July 21, 2022
Council Memorandum
To: Honorable Mayor Hall and Members of the City Council
From: Paz Gomez, Deputy City Manager, Public Works
Via: Geoff Patnoe, Assistant City Manager ti
Re: Orion Center Project Update (District 2)
{cityof
Carlsbad
Memo ID #2022086
This memorandum provides an update to a previous Council Memorandum dated Jan. 20, 2022,
provided as Attachment A, on the status of the Orion Center Project, Capital Improvement
Program {CIP) Project No. 3572 (project). The project will construct a maintenance and
operations facility that will house Public Works Branch and Parks~ Recreation Department
field staff at 2600 Orion Way.
Background
Attachment A provid,es background information on this project. Since the last update on
Jan. 20, 2022, project consultants have continued to work on engineering-related site details and
other supporting documents for the conditional use permit (CUP) application. The consultants
submitted revised documents to address prior plan-check comments in January and May 2022.
Staff provided plan-check responses to those submittals in February and July 2022, respectively.
Specific items included the transportation demand management (TDM) plan, preliminary
hydrology study, updated storm water quality management plan, storm water detention basin
design, square footage on grading plans, cross section of the new retaining wall and other details.
Additionally, staff have updated their comprehensive time-based schedule for all drawings and
documents, including environmental documents and technical studies, required as part of the
project's discretionary review process. Staff met with the consultant on July 18, 2022, to discuss
their resubmittal and the way forward.
Discussion
The civil engineering site details affecting storm water treatment on site have been revised, and
an updated site plan has been prepared and were discussed with staff on July 18, 2022.
Additionally, environmental documents have been revised and updated. An updated set of
revised plans is scheduled to be resubmitted this week.
In addition to working toward finalizing all CUP supporting documents, staff have been tracking
the progress of each supporting document's review in a time-based schedule leading up to a
Planning Commission hearing date, which is anticipated to be in early 2023.
Public Works Branch
Fleet & Facilities Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 442-339-2730 t
Council Memo -Orion Center Project Update (District 2)
July 21, 2022
Page 2
Next Steps
Staff currently anticipate that the project application, revised reports and updated
environmental document will be deemed complete and subsequently posted for public review
in October 2022, which was previously anticipated to be in May 2022. The revised timeline is as ·
follows:
October 2022
Early 2023
Spring 2023
Fall 2023
Fall 2024
Spring 2026
Post CUP application documents for public review
Planning Commission approval of CUP
Request City Council approval of bridging documents
Request City Council approval of design-build contract
Design-builder completes design and permitting for start of construction
Estimated completion of construction
Attachment: A. Council Memorandum dated Jan. 20, 2022
cc: Scott Chadwick, City Manager
Celia Brewer, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Cindie McMahon, Assistant City Attorney
Robby Contreras, Assistant City Attorney
Tom Frank, Transportation Director/City Engineer
Kyle Lancaster, Parks & Recreation Director
Jeff Murphy, Community Development Director
Vicki Quiram, Utilities Director
James Wood, Environmental Sustainability Director
· Eric Lardy, City Planner
John Maashoff, Public Works Manager
Babaq Taj, Engineering Manager
David Padilla, Engineering Manager
Scott Donnell, Senior Planner
Steven Stewart, Municipal Projects Manager
To the members of the:
CITY COUNCIL
Date 1/?,QJ1ZCA.JL CC \/
tM ,/ ACM ti DCM {3)~ .. ~ -
Jan. 20, 2022
ATTACHMENT A
Council Memorandum
To: Honorable Mayor Hall and Members of the City Council
From: Paz Gomez, Deputy City Manager, Public Works
Via: Geoff Patnoe, Assistant City Manager fSiJ.
Re: Orion Center Project Update (District 2)
{city of ·
Carlsbad
Memo 10#2022009
This me_rnorandum provides an update to a previous Council Memora~ndum dated July 8, 2021,
provided as Attachment A, on the status of the Orion Center Project, Capital Improvement
Program, or CIP, Project No. 3572, which will construct a maintenance and operations facility
. that will hous_e Public Works Branch and Parks & Recreation Department field staff at 2600
Orion Way.
Background
Attachment A provides background information on this project. Since the last update on
July 8, 2021, staff and project consultants have co_ntinued to work on traffic and mobility
related reports and other support documents for the qonditional use permit, or CUP,
application. Additionally, staff have updated their comprehensive time-based schedule for all
drawings and documents, including environmental documents and technical studies, required
as part ofthe project's discretionary review process.
