Loading...
HomeMy WebLinkAboutPUD 2020-0001; HEMLOCK COAST HOMES; PRELIMINARY HYDROLOGY STUDY; 2020-09-01PRELIMINARY HYDROLOGY STUDY FOR TENTATIVE PARCEL MAP I MINOR SITE DEVELOPMENT PLAN/ COASTAL DEVELOPMENT PERMIT HEMLOCK COAST HOMES -320 HEMLOCK A VENUE DEV 2020-0023 CITY OF CARLSBAD, CA PREPARED FOR: KMJ REAL ESTATE 2888 LOKER A VENUE EAST, SUITE 200 CARLSBAD, CA 92010 PH: (949) 678-4927 PREPARED BY: PASCO LARET SUITER & AS SOCIA TES, INC. 535 N. HIGHWAY 101, SUITE A SOLANA BEACH, CA 92075 PH: (858) 259-8212 Prepared: September 2020 BRYAN ANDREW KNAPP, PE #86542 DATE No. 86542 p. 03/31/ Executive Summary Introduction Existing Conditions Proposed Project Conclusions References Methodology Introduction TABLE OF CONTENTS County of San Diego Criteria Runoff Coefficient Determination Hydrology & Hydraulic Model Output Pre-Developed Hydrologic Calculations (100-Year Event) Post-Developed Hydrologic Calculations (100-Year Event) Pre-Developed vs. Post-Developed Peak Flows (100-Year Event) Detention Analysis Appendix Isopluvial Maps Intensity Duration Design Charts Runoff Coefficients Hydrologic Soil Group -USDA Web Soil Survey Pre-Development Hydrology Node Map Post-Development Hydrology Node Map SECTION 1.0 I.I 1.2 1.3 1.4 1.5 2.0 2.1 2.2 2.3 3.0 3.1 3.2 3.3 3.4 4.0 PLSA 3392-01 1.0 EXECUTIVE SUMMARY 1.1 Introduction This Preliminary Hydrology Study for the proposed development at 320 Hemlock A venue, known as Hemlock Coast Homes, has been prepared to analyze the hydro logic and hydraulic characteristics of the existing and proposed project site. This report intends to present both the methodology and the calculations used for determining the runoff from the project site in both the pre-developed (existing) conditions and the post- developed (proposed) conditions produced by the 100-year, 6-hour storm. 1.2 Existing Conditions The subject property is located along Hemlock A venue, northeast of the intersection of Hemlock A venue and Garfield Street, in the City of Carlsbad. The site is bound by a combination of existing single-family and multi-family developments to the west, north, and east, as well as Hemlock A venue, a public road, to the south. The existing site consists of a single-family residence, driveway, walkways, landscaping, and miscellaneous improvements typical of this type of development. The project site is located in the Agua Hedionda Hydrologic Area, and, more specifically, the Los Monos Hydro logic Sub-Area (904.31) of the Carlsbad watershed. The subject property has an approximate area of 0.189 acres and is approximately 34% impervious in the existing condition. Per the Web Soil Survey application available through the United States Department of Agriculture, the basin is generally categorized to have type B hydrologic soils. Based on the existing impervious area and land use type, a pre-development weighted runoff coefficient of 0.47 was calculated for the subject property using the methodology described in section 3.1.2 of the San Diego County Hydrology Manual and the formula provided therein. After review of the site edge conditions, existing topography, and adjacent developments, it was determined that there is no additional offsite runon entering the site from the neighboring properties. The existing site can be categorized into one (1) major drainage basin, with one (1) primary discharge location leaving the property. Drainage basin EX-1 consists of the entirety of the project site and primarily drains from the northeast comer of the property to the southwest, discharging to the Hemlock A venue right-of-way by surface and sheet flow methods. Once in the Hemlock Avenue right-of-way, runoff leaving the site travels west in the existing curb and gutter toward an existing storm drain sump curb inlet approximately 100 feet west of the property. Once surface flow enters the curb inlet, it is conveyed east in the underground public storm drain system toward the Coastal Rail Trail and outlets on the surface of the SDNR right-of-way. From there, runoff is ultimately conveyed south to outlet in the Agua Hedionda Lagoon prior to entering the Pacific Ocean. Using the Rational