Project Task Description & Budget
This is the first Project Task Description And Budget describing tasks, establishing payment
amounts to complete said tasks and establishing the time of completion for the tasks described
herein pursuant to paragraphs 1, 3 and 4 of the contract entered into by GVP Consultants,
hereinafter referred to as "Contractor'' and the City of Carlsbad, hereinafter referred to as "City"
on the 4t1J·day of November, 1997.
1. CONTRACTOR'S OBLIGATIONS
The Contractor shall provide contract management and design services in accordance with the
"Project Development Manual", 1990 edition, hereinafter PDM, as published by the City's
Engineering Department, City "Standards for Design & Construction of Public Works
lmprov.ements in the City of Carlsbad" and the schedule and task list, hereinafter S&T, attached
as Appendix 'A' for the Curb Ramp 1997-98 Northwest Quadrant project, account number
3523-2, hereinafter "Project". Said services shall include the planning tasks, administrative
tasks, plan preparation, estimate preparation, specification preparation, document preparation,
project management, plan checking, scheduling, coordination and reporting tasks of the PDM,
the S& T and such other tasks that the City may assign to the Contractor that are required to
complete the documents required to issue a construction contract for said project.
3. PROGRESS AND COMPLETION
The Contractor's receipt of this Project Task Description and Budget, signed by the City
Engineer, constitutes notification to proceed to the Contractor. The Contractor shall begin work
within ten (10) working days after receipt of this fully executed document and shall complete the
work within 150 working days thereafter. Working days shall be as section 6-7.2 "Working Day"
of the Standard Specifications for Public Works Construction and shall additionally exclude days
used by public agencies, including City, in excess of the estimated processing time for said
agencies shown in the S& T.
4. FEES TO BE PAID TO THE CONTRACTOR
The budget for the Project shall be as shown in Table 1, "Project Management & Design
Services", herein. Fees shall be paid as lump sums for each task group shown in said table.
Progress payments shall be based on the percentage of completion of each task group as
approved by the City. Appendix 'A', attached, has been prepared by the Contractor and
reviewed by City and shows the intent of parties as to the elements, scope and extent of the
task groups. The Contractor acknowledges that performance of any and all tasks by the
Contractor constitutes acknowledgment by the Contractor that such tasks are those defined in
Appendix 'A'. If the need to perform task groups or individual tasks that are not shown in said
table or in Appendix 'A' is identified by the Contractor or City the additional task groups will be
performed by the Contractor only upon authorization of the City through the mechanism of a
separate Project Task Description And Budget. The elements, scope and extent of the
additional task groups and tasks and fees to be paid for performing such additional task groups
and tasks shall be established, upon the mutual agreement of City and Contractor, in said
separate Project Task Description and Budget. In the event that City directs Contractor to
curtail or eliminate all, or portions of the task groups and tasks identified in said table the lump
sum fee for each task so eliminated shall be reduced proportionately by the ratio of the number
of hours shown for each element of said task groups and task(s) so curtailed or eliminated
divided by the number of hours shown for each element of said task groups and task(s) shown
in the S& T. The maximum total cost of Contractor's services for this project task description
and budget is $37,500.00 and the maximum total of this and all Project Task Description and
Budgets that are a part of the contract entered into by the Contractor and the City is
$150,000.00. The total of the maximum cost, up to and including this project, of all projects
total cost authorized for Contractor's services for specific projects is $37,500.00.
Table '1'
PROJECT MANAGEMENT & DESIGN SERVICES
TASK GROUP LUMP SUM FEE
Establish Project Scope
Project Management (Scheduling & Tracking)
Obtain Environmental Approvals
$4,800.00
$2,200.00
$900.00
Manage Right-of-Way Acquisition Not Included
Perform and Manage PS&E Preparation
Manage Construction Contract Award
Total
Executed by Contractor this _____ day of ___________ , 1997.
CONTRACTOR:
(name of Contractor)
By: _________________ _
(sign here)
(print name/title)
I corporation of the State of California
Page 2 of 2 Pages Project Task Description & Budget for Project# 3523-2
Date of Preparation 11/26/97
$24,500.00
$5,100.00
$37,500.00
' Consultants Curb Ramp 1997-98 -Northwest Quadrant
Dec
Task Name I Duration 7 114121
0
1
12
13
14
15
16
TOTAL PROJECT DURATION (NOT INCLUDING CONSTRUCTION I 1118h
START PROJECT
START ASSIGNMENT & ASSESSMENT
Assess Project for Assignment
Assign Project to Project Mgr.
Initiate File
Obtain Project Account Number(s)
Check Funding
Establish Project File
Obtain Drawing No.
Prep Project Folders
Set Up Telephone & Meeting Logs
PROJECT ASSIGNED & FILES SET UP
ESTABLISH SCOPE OF PROJECT
Scope Project
Rev GIP Description & Budget
113.25h
22.25h
0.5h
0.5h , ,Princiibal Ciwil
4.5h
0.5h
0.5d
1.25h
0.25h
0.5h
0.5h
i
i
nsultant I : ' ! ltan
tontl~an
tlerkf C?n$ultant
~lerk
Od I• ,11,'t2 I,
91h
91h
!
,,. 1 l 1h hconiuli
·• ! I 17-----l--------C:::-h~e-c:-:-k--;f:=-o::-r A-;:d::;;j=a=ce::-:n::;t-;:P;:r::oj:::e:;:;ct;::-s--------i---:2z°th;-l ~ on~ul~
18 Review Pedestrian Ramp Inventory 4h ~on,ul/
19 I Review Sidewalk Inventory I 2h I 'tontu\1aot
20 I Site reconnaissance I 4h I ~on~u\ta,U
21 I Photo Site I 16h I Jnsu111,m
22 I Arrange and Organize Photos I 4h I · IC1 mlultant
23 I Prepare Photo Key Map I 1 h I ....tcdn~ultant
I
24 Conceptual Plan of Project Extents 10h
Jan
4 I 11 I 18I25
Feb Mar I Apr I May I Jun
8 115122 8 1151221291511211912613 I10I17I24I31I7I14I21
,.