Discussion
The traffic impact analysis; or TIA, local mobility analysis_, or LMA, and transportation demand
management, or TOM, plans for the project have been revised, and an updated site plan has
been prepared. Additionally, cultural resource groups have been contacted, and consultation
with them is underway. The scenic tra11 surrounding the project has been removed from the.
project scope to avoid impacts and the corresponding environmental documents were revised
accordingly. An updated set of revised plans and updated cultural reports have not yet been
completed. The revised target date for these pending documents to be completed and
submitted is late January 2022.
In addition to working toward finalizing all CUP support documents, staff have been t racking
the progress of each support document's review in a time-based schedule leading up to a
Planning Commission hearing date, which is anticipated to be in fall 2022.
Public Works Branch
Fleet & Facilities Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 760-602-2730
l
I
I
Council Memo-Orion Center Project Update (District'2)
Jan. 20, 2022
Page 2
Next Steps
Staff currently anticipate tha.t the project application, revised reports and updated
environmental documenLwill be deemed complete and subsequently posted for public review
in late May 2022. The"revised timeljne is as follows:
May 2022
Fall 2022
Late 2022
Spring 2023
Spring 2024
Fall 2025
Post CUP application documents for public review
Planning Commission approval of CUP
Request City E:ouncil approval of bridging documents
Request City Council approval of design-build contract
Design-builder completes design and permitting for start of construction
Estimated completion of construction
Attachment: A. CounciJ Memorandum dated July 8, 2021
cc: Scott Chadwick~ City Manager
Celia Brewer, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha_, Depdty City Manager, Administrative Services
Robby Co1itr"eras, Assistant City Attorney
Tom Frank, -Tra1;:t~portation Director/City Engineer
Kyle Lan~aster, P1rks & Recreation Director
Jeff Murphy, Community Development Director
Vicki duiralil, Utiliti~s Director
Jame'.fWoo_c( Environmental Management Director
Dor1:Neu; City PJaDner
John-MaasJ,off, Public Works Manager
Babaq Taj, Engineering Manager
David Padilla, Utillties Engineering Manager
Steven Stewart, Municipal Projects Manager
Eric Lardy, Principal Planner
I
I
l
I
To the members of the:
c;rry COUNCIL
Date~ CA ii . ct ✓
CM ..L ACM .L DCM (3) L
ATTACHMENT A
Ji.Jly8, 2021
To:
From:
Via:
Re:
Council Memorandum
Honorable Mayor Hall and Members of the City Council
Paz Gomez, Deputy City Manager, Pqblic.WJ.?rks
Geoff Patnoe, Assistant City Manage(_ Gfl ·
O'rion Cent~r Project Update (District 2)
{cityof
Carlsbad
Memo IP #202;1134
This memorandum provides an update to a previous memorandum dated April 29; 2021,
(Attachment A) on the status of the Orion Center Project, Capital Improvement Program (CIP)
Project No. 3572 (project), which will construct a maintenance and operations facility that will
house Public Works Branch and Parks & Recreation Depari:ment field staff.
Background
As ofthe las_t project update on April 29, 2021, staff and project consultants continue to work
on traffic ai:id n.,obility related reports for the project, and staff created a comprehensive time-
based schedule for all drawings and documents required as part of the project's discretionary
review process.
Discussion
The vehicle miles traveled (VMT) analysis for the project was-completed on May 17, 2021. The
lo.cal mobility analysis (LMA) and transportation d'emand management (TDM) plan for tbe
project continue to be revised and updated as needed lo ensure the documents are cgmplete
qncJ r~ady for public review prior to deeming the project's Condition.al Use Permit KUP)
application complete.
In addition to working towards flnalizing the LMA and TDM plan, staff prepared a
comprehensive schedule detailing the list of CUP application documents on file for the project
and their review status. This sc;:hedule projected milestone dates for project plan check review,
environmental compliance and Planning Commission hearing dates. The anticipated Planning
Commission hearing date for thff projeds CUP has been revised to May 2022.
Next Steps
Staff currently anticipate that the project application, revised reports and updcited
environmental document. will be deemed complete and subsequently posted for public review
in January 2022. The revised timeline is as follows:
January 2022
May 2022
August 2022
Post CUP application documents for public review
Planning Commission approval of CUP
Request City Council approval of bridging documents
Public Works Branch
Fleet& Facilities Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 760-602-2730
Council Memo -Orion CenterProject Update (District 2)
July 8, 2021
Page 2
January 2023 .
