HomeMy WebLinkAboutCDP 15-45; ABDI RESIDENCE; FINAL SOILS REPORT; 2022-04-05April 5, 2022 Mr. and Mrs. Behrooz Abdi CWE 2150264.10 5263 Shore Drive CDP 15-45 Carlsbad, California 92008 GR 2017-0010 Subject: As-Graded Geotechnical Report Abdi Residence, 5263 Shore Drive, Carlsbad, California References: Christian Wheeler Engineering, Report of Preliminary Geotechnical Investigation (Report CWE 21502611.01), November 8, 2015 Ladies & Gentlemen: In accordance with your request and our proposal dated February 14, 2018, we have prepared this report to summarize our services during the earthwork operations at the subject site. This report presents the as-graded geotechnical conditions of the site, our observations, the results of our laboratory testing, and the results of relative compaction tests performed in the fills and backfills that were placed during the grading operation as well as the preparation of subgrade and subsequent asphalt concrete placement at the project site. The observation and testing services addressed by this report were coordinated by Hulton Development, Inc and were provided between June 29, 2018 and June 23, 2020. In order to assist in our understanding of the designed configuration of the project, our firm was provided with grading plans for the site prepared by LGS Engineering, revision date January 17, 2017. Plate Nos. 1 through 3 of this report are reproduction of sheets 4 through 6 of the plans, modified to show the approximate locations of our field tests and the relevant limits of the earthwork operation which consist of the excavation for the basement, entryway and the patio. INTRODUCTION AND PROJECT DESCRIPTION The subject site is a developed residential lot located at 5263 Shore Drive, Carlsbad, California. Prior to the earthwork addressed in this report, the site supported a one- and two-story, single-family residence with an attached garage and other normally associated improvements. Topographically, the developed portions of the CWE 2150264.10 April 5, 2022 Page 2 subject lot are relatively level. The western portion of the lot is characterized by a moderately to steeply sloping coastal bluff, which is approximately 39 feet high. The bluff face is covered with gunite, which we understand was first placed along the lower ±20 feet of bluff face in or around 1962. Review of the referenced aerial photographs indicates that the upper bluff face was covered with gunite sometime between January of 1989 and 1993. The subject project consisted of the construction of a new two-story residence over a basement, a spa, and other normally associated appurtenances. The proposed residence and site improvements were supported by new conventional, shallow foundations and the basement incorporated a conventional concrete slab-on-grade floor system. Grading consisted of cuts up to about 11 feet below existing grade for proposed basement construction. SCOPE OF SERVICE The following services were provided by Christian Wheeler Engineering during the course of the earthwork operations. Provided observations of the earthwork