Method Procedure outlined in the San Diego County Hydrology Manual, a peak flow rate and time of concentration was calculated for the 100-year, 6- Page 1 of 11 PLSA 3392-01 hour storm event for the onsite drainage basin. Table 1 below summarizes the results of the Rational Method calculations. EXISTING DRAINAGE FLOWS DRAINAGE DRAINAGE AREA Q100 lioo AREA (ACRES) (CFS) (IN/HR) EX-1 0.189 0.58 6.59 Table 1. Existing Condition Peak Drainage Flow Rates Refer to pre-development hydrology calculations included in Section 3 .1 of this report for a detailed analysis of the existing drainage basin, as well as a pre-development hydrology node map included in the appendix of this report for pre-development drainage basin delineation and discharge locations. 1.3 Proposed Project The proposed project includes the demolition of all existing onsite improvements and the construction of two (2) new multi-family/ duplex structures consisting of four (4) total condominium units. The project proposes a driveway to provide vehicular access to the proposed garages consisting of two types of pervious pavers, delineated by color, style and finish to demarcate proposed walkway locations. Two private onsite parking stalls interior to the site are also shown for site residents. The proposed pad elevations for the two structures are 56.6, which appears to be roughly the same elevation as the existing residence. Site grading, drainage and utility improvements typical of this type of multi- family residential development will also be constructed as can be seen on the Preliminary Grading Plan prepared by Pasco, Laret, Suiter & Associates under separate cover. The subject property is approximately 53% impervious in the proposed condition. Based on the proposed impervious area and land use type, a post-development weighted runoff coefficient of 0.59 was calculated for the subject property using the methodology described in section 3 .1.2 of the San Diego County Hydrology Manual and the formula provided therein. The proposed site consists of one (1) major drainage basin, with one (1) primary discharge location from the southwest comer of the property similar to the existing condition. Drainage basin PR-1 consists of the entirety of the site and will continue to convey runoff generally from a high point in the northeast comer of the site to the Hemlock Avenue right-of-way by means of surface flow. A concrete ribbon gutter located at the center of the pervious paver driveway will also serve to capture and convey drainage to the existing curb and gutter along Hemlock A venue. Using the Rational Method Procedure outlined in the San Diego County Hydrology Manual, a peak flow rate and time of concentration were calculated for the 100-year, 6- hour storm event for the onsite drainage basin. Table 2 below summarizes the results of the Rational Method calculations in the post-developed condition. Page 2 ofll PLSA 3392-01 PROPOSED DRAINAGE FLOWS DRAINAGE DRAINAGE Q100 AREA hoo AREA (ACRES) (CFS) (IN/HR) PR-1 0.189 0.74 6.59 Table 2. Proposed Condition Peak Drainage Flow Rates Refer to post-development hydrology calculations included in Section 3 .2 of this report for a detailed analysis of the proposed drainage basin, as well as a post-development hydrology node map included in the appendix of this report for post-development drainage basin delineation and discharge locations. In an effort to comply with the City of Carlsbad storm water standards, the proposed site has incorporated LID design techniques to optimize the site layout. Runoff from proposed roofs and new or removed and replaced hardscape areas will be directed to landscaped areas or pervious pavers in an effort to disperse drainage to pervious surfaces. The landscaped areas will assist to remove sediment and particulate-bound pollutants from storm water. In addition, the storage layers of the pervious pavers will help to mitigate peak runoff by providing detention volume as well as slightly increasing the site's overall time of concentration. Refer to Section 3.4 of the report for a static detention analysis showing that the increase in overall volume generated by the slight increase in hardscape is accounted for in the gravel storage layer of the pervious pavers. 