·!
Task
Progress
Milestone
•"'''Ill , 1 illli.., , , ,· ~ .., , . ' 1.,....
i' ' ' ', ' Summary • • Rolled Up Progress
Rolled Up Task 'ill'Jljj,ll/," .,, ...... ,-·-~--.. ,. ~ .
♦ Rolled Up Milestone ◊
Page 1 of 14 Pages Curb Ramps Schedule NW Quad 11 /26/97 01 :40 PM
' Consultants Curb Ramp 1997-98 -Northwest Quadrant
3
9
0
1
2
13
14
15
!6
37
38
39
40
41
42
43
44
45
46
47
48
Task Name
Obtain Suitable Scale Overall Map
Prep Detailed Project Description
Layout Plan of Project Extents
Prepare Project Budget
Finalize Project Scope
Prepare Finalized Concept Plan
Proj Scope Approval
Submit Draft Scope, & Budget to Supervisor
Review Scope
Approve Final Project Scope & Budget
PROJECT SCOPE ESTABLISHED
PROJECT STARTED
MANAGE PROJECT
PROJECT MANAGEMENT
SETUP PROGRAM
Task/ Resource Utilization/ Duration (TUD) Lis
Prep TUD List
Prep TUD Input List
Input TUD List
Approve TUD List
PERT Analysis
Rev Precedences
Modify Precedence
Input Data
Duration
2h
4h
4h
4h
6h
6h
21h
2h
1h
2h
Od
Oh
973.75h
973.75h
39h
39h
39h
2h
1h
1h
12h
2h
1h
2h
Dec I Jan
7 I 14 121 I 28 I 4 111 I 18 I 25
ian
~~nLlant
lhc'cl>nl;ultant ·i ,
lh~,ml;ultant
1.1,..1
I +i
Pr,incipal Civil,Consultant
I
Feb
8 115122
Engineer,Principal Civil,Consultant
! '
Principal Civil,Consultant I .
I
I
Consultant
!
Consultant I
Apr I May I Jun
5 I12I19l26I 3 !1011712413117 I14l21
Task
Progress
Milestone
~·:,:~;: _,r~~-#' Summary • • Rolled Up Progress
♦
~ ,· •• :, '':<". . . . .. Rolled Up Task _
Rolled Up Milestone ◊
Page 2 of 14 Pages Curb Ramps Schedule NW Quad 11 /26/97 01 :40 PM
Consultants
Task Name
3
4
5
6
i7
;s
;g
iO
51
32
63
64
65
66
67
68
69
70
71
72
Resource Leveling
ID Available Resources
Confirm Hourly Rates
Input Data
PROJECT TRACKING SYSTEM IN PLACE
PROJECT TRACKING
Track Progress
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Curb Ramp 1997-98 -Northwest Quadrant
Nov I Dec Jan Feb
Duration I 9 11612313017 114121 11 I 18I25 8 115122
0.5h
0.5h
0.5h
6h
Od
934.75h
934.75h
1.75h
0.5h
0.25h
0.25h
1h
0.5h
0.25h
0.25h
4.75h
0.5h
0.25h
0.25h
1h
0.5h
0.25h
0.25h
1h
!
Consultant
i
Principal Civil,Consultant
I
Principal Civil
I
Consultant
l I
tier I
I
I
ton!uitant
Prin ipal Civil,Consultant
I I fonfltant
tie ,Consulti"t
[Prin ipal Civil'tonsultant
I
ton¾;ultant
7Cler , .... I I I
Prirlcip~I Civil,Consu
1
1tant h I
~o
I fie
I
Pri
I
ipal Civil,Consultant
I !
I
Task
Progress
Milestone
,~!lllil!L'l'&•~J[,:!l!".i/! -~..,..,~,'!;. Summary • • Rolled Up Progress
♦
~~\-:~ " :,•'i',-~;·~~ Rolled Up Task _
Rolled Up Milestone 0
Apr I May I Jun
5 11211912613110117124131I7114121
Page 3 of 14 Pages Curb Ramps Schedule NW Quad 11/26/97 01 :40 PM
P Consultants
D I Task Name
13
-r4
-75
-76
-77
-78
-79
-80
-81
-82
-83
-84
-85
-86
-87
-88
-89
-90
-91
-92
-93
-94
-95
-96
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Task
Progress
Milestone
Curb Ramp 1997-98 -Northwest Quadrant
Nov I Dec I Jan Feb Mar I Apr I May I Jun
Duration I 9 I16l23l30I 7 l14I21I28I 4 l11I18l25 8 I 15I22 a 1151221291511211912613110117124l31 I 7 l14I21
0.5h
0.25h
b;o
0.25h
1h
0.5h
0.25h
0.25h
i
ipal Civil,Consultant i• ; '
S .. -I
. I t ultant I
I ? ,Consulta~t
1.75h
0.5h
0.25h
ton;ult~nt
I 0.25h I
ipal Civil,Consultant
9.75h
0.5h ultant
0.25h
0.25h
1h
0.5h
0.25h
0.25h
1h
ipal Civil,Consultant
i
I
toni
tie
Pri
ultant
I
[
ipal Civil,Consultant i
0.5h
0.25h ,Consultant
0.25h I
ipal Civil,C(!nsultant
1h I
i (/~:~f ~ t?t~I .:~ ,> ~,~, Summary • • Rolled Up Progress
♦
~~• :\
4
j• 111;1' Ill~,. Rolled Up Task _
Rolled Up Milestone 0
Page 4 of 14 Pages Curb Ramps Schedule NW Quad 11/26/97 01 :40 PM
' Consultants
Task Name
10
11
12
)3
)4
05
06
07
08
09
10
111
112
113
114
115
116
117
118
119
120
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
Maintain Schedule Program
Data Collation
Data Input
Data Output Analysis
PROJECT TRACKED TO COMPLETION
START PROJECT ACCOUNT REVIEW
Review Monthly Staff Charges
Review Monthly Staff Charges 1
Review Monthly Staff Charges 2
Review Monthly Staff Charges 3
Review Monthly Staff Charges 4
Review Monthly Staff Charges 5
Review l\/lonthly Staff Charges 6
Task
Progress
Milestone ♦
Curb Ramp 1997-98 -Northwest Quadrant
Nov I Dec Jan Feb Mar I Apr I May I Jun
Duration 9 11612313017114121 4 I 11 I 18I25 8 I 15I22 8 1151221291511211912613110117124131I7114121
0.5h
0.25h
0.25h
1h
0.5h
0.25h
0.25h
I I·
!
tof ultan1t
~le I
Pri ipal C1v1l,Consult
I l
~o~lsultant
t 1e1
Prir
!