operation which consisted of the basement excavation, and removals in the entryway and patio area. Provided field recommendations for elements of the earthwork not specifically addressed by the referenced geotechnical report. Recorded the approximate elevations and limits of significant geotechnical elements. Performed in-place density tests in the fills and backfills placed within the building pad as well as the subgrade and asphaltic concrete preparation along Shore Drive. Determined the laboratory maximum density and optimum moisture content of soils encountered in the earthwork. Determined the laboratory maximum density of asphaltic concrete placed along Shore Drive. Prepared this report, which presents a summary of our observations and results of our relative compaction tests. GRADING OPERATION The earthwork addressed by this report was performed by Mike Lloyd Excavating. The site preparation consisted of the excavation for the basement. The bottom of the excavation extended into competent old paralic deposits. Minor (less than 2 inches) amounts of loose soils exposed at the bottom of the excavation were compacted with a manually operated reciprocating compactor to at least 90 percent relative compaction. CWE 2150264.10 April 5, 2022 Page 3 The approximate limits of removal are shown on the attached Plate Nos. 1 through 3. Fill materials consisting of the on-site and imported silty sands were typically placed in relatively thin, uniform lifts to reach the designed pad grade. Moisture-conditioning was applied as needed and compactive efforts were then performed by means of the reciprocating compactor to attain at least 90 percent of maximum dry density. RETAINING WALL BACKFILL OPERATION The retaining walls associated with the staircase and spa located in the northeastern corner of the site were backfilled using native and imported sandy soils. The backfills were placed in thin horizontal lifts, which were watered to near optimum conditions and compacted in place by means of the reciprocating compactors to at least 90 percent of maximum dry density. PAVEMENT OPERATION Within the area of the utility tie-ins, the subgrade preparation generally consisted imported silty sand being placed to the designed grade. The soil was placed prior to our arrival on site and was compacted to 95 percent of its maximum dry density for paved areas. Asphaltic concrete placement was monitored for its laydown temperature during its placement. Mix temperatures were noted to be within the acceptable range of 270F to 320F, as specified in section 302-5.5 of the Standard Specifications for Public Works Construction. Compactive efforts were made by dual drum vibratory rollers to attain a minimum of at least 95 percent of the maximum density. CONCLUSIONS It is the opinion of Christian Wheeler Engineering that the earthwork addressed by this report has been performed in accordance with the recommendations presented in the referenced geotechnical reports, the grading requirements of the City of Carlsbad and the California Building Code. This opinion is based