June 2, 2022
Council Memorandum
To: Honorable Mayor Hall and Members of the City Council
From: Gary Barberio, Deputy City Manager, Community Services Branch
Jeff Murphy, Community Development Director
Via: Geoff Patnoe, Assistant City Manager @
Re: Building Permit Self-Certification Program (Districts -All)
{city ofCarlsbad
Memo ID #2022066
This memorandum provides an overview of the Community Development (CD) Department's new
Building Permit Inspection Self-Certification Program (program).
Background
The city recognizes the amount of time and cost that goes into home improvement projects and is
consistently looking for ways to simplify the permitting and inspection processes for customers,
while still maintaining the city's high standards and ensuring safe and quality construction. In
keeping with the objective, the City Council on May 10, 2022, adopted changes to the city's
building code to allow the Building Official to accept reports from licensed professionals certifying
that construction was installed consistent with required codes.
Discussion
Starting June 10, 2022, the CD Department will be launching the new program. This program
allows a California-licensed contractor to self-certify inspection of code requirements on select
minor residential building permits without city inspections. Projects that are eligible for this
program include roof & window replacement, drywall installation, plumbing projects and water
heater replacements, just to name a few. Attachment A includes a copy of the informational
bulletin that provides additional information on the subject and is available to the public on the CD
Department's website.1
City staff estimates that this program can reduce the number of city field inspections performed
by as much as 10%, which equates to roughly 1,500 inspections per year. It is expected that this
program will help expedite the closing out of permits for customers and free up building
inspection staff to spend needed time on more complicated building inspection jobs.
1 https://www.carlsbadca.gov/departments/community-development/departmental-information-bulletins
Community Services Branch
Community Development Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 442-339-5088 t
Council Memo -Building Permit Self-Certification Program (Districts -All)
June 2, 2022
Page 2
Next Steps
Beginning June 1, 2022, staff will be promoting the start date of the new program, which will
officially start on June 10, 2022. Staff will be monitoring implementation of the program, including
conducting random inspections to ensure that the work certified complies with required state and
city codes and standards, as required under the program. If successful, the CD Department will
look into expanding the program to include other inspection types.
Attachments: A. Informational-Bulletin and application documents
cc: Scott Chadwick, City Manager
Celia Brewer, City Attorney
Ron Kemp, Assistant City Attorney
Tina Ray, Communications & Engagement Director
Eric Lardy, Principal Planner
Scott Donnell, Senior Planner
Sarah Lemons, Senior Program Manager
Mike Strong, Assistant Director
Jason Pasiut, Building Official
~ Attachment A
Building Permit Inspection
Self-Certification Program
(_ City of
Carlsbad
Informational Bulletin
18-270
The Carlsbad Building Permit Self-Certification Program
(SCP) allows for a California-licensed contractor to
certify that certain minor construction projects were
completed in compliance with required building codes
in-lieu of a city inspection.
This Info-Bulletin is intended to outline program
requirements and provide links to required processing
documents.
PURPOSE & AUTHORITY
The city recognizes the amount of time and cost that
goes into home improvement projects. In response, the
city has developed a program that allows a California-
licensed contractor to self-certify inspection of code
requirements on select minor building permits without
Building Division inspections.
Carlsbad Municipal Code §18.04.045 and §18.20.050
authorizes the Building Official to accept inspection
reports from approved agencies or individuals for work
performed under a building permit. The inspection
reports shall be in writing and certified by a responsible
officer of the approved agency or by the responsible
individual.
PROJECT ELIGIBILITY
Given the nature and complexity of the construction
work, the SCP allows for self-certification for work that
is conducted on a detached single-family dwelling,
accessory structure, or considered minor in scope and
scale.
Documents Referenced
Carlsbad Municipal Code: §18.04 & §18.20
2019 California Code Section; §R109.2
Building Permit Application; B-1
SCP Declaration; B-70A
SCP Inspection Checklist; B-70B
Eligible Projects
• Roof (shingle) replacement (non-structural)
• Re-plumbing or re-piping of existing plumbing
• HVAC system (new or replacement)
• Water heater replacement (except tankless/solar)
• Insulation installation
• Window replacement, with stucco/siding repair
• Exterior siding/ plaster
• Interior Drywall
• Fence
• Commercial sign
Minimum Requirements
The following requirements must be met in order to
participate in the program.
• The individual responsible for completing and
inspecting work under this program must hold a
valid and active credential, as reflected below:
o California B-General Building Contractor's
license; or,
o California C-type Contractor's license,
depending upon construction work being
completed; or,
o State certified civil or structural engineer.