1h
0.5h
0.25h
~o ulta
0.25h
1h
0.5h
0.25h
0.25h
Od
896.1h
896.1h
0.1h
0.1h
0.1h
0.1 h
0.1h
0.1h
t , ·~ ... , :-•" :i.· 10,. Summary
Rolled Up Task • • Rolled Up Progress
~ •• ~ "'t'' . . •' ~ . ....
Rolled Up Milestone 0
Page 5 of 14 Pages Curb Ramps Schedule NW Quad 11/26/97 01 :40 PM
✓P Consultants Curb Ramp 1997-98 -Northwest Qua drant
ID
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
Task Name Duration
Review Monthly Staff Charges 7 0.1h
PROJECT MANAGED Oh
OBTAIN ENVIRONMENTAL APPROVALS 438.25h
START PRELIMINARY ENVIRONMENTAL 150.5h
Environmental Application 150.5h
Environmental Impact Assessment Form 77.75h
Prepare E I A form, Part I 2h
Rev Application w/ Planner 1h
EIA Form Preparation Complete Od
EIA Processing 150.Sh
Submit EIA Form 0.5h
Follow Up EIA Process 6h
EIA Application Approved Od
ENVIRONMENTAL IMPACT ASSESSMENT COMPLETE Od
OBTAIN GENERAL PLAN CONSISTENCY DETERMINAT 1h
Research 1h
Check For Prior Approval -If None ... 1h
GENERAL PLAN CONSISTENCY DETERMINED Od
START DESIGN PROCESS 119h
PREPARE BASE SHEETS 79h
Research Record Drawings 3d
Scale and Arrange in Sheets 1d
Draft Base Plans 5d
Review Base Plans 8h
Nov
9 116/23/30
Dec I Jan Feb
7 I 14 I 21 / 28 I 4 I 11 / 18 / 25 8 I 15I22
~ant
~lanner,Consultant
♦ 12/31
!
I
7•nsu\lanl
~1/15
4+ 1/15
•
I
Consultant
I
Consultant
I
Technician
I Consultant
'
Apr I May
5 I 12 I 19 I 26 I 3 11 o I 17 I 24 I 31
♦ 3/15
Task
Progress
Milestone
G "l,~~1~$!~•1~1 ~ 111 11:t~{,1tiHJilt,flJ!l!}>!~1 • Summary • • Rolled Up Progress
Rolled Up Task l,i Olllll~•rl ' ~ 1--I • '<lfW
♦ Rolled Up Milestone 0
Page 6 of 14 Pages Curb Ramps Schedule NW Quad 11/26/97 01 :40 PM
6
' Consultants Curb Ramp 1997-98 -Northwest Quadrant
Task Name
5 I SURVEY FIELD CONDITIONS
6 I Create Field Survey Checklist
-7 I Field Survey
f8 I Review of Survey Data
19 I SURVEY OF FIELD CONDITIONS COMPLETED
;o I ANALYZE FIELD SURVEY DATA & SET PROJECT SCO
;1 I Assemble data
52 I Review ADA Retrofit Criteria
53 I Analyze non-standard cases
54 I Prepare Map
55 I Present Plan with Recommendations
56 I Approve Plan
57 I Circulate List of Corners to be Retrofitted
58 I FIELD DATA ANALYSED & PROJECT SCOPE SET
59 I START PLANS, SPECS & ESTIMATE (PS&E)
60 I START PREPARATION OF SUBMITTAL OF 70% PS&E
161
162
163
164
165
166
167
168
Prepare 70% Version of Plan Shts.
Redline Design on Plan Sheets
Prepare Plan Sheets
Redline Title & Note Sheet
Prepare Title & Note Sheet
70% Version of Plan Sheets Prepared
Prepare 70% Version of Specs. & Estimate
Make Copy of Standard Special Provisions
Task
Progress
Milestone ♦
Nov
Duration I 9 i 1 s i 23 f 30
20.75h
--1d
-2d
-Sh
-0d
--19.25h
--
2h
-4h
-1d
-
4h
-
2h
-1h
-2h
-
0d
---433.25h
---62.Sh
--44.75h
--24h
-
32h
-2h
-2h
-0d
-44.Sh
--
1h
Jan
28 I 4 111 11 a I 25
I
I • I to;sultant
Consultant
I
i nsultant
2/26 .
~
1
onsultant
1
Consultant '
Feb
a I 15122 I 1
I i
ttonsultant I
~onsultant, Technician
hconsultant j ·+ I
~rincipal Civil
~onsultant
~1m1
Technician
nsultant I
I
Technician
Apr I May I Jun
5 1121191261311011712413117 114121
•
Summary • • Rolled Up Progress
Rolled Up Task ~;~-~~~-~~~ ~-
Rolled Up Milestone ◊
Page 7 of 14 Pages Curb Ramps Schedule NW Quad 11 /26/97 01 :40 PM
' Consultants Curb Ramp 1997-98 -Northwest Quadrant
Nov Dec Feb Apr I May I Jun
Task Name Duration I 9 16 23 30 7 14 21 8 I 15I22 5 11211912613 I10I17I24I31I7I14I21
9
·o
'1
'2
73 I
74 I
75 I
76 I
77 I
78 I
79 I
80 I
181 I
182 I
183 I
184 I
185 I
186
187
188 I
189 I
190 I
191 I
192 I
Extract Non-Pertaining Provisions from Std. Spcl.