1.4 Conclusions Based upon the analysis included in this report, there is an increase of ~0.16 cfs in peak runoff as a result of the proposed development due to the 1,605 square feet of additional hardscape in the proposed condition as compared the existing site. Similar to the existing condition, the project will discharge from one (1) location leaving the property in the southwest comer to the Hemlock Avenue right-of-way. Thus, water will not be diverted away from existing drainage patterns, and the increase in proposed impervious area and resulting peak runoff -before taking into account the detention qualities of the proposed pervious pavers -will not have an adverse effect on the downstream watershed. The inherent detention characteristics and storage volume provided in the gravel layers of the pervious pavers will assist to detain and mitigate peak runoff to pre-project conditions. The proposed project will be exempt from hydromodification compliance requirements as it does not qualify as a Priority Development Project as defined in the Regional Municipal Separate Storm Sewer System (MS4) Permit and the San Diego County Model BMP Design Manual. Page 3 ofll PLSA 3392-01 1.5 References "San Diego County Hydrology Manual", revised June 2003, County of San Diego, Department of Public Works, Flood Control Section. "San Diego County Hydraulic Design Manual", revised September 2014, County of San Diego, Department of Public Works, Flood Control Section "City of Carlsbad Engineering Standards, Volume 5: Carlsbad BMP Design Manual (Post Construction Treatment BMPs) ", revised February 2016 "Low Impact Development Handbook-Stormwater Management Strategies", revised July 2014, County of San Diego, Department of Public Works Soil Survey Staff, Natural Resources Conservation Service, United States Department of Agriculture. Web Soil Survey. Available online at http://websoilsurvey.nrcs.usda.gov. Accessed September 2, 2020 Page 4 ofll PLSA 3392-01 2.0 METHODOLOGY 2.1 Introduction The hydrologic model used to perform the hydrologic analysis presented in this report utilizes the Rational Method (RM) equation, Q=CIA. The RM formula estimates the peak rate of runoff based on the variables of area, runoff coefficient, and rainfall intensity. The rainfall intensity (I) is equal to: Where: I= 7.44 x P6 x o-0·645 I = Intensity (in/hr) P6 = 6-hour precipitation (inches) D = duration (minutes -use Tc) Using the Time of Concentration (Tc), which is the time required for a given element of water that originates at the most remote point of the basin being analyzed to reach the point at which the runoff from the basin is being analyzed. The RM equation determines the storm water runoff rate (Q) for a given basin in terms of flow (typically in cubic feet per second (cfs) but sometimes as gallons per minute {gpm)). The RM equation is as follows: Where: Q=CIA Q = flow (in cfs) C = runoff coefficient, ratio of rainfall that produces storm water runoff (runoff vs. infiltration/evaporation/absorption/etc) I= average rainfall intensity for a duration equal to the Tc for the area, in inches per hour. A = drainage area contributing to the basin in acres. The RM equation assumes that the storm event being analyzed delivers precipitation to the entire basin uniformly, and therefore the peak discharge rate will occur when a raindrop that falls at the most remote portion of the basin arrives at the point of analysis. The RM also assumes that the fraction of rainfall that becomes runoff or the runoff coefficient C is not affected by the storm intensity, I, or the precipitation zone number. Page 5 of 11 PLSA 3392-01 2.2 County of San Diego Criteria As defined by the County Hydrology Manual dated June 2003, the rational method is the preferred equation for determining the hydrologic characteristics of basins up to approximately one square mile in size. The County of San Diego has developed its own tables, nomographs, and methodologies for analyzing storm water runoff for areas within the county. The County has also developed precipitation