• Current worker's compensation insurance or
certificate of exemption.
PROCESSING STEPS
Application Process
To participate in the SCP, applicants must complete and
submit the following information and application forms.
• Building Permit Application (B-1 )
• SCP Declaration Form (B-70A)
• Payment of application fee.
Community Development Department I 1635 Faraday Ave. I Carlsbad, CA 92008 I www.carlsbadca.gov
Applications for the following projects can submitted
through the Carlsbad Customer Self Service Portal.
• Roof (shingle) replacement (non-structural)
• Re-plumbing or re-piping of existing plumbing
• HVAC system (new or replacement)
• Water heater replacement (except tankless/solar)
Applications for the following projects can submitted
via e-mail at bu ilding@carlsbadca.gov
• Insulation installation
• Window replacement, with stucco/siding repair
• Exterior siding/ plaster
• Interior Drywall
• Fence
• Commercial sign
Once the application has been approved, the applicant
will be given a building permit, which will authorize
construction. Included with the building permit will be
the SCP Inspection Checklist Form (B-70B).
Final Inspection Certification
Upon completion of the project, the authorized
contractor or engineer shall complete the SCP
Inspection Checklist (B-70B). It is important that the
responsible individual check all applicable items in the
checklist confirming that they reviewed and confirmed
that they were completed.
IB-270_REV: June 2022
Once the checklist has been completed and signed, the
form must be sent to the Building Division for
processing as reflected below.
• For applications submitted using the self service
portal, upload the completed form as a .PDF
submit it through the Carlsbad Customer Self
Service Portal and e-mail
bldginspections@carlsbadca.gov to inform staff
of the completed inspection.
• For all other applications, email the form to
bldginspections@carlsbadca.gov. Include the
permit number in the subject line of the email,
along with the caption "Attention Self-Certification
Program."
• Once received and processed, all of the forms will
be saved and accessible to the public via the
Carlsbad Public Records Access portal.
• Additionally, the city's permit tracking system will
be updated to reflect a "passed" inspection and
the permit closed out.
• Lastly, an email will be sent informing the
applicant that the permit has been approved.
If you are requesting to self-certify an eligible inspection
that is part of a larger permitted project (e.g., new
single-family home), simply e-mail the completed B-70A
and B-70B to bldginspections@carlsbadca.gov to inform
staff of the completed inspection.
At the time of receiving the signed checklist, the city
reserves the right to conduct a random inspection to
verify that work was completed to plan and building
code. If a project is found to not follow approved plans,
building codes or certification forms as submitted, the
self-certification approval will be revoked, and the
contractor or engineer may be reported to the state
licensing board and not be eligible for SCP in the future.
Re-inspection fees may apply for self-certified permits
that fail an audit.
YOUR OPTIONS FOR SERVICE
To schedule an appointment or to learn more about this
process, please contact the Building Division at 442-339-
2719 or via email at Building@CarlsbadCA.gov
Page 2 of 2
(City of
Carlsbad
Minor Building Permit Inspection
Self-Certification Declaration
B-70A
This form is required to participate in the city's Building Permit Inspection Self-Certification Program (SCP), which
allows for a California-licensed contractor to self-certify that certain minor building construction projects were
completed in compliance with relevant building code standards in-lieu of a final inspection from the city. Refer to
Informational Bulletin IB-270 for additional information and requirements. This form is to be completed and
submitted with a Minor Building Permit application (form B-1).
TO BE COMPLETED BY THE CONTRACTOR/ ARCHITECT /ENGINEER
Name License Type and No. Business Address
Phone Email Address Permit No.
Brief description of work being conducted
Declaration
I affirm and certify under penalty of perjury that:
1. I have reviewed and understand the requirements of the City of Carlsbad's SCP program as detailed in
Informational-Bulletin IB-270 and will comply with those requirements.
2. I have received approval from the property owner to complete the work authorized under the referenced
building permit and made them aware that completed work will be self-certified under this program.
3. I am a California-licensed B General Building Contractor with current worker's compensation insurance, C-
type Contractor depending on specialty with current worker's compensation insurance, Civil Engineer or
Structural Engineer, and my license in active.
4. I shall assume responsibility and liability for the overall installation, inspection, and certification of all work
associated with the referenced building permit and will ensure that all work is completed in compliance
with all applicable requirements of the California Building Standards Code as adopted and amended by the
City of Carlsbad and in accordance with any manufacturer's installation requirements.