upon our observations of the earthwork operations, the results of the density tests taken in the field, and the maximum density tests performed in our laboratory. It is our further opinion that the site is suitable for the proposed construction. AS-BUILT GEOLOGY The geologic units encountered during the earthwork operations were generally consistent with those anticipated in the referenced report of geotechnical investigation. No unforeseen, adverse geologic conditions or features were noted by our field personal during the earthwork operation addressed herein. The earthwork operations addressed by this report have, in our opinion, satisfactorily mitigated the potentially adverse conditions described in the referenced report. CWE 2150264.10 April 5, 2022 Page 4 LIMITATIONS The descriptions, conclusions and opinions presented in this report pertain only to the work performed on the subject site from June 29, 2018 to June 23, 2020. As limited by the scope of the services that we agreed to perform, the conclusions and opinions presented herein are based upon our observations of the work and the results of our laboratory and field tests. Our services were performed in accordance with the currently accepted standard of practice in the region in which the earthwork was performed, and in such a manner as to provide a reasonable measure of the compliance of the described work with applicable codes and specifications. With the submittal of this report, no warranty, express or implied, is given or intended with respect to the services performed by our firm, and our performance of those services should not be construed to relieve the grading contractor of his responsibility to perform his work to the standards required by the applicable building codes and project specifications. Christian Wheeler Engineering sincerely appreciates the opportunity to provide professional services on this project. If you should have any questions after reviewing this report, please do not hesitate to contact our firm. Respectfully submitted, CHRISTIAN WHEELER ENGINEERING Daniel B. Adler, RCE # 36037 David R. Russell, CEG #2215 DBA:drr:mah ec: rick@hkarchs.com; gary@hkarchs.com; thomas@hultondevelopment.com; blabdi@yahoo.com 1279486328.0'28.0'QafQopQafQopAC1SG1AC2AC3PROPOSED ABDI RESIDENCE ADDITION5263 SHORE DRIVE, CARLSBAD, CALIFORNIADATE: AUGUST 2019BY: MAHREPORT NO.: 2150264.10PLATE NO.: 1APRIL 2022AS-GRADED GEOTECHNICAL MAP28.0'QafQopRELATIVE COMPACTION TESTELEVATIONS AT EXCAVATIONBOTTOMARTIFIAL FILL OVER VERY OLDPARALIC DEPOSITSAPPROXIMATE LIMITS OFREMOVAL#CWE LEGENDEXISTING FIRE HYDRANT (PROTIECT IN PLACE) If) EXISTING WA TIER METIER AND LA TIERAL TO BE REMOVED AND REPLACED AS NECESSARY PER PLUMING ENGINEER'S PLANS INSTALL BACK FLOW DE~CE PER PLUMING ENGINEER'S PLANS. EXISTING STREET LIGHT WITH CONCRETIE PAD (PROTIECT IN PLACE) -EXISTING LANDSCAPING-UNITS NECESSARY PER PLUMING ENGINEER'S PLANS • CHRISTIAN WHEELER ENGINEER.ING D:\DRAWING FILES\llllE SHEElS\GRADING TITLE SHEET.DWG RE\/ISED:01/05/16 I If) 1/J EXISTING UTILllY PULL BOX (PROTIECT IN PLACE) I