isopluvial contour maps that show even lines of rainfall anticipated from a given storm event (i.e. 100-year, 6-hour storm). One of the variables of the RM equation is the runoff coefficient, C. The runoff coefficient is dependent only upon land use and soil type and the County of San Diego has developed a table of Runoff Coefficients for Urban Areas to be applied to basin located within the County of San Diego. The table categorizes the land use, the associated development density ( dwelling units per acre) and the percentage of impervious area. Each of the categories listed has an associated runoff coefficient, C, for each soil type class. The County has also illustrated in detail the methodology for determining the time of concentration, in particular the initial time of concentration. The County has adopted the Federal Aviation Agency's (FAA) overland time of flow equation. This equation essentially limits the flow path length for the initial time of concentration to lengths under 100 feet, and is dependent on land use and slope. The time of concentration minimum is 5 minutes for purposes of calculating rainfall intensity per the County of San Diego Hydrology Manual requirements. 2.3 Runoff Coefficient Determination As stated in section 2.2, the runoff coefficient is dependent only upon land use and soil type and the County of San Diego has developed a table of Runoff Coefficients for Urban Areas to be applied to basin located within the County of San Diego. The table, included in the Appendix of this report, categorizes the land use, the associated development density ( dwelling units per acre) and the percentage of impervious area. For this study, a weighted runoff coefficient was used for both the pre-project and post- developed site in accordance with the equation provided in Section 3.1.2 of the County of San Diego Hydrology Manual. The weighted runoff coefficient is a function of the total impervious and pervious surface areas in the existing and proposed conditions. Page 6 ofll PLSA 3392-01 3.0 HYDROLOGY MODEL OUTPUT 3.1 Pre-Developed Hydrologic Model Output (100-Year Event) Pre-Development: *Rational Method Equation Q=CIA P100= 2.5 * 100-Year, 6-Hour Rainfall Precipitation Basin EX-1 Total Area= 8,241 sf-+ 0.189 Acres Impervious Area= 2,760 sf-+ 0.063 Acres Pervious Area= 5,481 sf-+ 0.126 Acres Cn, Weighted Runoff Coefficient -0.25, Cn value for natural ground, Type B soils * Per San Diego Hydrology Design Manual (SDHDM) Section 3.1.2 -0.9, C value for developed/ impervious surface * Per SDHDM Section 3.1.2 Cn = 0.9 x 2,760 sf+ 0.25 x 5,481 sf= 0.47 8,241 sf Tc= 5.0 Min r = 7.44 x P6 x o-0·645 *Minimum Tc for Rainfall Intensity per SDHDM *Rainfall Intensity Equation r = 7.44 x 2.5 x 5.o-0·645 ::::: 6.59 in/hr Q100 = 0.47 x 6.59 in/hr x 0.189 Ac= 0.58 cfs Page 7 ofll PLSA 3392-01 3.2 Post-Developed Hydrologic Model Output (100-Year Event) Post-Development (without considering HMP/BMP treatment): *Rational Method Equation Q=CIA P100= 2.5 * 100-Y ear, 6-Hour Rainfall Precipitation Basin PR-1 Total Area= 8,241 sf-+ 0.189 Acres Impervious Area= 4,365 sf-+ 0.100 Acres Pervious Area= 3,876 sf-+ 0.089 Acres Cn, Weighted Runoff Coefficient -0.25, Cn value for natural ground, Type B soils * Per San Diego Hydrology Design Manual (SDHDM) Section 3.1.2 -0.9, C value for developed/ impervious surface * Per SDHDM Section 3.1.2 Cn = 0.9 x 4,365 sf+ 0.25 x 3,876 sf= 0.59 8,241 sf Tc= 5.0 Min 1 = 7.44 x P6 x o-0·645 *Minimum Tc for Rainfall Intensity per SDHDM *Rainfall Intensity Equation 1 = 7.44 x 2.5 x 5.o-0·645 :::::: 6.59 in/hr Q100 = 0.59 x 6.59 in/hr x 0.189 Ac= 0.74 cfs Page 8 ofll 3.3 Pre-Developed vs. Post-Developed Peak Flows (100-Year Event) Total Pre-Development (Discharge Leaving Site) Basin EX-1 Q100 = 0.58 cfs *Discharging from the site at the southwest comer to Hemlock A venue Total Q100 = 0.58 cfs Total Post-Development (Discharge Leaving Site) Basin PR-1 Q100 = 0.74 cfs *Discharging from the site at the southwest comer to Hemlock A venue Total Q100 = 0.74 cfs Pre-Development vs. Post-Development (Discharge Leaving Site): Delta PLSA 3392-01 Pre-Development Q100 = 0.58 cfs