5. I have reviewed and understand the requirements set forth in the Self-Certification Inspection Checklist
(Form 70-B) and shall complete, sign, and return the form to the city following completion of all work
authorized under the above referenced building permit.
6. I understand that the city may randomly audit the construction work for quality assurance, and I agree to
provide access to work performed under this program when requested by the City of Carlsbad.
Signature Date
□ Approved
□ Denied Staff Name Date
B-70B_REV: June 2022 Page 1 of 1
(city of
Carlsbad
Minor Building Permit Inspection
Self-Certification Inspection List
B-70B
Completion and return of this form is required in order to complete participation in the city's Building Permit Self-
Certification Program. Refer to the Minor Building Permit Inspection Self-Certification Declaration (Form B-70A) that
was approved by the city for the building permit requiring final certification. Refer to Informational Bulletin IB-270
for additional information about the program.
TO BE COMPLETED BY THE CONTRACTOR/ARCHITECT/ENGINEER
The information below must match the same information provided in Form 8-lOA that was approved for this project
Name License Type and No. Business Address
Phone Email Address Permit No.
Brief description of work being conducted
Declaration
I affirm and certify under penalty of perjury that:
1. The information provided in Form B-70A remains true and accurate (attach a copy of the form).
2. All work authorized under the referenced permit was installed in compliance with approved building permit,
plans and manufacturer installation instructions and/or listing.
3. All work authorized under the referenced permit was installed in compliance with relevant state ,and city
building code standards.
4. All work authorized under the referenced permit was installed in compliance with relevant requirements
listed in checklist that is attached hereto.
Signature Date
Upload completed form to the Customer Self-Service Portal HERE. E-mail all other completed forms to:
bldginspections@carlsbadca .gov. Include the permit number in the subject line ofthe email, along with the
caption "Attention Self-Certification Program." After the completed document has been received and processed
by the city, the document will be scanned into the city's Laserfiche on line permit history research application,
which can be accessed at: https://records.carlsbadca.gov/Weblink/. Additionally, the department's permit
tracking system will be updated to reflect a "passed" inspection, an email will be sent to the point of contact on
for the building permit notifying them of the determination, and the permit closed out.
□ Approved
D Denied
Form B-70B_REV: June 2022
Staff Name Date
Page 1 of 4
INSTALLATION REQUIREMENTS BY PERMIT TYPE
Please check the appropriate checkboxes for the work authorized under this program to confirm that the identified
installation requirements have been met at the time of work completion. All checkboxes must be filled in order to
qualify for self-certification.
D Re-roof
□ No structural changes
□ Removed water-soaked or deteriorated elements and replaced with competent material
□ If new roof diaphragm has been installed, code-compliant fasteners installed
□ Verified all existing vents were extended through roof per code and painted
□ Provided minimum clearances to combustible material for B Vent(s} or Chimney(s} per code
□ Installed flashing and counterflashing per code
□ Installed underlayment per code
□ Installed a class A rated roof
□ Installed roof covering per code (include completed waste management form B-59 for concrete tile
recycling showing proof of a minimum 65% recyclables}
□ If a built-up roof was installed, designed slope to be minimum of 2% per code
□ Code-compliant attic ventilation, Wild land Urban Interface compliant
□ Cool Roof Rating Council product certification, CF2R forms completed and included as necessary
D Re-plumbing/piping
□ Installed a listed potable water piping system
□ Pipe material is approved for the location installed
□ Sized the piping per code
□ Secured, insulated, and isolated per code
D Reamed all piping
D Removed all excess flux
□ Thoroughly flushed the system
□ Electrically grounded the system (if metallic)
□ If plastic water system, affix sticker located at meter main stipulating: "No ground required, plastic
water piping."
□ Restored the integrity of the firewa II
□ Installed an anti-siphon valve at each new hose bib
□ Insured that the maximum water pressure does not exceed 80 p.s.i.
□ Protected all piping
□ Completed all insulation, drywall, taping, mud, and painting
D Heating, Ventilation, and Air Conditioning replacement (HVAC)
This permit may cover a new or replacement heater and/or air conditioner
□ Grounded per code
□ No new gas or electric lines are being installed
□ Fused correctly per manufacturers name plate
□ Liquid tight conduit secured
□ Line set 3/4" wall insulation, UV-resistant exterior or protected
Form B-70B_REV: June 2022 Page 2 of 4
□ Disconnect and circuit sized per name plate rating and installed per code
□ Condenser set on a level and secure platform
□ Code required working clearances (30" wide x 36" deep) for electrical disconnect
□ Openings into building sealed
□ CFlR, CF2R, CF3R registered forms completed and included as necessary
□ Exterior refrigerant service ports fitted with tamper-resistant locking cap
□ Condenser installed outside of required side or rear yard setbacks
D Water Heater
This permit shall only cover replacement of existing storage tank water heaters. This permit does not cover
installation of a tankless or solar type water heater.
