HomeMy WebLinkAbout2022-10-13; Utility Improvements in the Downtown and Terramar Area Update (Districts 1 & 2); Gomez, PazTo the members of the:
CITY COUNCIL
Dat~\~22.CA__iL'cc /
CM _A M L DCM(3).JL"
October 13, 2022
Cou ncil Me mora ndum
To:
From:
Honorable Mayor Hall and Members of the City Council
Pa z Gomez, Deputy City Manager, Public Works
Via:
{cityof
Carlsbad
Memo ID# 2022 111
Re:
Geoff Patnoe, Assistant City Manager~
Utility Improvements in the DowntoM nd Terramar Area Update (Districts 1 & 2)
This memorandum provides an update on two water and sewer utility replacement projects :
the Carlsbad Boulevard Water and Sewer Improvements at Terramar, Capital Improvement
Program (CIP) Project Nos. 5048 and 5503 (Dist rict 2), and the Downt own and Terramar Water
Main Replacement, CIP Project No. 3904-C (Districts 1 & 2).
Background
Outreach and construction act ivities on these two construction projects have begun and will
continue until the end of 2024, as further described below. Phased construction is planned to
minimize disruption of water service to the residents and businesses served. Public Works staff
are working with the Communication & Engagement Department to reach out in advance of
these critical projects to meet with, notify and coordinate with the businesses and residents
that will be temporarily impacted during these facility improvements.
Carlsbad Boulevard Water and Sewer Improvements at Terramar, CIP Project Nos. 5048 and
5503 (District 2)
A Council Memorandum dated April 7, 2022, provides background information on CIP Project
Nos. 5048 and 5503. This project will replace some of the oldest asbestos cement (AC) water
mains in the city, approximately 5,000 lineal feet, and will abandon and/or remove 7,600 lineal
feet of water mains. It will also replace and/or rehabilitate 1,500 lineal feet of sewer mains and
manholes. The project is located on Carlsbad Boulevard from Tierra Del Oro Street south to
approximately 300 feet south of Manzano Drive. It also includes a one-quarter mile segment on
Cannon Road from Carlsbad Boulevard east across the railroad tracks to Avenida Encinas.
Downtown and Terramar Water Main Replacement, CIP Project No . 3904-C (Districts 1 & 2)
On August 30, 2022, Carlsbad Municipal Water District {CMWD) awarded a contract to Burtech
Pipeline Incorporated for construction of CIP Project No. 3904-C. This project will replace
approximately 4,400 lineal feet of aging AC water mains with eight-inch diameter polyvinyl
chloride (PVC) water mains that serve five residential areas and one business area at the
following locations:
• State Street alley -from Grand Avenue to Carlsbad Village Drive
• Juniper Avenue -from Carlsbad Boulevard to Garfield Street
• Hemlock Avenue -from Carlsbad Boulevard to Garfield Street
Public Works Branch
Utilities Department
5950 El Camino Real I Carlsbad. CA 92008 I 442-339-2722 t
Council Memo -Utility Improvements in the Downtown and Terramar Area Update (Dist. 1 & 2)
October 13, 2022
Page 2
• Garfield Street -from Chinquapin Avenue to southern end of street
• Tierra del Oro Street and Shore Drive -entire streets
Discussion
Carlsbad Boulevard Water and Sewer Improvements at Terramar, CIP Project Nos. 5048 and
5503 (District 2)
The project preliminary design is complete and final design is in progress.
On August 29, 2022, staff presented the proposed utility work to the California Coastal
Commission, which reserves permitting authority north of Cannon Road. Coastal Commission
staff opined that the portion of the project within the Local Coastal Plan area of deferred
certification should qualify for a Coastal Development Permit (CDP) waiver. Staff will continue
to work with the Coastal Commission for approval of the CDP waiver. The Planning Division of
the Community Development Department will also review the project for conformance with
the city's Local Coastal Plan, and staff are preparing the applications to initiate that process.
Subsurface investigations for the project will continue in October 2022 along Carlsbad
Boulevard and Cannon Road. Utility potholing will commence at 20 locations in one to two
weeks throughout the project area. This is a continuation of field exploration which began in
late June when three soil borings were completed at these locations. These investigations will
allow the project design to be finalized in the coming months. Public Works staff are working
with the Communication & Engagement Department on notifications related to these activities.
Water and sewer utilities construction is estimated to commence in fall 2023 and be completed
in late 2024. The project is subject to the Coastal Commission's summer work moratorium, and
the construction scheduling constraints to be specified in the contract documents will be
developed in consideration of CIP Project No. 3904-C construction activities.