Post-Development Q100 = 0.74 cfs 0.16 cfs increase 3.4 Detention Analysis The 100-year, 6-hour storm event detention analysis was performed in accordance with Chapter 6 of the San Diego County Hydrology Manual (SDCHM). The results of the analysis provide a static detention requirement by comparing the total volume produced by the 100-year, 6-hour storm in the existing and post-project conditions. The total volume can be calculated after producing a hydrograph for each event (pre-and post- developed) with the results of the Rational Method analysis. Calculations and results of this analysis can be shown below. The proposed pervious pavement driveway provides mitigation of the 100-year, 6-hour storm event peak flow rate. Underneath the paver units and bedding layer is a 6-inch gravel storage layer that provides sufficient detention volume to offset the increase in total volume generated in the proposed condition due to the increase in overall hardscape. See sections 3.4.1 and 3.4.2 below for the results of these calculations. Page 9 ofll 3.4.1 Static (No Routing) Detention Calculation Pre-Development: 100-Year Event (Basin EX-I) PLSA 3392-01 Volume = C*P6* A *Equation 6-1 of SDCHM Volume= 0.47 * (2.5 in* 1 ft/ 12 in)* (8,241 SF)= 807 CF Post-Development: 100-Year Event (Basin PR-I) Volume= C*P6*A *Equation 6-1 of SDCHM Volume= 0.59 * (2.5 in* 1 ft/ 12 in)* (8,241 SF)= 1,013 CF Required Detention Volume = Total Post-Development -Total Pre-Development = Basin PR-I -Basin EX-I = 1,013 CF-807 CF= 206 CF -> 206 CF static storage required for proposed basin PR-I 3.4.2 Pervious Pavement Drive Aisle -Storage Detention Volume Provided = Driveway Area x 6" Gravel Layer x 40% Voids = 2,930 SF* (6 in* 1 ft/ 12 in)* 0.40 = 586 CF PERVfOUS PAVERS • TYPICAL DETAIL 586 CF storage in gravel layers under pervious paver driveway > 206 CF static storage required for drainage basin PR-1 per SDCHM. ** As stated in the conclusion of the report, the slight increase in total peak flow leaving the project site will be mitigated by the storage volume provided by the pervious pavers proposed throughout the site, as shown above. Refer to Sheet 3 of the Civil plans prepared by Pasco, Laret, Suiter & Associates for the Tentative Parcel Map (MS) and minor Site Development Plan application under separate cover for a cross-section of the pervious pavers showing a gravel storage layer underneath the paver and bedding layers. Page 10 of 11 PLSA 3392-01 4.0 APPENDIX Page 11 of 11 0 C') 0 I"-.... ..... "'O ~ () ro ..... ;:... ..... .... 0 0 0 I"-.... Riverside County ro v 0 <D .... .... ,-· . ~ : 0 C') (0 ..... ..... ro ..... (0 ..... ..... . . . . . . . . . . . . . . 33°30' 33°00' ----------t----==';;;;_-0 ---------------i~l:J;;~~~~+=...c:.._.1....,,.,J-4L-J:.--\--+~.:_1,,;',l--~:_ __ .1.,""':.c=~---i----!---+-,'~l---f-~Q..~~~-~;l_--..\.-----------_j-~':_' _____ _ () 3°00' 32°45' 32°30' 0 ro C') ..... 0 0 r--r--..... .... 0 0 0 r--.... . . . ro v 0 <D .... fS,q.'. C(?UN"N •• • I I • •• . , . : '• : ~ "Q . M e XI C 0 C') 0 <D ... ... 3 "O (D :::::!. Q) () ········· 0 ..... -.. . .. ' . C: ::::J :j~'< 2°45' ,;.:;::.;.-.;;::::::::~--' · ...... ro ... 0 <D ... 32°30' County of San Diego Hydrology Manual Rainfall Isopluvials 100 Year Rainfall Event -6 Hours lsopluvial (inches) DPW ~GIS S.-GIS ,L an We Have San Diego Covered! THIS MAP IS PROVIDED WITHOUT WAAR>HTY OF N('( KJNO, BTHER EXPRESS OR IMPLIED, INCLUDING, BUT NOT LI~ TO, lHE IWLIEO WARRANTIES OF MERCHANTABILITY AND FITNESS FOR A PARTICl.ll.AR PURPOSE. Copyright SanGIS. Al Rights Res.-wd • This products rMY contaln rlformation horn the SANOAG Regional Information System W'llc:h CWWl0t be ,llp'Oduced IMh>trt the ---al SANOAG, This product may conta1 Information wtild'I has been reproduced \lllllth peffl'lss1on granted by Thomas Bn:lttw'I Maps. Miles b io C') ..... 0 ;:... ,.._ ..... ..... ..... 33°00' 32°45' 32°30' b io C') ..... 0 0 ,.._ ,.._ ..... ..... .... ..... b 0 0 ,.._ ..... ..... b 0 ;:... Riverside County ,• . . io "<t 0 tO ..... ..... . io "<t 0 tO . . . . ' ' . ... -.. q .. . .. .. .. :::--........... _ -........... .. . .. .. .. . .. .. .. ,;........ ,, ........ . : "!