Review SSPWC Addenda for Conflicting Provision
Update Standard Special Provisions
Prep. Estimate
Check for Current Unit Prices
Compute Quantities
Prepare Spreadsheet
Estimate Prepared
70% PS&E PREPARED
DISTRIBUTE 70% PS&E
Prep Submittal Sets
Copy Drawings
Copy Specs
Copy Estimate
Assemble Sets
Prep Letter of Transmittal
Submittal Set Prepared
--Distribute 70% Submittal
70% PS&E PREPARED & DISTRIBUTED
REVIEW OF 70% PS&E
Start 70 % Review, PS&E
Receive Submittals
Verify Contents of Submittals
Schedule Return of Sub by Utilities, Other De
Task
Progress
Milestone
~-~I ~,li1ti:'.~,1'j!itl~.,• :mt,~
♦
4h
2h
1h
39.5h
2h
2d
4h
0d
0d
9.75h
8.75h
1h
0.5h
0.5h
2h
1h
0d
1h
0d
86.75h
86.75h
6.25h
0.25h
1h
Summary •
Iechni:ian
Clerk I
I Clerk .
itlerk
ionsultant
1115 I . I
Consultant
I
1,1s I
I
rechni
1
cian
• I
Consultant
• Rolled Up Progress
Rolled Up Task _ ... £~~ I! • > I • c 'i ~]~
Rolled Up Milestone ◊
Page 8 of 14 Pages Curb Ramps Schedule NW Quad 11 /26/97 01 :40 PM
' Consultants Curb Ramp 1997-98 -Northwest Quadrant
Nov I Dec Feb Mar I Apr I May I Jun
Task Name Duration 9 l16l23l30I 7 l14I21 a l 15I22 8 l15l22I29I 5 l12I19l26I 3 l10l17l24l31 I 7 l14I21
3
,4
15
16
37
38
39
00
01
02
03
:04
!05
!06
!07
!08
209
210
211
212
213
214
215
216
Distribute Submittal to City Depts. 1h
Set up Meeting w/ City Depts. 2h, ' -'ltant
Distribute Submittal to Utilities I ...... _ I i-2hl I \ · I ician · I
Review Submittals 15h I I ! ! ....,1 1 I
Compare Submittal to Proj Scoping Docs 2h I I I 1 -.I li~al Civil
Conformity to City Standards 2h I I ! 1...,,-.I li~al Civil
Compare Submittal to Prev. Subm. Check Co 2h I I I ..... I I I 1 -• ipal Civil
Check for Utility Conflicts
Review & Confirm City Dept. Comments
9hl I I I a ..I . I ~ipal Civil
I I .......... I I 2hl 1 -sultant
I
Meet w/ City Depts. to Review Comments
Transcribe City Dept. Comments
Prepare Review Report
Review Comments
Review Timeliness of Submittals
COMPLETE REVIEW OF 70% PS&E
~ I i I \onsultant
2h 'J;onsultant
4h I I I I t ••ltant ! 2h I I i I Principal Ci~il,Consultant
I I 0.5h I I i I b~rincipal Ci~il
0d I I I I
--START PREP OF SUB OF 90% PS&E 61.75h
Prepare 90% Version of Plan Shts. 1 1 I
"II
24h I i • Revise Sketch Sheets for Technician
Revise Plans
Sh I I I I t onsultant
16h I I I Technician
90% Version of Plan Sheets Prepared
Prepare 90% Version of Specs.
0d I I I I ♦1212 l 16h'
-Review Entire Specifications for Conflicting Provisi 8h
-Update Standard Special Provisions 8h
--Revise Estimate 53.75h
~"'"' '~~!llil4,'l.,.,,1!...;~~~ Summary • • Rolled Up Progress Task
Progress
Milestone
~~,f "j:' Rolled Up Task _
Rolled Up Milestone ◊ ♦
Page 9 of 14 Pages Curb Ramps Schedule NW Quad 11/26/97 01 :40 PM
✓P Consultants
ID Task Name
!17 Confirm Unit Prices
!18 Confirm Quantities
219 Update Spread Sheet If Necessary
220 Review Estimate
221 Estimate Revised
222 90% PS&E PREPARED
223 DISTRIBUTE 90% PS&E
224 Prepare Submittal Sets
225 Copy Drawings
226 Copy Specs
227 Copy Estimate
228 Assemble Sets
229 Prep Letters of Transmittal
230 Submittal Set Prepared
231 Distribute 90% Submittal
232 90% PS&E PREPARED & DISTRIBUTED
233 REVIEW OF 90% PS&E
234 Start 90 % Review, PS&E
235 Receive Submittals
236 Verify Contents of Submittal
Curb Ramp 1997-98 -Northwest Quadrant
Nov I Dec I Jan
Duration 9 1161231301711412112814111118125
2h
4h
2h
2h
Feb
8 115122
,. I
I • Principal Civil
Oh
Od ~'.'"]
~/13
10h
9h
1h
4h
1h
2h
2h
Od
1h
Od
84.5h
84.5h
4.25h
0.25h
.I
iech:nician
Clerk
I I
Clerk
i
~ler~
l_tonrultant
+t'1~
~on:ultant
~ I ♦, •
I
Apr I May I Jun
5 11211912613110117124131I7114121
237 Sched Return of Sub by Utilities, Other City D 1h ultant
238
239
240
Distribute Sub to City Depts.