EXISTING CONCR TIE CURB (PROTIECT IN P ACE) , _,,----EXISTING UTILllY PULL BOX (PROTIECT IN PLACE) , _,,----EXISTING WALL (PROTIECT IN PLACE) EXISTING RESIDENCE LO • EXISTING CONCRETIE 0 L 0 S----->,---S--+--~ EXISTING GAS LA TIERAL TO BE REMOVED AND REPLACED AS NECESSARY PER PLUMING ENGINEER'S PLANS PROPERlY LINE EXISTING BRICK WALL (PROTIECT IN PLACE) 8 12 '---------.' SCALE IN FEET 1111 D . . . . . . c., . . ·,.: · .. . c., . . . PROPOSED STIEM WALL PER ARCHITIECT'S DETAILS AS NECESSARY r~ PROPOSED EQUIPMENT AREA ~ AND ENCLOSURE WALLS PER ,!j/' ARCHITIECT'S DETAILS --1·· ·.-_ . . . . Cj ~ ~~ ~ ~ --~?'> ,,,t G ~~ >v ~ 0 . . ~-,\" . <:,· '-..· ,,,.. ~~ 9)" ,zv '5~-EXIST. LANDSCAPE AREA PROPOSED WATER LINE PER PLUMING ENGINEER'S PLANS . 0 EXISTING FENCE (PROTECT IN PLACE) PROPOSED GAS METIER PER PLUMING ENGINEER'S PLANS EXISTING UTILITIES TO BE RELOCA TIED PER PLUMBING ENGINEER'S PLANS PROPOSED AIR CONDITIONER UNITS .. '"' . . --....::: . . . -:!!~ . . . . . -_ ~ >'-,\" EXIST. LANDSCAPE AREA <:,· '-..· ,,,.. ~~ \l," 'V '5 ~-PROPOSED SEWER LINE PER PLUMING ENGINEER'S PLANS EXISTING BRICK PILASTIER (PROTIECT IN PLACE) ----~. IMPORTANT NOTICE SECTION 4216 OF THE GOVERNMENT CODE REQUIRES THAT A DIG ALERT IDENTIFICATION NUMBER BE ISSUED BEFORE A "PERMIT TO EXCAVATE" WILL BE VALID. FOR YOUR DIG ALERT I.D. NUMBER CALL UNDERGROUND SERVICE ALERT AT 8-1-1 TWO WORKING DAYS BEFORE YOU DIG NOTIE: DRAIN TO BE RESSESED UNDER WOOD SHOWER MA TT EXISTING LANDSCAPING :._$;::~~~~~~~tr~ =?"=7~-~,----E) 1/ t? {!):> .,_;~ 0 "" "" co F.F. = 40.10:aj~ PAD = 39.27 ci > >-' z LIMITS OF LOWER LEVEL ci > >-' z 0 '° "" '° ~ ~ PROPOSED RESIDENCE LOWER LEVEL FLOOR = 30.10 PAD = 29.27 r-----0 . U') H El NO a: 0 w a: 0 r -RIGHT-OF-WAY (PROTIECT IN PLACE) (PROTIECT IN PLACE) EXISTING CONCRETIE DRIVEWAY TO BE REMOVED EXISTING ROLILED CURB AND GUTTER (PROTECT IN PLACE) PROPOSED CONCRETIE DRIVEWAY EXISTING AC PAVEMENT (PROTIECT IN PLACE) SECTION G-G: SCALE HORIZONTAL: 1" = 4' VERTICAL: 1" = 4' EXISTING GARAGE (PROTIECT IN PLACE) o-"" "' oi LO "' "' • LANDSCAPE AREA ___ o> ._:z 0 ... NO ~ ~ 6 PROPOSED RESIDENCE FINISH FLOOR = 40.10 LOWER LEVEL FLOOR = 30.10 EXISTING WALL (PROTIECT IN PLACE) 0"' ,.._ co :zj ~ w w CJ) "AS BUil T" RCE __ _ EXP ____ _ REVIEWED BY: INSPECTOR DATE DATE LGS ENGINEERING, INC. 628 N ECKHOFF STREET ORANGE, CALIFORNIA 92868 r----t---+-----------+--l------l------l------llsH!ETl_c_1_r_Y=O=F=c=A~R=L=s~B-A_D~~ _ ENGINEERING DEPARTMENT ~ PHN (714) 385-0017 FAX (714) 385-0019 ENGINEER OF WORK 1/17/17 LOREN SANDBERG, P.E. DATE REGISTRATION NO. 44931 EXP: 3-31-18 1------ll--+----------------l------l--+--+------I GRADING PLANS FOR: ABDI RESIDENCE PRECISE GRADING PLAN SHEET APPROVED: JASON S. GELDERT 1-------11---+--,..------------------I------l---+---+------I CITY ENGINEER RCE 63912 EXPIRES 9 30 18 DATIE I-D"'A'""TE~f--;1""'N1"'TIA"'"'L-+-' ..... ---------------I-D-ATE-+-IN_IT1_A_L+-DA-TE-+-IN_lll_A_L---I ~D:;:;W;;:;N=B;;Y:;:,===:::;-;:===P=Ro=J=E=c=T=N=o=.=~;::D=R=A=Wl=N=G=N=o:::!