-'~' . . . .. . M e X ' C b C') 0 tO ..... ..... b C') 0 tO .... .... io ..... (0 ..... ..... .. :: : : ::·: . ...-::: .. :. ·:.:::-:~---... ........ .. .. , .... \, .. " I I I .. __ .. .. . . ' .. ........ .. .... .... .. .. ,. .. .. '\ ·.. ,,.. ~ ........ .... ... __ .. .... : ..... ..... / ", . ..... .. ....... 41 ••• : :' .... 4 :6' -,,.: .. ·...... ........ ~ . :" .... , ................ "' ~ ·. '" ...... .. ·-.. ·... ...... ~ ... \ ~ .. , .. \ ... \ \. · .... {(' I I '\ I "• \ \ ·-.... ~--. .. • ' io ..... 0 tO .... .... ' •.• : ' ' ' . / 33°30' . . . . ,• -3°00' 3 "C CD Q) () 0 C: ::J ...... '< 2°45' 32°30' County of San Diego Hydrology Manual Rainfall lsopluvials 100 Year Rainfall Event -24 Hours lsopluvial (inches) DPW ~GIS s:fGIS We Have San Dicgn Cnvcrcd! THIS MAP IS PROVIDED WITHOUT WARRANTY OF ANY KIND, EITHER EXPRESS OR IMPLIED, INCLUDING, BUT NOT UMTED TO. lHE IM>UED WARRANTIES OF MERCHANTABILITY ANO ATNESS FOR A PARTIClA.AR PURPOSE. Copyright SanGIS. All -RoseMld . This -moy oontoln lnfonna11on hom ttle SANDAG Reglonol Information System which cannot be reprodUcad Mf'Klut the ¥ffltten pemnslon d SANOAG. Thlsprodudmoyoontoln __ ... _,_...._ pomuslon g-... by Thomas ........ -· Miles 10.01 <i ct N K i'<L ( j ~I ' I ~11111:litiiliHiiiiiiliiid!liihiidililiihiiii; I I I I I I I l11111l1111d111111, EQUATION I = 7.44 p6 D-0.64S 1f'l! f"N P'N:: I ~~~!1111111 111 1! 11 11111111 = Intensity (in/hr) 1 . '-, I* Pl-, , ~ I p I I I I HI Ill P 6 = 6-Hour Precipitation (in) 1L I I ,:i,.J. I N I !7iiJMtr 7 ~ , > o = Duration {min) 3.01 11 F'N I ! 11''4:::!l l l-t!I IN !fl'II IH™~f!i1H,Lll~IIIIH IIIH I I I 111 111111 1111111 11111111 2.01 I I F"'t..J: I I I I l"1i1,. I I ! 11 !NJ i fl !llllil±!lll™-il R'tl I m+MJ:Jl l!l~ 1-l'-l:I I I I I I I I I 111111111111111 a, ± ~ "'~ I T [ ~· t , J. 1 ~ "',' r-.,..,.. ~ ' U ~ I. ~ _g i N., •~I. ' :, ''°"''r-.r,.~,..,~~~ 4' <i'i '! ! . . ~ l I I r-.. '' "'-,-. ' ~-I ~ £ i i l ~ ~, ) l l ~ r,.., ,. r,. ~ . 6 0 '§: §.1·0 l i ! ,'ii I , ~~ I P r,.. ,...,._ ~ ~ j ! s:s i ~0.9 ! 1 ! I I ,'i ,. ~ ' "' J. 5.0 g ~ o.e · ; i . l i t-... , , ~ ! 4_s 5 a, ! ! 1. . 0 .E O 7 l 1 ~ ·~ 11 ',... ""' ' ~ I 4.0 [ 0.6 .... . ... ' 3.5 - o.51 I I I I I I I I I ll l l l l llll lllllllllllllllllllll ll!II IIN!!l!llllllll l "N:l ll l n-lJ ll llll llll!ft1ll3.o o.,q I I I I I I I I I I 1111 11 111111111 111111111111 I I I llllllllll!IIIIHI~ I I I 11 11-ll 2.5 2.0 1.5 1.0 0.1 \ l I I I I I I ! j I . I > I I I I i ; p i II I I I lj JI 111 I I J I J p . I' I' pt fl ll I JI, sill H I I I I I I I I 5 6 7 S 9 10 15 20 30 40 50 1 2 3 4 5 6 Minutes Hours Duration Intensity-Duration Design Chart -Template Directions for Appllcatlon: ( 1) From precipitation maps determine 6 hr and 24 hr amounts for the selected frequency. These maps are included in the County Hydrology Manual (10, 50, and 100 yr maps included in the Design and Procedure Manual). (2) Adjust 6 hr precipitation (if necessary) so that it is Within the range of 45% to 65% of the 24 hr precipitation (not applicaple to Desert). (3) Plot 6 hr precipitation on the right side of the chart. (4) Draw a line through the point parallel to the plotted lines. (5) This line is the intensity-duration curve for the location being analyzed. Application Form: (a) Selected frequency~ year p (b) p = 2.5 in. p = 4.5 _§_ = 55.6 %(2) 6 -· --• 24 --•p24 -- (c) Adjusted p6<2> = ~ in. (d) tx = ~min, (e) I = 6.59 in.lhr. Note: This chart replaces the Intensity-Duration-Frequency curves used since 1965. 3-1 San Diego County Hydrology Manual Date: June 2003 Table 3-1 Section: Page: RUNOFF COEFFICIENTS FOR URBAN AREAS Land Use Runoff Coefficient "C" Soil T~ee NRCS Elements Coun Elements % IMPER. A 8 Undisturbed Natural Terrain (Natural) Pennanent Open Space 0* 0.20 1 0.25 I Low Density Residential (LDR) Residential, 1.0 DU/A or less 10 0.27 0.32 Low Density Residential (LDR) Residential, 2.0 DU/A or less 20 0.34 0.38 Low Density Residential (LDR) Residential, 2.9 DU/A or less 25 0.38 0.41 Medium Density Residential (MDR) Residential, 4.3 DU/A or less 30 0.41 0.45 Medium Density Residential (MDR) Residential, 7.3 DU/A or less 40 0.48 0.51 Medium Density