J;rnuary 2024 ·.
JulY'262s
Reques:t City Council approval of cfosign-build cohfri:fct
DJ~sign-byilder completes. des_ign and permitting for start of construction
Estimated completion of tonstruction
Attachment, A CoLtne.il Memorandum dated April 29, 2021
cc:· Scott Chadwkk, CttyMaAager
Celia BrewerJ City Atto-mey
G¥Y Bar!;>eri9, Deputy City Manager, <::ommunityServic~s
la1,1ra Rocha., Depµty Cjty Maoagf;.'r, A(:iministr·atlve Services
Robby Contreras,Assistant City Attorney
Tom Fra11k, Transportatio□Director/City EQgineer
Kyle. Lancaster; Parks & Recreation D1tector
Jeff Murphy, Comrnuriity DeveloprtieotDirector
Vicki Quiram, Utilities D_irector
Jam:es Wood, Environmental Management Director
John Maashoff, Public Works Manager
David Padilla, Utilities Engineering Manager
Tim Selkec, Parks Services Manager
Babaq Taj, Engineering Manager
D011 l\leu, City Planner
Nathan Sqhniidt, Transportation Planning and Mobility Manager
Steven Stewart, Municipal Projects Manager
To the members ofthe:
CITY COUNCIL . . ·
bate'tfa.;,,/2,i ~A ✓-c:C -✓-
CM_ -✓-A-~i\-f/. DCM {3),L _
AprJl-29, 2021
To:-
Froin:
Via:
Re:
Council Memorandum
Honoral:ile Mayor HaJI and Mem_bersof th~ City Council
Paz Gorn __ ez, Dep_ 1.1_,_~Y ~Jty_ ~-an~~§-· r, P~bli~_-__ porks
Geoff Patnpe1 Ass,staot CJ~y Manager ~
Orion Center Project Update {District 2) .
Attachment A
_ {cityof
Carlsbad
Memo ID #2021088
This memorandum provides c11i upcl~te to a previc:>us memorandum dated Mar~h 11, 2Q21, on
the status of the Orion Center Project, ~apifal lrnprovement Program (CIP) Project 'N_o. 3572
(project)~ which Will t::olistruct a. inaiht.enante and operations facility that wnl house Public
Works Branch a_n·d Parks & Recreation Depc1rtment field staff.
Backgr9und
As of the last project update on Mardi 11, 2021, Attachment A, staff and proJect e·on~sultants
have _ co1;1tinued to work toward revising: and finalizing the local mobility ,an9.l~~is (LMA),
transp.9rt;;it)on dem@d rnc111_ag~(Jlent (TDM) plan an_dthevehicle miles traveled (\!Mt) analysis
for thE:! proJe_ct.
Discuss.ign
Staff tPnJiope tq rE:!vjew the VMT ana_lysi~ prepared by Felir & Peers, who revise th_e documents
as_ needed. They-st:ibmftte_d the most recent version of the arialysisfo( staff review the week of
. AprTI 19~ 2021.
In addition to reviewing the reports, staffare deve(opingl;:1nguag:e·to condition the project on
the tr~nsportation system management retjllir~meot to. mit,igpte project impi:lctstp
southbound El Cam,ino Real c1t Faraday AveouJ! lefHurn pockets. Staff anticipated incorporating
the cost of the lefMurn pocket modificatiops into the fiscal year 2021-22 CIP Budget request,
but this will likely be deferred to a future date:
. NextSteps
Staff currently anticipate that the pr_oject applii;ation, revised reports and up.dated
environmental docJ.J_ment will be deeme_d complete and subsequently posted for P,UbUG review
in June 2021. The revi.sed tiroeline is as fol_lows:
June 2021
August1Q21
October 2021
March 2022·
February 2023
June 2,0_24
Post Conditional Use Permit (CUP) application documents for pubfo::.review
Planning Commission f!ppro1,1al of CUP
Request C;'.ity Co.uncil approval of bridging documents
Requestcl'ty Co,uridl _approval of design~build contract
Design-builder completes desigp and permitting for start Qf construction
E,stbnc1t_eg comp.letJon of1:onstruction
Public;·Works Brc1_nch
Fle~t ~ Facilities Department
1635 Far~day Avenue l Carlsbad, CA 92008 l 760-602~2730
I I I. .,
I r ' .L i I
Council Memo -Orion Center Project Update (District 2)
APiil 2~i :2021
Page2
Attachment: A. eouncil Memorandum dated March 11, 2021
cc: Scott Chadwick, City Manager
Celia Brewer, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha; Deputy City Manager, Administrative Services
Robby Contreras, Assistant City Attorney
Tom frank, Transportation Director
I<yle Lancaster, Parks & Recreation Director'
Jeff Murphy, tommynity Development Director
Vjcki Quiram, UtiliVes Director
John Maashoff, Public Works M,mager
David P~dilla, Engineering Manc1ger nm Selke, ParksServices Manager
Babaq Taj, l::ngh;eering Mat1ager
James Wood, Ehvironmental Manager
DaviJ! Pa.r:lilla, Engineering Manager
St¢Ven Stewart, Munidpal Projects Manager
)
Tg tpe member,s of the;
€11Y COUNCIL · oat~g/tr /2.t cA :L cc J .