Distribute Sub to Utilities
Review Submittal
Task
Progress
Milestone
.':'.:1 ~\tf,.. I'!•, ~:r.i~~~::.1~1
♦
1h ician
2h ician
9h ipalCivil 1
Summary • • Rolled Up Progress
',Ill 1 " '► Rolled Up Task _
Rolled Up Milestone ◊
• J -
Page 10 of 14 Pages Curb Ramps Schedule NW Quad 11/26/97 01 :40 PM
--··---·--
' Consultants Curb Ramp 1997-98 -Northwest Quadrant ;
Nov I Dec Jan Feb Mar Apr May I Jun
Task Name Duration 9 11612313017 114121 4 I 11I18I25 8 8 I 15 I 22 I 29 I 5 12119126 3 11011712413117114121
.1 Compare Submittal to Project Scoping Documents 1h
,2 Check Conformity to City Standards 0.88d
13 Compare Sub to Previous Submittal Check Comm Sh
i4 Check for Utility Conflicts 4h
l5 Review & Conform City Dept. Comments 4h
46 Meet w/ City Depts. to Review Comments 2h
Printipal Civil
~rin ipal Civil ..
• tri_jipal Civil
ipal Civil
. . . I
ultant I
Consultant
47 Transcribe City Dept. Comments 4h
48 Prepare Review Report 1h
49 Review Comments 2h
50 Review Timeliness of Submittal 0.5h
.51 COMPLETE REVIEW OF 90% PS&E Od
!52 START PREP OF SUB OF 100% PS&E 27h
r i
'tonsulint
tonsulint
hPrincipal Civil,Consultant
'.,j,.. I I
trincipal Civil I
~11 I !
!53 Prepare 100% Version of Plan Shts. 14h
• I !54 Revise Sketch Shts. for Technician Sh
!55 Revise Plans 6h
I if onsul;nt
Technician
?56 100% Version of Plan Sheets Prepared Od
257 Prepare 100% Version of Specs. 18h
258 Review Entire Specifications for Conflicting Provisi Sh i
onsultant
259 Update Standard Special Provisions Sh I
Consultant
260 Prepare 100% Version of Estimate 13h I I
261 Confirm Unit Prices 1h i onsultant
262 Confirm Quantities 1h l
Consultant
263 Update Spreadsheet If Necessary 1h ! Consultant
I
264 Review Estimate 2h Principal Civil
Task
Progress
Milestone
'"'~"!llf""1'.~" :".rt:1Tl8/·· ~ J1~"'·•~ Summary • • Rolled Up Progress
♦
~:-: .. :-\: ". -',~~ .. Rolled Up Task _
Rolled Up Milestone ◊
Page 11 of 14 Pages Curb Ramps Schedule NW Quad 11 /26/97 01 :40 PM
vP Consultants Curb Ramp 1997-98 -Northwest Quadrant
Nov I Dec Jan
ID I Task Name Duration I 9 11612313017114121 4 I 11 I 18I25
265 I 100% PS&E PREPARED 0d I I l
266 I DISTRIBUTE 100% PS&E 8h
267 I Prep. Submittal Sets 7h
268 I Copy Drawings 1h
269 I Copy Specs 4h
270 I Copy Estimate 1h
271 I Assemble Sets 2h
272 I Prep Letter of Transmittal 1h
273 I Submittal Set Prepared 0d
274 I Distribute 100% Submittal 1h
275 I 100% PS&E PREPARED & DISTRIBUTED 0d
276 START REVIEW OF 100% PS&E 6.5h
277 Receive and Review Submittal 4.5h
278 Verify Contents of Submittal 0.25h
279 Review Submittal 8h
280 Compare Sub to Previous Sub Check Comments 4h
281 Obtain Applicable Signatures 0.25d
282 PLANS & ESTIMATE COMPLETED 0d
283 SPECIFICATION ASSEMBLY 42.5h
284 Start Specification Assembly 42.5h
285 Insert Bid Docs & Special Provisions into Boiler Pl 9h
286 Proof Read Specs 18h
287 Correct Specs 9h
288 Obtain & Insert Std Dwgs 2h
Feb
8 115122
Apr I May I Jun
s 11211912613110117124131I7114121
• I
-~echnlcian
Clerk
Clerk
ierk
onsf ltant
3/171 i
Consultant
3/17i
•
~ech
I
nician 1f onf ultant
• I ,Consultant
!
I
Consultant
I
3
I
Clerk
I Consultant
I Consultant
Task
Progress
Milestone
sJTI' r~,~~rt •:::t'il}i:' Summary • • Rolled Up Progress
Rolled Up Task ,,.,~•~• , I ' • ... , 1 ••~
-; 14 + .. ~ , • ';i , ,r
♦ Rolled Up Milestone ◊
Page 12 of 14 Pages Curb Ramps Schedule NW Quad 11/26/97 01 :40 PM
' Consultants Curb Ramp 1997-98 -Northwest Quadrant
3 I
D I
1 I
2 I
,3 I
14 I
15 I
~6 I
H I
38 I
99 I
00 I
01 I
02 I
,03 I
:04 I
105 I
306 I
307
308
309
310 I
311 I
312 I
Jan Feb Apr I May I Jun Nov I Dec
Task Name Duration 19 l16l23l3ol 7 114121 4 111118125 8 I 15I22 5 1121 191261311011712413117 114121
Print Master Specs
SPECIFICATIONS COMPLETED
DESIGN PROCESS COMPLETED
START 1ST PHASE CONST. CONTRACT AWARD PHASE
ST ART BID PROCESS
Council Authorization to Request Bids
Agenda Bill (AB) to Authorize Bidding
Write Project Description
Prep Fiscal Impact Section
Prep Resolution
Prep Location Map
Agenda Bill Reviewed
Agenda Bill Approved
SOLICIT BIDS
Bidding Period
Plan & Spec Publication
Prep Purchase Requisition
Obtain City Clerk Sig on Auth to Bid
Deliver Plans & Specs to Purchasing
Prep Bid Abstract Base Sheet
Bidder Inquiries
Accept Inquiries (All responses are given in w
Prep Addenda
Receive Bids
Task
Progress
Milestone
~ 1-. • ~ • I ! ,..-~, .. l
. ~'ft~
♦
4h
0d
Oh
475h
115.Sh
115.Sh
3.5h
0.5h
0.5h
2h
0.5h
0d
0d
262.Sh
262.Sh
6h
1h
4h
1h
6h
12h
6h
6h
20h
ltlerk
•
~o1sultaW!t
tor sultaW!t
'tor sultaW"it
1ef hnicitn n 1
I
'J;onsl ltant
I Consultant
I
Summary • • Rolled Up Progress
'l!ir• . _, r
,. '~ • ~ I Rolled Up Task _
Rolled Up Milestone 0
Page 13 of 14 Pages Curb Ramps Schedule NW Quad 11/26/97 01 :40 PM
1 Consultants. Curb Ramp 1997-98 -Northwest Quadrant ;
3
4
5
6
7
8
,9
?O
!1
!2
23
24
25
26
27
28
29
,30
,31
32
,33
134
J35
Task Name
Attend Bid Opening
Analyze Bids
Prep Bid Abstract
Examine Bid Docs
Confirm Data in Bidder's Statements
Recommend Award to Lowest Resp Bidder to
BID PROCESS COMPLETED
CONTRACT AWARD
Prep Council Award Pkg.