Residential (MDR) Residential, I 0.9 DU/ A or less 45 0.52 0.54 Medium Density Residential (MDR) Residential, 14.5 DU/A or less 50 0.55 0.58 High Density Residential (HDR) Residential, 24.0 DU/A or less 65 0.66 0.67 High Density Residential (HDR) Residential, 43.0 DU/A or less 80 0.76 0.77 Commercial/Industrial (N. Com) Neighborhood Commercial 80 0.76 0.77 Commercial/Industrial (G. Com) General Commercial 85 0.80 0.80 Commercial/Industrial (O.P. Com) Office Professional/Commercial 90 0.83 0.84 Commercial/Industrial (Limited I.) Limited Industrial 90 0.83 0.84 Commercial/Industrial (General I.) General Industrial 95 0.87 0.87 C 0.30 0.36 0.42 0.45 0.48 0.54 0.57 0.60 0.69 0.78 0.78 0.81 0.84 0.84 0.87 3 6 of26 D 0.35 0.41 0.46 0.49 0.52 0.57 0.60 0.63 0.71 0.79 0.79 0.82 0.85 0.85 0.87 *The values associated with 0% impervious may be used for direct calculation of the runoff coefficient as described in Section 3.1.2 (representing the pervious runoff coefficient, Cp, for the soil type), or for areas that will remain undisturbed in perpetuity. Justification must be given that the area will remain natural forever (e.g., the area is located in Cleveland National Forest). DU/ A = dwelling units per acre NRCS = National Resources Conservation Service 3-6 Hydrologic Soil Group-San Diego County Area, California Map Scale: 1:396 if pmted on A portrait (8.5" X 11") sheet N ----=====--------========Meter.; :I) 0 5 10 20 A ---===------======feet 0 ~ :II 00 00 Map projection: ~ MercalDr C.orner CDOrdinates: WGS84 Edge tic;: UTM Zone llN WGS84 !J_SDA Natural Resources ;..-Conservation Service Web Soil Survey National Cooperative Soil Survey 9/2/2020 Page 1 of 4 Hydrologic Soil Group-San Diego County Area, California MAP LEGEND MAP INFORMATION Area of Interest (AOI) D Area of Interest (AOI) Soils Soil Rating Polygons • A D AID .B BID □ C D CID D D ._J Not rated or not available Soil Rating Lines A AID ~ B ~ B/D C CID D ,. ~ Not rated or not available Soil Rating Points ■ A a AID ■ B ■ B/D USDA Natural Resources :iiiiii Conservation Service C C C CID C D C Not rated or not available Water Features Streams and Canals Transportation +-+-+ ~ Rails Interstate Highways _., US Routes Major Roads local Roads Background • Aerial Photography Web Soil Survey National Cooperative Soil Survey The soil surveys that comprise your AOI were mapped at 1:24,000. Warning: Soil Map may not be valid at this scale. Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale. Please rely on the bar scale on each map sheet for map measurements. Source of Map: Natural Resources Conservation Service Web Soil Survey URL: Coordinate System: Web Mercator (EPSG:3857) Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required. This product is generated from the USDA-NRCS certified data as of the version date(s) listed below. Soil Survey Area: San Diego County Area, California Survey Area Data: Version 15, May 27, 2020 Soil map units are labeled (as space allows) for map scales 1 :50,000 or larger. Date(s) aerial images were photographed: Jan 24, 2020--Feb 12,2020 The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident. 9/2/2020 Page 2 of 4 Hydrologic Soil Group-San Diego County Area, California ~ Hydrologic Soil Group Marina loamy coarse sand, 2 to 9 percent slopes Totals for Area of Interest Description 0.3 Hydrologic soil groups are based on estimates of runoff potential. Soils are assigned to one of four groups according to the rate of water infiltration when the soils are not protected by vegetation, are thoroughly wet, and receive precipitation from long-duration storms. The soils in the United States are assigned to four groups (A, B, C, and D) and three dual classes (AID, 8/D, and C/D). The groups are defined as follows: Group A. Soils having a high infiltration rate (low runoff potential) when thoroughly wet. These consist mainly of deep, well drained to excessively drained sands or gravelly sands. These soils have a high rate of water transmission. Group 8. Soils having a moderate infiltration rate when thoroughly wet. These consist chiefly of moderately deep or deep, moderately well drained or well drained soils that have moderately