-CM€~:,£.l(@K/I__L DCM {3) _L
MarJ:h-11, 1021
ATTACHMENT A -' + ••• ----• -
CounGif M.e)norandum
T9;
From:
Honorable NJayor Hi:111 ,fnd0 Meml:lei's_ of tlieCity Council
Paz Gomez, Deputy Qty ~aoa~1rr,J'1.Jijli~rks
Via:
~e:
Geoff Patnoe, Assistant City Ma11ag~r f2il'
Oriol, Center, Project Update (Dis(rktil'--,
_ {cityof
Carl$oad
Memo ID #2021058
This n,emor§p_clu111-proviffes:c1n update to a previou~ _memorand!-(m clct!~d Oct. 1, 2020, on the
status-oftlie Orion:Cer,_tet Proj~ct, Capital lmprovementprogr~m (c:IP) Projfc_t No. 3572
(project), wh~h wW con$trJl_t{f! l!laintenance and operation_s focili!y that will lioLJse f>ublic
Works Branch and Parks & Recreation Department field staff.
Background
As of the la'st p'rojec_t u_pd~Je Qn Oct. 11 2020 (Attachment A), staff and project cpnsultaots have
contih~ed to work-toward revising andJimilizingthe local mobility aoalysJs {LMJ.Q,
transportation demand m_anagement (TD_!vl) plan and the_. vehicle miles traveled {Vf'-'.'(:0 aoalysjs
foWthe project: ---
Discussion
ln December 2020, staff was conce_rnedthat the VMT ana!ysis being prepared by t_he trafftc
0engirieering. consult~mt was _not prC>gresslrtg-,is-expette-d. Jn J_anllary 2021, staff retainecfFebr &
Peers; aconsultantthat h~lpec! the Cotn_rn~Q.i!\i _p_elleJop&Jent (Cb) Department preparefhe
citbV[ii[T analysis guide, to prepare an independent VMT arjalysisfor the Orion Center p;rnject
On feb; 12, 2021, Fehr & Peers comP-_iefod tl'\eir-compreh~ns1ve a'nalysi~ and submitted it for
city review~ On feb. 23, 2021, CD staff reJLJrned revlew,corr11nents, aRd the analysis is currently
being Qpaated by Fehr & Peers.
hJ Ja11uary }.021, qn updated version of the LMA report and TQM plan were submitted to CD
staff, wh_o-ret_u(ned review comments last month. Tbe curr-entlyidentified measures to mitigate
thetran;mcirfotion ~y~tem management (TSM) requfrernents ili<;_lu_gep_ilymemt of a fair-share
contributtort t~wa~c! extending the left-turn pockets Qrfs-outnbouod El Camino Real at Faraday
Avenue and p~ying for signal controller modifi<:;~tioris atthat intersection. lhe costs ofthe
roadway modi_fitatio6s are ~ntlcipated to be incorporated into the _ClP 1;3(!c:![et forfiscal year
2021-22.
Next Steps
Staff anticipates thattbe Q_ro)ett application, revised reports and updated environmental
document will be cjeern_ed complete and subseq_uently posted for public review in April 20~1.