□ 18" raised platform or per manufacturer's listing
□ P/T drain to exterior as per code
□ Water lines insulated for 5' minimum or to wall
□ Shut off valve installed on cold water side
□ Gas line secure with sediment trap
□ New gas flexible connector and sized correctly
□ Flue vent intact, secured, still serviceable
□ Flue cap and diverter in place
□ Code compliant flue vent clearances
□ Clearances for replacement water heater per manufacturer
□ Combustion air vents properly sized and located per code
□ Evaluated other exhaust systems for possible draw down of flue gases in vent.
□ Earthquake strapping per code
□ Vacuum relief valve for attic installs
□ Drain pan with separate discharge for attic installations or as required by manufacturer
□ Access, walkway, working space and headroom for attic installs
□ Switched lighting for attic installations
□ No "pit" situations where LPG could pool
□ Expansion tank or listed device as required is installed
□ CFlR, CF2R, CF3R registered forms completed and included as necessary
Additional items specific to electric water heater:
□ Electrical disconnect sized and installed per code, hard wired with correct conductors, conduit
and properly grounded
□ Minimum 18" platform
□ Applicable code requirements that apply to gas type water heaters
D Insulation Installation
□ All insulation material, including facing, such as vapor barrier or breather paper installed within floor-
ceiling assemblies, walls, crawl spaces or attics, shall have a Flame spread rating not to exceed 25 and a
smoke density not to exceed 450.
□ Check all clearances from B vents, flues, combustible air chases, ducts and ventilation.
Form B-70B_REV: June 2022 Page 3 of 4
□ Seal all floor sill plates and exterior openings. Make sure all surfaces are clean prior to sealing.
□ Minimum R-38 attic insulation installed
□ Rough frame inspection approved prior to insulation installation
□ Insulation is installed at roof, walls, and floors at the thickness indicated per prescriptive or mandatory
requirements unless superseded by the approved plans
D Window Replacement
□ Windows shall not reduce egress from existing conditions
□ Windows fitted to existing opening only
□ Windows full tempered where closer than 18" to floor and over 9 feet square
□ Full tempered glass where within 24" arc of door and within 60" of floor
□ Guard rail where windowsill is greater than 6 feet above grade and less than two feet above floor
□ Wildland Urban Interface compliant, dual pane glazing with one pane tempered
□ Windows comply with Title 24 requirements, CF2R completed and included as necessary
D Exterior Siding and Plastering
□ Code-compliant approved paper and lathing
□ Code-compliant backing for lath
□ Double paper for existing sheer
□ Code compliant flashing of windows and doors
□ Installation of drip screed per code with compliant clearances from finished grade
□ Installed corner rite or bead for all edges
□ Listed caulking for all tears and penetrations
□ Scratch coat, brown and color to achieve 7 /8" approximate stucco or per listing of alternate product ·
□ Installed paper backed ribbon lath for all soffit location
D Interior Drywall
□ These permits shall only cover drywall replacement within an existing permitted structure.
□ Installed correct size and type of drywall with approved fasteners per code
□ Fastening pattern for multiple layers was verified and rated walls were appropriately fire caulked
□ Completed all taping, mud, and painting
D Fence meets all applicable setbacks, including, but not limited to, the
□ Installation meets applicable City of Carlsbad Municipal Code
□ Installed on owner's property meeting all applicable setbacks (within setback may not be self-certified)
□ Maximum height matches the approved plans
□ fence and pool/ spa gate installed according to the swimming pool safety act
□ Material matches the approved plans
□ No electrical; no luminaries; no retaining walls over 4 ft. in height (otherwise, may not be self-certified)
D Commercial Sign
□ The sign, it's fasteners and electrical components are installed in compliance with local codes and
ordinances and in accordance with the approved plans
□ UL listed equipment was used for the sign installation
□ Wall penetrations were adequately sealed
□ The grounding and bonding system was verified back to the main electric source
Form B-70B_REV: June 2022 Page 4 of 4