_ ENGINEER OF WORK REVISION DESCRIPTION OTHER APPROVAL CITY APPROVAL 2~~g ~~;---CDP 15-45 501-8A 15-084 ~ 0 "' 0 a. (!) ... <O 0 RW8RW10RW7RW11RW9RW1RW2RW3RW4RW5RW6PROPOSED ABDI RESIDENCE ADDITION5263 SHORE DRIVE, CARLSBAD, CALIFORNIADATE: AUGUST 2019BY: MAHREPORT NO.: 2150264.10PLATE NO.: 2APRIL 2022AS-GRADED GEOTECHNICAL MAP28.0'QafQopRELATIVE COMPACTION TESTELEVATIONS AT EXCAVATIONBOTTOMARTIFIAL FILL OVER VERY OLDPARALIC DEPOSITSAPPROXIMATE LIMITS OFREMOVAL#CWE LEGENDDRAINAGE DETAIL: SCALE: 1" = 3' 39.20 T.G. 34.31 INV. -----------=6" so=---=-~__, -- - - -7 I ----PROPOSED STORAGE CHAMBER PER DETAILS ON SHEET NO. 8 28.35 TOP OF CHAMBER 22.52 INV. CHAMBER • \\ x'-,, ~ ~ \ ~\ \ \ 26.40 \\ c.L.. I ; I \\j, =4 so= \ 29.00 I / INV. Es " PROPOSED PUMP DISCAHRGE PER PLUMBING ENGINEER'S DETAILS I I I I I I I I I J ,_.., I I '---'--------------'-L.L__C I I I ~ J I t.l\ 30.00~ 11 INV. I >-' z 0"' c:i r.o ..., "' 11111 _J I "' -I Es I z < §; g§ a. CD. vi .... .:,: >z z-r---1n "' . . "' "' "' "' (/) (0 I I I I I I I I I I I I m > ~2.57 ~ z INV. c.o. c.o. O o ,--, \ 15 I I I I I I (/) J\ fis =00 32.53 __....+-;f-.... INV. _J I I " PROPOSED 4" SUBDRAIN PER DETAILS ON SHEET NO. 11 1111 CHRISTIAN WHEELER ENGINEER.ING D D:\DRAWING FILES\llllE SHEElS\GRADING TITLE SHEET.DWG RE\/ISED:01/05/16 PROPOSED 4• SUBDRAIN PER DETAILS ON SHEET NO. 11 PROPOSED PRE-TREATMENT MANHOLE PER DETAILS ON SHEET NO. 8 39.30 TOP OF MANHOLE 29.14 BOTTOM OF MANHOLE PROPOSED STORAGE CHAMBER PER DETAILS ON SHEET NO. 8 36.00 TOP OF CHAMBER 27.17 INV. CHAMBER 1-w 39.70 T.G. 34.83 INV. w w w (/) 11 Cl 0:: w 0 -(/') w 0::: 0 w (/') 0 0.... 0 0::: 0.... IMPORTANT NOTICE SECTION 4216 OF THE GOVERNMENT II Q:'. 0 0 __J lJ_ __J w > w __J Q:'. w ~ 0 __J CODE REQUIRES THAT A DIG ALERT IDENTIFICATION NUMBER BE ISSUED BEFORE A "PERMIT TO EXCAVATE" WILL BE VALID. FOR YOUR DIG ALERT 1.D. NUMBER CALL UNDERGROUND SERVICE ALERT AT 8-1-1 TWO WORKING DAYS BEFORE YOU DIG r----N . m N II 0 <C 0... LGS ENGINEERING, INC. 628 N ECKHOFF STREET ORANGE, CALIFORNIA 92868 PHN (714) 385-0017 FAX (714) 385-0019 ENGINEER OF WORK LOREN SANDBERG, P.E. REGISTRATION NO. 44931 EXP: 3-31-18 1/17/17 DATE .. ~ r EXISTING WALL (PROTECT IN PLACE) . S=0.040 ~ ~;-2 -6" STEPS· .. ·. . ""'~\ '< ~ ./\--'-~-~ ....... · . . ,... • . • • . I . '· 9· - 6 3/4" STEP,~ . , . . . . •. I\ .. .... '-... . ,, '· '-· .. \\ . . \\ ,, -.->> 39.20 T.G. 34.31 INV. I I Cl U1 ' <O ", 11 39.6 ,kt F.G. " " I iADE BREAK 11 ---1 ----I 32.50 INV. 11' --__J " " " " " 32.79 jNV. PROPOSED SPA l't1TH STROM DRAIN CONNECTION. DISCHARGE AND VALVES PER SPA PLANS. EXISTING LANDSCAPING / 7 -6 3/4" STEPS EXISTING WALL (PROTECT IN PLACE) PROPOSED STORAGE G~AMBER era m•~ c,; '"\ ----PROPOSED PUMP DISCAHRGE P R PLUMBING ENGINEER'S DETAILS 14-J I z: w 0 (/') w 0::: 0 w (/') 0 0.... 0 0::: 0.... -.._._-h--' ~~ ~ .. NO. «931 EXARES: 3-31-18 CJV\\ 8 I SCALE IN FEET 12 I • "AS BUil T" RCE___ EXP. ___ _ DATE REVIEWED BY: INSPECTOR DATE I ---1---+-----------+--t-----t-----t------il SH;ET I CITY OF CARLSBAD ~ t-~::::::::::::::;_::;::::::;:;:E::N~G;;IN;=E:::ER::l::NG=DE=P=A=R=TM=E=N=T==::::'..'.