Public Works Branch
Fara-day tenter 1635 Faraday Ave I Carlsbad, C,A !!2008 I 760-602-2730 t
t I
I ' ' '
' t i
Council"Memo -Oriofr Center Pr0ject Update (Distri~t 2)
March 11, 2021 ·
Page 2
The re,vis,ed projecUime,lipe is as follcilfl.ls:
April2021
June/July 2021
Qctober 2021
January I022
October 2022
. feb.ruary,2oi,4
Pos~ Conqitiorial Use Permit (CUP) appli~atioh . c(pcu·ments for public
revi.~w
Plarming <;omm,ission approvai of CUP
RequesJ City Council approval of britlgi11g docament,s
Regu~st City Council approval CJf de~fgn_-build con~ract
Design~builder.completes design a11_tl'perinitting for sfart of construction
Estimated comgletioh of construction
Atfachment:A. Coun_c;il Memorandum dated Oct. 1, 2020
cc: -~fo!t,CbasJi,yic~,-,CityMauag~J
Cella Bi:_ewer; ~hi,a;norney -
f}ary Bar6edo,_D~fiuly Cit'{ rv1_ana-ger, Conimunlty s~_rvices
L,aura Roclfa~ Depu:ty:City Ma_nager; Administrative SeMh~s
~ob ~y CQ,ntr:etc!?, AssJst_aritCity1\1torruw
Tom frank, Transgo't'tafiQo .bitector
Kyle Lancaster,.Parii§ 8/!tecreru:ion Qirector
Je~ff-MurphV,J::omJ!ji,tnity Dev~_logm~~!ltl"i•H~Jtor
\/ick_i Qu(rami U1:ilities DirectQr -·
Jolin l\/laasfioff, 'Puolic Wor~s-Ma.11ag~r
David P..idil!a,-l::i1gineering.Manager·
Tim S.elkt, parks ServicesMitnager
Babaq Taj;En,gilieeringManage~
James Wood, Environmental Manager ,"
Steven Stewart, Municipal Projects l\llc1nager
To~he mernb§rs of the:
· CITY CQ_UNCl t . . .
pate 10/i /2JJCA V . c;¢_ 'f'_ ,CM ~/,,_CM ? ·. p_qt\n'[3f';; ..
Oct.1, 20~0
t_q_; . Ho11Qnijil~ 1\/layg_r Hall and l\.'.)eq,~bers_9{the Ci~ycouncil
From: (>qZ ~·omez, Dep4ty my Manage·r, Pu_plic Works
.G~_r(Ba! __ p~tl?~\;>e~uty ci~y Mitiw~er, C~nityServices
\iia: Geoffr1?at110.@;_Ass1s~nt Cltyl\/lanaget e-
J!e:' _Qrio!l_C~!}J~r Prc&ect ~pdate .
AttachmentA
(cityof -
Car]sbad .
Memo ID #io20203
This 1lie'.m~-r~ndum ptcivides an update on the status-of the Orion Center ProJect, <;:apital
Improvement P·rcigram -{CIP) Project No. 3572 (project)1 which wilJ <;.onstruct-a maintetiant~ang
operations facility that will house Public Works Branch c!tld Parl_cs b~,~~~rtm~nt ffo!gst:_a_ff~ . -
B1:1ckground
Sihce. the last project update sybmitted on May 9,. 201i Puiiltc Works ~taff h~ q_~en wo_tl~Lng
diligElntly with Roesfrng Nakamura Terada ArchitectsJ In-;;. (RNT) and Griffin struttures, Inc: (GSI)
to address regulatory and other c9inments ralsecfby CommunitycQevE!lgpinentstaffregardihg
the Conditipnal Use Pe,:mit (CU_P) ilRPlka_!ioo, wjjicb l{llas_o_Jjglo~iiy_~ubrnittE!cUo Dec:emper ·
2018; T~e comments were related_-to st9rmwateJ tr-e;:i__trtient ang conrrol, la-ndscaping, fire
safety and traffic,impacts-~nd fi!1t1~at1on..: -----·. ---
Over the course oJ the year,:city staff worJceg_ withttie co_n~ulta11tsto address potential impacts
and develop apgrof:ir-i~te.-[JIJtjg~fiqh n,e~!!f~S ~~ pro]e_ctmCJqlijcati6ns to ensure the project
c;o111pli~d Witb appi:opri~te 1~!1~ !JS~ n~gl,Jj_giJb!'rsrJ0Bcirtlcll_l,?r,traffic impacts.
In ial:e Wl9, staffw~din<:1lizii1gthe dtaft .environmental diS-~ument to prepare for public review.