Prep Bid Bond Release Form
Prep AB & Resolution for Award
Approve AB
Attend Council Meeting (if Necessary)
CONTRACT AWARD APPROVED
Advise Inspection Div. -Contract Awarded
CONSTRUCTION CONTRACT AWARDED
COMPLETE CONSTRUCTION AWARD PHASE
DESIGN & AWARD PHASE CLOSEOUT
Attend Pre-Construction Meeting
Filing
Handoff Meeting to Inspection
Prep Files for Archiving
PROJECT DESIGNED & TRANSFERRED TO INSPECTION
Task
Progress
Milestone ♦
Nov I Dec I Jan Feb
Duration 19 1161231301711412112814111118l25 a I1s I22
2h
6h
2h
4h
4h
2h
Od
97h
13h
2h
9h
2h
3h
Od
1h
Od
Oh
12h
2h
4h
2h
4h
Od
Apr I May I Jun
s 112 I 19 I 26 I 3 11 o I 17 I 24 I 31 I 7 I 14I21
itonsultant
'tonsultan
'tonsultan
'tonsultan
'tonsultan
b;onsultan
.. 614
1.,
I
'tonsulta
• Consulta
r ·a
Summary • • Rolled Up Progress
"'$r., Rolled Up Task _
Rolled Up Milestone 0
Page 14 of 14 Pages Curb Ramps Schedule NW Quad 11/26/97 01 :40 PM
Project Task Description & Budget
This is the second Project Task Description And Budget describing tasks, establishing payment
amounts to complete said tasks and establishing the time of completion for the tasks described
herein pursuant to paragraphs 1, 3 and 4 of the contract entered into by GVP Consultants,
hereinafter referred to as "Contractor" and the City of Carlsbad, hereinafter referred to as "City"
on the 4th day of November, 1997.
1. CONTRACTOR'S OBLIGATIONS
The Contractor shall provide contract management and design services in accordance with the
"Project Development Manual", 1990 edition, hereinafter PDM, as published by the City's
Engineering Department, City "Standards for Design & Construction of Public Works
Improvements in the City of Carlsbad" and the schedule and task list, hereinafter S&T, attached
as Appendix 'A' for the Curb Ramp 1997-98 Northwest Quadrant project subtitled "Gladden
Ramps", account number 3523-1, hereinafter "Project". Said services shall include the
planning tasks, administrative tasks, plan preparation, estimate preparation, specification
preparation, document preparation, project management, plan checking, scheduling,
coordination and reporting tasks of the PDM, the S&T and such other tasks that the City may
assign to the Contractor that are required to complete the documents required to issue a
construction contract for said project. The scope of this project includes the additional work
necessary to include curb ramps and sidewalk on Yarrow Drive, south of Palomar Airport Road
and curb ramps on the four corners of the intersection of El Camino Real and Marron Road.
3. PROGRESS AND COMPLETION
The Contractor's receipt of this Project Task Description and Budget, signed by the City
Engineer, constitutes notification to proceed to the Contractor. The Contractor shall begin work
within ten (10) working days after receipt of this fully executed document and shall complete the
work within 75 working days thereafter. Working days shall be as section 6-7.2 "Working Day"
of the Standard Specifications for Public Works Construction and shall additionally exclude days
used by public agencies, including City, in excess of the estimated processing time for said
agencies shown in the S&T.
4. FEES TO BE PAID TO THE CONTRACTOR
The budget for the Project shall be as shown in Table 1, "Project Management & Design
Services", herein. Fees shall be paid as lump sums for each task group shown in said table.
Progress payments shall be based on the percentage of completion of each task group as
approved by the City. Appendix 'A', attached, has been prepared by the Contractor and
reviewed by City and shows the intent of parties as to the elements, scope and extent of the
task groups. The Contractor acknowledges that performance of any and all tasks by the
Contractor constitutes acknowledgment by the Contractor that such tasks are those defined in
Appendix 'A'. If the need to perform task groups or individual tasks that are not shown in said
table or in Appendix 'A' is identified by the Contractor or City the additional task groups will be
performed by the Contractor only upon authorization of the City through the mechanism of a
separate Project Task Description And Budget. The elements, scope and extent of the
additional task groups and tasks and fees to be paid for performing such additional task groups
and tasks shall be established, upon the mutual agreement of City and Contractor, in said
separate Project Task Description and Budget. In the event that City directs Contractor to
curtail or eliminate all, or portions of the task groups and tasks identified in said table the lump
sum fee for each task so eliminated shall be reduced proportionately by the ratio of the number
of hours shown for each element of said task groups and task(s) so curtailed or eliminated
divided by the number of hours shown for each element of said task groups and task(s) shown
in the S&T. The maximum total cost of Contractor's services for this project task description
and budget is $3,600.00 and the maximum total of this and all Project Task Description and
Budgets that are a part of the contract entered into by the Contractor and the City is
$150,000.00. The total of the maximum cost, up to and including this project, of all projects
total cost authorized for Contractor's services for specific projects is $41,100.00.
