 120.1 92 4 Test failed, see # 25 25 1211/06 Retest of# 24 FSG 7 123.9 95 4 26 1214/06 Waterline-north of building FSG-1 7 122.8 94 4 27 1214/06 Waterline -sidewalk FSG-1 6 117.3 90 4 28 1214/06 Waterline sidewalk FSG 6 124.3 95 4 29 1214/06 Waterline -paseo del norte FBG 7 134.8 98 5 30 1214/06 Waterline -paseo del norte FBG 5 128.6 94 5 Test failed, see# 31 Figure No. Illa Notes: 1) Curve number refers to Table B 2) FSG denotes finish subgrade elevation 3) FBG denotes finish base grade elevation 4) FPG denotes finish pavement grade Project No. 03-8638 TABLE A -SUMMARY OF FIELD DENSlTY D:5TaESUL TS (ASTM D1666-90 and/or ASTM D2922-91, ASTM D3017-88) Approximate Water Dry Degree of Test Elevation Content Density Compaction Compaction _.N2,_ Date ofTest Test Locgtion (FEET) _lliL --1E£tl_ _lliL Curve No. Remarks 31 12/4/06 Retest of # 30 FBG 6 131.4 96 5 32 12/5/06 Waterline FBG 7 135.6 99 5 33 12/5/06 Waterline FBG 6 130.4 95 5 34 12/5/06 Waterline -paseo del norte FSG 6 117.5 90 4 35 12/8/06 Waterline -paseo del norte FSG-1.5 6 118.9 91 4 36 12/8/06 Waterline -paseo del norte -2 6 119.5 91 4 37 12/8/06 Waterline -paseo del norte FSG 8 123.5 94 4 Test failed, see #39 38 12/8/06 Waterline -paseo del norte FSG 6 124.6 95 4 39 12/8/06 Retest of # 37 FSG 8 124.1 95 4 40 12/28/06 Curb-north east of building FSG 5 129.9 96 41 12/28/06 Curb-east of building FSG 5 119.4 91 4 42 1/12/07 Curb -south of building FSG 6 117.4 90 4 43 1/12/07 Curb-south of building FSG 7 119.3 91 4 44 1/12/07 Curb-south of building FSG 6 123.9 95 4 45 1/12/07 Curb -south east of building FSG 5 121.4 93 4 46 1/22/07 Curb -south side of building FSG 7 128.7 98 4 47 1/22/07 Curb -north of building FSG 5 118.7 91 4 48 1/22/07 Concrete drive north of building FSG 3 119.7 90 2 Test failed, no retest 49 2/6/07 Sidewalk-south of building FSG 7 121.0 92 4 50 2/6/07 Sidewalk-south of building FSG 7 118.0 90 4 51 2/6/07 Sidewalk-south of building FSG 7 119.0 91 4 52 2/6/07 Sidewalk-east of building FSG 7 120.0 92 4 53 2/6/07 Pavement-south west of building FSG 6 122.0 93 4 Fail, see# 67 54 2/6/07 Pavement-south west of building FSG 6 124.0 95 4 55 2/6/07 Pavement -south east of building FSG 6 118.0 90 4 Fail, see#64 56 2/6/07 Pavement-north east of building FSG 5 119.0 91 4 Fail, see# 61 57 2/6/07 Pavement-north west of building FSG 7 121.0 92 4 Fail, see# 60 58 2/6/07 Pavement-north west of building FSG 7 121.0 92 4 Fail, see# 59 59 2/26/07 Retest of# 58 FSG 7 128.6 98 4 60 2/26/07 Retest of # 57 FSG 7 125.8 96 4 Figure No. lllb Notes: 1) Curve number refers to Table 8 2) FSG denotes finish subgrade elevation 3) FBG denotes finish base grade elevation 4) FPG denotes finish pavement grade Project No. 03-8538 TABLE A -SUMMARY OF FIELD DENSITY JEST RESULTS (ASTM 01556-90 and/or ASTM 02922-91, ASTM 03017-88) Approximate Water Dry Degree of Test Elevation Content Density Compaction Compaction ~ ~ate of Test Test bocatioa {FEET) _iliL _{2g}_ _iliL Curve No. Remarks 61 2/26/07 Retest of # 56 FSG 6 124.5 95 4 62 2/26/07 Pavement -north east drive FSG 5 124.2 95 4 63 2126107 Pavement -east of building FSG 6 126.1 96 4 64 2/26/07 Retest of# 55 FSG 6 128.4 96 4 65 2/26/07 Pavement south east of building FSG 6 129.7 99 4 66 2/26/07 Pavement south east of drive FSG 7 129.4 99 4 67 2/26/07 Retest of # 53 FSG 8 124.0 95 4 68 2/26/07 Pavement south west drive FSG 7 124.5 95 4 69 2/26/07 Pavement -south of building FSG 7 125.6 96 4 70 2/26/07 Pavement-south east of building FSG 6 128.0 98 4 71 3/2/07 Pavement -south of building FBG 11 114.5 92 6 Test failed, see# 75 72 3/2/07 Pavement -south of building FBG 12 115.9 93 6 Test failed, see# 76 73 3/2/07 Pavement -south of building FBG 10 114.4 92 6 Test failed, see# 77 74 3/2/07 Pavement -south of building FBG 12 118.5 95 6 75 3/2/07 Retest of # 71 FBG 11 120.5 97 6 76 3/2/07 Retest of # 72 FBG 11 124.5 100 6 77 3/2/07 Retest of # 73 FBG 12 118.6 95 6 78 3/2/07 Pavement-south east of building FBG 11 120.8 97 6 79 3/2/07 Pavement-south east of building FBG 12 113.5 91 6 Test failed, see# 89 80 3/2/07 Pavement-south east of building FBG 11 123.3 99 6 81 3/2/07 Pavement • east of building FBG 12 114.8 92 6 Test failed, see# 85 82 3/2/07 Pavement • east of building FBG 12 115.6 93 6 Test failed, see# 86 83 3/2/07 Pavement • north east of building FBG 12 114.9 92 6 Test failed, see# 87 84 3/2/07 Pavement • north of building FBG 12 113.2 91 6 Test failed, see# 88 85 3/5/07 Retest of# 81 FBG 9 120.8 97 6 86 3/5/07 Retest of # 82 FBG 9 122.3 98 6 87 3/5/07 Retest of # 83 FBG 9 118.3 95 6 88 3/5/07 Retest of# 84 FBG 9 120.0 96 6 89 3/5/07 Retest of# 79 FBG 10 121.1 97 6 Figure No. Ille Notes: 1) Curve number refers to Table B 2) FSG denotes finish subgrade elevation 3) FBG denotes finish base grade elevation 4) FPG denotes finish pavement grade