The 01itigatio_n me~sure_s tb~tll){ere igentified to addrt;ss traffic impacts included payroent of a
fai t~~llilre ~Qnfrll:i_ution-towafdi:he co~t of §>C_tendio-gthe left-turn lanes at the intersections ofEI
Cami~o Ret:11/i=araBav Al;;en1.tecll1Ji:l EJ Caniihb Reai/Palotnar Airport Road.
Hgweygr, QD Ja,ri. ti, io;w, stati'Jnfor.med the City Council that the city's Climate Action Pl~ri
(i AP) con_taifi~.~-arf. ih~o~recJ c;alcl!lation of the vehicle miles traveled (VMT), andfor t~t1_t ·
re~son, the-€AH; was"u11qualified" as a mitigation tool to add res~ and mjtigate prqj~_ct{evel
1rripacts r~sult,ingfr9 m greenhous~gas (GHG) emissions. Because the ¢.<!.lifornia En.vi,:obrnental
Quality Act (CEQA) determinat_iqn forth,e Orlon Center Project relied on the CAP to ad~res_$
G}fG 1mpae::ts; the project could not move forwa,rd until either a $ite:-spe,cifir.;G_HG amilys~ wa~
~i'ept1_red or the CAP deficiencies were addressed. ·
Public Works Branch
Faraday Center 1635 Far~day Ave I Carlsbad, CA 92008 I 760-602-2730
' . ' I r I, 1
I( I.
I f ; I I' i
f f I L
,,
I.
I
J . J
r
-Council Memo -orion Center Project l:lpd<1te,
0W-1, 2020
Bag¢2
On j~ne16, :fow, tfie City Q::iu11dtJ~~pted ~'e\/\/ Vehicl~ Miles TraveledNIVlTl standards
p.!;!rsyant tei__,sl~t~,law and; oft JyJv J_t 2Qio~ ihe (i;m, (;;oJmci! ;:ir>~ro1Jed a re_\[l~.eo <ZA~, '.which
r~sµlted ina qualified CAP that_fo_yjd_a~?in be used•to adgre?s p,roJect-le'@l §HG impacts,
G11Sept, 21, 2020, t_he consJJJti~g-t~~msubniitt~d !-J!Jdaj:~d tni{fkit;npact reports_ ancl studies to
shQ\11/ (10!J1()fi~nce 1iYith the ~~wia__odm-ds; w~leh are currintlyb__~ing revjeYl(ed by Staff.
,fl,!eil!i$t~pj _
Staff'anticlpates tliat tlfe pJojett apLpncation, revised reports and upclated environmental · Qt_~tim~~twili_lle: d¢~1)ied ~omi1i te<1:,~d~subseq~e~tly p~o~t~d-fpr p_~bli~ revi~~ ih e~-riy~.
D§eemJtefr'i The r§vis~g {i_i)l_ffeJl,i1~is as-f_f>JloW$:
January 2021 Post co.P-applfcation and environnientai docume_nt for pubiii:: re~iew
March/April 2021 Plannipg£q_mmlssion app,rovi;il of CUP
May/June 2021 Request City Council approval of bridging documents
October 2021 Request Cit\/ Coun~il approval of design-build contract ,
Aug!Js~ 2022 Design-buili:ler completes design and permitting for start of construction
December 2023 Estimated cqmpletion of con;;truction
cc: Scott Chadwick; City Manager
C:elia Brewer, Eity Attorney
Laut a Rp.,.c;hi;l,;g~pyty,City M_anager, Adminis.trathle ~er.vic~s
rQ.fII F_ra_llli; T,rao~p.9rtatfo_11 Qir~ctor
fCyl~ Lanc~sf ~r~ Parks & R~creati.bn D[i'ecJ:or
Jef{M.urp,fiy;,co~muni,t'i Qevetoprner.it-Director
Vicki qui(a,m, f)tiptieS Dii'eft(lr·
JqJib M1ra_shoff;' Pub'lic Wor!cs M:a_n_aggr
Tim ~ell;~; p.~rl<s Seiyl~e~Mar,_ager · ·
Babaq taj, Engioeeripg J\ilanager·
james Wood, Envirbnmental JV(anager . ---. ,.. -
David Paailla, Interim Engineering Manager
I
1
I, !
.,: i
;-
t
l J 1
.I· ;!; I I l l ,,
'I,_,
I :1 "f
r