fine texture to moderately coarse texture. These soils have a moderate rate of water transmission. Group C. Soils having a slow infiltration rate when thoroughly wet. These consist chiefly of soils having a layer that impedes the downward movement of water or soils of moderately fine texture or fine texture. These soils have a slow rate of water transmission. Group D. Soils having a very slow infiltration rate (high runoff potential) when thoroughly wet. These consist chiefly of clays that have a high shrink-swell potential, soils that have a high water table, soils that have a claypan or clay layer at or near the surface, and soils that are shallow over nearly impervious material. These soils have a very slow rate of water transmission. If a soil is assigned to a dual hydrologic group (AID, B/D, or C/D), the first letter is for drained areas and the second is for undrained areas. Only the soils that in their natural condition are in group D are assigned to dual classes. Rating Options Aggregation Method: Dominant Condition Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 100.0% 9/2/2020 Page 3 of 4 Hydrologic Soil Group-San Diego County Area, California Component Percent Cutoff: None Specified Tie-break Rule: Higher Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 9/2/2020 Page 4 of 4 .. PORLOT3 BLCXKR PALJSADES #2 MA/'18()3 EXISTING HYDROLOGY EXHIBIT HEMLOCK COAST HOMES -320 HEMLOCK AVENUE !l~FG PORLOT3 BLOCKR PALJSADES #2 MA/'18()3 A== I I 51.2FG ~IFG -------..... I-ti........ "iii{-4"■'·°"---4■---4■--I I J.IACTNE ..oBSUmNORtN 1-EAC.OCKICML'MPORTSWYDROtOG~~-APPfNDIX\lW-CV-HYCEOWG 57.7 /57.2 TW@EG) /57.2 BW@FG) 51,rw, (51 I BW(tfGJ 57.1 EGJ (56.t8W)@FG PORLOT2 BLCXKR "·' (563TW/IEG) (5618W@'G/ I "'- I ii / BASIN EX-1 A= 8,241 SF Cn=0.47 ~ PARCEL 1 PM 16596 EXJSnNG/ STRUCTURE TOFl£MAI/ NOOEEX-1 1 (55.2FG) 0100 • 0.58 CFS PLAN VIEW -PRE-DEVELOPMENT NODE MAP SCA.LE_ 1•"' 10' HORIZONTAL. I I I I I I ~ EXJSTWG 171?01 I :::~~:., I I I I ~I ~ I :J 1---r-, --,-7'-0TC _ _, LEGEND PROPERTY BOUNDARY CENTERLWE Of ROAD ADJACENT PROPERTY U,E I RIGHT-OF-WA.Y EXJSTWGCCJHT~I.M EXJSTWGPATHOF TRAVEL EXISTWG DIRECTION Of ROW EXISTING IMPERVJOUSAREA UAJ0R. DRAINAGE BASIN 800'/0AAY r2ZZZZVZZ/21 --- BASIN EX-1 · AREA CALCULA T/ONS TOTAL SITE AREA BASINEX·1 roTAt.AR£A BASIN EX-1 IMPERVIOUSAREA BASINEX-1PER\IIOUSAREA s JMPER\?OUS en TIM£ Of CONCENTAA TION UH Sf (O 119 AC} 8.241 SF(0.1S9ACJ 2,760SF(0063ACJ 5.481 SF (0,126;.CJ "" 0.47 5.0 l.tNttrES (PER SDC>M} -----GRAPHICSCALE 1"=10' 10 a 10 ~ EXISTING HYDROLOGY EXHIBIT 320 HEMLOCK AVENUE CITY Of CARLSBAO PASCO LARET SUITER -----& ASSOCIATES San Diego I Solana Beach I Oranse County Phone 858.259.8212 lwww.plsaenslneering.com Pl.SAl39"2 30 • J:\ACTNE JOBSl3392 NORUM tEMl..oaGaVll.'Af.PORTsv«DRCXOGYOSCRETkWAR'r\?_APPENDOOJ3~-CV.ffi'tXI Dlw. PROPOSED HYDROLOGY EXHIBIT HEMLOCK COAST HOMES -320 HEMLOCK AVENUE PORLOT3 BLOCKR PALISADES #2 MAP 1803 51.l 51.3 TW§FG (512 TW@EG} (5l.18WtlfG) 511 Tw. EG 56.9 TW@FG (5o.,8\'10fG PORLOT2 BLOCKR PAI.JSADES#2 MAP 1803 56.,FG 'Ii ., ~ I ,.,,.N""'-'-'"'-"'-'---' 56.6~VG I :::~; I I I PARCEL 1 PM 16596 S11WC1URE TOREMAM PORLOT3 BLOCKR PAI.ISADES#2 MAP 1803 ., 5HTWOfG (SS.9 TW@EG) (55.1 BW@FGJ NODEPR-1 ~ 54.5ft 0100 = 0.74 CFS PLAN VIEW -POST-DEVELOPMENT NOOE MAP SG4LE.. f' .-10' HORIZONTAL ~--~- /: GUnERT0~- 1 I I I I I I ~ EXISTING 11'RCP PEROWG 139-1 I STORM DRAIN I I I I EXISTIJG CURS N#J GUTTERTOR£.MAII LEGEND PROPERTY """"1ARY CENTERL~E OF~ ADJACENT PROPERTY UIE I RIGHT-Of-WAY EXISTWG CONTOUR LINE PR0PosED CONTC/f.R LWE PROPOSED PA 1H OF 7RA \/EL PROPOSE.D DfifCJlONOF now PROPOSED IMPffMOOS AREA MAJOR DRAJNAGE ~ BOI.WOARY ___ ., __ _ t7ZZZZZ7h:½J --- BASIN PR-1 -AREA CALCULA T/ONS TOTAL SITE AREA 8.ASWPR.-1 TOTAL AREA 8ASJH PR-I IUPERV10IJSAREA. BA.SJHPR-IPERVIOUSARfA. c,, TIME: OF CONCENTRATION V" SF(0.189ACJ &.2'1SF(0.189AC) ,,365SF(0.IOOAC) 3.376 SF (0.089AC) "' 5.0 MINUTES (PER SDCHM) ._.._._ 10 GRAPHICSC!J..E 1'•10' 10 20 PROPOSED HYDROLOGY EXHIBIT 3ro HEMLOCK AVENUE CITY OF CARLSBAD PASCO LAREY SUITER & ASSOCIATES San Diego I Solana Beach I Clnlnae County Phone 858.259.8212 lwww.plsaeneneertng.com PLSA3392 31)