Loading...
HomeMy WebLinkAbout2022-06-21; Municipal Water District; ; Approval of Plans and Specifications and Authorization to Advertise for Bids for the Palomar Airport Waterline Realignment ProjectCA Review _RMC_ Meeting Date: June 21, 2022 To: President and Board Members From: Scott Chadwick, Executive Manager Staff Contact: Dave Padilla, District Engineer dave.padilla@carlsbadca.gov, 442-339-2356 Keri Martinez, Utilities Senior Engineer keri.martinez@carlsbadca.gov, 442-339-2354 Subject: Approval of Plans and Specifications and Authorization to Advertise for Bids for the Palomar Airport Waterline Realignment Project District: 2 Recommended Action Adopt a resolution approving plans, specifications and contract documents, and authorizing the Secretary of the Board of Directors to advertise for bids for the Palomar Airport Waterline Realignment, Capital Improvement Program Project No. 5055. Executive Summary The project will construct approximately 1,965 linear feet of 8-inch, 10-inch and 12-inch diameter water pipeline to realign and replace existing distribution lines serving the San Diego County McClellan-Palomar Airport in Carlsbad. The Carlsbad Municipal Water District Board approval of these plans and specifications is required under Carlsbad Municipal Code Section 3.28.080(E) because the expected value for this work is greater than $200,000. The construction cost estimate, including contingency funds, is $2,128,000, making the project subject to this requirement. Staff recommend that the CMWD Board approve the plans, specifications and contract documents, and authorize the Secretary of the Board of Directors to advertise and receive project bids. Discussion The single runway airport is located at 2198 Palomar Airport Road in Council District 2. The CMWD owns and operates a system of water distribution mains on the premises. These mains provide potable water service and fire protection for the airport’s operations and tenants. The mains are comprised of steel, PVC and asbestos-cement pipelines, and other components, installed at various times over the past decades. June 21, 2022 Item #8 Page 1 of 8 MUNICIIPAL WATER D IISTRIC'f Staff Report One of these water lines, a 10-inch diameter steel pipe approximately 1,600-linear-feet long, serves as the central main for the airport’s water system. Approximately 450 linear feet of this pipeline runs under the commercial ramp and taxiway, which have thick pavement sections to meet Federal Aviation Administration specifications. In 2017, a portion of the water line under the commercial ramp leaked and required an emergency repair that cost $170,000. During the repair, CMWD found the water line to be corroded and pitted. Based on these observations and coupled with the age of the pipe, which is about 40 years old, this and other water mains of similar condition are potentially at risk for future breaks. Additionally, the airport was constructed over portions of a landfill which was in operation between 1962 and 1975. The closed landfill is managed by the San Diego County Solid Waste Lead Enforcement Agency, which is responsible for ongoing gas and groundwater monitoring. This former land use presents unique site conditions that can impact below-grade pipelines due to settlement and landfill gas migration. Several segments of the existing pipeline are situated within approximately 100 feet of parts of the former landfill. The project realigns the distribution system to remove from service approximately 1,300 linear feet of pipe located under the commercial ramp, taxiway and in close proximity to the former landfill areas as shown in Exhibit 2. A total of 1,965 linear feet of new PVC pipe will be installed to replace aging asbestos-cement and steel pipelines, and 1,800 linear feet of pipeline will be abandoned in place. The California Division of Drinking Water has approved the pipeline design, which incorporates special materials for the site conditions. The project will require dedication of approximately 15,000 square feet in the form of a 20- foot-wide water easement for the new pipelines and the related components. It will also require CMWD to quitclaim, or relinquish, the easement that had granted it access to approximately 18,700 square feet for the pipelines that are now to be abandoned. San Diego County has agreed to execute the easement grant deeds and quitclaims. Easement quitclaim documents will be presented to the board after the district receives of public bids for the project and before the construction contract is awarded. In addition to standard CMWD construction specifications and requirements, the contractor must comply with Federal and County Airport Operations’ right-of-entry requirements, as well as the county Lead Enforcement Agency’s community health and safety monitoring and reporting requirements throughout construction. CMWD staff have coordinated with various county agencies throughout the design process, including Airport Operations, Public Works, Environmental Health, and Landfill Operations, on the design, schedule, phasing, onsite requirements and restrictions. Since the construction work may temporarily and briefly disrupt traffic to aircraft maintenance hangars, staff incorporated the county’s requests for onsite traffic control and specifically night work at construction locations in and near the taxiway. Airport Operations staff have agreed to attend the CMWD pre-construction and weekly construction meetings throughout the project, as coordinated by the city’s Construction Management and Inspection Department staff, and to assist in facilitating access and construction activities. June 21, 2022 Item #8 Page 2 of 8 Options Staff provide the following options for the CMWD Board’s consideration: 1. Adopt a resolution approving the plans, specifications and contract documents and authorizing the Secretary of the Board of Directors to advertise for bids for the project Pros • Reduces the risk associated with potential pipe breaks and emergency repairs and proximity to closed landfill cells • Allows for more efficient future pipeline maintenance outside of an operating taxiway and away from historical buried refuse Cons • Work may temporarily and briefly disrupt traffic to aircraft maintenance hangars. 