Downtown and Terramar Water Main Replacement, CIP Project No. 3904-C (Districts 1 & 2)
Construction of the Downtown and Terra mar project will commence in the coming
months. Construction activity is anticipated to start at Tierra del Oro Street and Shore Drive,
followed by the State Street alley site, then at three other sites on Garfield Street, Hemlock
Avenue and Juniper Avenue.
Construction will occur over an estimated 14-month period with minimal work during summer
months. All the sites have scheduling challenges related to the summer construction
moratorium on Carlsbad Boulevard, the Farmer's Market at State Street, or water demand
requirements of the Hubbs Research Center, which leaves limited options for construction
scheduling. The construction periods for each site will be determined within the next several
weeks with the approval of the contractor's construction schedule.
Phased construction is planned to minimize disruption of water service to the residents and
businesses served. Public Works staff are working with the Communication & Engagement
Council Memo -Utility Improvements in the Downtown and Terramar Area Update (Dist. 1 & 2)
October 13, 2022
Page 3
Department to reach out in advance of this critical project to meet with, notify and coordinate
with the businesses and residents that will be temporarily impacted during these facility
improvements.
Next Steps
An estimated timeline for future utility improvement work in the Downtown and Terramar
areas is as follows:
• October 2022 -Subsurface utility investigations/potholing work will occur in Carlsbad
Boulevard and Cannon Road, as part of Carlsbad Boulevard Water and Sewer
Improvements at Terramar, CIP Project Nos. 5048 and 5503
• December 2022 -Construction is expected to commence on the Downtown and
Terramar Water Main Replacement, CIP Project No. 3904-C
• Fall 2023 -Estimated construction start of the Carlsbad Boulevard Water and Sewer
Improvements at Terramar, CIP Project Nos. 5048 and 5503
• Early 2024 -Estimated construction completion of the Downtown and Terramar Water
Main Replacement, CIP Project No. 3904-C
• Late 2024 -Estimated construction completion of the Carlsbad Boulevard Water and
Sewer Improvements at Terramar, CIP Project Nos. 5048 and 5503
Attachment: A. Location Map -Carlsbad Boulevard Water and Sewer Improvements at
Terramar, CIP Project Nos. 5048 and 5503
B. Location Map -Downtown and Terramar Water Main Replacement, CIP
Project No. 3904-C
cc: Scott Chadwick, City Manager
Cindie McMahon, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Mickey Williams, Police Chief
Michael Calderwood, Fire Chief
Robby Contreras, Assistant City Attorney
Vicki Quiram, Utilities Director
Tom Frank, Transportation Director/City Engineer
Kyle Lancaster, Parks & Recreation Director
Jeff Murphy, Community Development Director
Kristina Ray, Communication & Engagement Director
Babaq Taj, Engineering Manager
Dave Padilla, Utilities Engineering Manager
Hossein Ajideh, Engineering Manager
John Kim, City Traffic Engineer
Nathan Schmidt, Transportation Planning and Mobility Manager
Eric Lardy, City Planner
(_ City of
Carlsbad Carlsbad Boulevard Water & Sewer Improvements j
Project Location Map i Not to Scale
LOCAT ION MAP Page 1 of 4
NOT TO SCALE
PROJECT LOCATION
STATE STREET
ALLEY
PROJECT LOCATION
JUNIPER AVE.
PROJECT LOCATION
HEMLOCK A VE.
NOT TO SCALE
VICINITY MAP
PROJECT LOCA
GARFIELD ST.
PROJECT LOCATION
TIERRA DEL ORO
ST.
PROJECT LOCATION
SHORE DR.
PROJECT NAME PROJECT
DOWNTOWN AND TERRAMAR WATER NUMBER
MAIN REPLACEMENT PROJECT 3904 -C B
LOCATION MAP Page 2 of 4
NOT TO SCALE D
\
PROJECT NAME PROJECT TTACHMEN
DOWNTOWN AND TERRAMAR WATER
MAIN REPLACEMENT PROJECT
NUMBER
3904 -C B
LOCATION MAP
NOT TO SCALE
NOT TO SCALE
VICINITY MAP
PROJECT NAME
DOWNTOWN AND TERRAMAR WATER
MAIN REPLACEMENT PROJECT
Page 3 of 4
PROJECT
NUMBER
AGUA
HEDIONDA
LAGOON
TTACHMENT
3904 -C B
LOCATION MAP Page 4 of 4
PROJECT SITE (
\ NOT TO SCALE
\
\
\
NOT TO SCALE
VICINITY MAP
PROJECT NAME
DOWNTOWN AND TERRAMAR WATER
MAIN REPLACEMENT PROJECT 3904 -C B