Table '1'
PROJECT MANAGEMENT SERVICES
TASK GROUP LUMP SUM FEE
Establish Project Scope
Project Management (Scheduling & Tracking)
Perform and Manage PS&E Preparation
Total
Executed by Contractor this 18 t/,1,, day of_~Af-'_;/ _____ , 1997 8
CONTRACTOR:
(; VP Coyl60l+(Mb
(name of Contractor)
By: ~hei ii,. 4j;
GI~ i. VtUI ~ Sale P"°f ''·~ (print name/title) '
· cipal corporation of the State of California
Page 2 of 2 Pages Project Task Description & Budget for Project# 3523-1
Date of Preparation 4/27 /98
$600.00
$400.00
$2,600.00
$3,600.00
VP Consultants City of Carlsbad Project #3523-4 Curb Ramp Schedule -Northwest Quadrant -Gladden Ramps L
ID Task Name Duration Start Finish Predecessors Resource Names
0 Curb Ramp Schedule -Northwest Quadrant 67.53 days 4/13/98 7/15/98
1 TOTAL PROJECT DURATION (NOT INCLUDING CONSTRUCTION) 67.53 days 4/13/98 7/15/98
2 START PROJECT 10.13 days 4/13/98 4/27/98
3 START ASSIGNMENT & ASSESSMENT 1.13 days 4/13/98 4/14/98
4 Assess Project for Assignment 0.06 days 4/13/98 4/13/98
5 Assign Project to Project Mgr. 0.5 hrs 4/13/98 4/13/98 Principal Civil
6 Initiate File 0.06 days 4/14/98 4/14/98
7 Obtain Project Account Number(s) 0.5 hrs 4/14/98 4/14/98 5FS+ 1 eday,9 Consultant
8 Establish Project File 0.16 days 4/13/98 4/13/98
9 Obtain Drawing No. 0.25 hrs 4/13/98 4/13/98 Technician
10 Prep Project Folders 0.5 hrs 4/13/98 4/13/98 9 Clerk
11 Set Up Telephone & Meeting Logs 0.5 hrs 4/13/98 4/13/98 10 Clerk
12 PROJECT ASSIGNED & FILES SET UP 0 days 4/13/98 4/13/98 11
13 ESTABLISH SCOPE OF PROJECT 10.13 days 4/13/98 4/27/98
14 Scope Project 10.13 days 4/13/98 4/27/98
15 Site reconnaissance 1 hr 4/13/98 4/13/98 Consultant
16 Conceptual Plan of Project Extents 0.63 days 4/15/98 4/15/98
17 Prepare Conceptual Plan of Project Extents 2 hrs 4/15/98 4/15/98 15FS+2 edays Technician
18 Prepare Project Budget 2 hrs 4/15/98 4/15/98 17 Consultant
19 Prepare Prelim Cost Estimate 1 hr 4/15/98 4/15/98 18 Consultant
20 Proj Scope Approval 5.38 days 4/17/98 4/27/98
21 Submit Draft Scope, & Budg to Supervisor 1 hr 4/17/98 4/17/98 19FS+2 edays Consultant
22 Review Scope 1 hr 4/21/98 4/21/98 21FS+2 days Principal Civil, Consultant
23 Approve Final Project Scope & Budget 1 hr 4/27/98 4/27/98 22FS+5 edays City Engineer,Principal Civil.Consultant
24 PROJECT SCOPE ESTABLISHED 0 days 4/27/98 4/27/98 23
25 PROJECT STARTED O hrs 4/27/98 4/27/98 24
26 MANAGE PROJECT 48 days 4/27/98 7/2/98 U,25
Page 1 of 4 Pages Gladden Ramps 4/27/98 2:41 PM
rp Consultants City of Carlsbad Project #3523-4 Curb Ramp Schedule -Northwest Quadrant -Gladden Ramps
ID Task Name Duration Start Finish Predecessors Resource Names
27 Prep TUD List 48 days 4/27/98 7/2/98
28 Prep TUD Input List 1 hr 4/27/98 4/27/98 Consultant
29 Approve TUD List 1 hr 4/27/98 4/27/98 28 Principal Civil,Consultant
30 PERT Analysis 2 hrs 4/27/98 4/27/98 29 Consultant
31 PROJECT TRACKING SYSTEM IN PLACE 0 days 4/27/98 4/27/98 30
32 Track Project 48 days 4/27/98 7/2/98
33 Track Project 1 1 hr 4/27/98 4/27/98
34 Track Project 2 1 hr 5/7/98 5/7/98
35 Track Project 3 1 hr 5/21/98 5/21/98
36 Track Project 4 1 hr 6/4/98 6/4/98
37 Track Project 5 1 hr 6/18/98 6/18/98
38 Track Project 6 1 hr 7/2/98 7/2/98
39 PROJECT MANAGED 0 hrs 7/2/98 7/2/98 32
40 START DESIGN PROCESS 9 days 4/27/98 5/8/98 24
41 PREPARE BASE SHEETS 9 days 4/27/98 5/8/98 24
42 Research Record Drawings 2 hrs 4/27/98 4/27/98 Consultant
43 Draft Base Plans 1 day 5/4/98 5/5/98 42FS+5 days Technician
44 Review Base Plans 2 hrs 5/7/98 5/7/98 43FS+2 days Consultant
45 Field Survey 4 hrs 5/7/98 5/8/98 44 Consultant
46 BASE SHEETS PREPARED 0 days 5/8/98 5/8/98 45
47 ANALYSE FIBLD SURVEY DATA & SET PROJECT SCOPE 0.25 days 4/27/98 4/27/98
48 Circulate Sketch of Design 2 hrs 4/27/98 4/27/98 Consultant
49 FIELD DATA ANALYSED & PROJECT SCOPE SET 0 days 4/27/98 4/27/98 48
50 START PLANS, SPECS & ESTIMATE (PS&E) 57.16 days 4/27/98 7/15/98 49
51 START PREP OF SUB OF 90% PS&E 6.44 days 4/27/98 5/5/98
52 Prepare 90% Version of Plan Shts. 6.25 days 4/27/98 5/5/98
53 Prepare Sketch Sheets for Technician 2 hrs 4/27/98 4/27/98 Consultant
Page 2 of 4 Pages Gladden Ramps 4/27/98 2:41 PM
.