2. Do not adopt a resolution approving the plans, specifications and contract documents and authorizing the Secretary of the Board of Directors to advertise for bids for the project Pros • None identified Cons • Increases risk of pipe leaks or breaks and emergency construction • Delays bidding and construction contract award • Potential increase in construction cost Staff recommend Option 1 for the CMWD Board’s approval. Fiscal Analysis Sufficient funds are available to complete the project. The engineer’s estimate of construction costs is $1,677,000. The total project cost of $2,128,000 includes estimated construction costs, contingency, staff engineering and construction management and inspection services. A summary of the estimated costs and available funds is shown in the table below: Palomar Airport Water Line Realignment Capital Improvement Project No. 5055 Total appropriation to date $1,750,000 Total expenditures and encumbrances to date $179,000 Fiscal year 2022-23 proposed CIP budget appropriation $560,000 Total available funding $2,489,000 Construction contract (estimated) $1,677,000 Construction contingency (15%) $251,000 Construction management, inspection, material testing, communications services (estimated) $180,000 Staff time (estimated) $20,000 Total estimated project costs $2,128,000 Remaining balance $361,000 June 21, 2022 Item #8 Page 3 of 8 As part of the fiscal year 2022-23 Capital Improvement Program proposed budget, staff requested an additional appropriation of $560,000 for the project. If that is approved, no additional appropriation will be required based on the current estimate. Next Steps Upon the CMWD Board’s approval of the FY 2022-23 Capital Improvement Program proposed budget, the Secretary of the Board of Directors will advertise a request for bids to construct the project. Staff estimate bids will be advertised in summer 2022. Staff will evaluate the bids received, and the lowest responsive and responsible bidder will be identified. Staff will then return to the CMWD Board to consider the lowest responsive and responsible bid and possible award of a contract to the identified bidder, which is expected to be in fall 2022. Staff will request CMWD Board approval of easement quitclaims and recommend to the Executive Manager the acceptance of new easements at that time. Construction duration is estimated to be six to nine months, so construction is estimated to be completed in fall 2023. Environmental Evaluation The project classifies as a replacement or reconstruction of existing utility or facilities involving negligible or no expansion of capacity and is exempt from environmental review under California Environmental Quality Act Guidelines Section 15302(c). If the resolution is approved, staff will file a notice of exemption with the San Diego County Clerk in compliance with Section 21152 (b) of the California Public Resources Code. Public Notification This item was noticed in accordance with the Ralph M. Brown Act and it was available for public viewing and review at least 72 hours prior to the scheduled meeting date. Exhibits 1.CMWD board resolution 2.Location map 3.Plans, specifications and contract documents (on file at the Office of the Secretary) June 21, 2022 Item #8 Page 4 of 8 RESOLUTION NO. 1678 A RESOLUTION OF THE BOARD OF DIRECTORS OF THE CARLSBAD MUNICIPAL WATER DISTRICT OF THE CITY OF CARLSBAD, CALIFORNIA, APPROVING PLANS, SPECIFICATIONS AND CONTRACT DOCUMENTS AND AUTHORIZING THE SECRETARY OF THE BOARD OF DIRECTORS TO ADVERTISE FOR BIDS FOR THE PALOMAR AIRPORT WATERLINE REALIGNMENT PROJECT EXHIBIT 1 WHEREAS, the Carlsbad Municipal Water District, or CMWD, Board of Directors of the City of Carlsbad, California has determined that it is necessary, desirable and in the public interest to realign and replace water distribution pipelines at the County of San Diego McClellan-Palomar Airport for the Palomar Airport Waterline Realignment, Capital Improvement Program, or CIP, Project No. 5055, or Project; and WHEREAS, the plans, specifications and contract documents for the Project have been prepared and are on file at the Secretary's office and are incorporated herein by reference; and WHEREAS, Carlsbad Municipal Code Section 3.28.080(E) requires the CMWD to approve plans and specifications for all construction projects that are to be formally bid upon when the value exceeds $200,000; and WHEREAS, the cost of the Project is estimated to be $2,128,000, including construction contingency and construction management costs; and WHEREAS, additional funding has been requested in the proposed fiscal year 2022-23 CIP budget to complete construction of the Project; and WHEREAS, the City Planner has determined that the Project is categorically exempt from the California Environmental Quality Act, or CEQA, pursuant to CEQA Guidelines Section 15302(c), as a replacement or reconstruction of existing utility and/or facilities involving negligible or no expansion of capacity, and that no exception to the exemption as set forth in CEQA Guidelines section 15300.2 applies. NOW, THEREFORE, BE IT RESOLVED by the CMWD Board of Directors of the City of Carlsbad, California, as follows: 1.That the above recitations are true and correct. 2.That the plans, specifications and contract documents for the Project are hereby approved and on file in the Office of the Secretary. June 21, 2022 Item #8 Page 5 of 8 3.That the Secretary of the Board of Directors is hereby authorized and directed to publish in accordance with state law and Carlsbad Municipal Code section 3.28.080((), a Notice to Contractors Inviting Bids for construction of the Project, in accordance with the plans, specifications and contract documents referred to herein. PASSED, APPROVED AND ADOPTED at a Regular Meeting of the Board of Directors of the Carlsbad Municipal Water District on the 21st day of June, 2022, by the following vote, to wit: AYES: NAYS: ABSENT: Hall, Blackburn, Bhat-Patel, Acosta, Norby. None. None. 11{ ,,/<.V FAVIOLA MEDINA, City Clerk Services Manager (SEAL) June 21, 2022 Item #8 Page 6 of 8 LOCATION MAP PROJECT NAME PROJECT EXHIBIT NUMBER 2 Exhibit 2 June 21, 2022 Item #8 Page 7 of 8 NOT TO SCALE PROJECT SITE PALOMAR AIRPORT WATERLINE REALIGNMENT PROJECT 5055-1 Exhibit 3 Plans, Specifications and Contract Documents (on file in the Office of the City Clerk) June 21, 2022 Item #8 Page 8 of 8