~==::::; l-----1--+----------------1----t--t----t--i GRADING PLANS FOR: DATE INITIAL DA TE INITIAL DA TE INITIAL ENGINEER OF WORK REVISION DESCRIPTION OTHER APPROVAL CITY APPROVAL ABDI RESIDENCE PRECISE GRADING PLAN SHEET CDP 15-45 APPROVED: CITY ENGINEER DWN BY: __ _ CHKD BY: __ _ RVWD BY: JASON S. GELDERT RCE 63912 EXPIRES 9 30 18 DA TE PROJECT NO. CPD 15-45 DRAVvlNG NO. 5O1-8A 15-084 ~ 0 .,.; 0 a. (!) ... <O 0 25101128.0'38.0'PROPOSED ABDI RESIDENCE ADDITION5263 SHORE DRIVE, CARLSBAD, CALIFORNIADATE: AUGUST 2019BY: MAHREPORT NO.: 2150264.10PLATE NO.: 3APRIL 2022AS-GRADED GEOTECHNICAL MAP28.0'QafQopRELATIVE COMPACTION TESTELEVATIONS AT EXCAVATIONBOTTOMARTIFIAL FILL OVER VERY OLDPARALIC DEPOSITSAPPROXIMATE LIMITS OFREMOVALS#CWE LEGENDNOTE: DRAIN TO ~ESSESED UNDE WOOD SHOWER MA TT EXISTING FENCE (PROTECT IN PLACE) ~ es a. 8 12 '-------;' SCALE IN FEET • CHRISTIAN WHEELER_ ENGINEERING D NO • LOWER LEVEL FLOOR = 28.85 PAD = 28.02 4 PROPO D RETAINING WALL PER DETAIL N SHEET NO. 11 40.60 w. 35.93 F. PROPOSED SEWER SUMP PUMP PER PLUMBING ENGINEER'S PLANS PROPOSED SEWER LINE PER PLUMING ENGINEER'S PLANS EXISTING FENCE (PROTECT IN PLACE) I 0 IMPORTANT NOTICE SECTION 4216 OF THE GOVERNMENT CODE REQUIRES THAT A DIG ALERT IDENTIFICATION NUMBER BE ISSUED BEFORE A "PERMIT TO EXCAVATE" WILL BE VALID. FOR YOUR DIG ALERT I.D. NUMBER CALL UNDERGROUND SERVICE ALERT AT 8-1-1 TWO WORKING DAYS BEFORE YOU DIG PROPOSED RESIDENCE LOWER LEVEL FLOOR = 30.10 PAD = 29.27 EXISTING STROM DRAIN CONTRACTOR TO VERIFY LOCATION AS NECESSARY TO MAKE JOIN (PROTECT IN PLACE) ~\I.LO r = NO. «931 EXPIRES: l-31-18 C/V\\ PROPOSED PUMP DISCHARGE PER PLUMBING ENGINEER'S DETAILS LGS ENGINEERING, INC. 628 N ECKHOFF STREET ORANGE, CALIFORNIA 92868 PHN (714) 385-0017 FAX (714) 385-0019 ENGINEER OF WORK 1/17/17 LOREN SANDBERG, P.E. DATE REGISTRATION NO. 44931 EXP: 3-31-18 \ EXISTING WALi\ (PROTECT IN RLACE) CONTRACTOR TO LOCATE EXISTING STORM DRAIN PIPE AND INSTALL PUMP DISCHARGE BOX TO PLUMBING ENGINEER'S SPECIFICATIONS. ( -s~ r:::::::o-,'~--====-~~----+k--EXISTING STROM DRAIN CONTRACTOR TO VERIFY LOCATION AS NECESSARY TO MAKE JOIN (PROTECT IN PLACE) "AS BUil T" ) RCE __ _ EXP ____ _ REVIEWED BY: INSPECTOR DATE DATE I SH~ET I CITY OF CARLSBAD ~ 1-----+--+----------------+-----+---1-----+--------1 ENGINEERING DEPARTMENT ~ l----+--+----------------+----+--1----+------I 1----+--+----------------+----+--1----+------1 GRADING PLANS FOR: ABDI RESIDENCE PRECISE GRADING PLAN SHEET CDP 15-45 APPROVED: JASON S. GELDERT i------------t---t,,,-------------------i------------i-----i-----------i----------i CITY ENGINEER RCE 63912 EXPIRES 9 30 18 DATE 1-----cD~A=TEc-+~1N=rn~AL,---+-<...._ _____________ -+_D_ATE-+-INI-TlA-L-+-DA-TE-+-I-NI-TlA-L---I :::D=w=N=B==Y=, ==::::::;---;:::::==P=R=o=JE=c=T=N=o:::'.. =:::;;:D=R=A=Wl=N=G=N=o:::::. ENGINEER OF WORK REVISION DESCRIPTION OTHER APPROVAL CITY APPROVAL 2~~g ~~;---CPD 15-45 501-8A 15-084 Appendix A Test Results CWE 2150264.10 April 5, 2022 Appendix A, Page A-1 Soil Type 1 2 3 4 5 AC Type AC1 Test No.Date Location Elev. (feet) Soil Type Field Moisture (%) Field Dry Density (pcf) Max. Density (pcf) Rel. Comp. (%) 1 7/2/2018 Southerly Portion of Basement 28.0 2 12.4 110.7 112.3 98.6 2 7/2/2018 Southerly Portion of Basement (FG) 29.0 2 12.9 109.3 112.3 97.3 3 7/3/2018 Northerly Portion of Basement 28.0 2 10.7 109.1 112.3 97.2 4 7/3/2018 Southerly Portion of Basement (FG) 29.0 2 10.9 110.6 112.3 98.5 5 10/2/2018 Northerly Portion of Basement (FG) 29.0 2 12.1 104.7 112.3 93.2 6 10/2/2018 Northerly Portion of Basement (FG) 29.0 2 11.7 111.5 112.3 99.3 7 10/2/2018 Southerly Portion of Basement (FG) 29.0 2 11.8 108.4 112.3 96.5 8 10/2/2018 Southerly Portion of Basement (FG) 29.0 2 11.4 107.9 112.3 96.1 9 10/2/2018 Southerly Portion of Basement (FG) 29.0 2 11.6 108.7 112.3 96.8 10 11/28/2018 Patio Area 39.5 4 7.8 124.3 135.0 92.1 11 11/28/2018 Patio Area 39.0 4 7.1 126.5 135.0 93.7 12 12/28/2018 Entryway Addition (FG) 39.6 2 10.5 110.2 112.3 98.1 Test No.Date Location Elev. (feet) Soil Type Field Moisture (%) Field Dry Density (pcf) Max. Density (pcf) Rel. Comp. (%) RW1 9/26/2018 Northeast Staircase 34.0 2 14.2 108.7 112.3 96.8 RW2 9/26/2018 Northeast Staircase 34.0 2 14.5 106.7 112.3 95.0 RW3 9/26/2018 Northeast Staircase 36.0 2 14.1 105.9 112.3 94.3 RW4 9/26/2018 Northeast Staircase 36.0 2 13.9 105.3 112.3 93.8 RW5 9/26/2018 Northeast Staircase 38.0 2 14.3 103.8 112.3 92.4 RW6 9/26/2018 Northeast Staircase 39.0 2 15.1 104.7 112.3 93.2 RW7 11/20/2018 Southerly Wall of Staircase 30.0 1 9.8 120.4 133.2 90.4 RW8 11/26/2018 Proposed Spa 32.0 1 9.1 120.7 133.2 90.6 RW9 11/26/2018 Southerly Wall of Staircase 32.0 1 8.9 121.1 133.2 90.9 RW10 11/27/2018 Proposed Spa 34.0 4 7.9 124.8 135.0 92.4 RW11 11/27/2018 Southerly Wall of Staircase 34.0 4 8.1 123.6 135.0 91.6 TABLE I: SUMMARY OF OPTIMUM MOISTURE & MAXIMUM DENSITY TEST RESULTS (ASTM D1557) TABLE IV: SUMMARY OF FIELD IN-PLACE DENSITY TEST RESULTS (ASTM D6938) - RETAINING WALL Description Brown, Sandy Silt (Investigation) Light brown, Poorl- graded Sand with Silt Brown to Reddish Brown, Silty Sand (Import) Brown, Silty Sand (DG-Import) Brown, Silty Sand (Import) Maximum Density (pcf) 147.3 TABLE II: LABORATORY COMPACTED UNIT WEIGHT, HVEEM METHOD (ASTM D1560) 133.2 112.3 123.0 Optimum Moisture (%) Maximum Dry Density (pcf) 7.9 14.7 9.5 Description 3/4 Type III TABLE III: SUMMARY OF FIELD IN-PLACE DENSITY TEST RESULTS (ASTM D6938) - MASS GRADING 135.0 123.310.0 7.0 I I CWE 2150264.10 April 5, 2022 Appendix A, Page A-2 Test No.Date Location Elev. (feet) Soil Type Field Moisture (%) Field Dry Density (pcf) Max. Density (pcf) Rel. Comp. (%) SG1 6/23/2020 Front of Driveway SG 5 8.0 122.1 123.3 99.0 Test No.Date Location Elev. (feet) Soil Type Field Moisture (%) Field Dry Density (pcf) Max. Density (pcf) Rel. Comp. (%) AC1 6/23/2020 Front Driveway BC 1 140.1 145.0 147.3 95.1 AC2 6/23/2020 Front Driveway BC 1 140.4 145.0 147.3 95.3 AC3 6/23/2020 Front Driveway BC 1 141.6 145.0 147.3 96.1 * BC= Base Course TABLE V: SUMMARY OF FIELD IN-PLACE DENSITY TEST RESULTS (ASTM D6938) - SUBGRADE TABLE VI: SUMMARY OF FIELD IN-PLACE DENSITY TEST RESULTS (ASTM D6938) - ASPHALTIC CONCRETE I I I I I I I I I I