iP Consultants City of Carlsbad Project #3523--4.-Curb Ramp Schedule -Northwest Quadrant -Gladden Ramps
ID Task Name Duration Start Finish Predecessors Resource Names
54 Revise Plans 1 day 5/4/98 5/5/98 53FS+5 days Technician
55 90% Version of Plan Sheets Prepared 0 days 5/5/98 5/5/98 54
56 Prepare 90% Version of Specs. 0.13 days 4/27/98 4/27/98
57 Reference Existing Specifications 1 hr 4/27/98 4/27/98 Consultant
58 Prepare Estimate 6.44 days 4/27/98 5/5/98
59 Confirm Unit Prices 0.5 hrs 4/27/98 4/27/98 Consultant
60 Confirm Quanities 1 hr 5/5/98 5/5/98 54 Consultant
61 Prepare Spread Sheet 0.5 hrs 5/5/98 5/5/98 59,60 Consultant
62 90% PS&E PREPARED 0 days 5/5/98 5/5/98 61,57
63 DISTRIBUTE 90% PS&E 0.5 days 5/5/98 5/6/98 62
64 Prepare Submittal Sets 0.5 days 5/5/98 5/6/98
65 Copy Drawings 0.5 hrs 5/5/98 5/5/98 Consultant
66 Copy Specs 0 hrs 5/5/98 5/5/98 Consultant
67 Copy Estimate 0.5 hrs 5/6/98 5/6/98 Consultant
68 Assemble Sets 0.5 hrs 5/6/98 5/6/98 65,66,67 Consultant
69 Prep Leners of Transmittal 0.5 hrs 5/6/98 5/6/98 68 Consultant
70 Submittal Set Prepared 0 days 5/6/98 5/6/98 69
71 Distribute 90 % Submittal 1 hr 5/6/98 5/6/98 70 Clerk
72 90% PS&E PREPARED & DISTRIBUTED 0 days 5/6/98 5/6/98 71
73 REVIEW OF 90% PS&E 0.88 days 6/3/98 6/4/98
74 Review Submittal 1 hr 6/3/98 6/3/98 72FS+20 days Consultant
75 Check for Utility Conflicts 1 hr 6/3/98 6/3/98 74 Consultant
76 Review & Confirm City Dept. Co=ents 2 hrs 6/3/98 6/3/98 75 Consultant
77 Meet w/ City Depts. to Review Co=ents 2 hrs 6/3/98 6/4/98 76 Consultant
78 Transcnl,e City Dept. Co=ents 1 hr 6/4/98 6/4/98 77 Consultant
79 COMPLETE REVIEW OF 90% PS&E 0 days 6/4/98 6/4/98 78
80 Prepare 100% Version of Plan Shts. 8.13 days 6/4/98 6/16/98 79
Page 3 of 4 Pages Gladden Ramps 4/27/98 2:41 PM
' 'P Consultants City of Carlsbad Project #3523-4 Curb Ramp Schedule -Northwest Quadrant -Gladden Ramps . .
ID Task Name Duration Start Finish Predecessors Resource Names
81 Revise Sketch Shts. for Technician 1 hr 6/4/98 6/4/98 Consultant
82 Revise Plans 1 day 6/11/98 6/12/98 81FS+5 days Technician
83 100% Version of Plan Sheets Prepared 0 days 6/16/98 6/16/98 82FS+2 days
84 Prepare 100% Version of Specs. 0.13 days 6/12/98 6/12/98
85 Update Standard Special Provisions 1 hr 6/12/98 6/12/98 82 Consultant
86 Prepare 100% Version of Estimate 0.06 days 6/12/98 6/12/98
87 Update Speadsheet If Necessary 0.5 hrs 6/12/98 6/12/98 82 Consultant
88 100% PS&E PREPARED 0 days 6/12/98 6/12/98 87
89 DISTRIBUTE 100% PS&E 0.75 days 6/12/98 6/15/98 88
90 Prep. Submittal Sets 0.63 days 6/12/98 6/12/98
91 Copy Drawings 0.5 hrs 6/12/98 6/12/98 Technician
92 Copy Specs 0.5 hrs 6/12/98 6/12/98 Clerk
93 Copy Estimate 0.5 hrs 6/12/98 6/12/98 Clerk
94 Assemble Sets 0.5 hrs 6/12/98 6/12/98 91,92,93 Clerk
95 Prep Letter of Transmittal 0.5 hrs 6/12/98 6/12/98 Consultant
96 Submittal Set Prepared 0 days 6/12/98 6/12/98 95
97 Distribute 100% Submittal 1 hr 6/15/98 6/15/98 94,96 Clerk
98 100% PS&E PREPARED & DISTRIBUTED 0 days 6/15/98 6/15/98 89
99 START REVIEW OF 100% PS&E 2.41 days 7/13/98 7/15/98 98FS+20 days
100 Receive and Review Submittal 0.16 days 7/13/98 7/13/98
101 Verify Contents of Submittal 0.25 hrs 7/13/98 7/13/98 Technician
102 Review Submittal 0.5 hrs 7/13/98 7/13/98 101 Consultant
103 Compare Sub to Previous Sub Check Comments 0.5 hrs 7/13/98 7/13/98 102 Consultant
104 Obtain Applicable Signatures 2 hrs 7/15/98 7/15/98 103FS + 2 edays Consultant
105 PLANS & ESTIMATE COMPLETED 0 days 7/15/98 7/15/98 104
106 DESIGN PROCESS COMPLETED 0 hrs 7/15/98 7/15/98 105
107 PROJECT DESIGNED & TRANSFERRED TO INSPECTION 0 days 7/15/98 7/15/98 106
Page 4 of 4 Pages Gladden Ramps 4/27/98 2:41 PM