SAN DIEGO GAS & ELECTRIC COMPANY
CONTRACT FOR SPECIAL FACILITIES
THIS CONTRACT is made and entered into this :Z & day of tJ V lie M 1Je IL , 2011: ;,{ J d between
SAN DIEGO GAS & ELECTRIC COMPANY, a corporation, hereinafter called "Utility", and
CA1,LS13.+Q M v N, ,4KL W ftIC'.IL Q, SrR ic.t:: hereinafter called "Applicant".
WHEREAS, Applicant has requested and does hereby contract with Utility for the installation and/or maintenance of
special facilities, which is in addition to, or in substitution for, the standard facilities which the Utility normally
would install or maintain and which represents additional cost to Utility over normally installed facilities. The
special facilities are for use at Applicant's premises located at 5300 Sunny Creek Rd C CG, Carlsbad, County of
San Diego, State of California;
WHEREAS, Utility has agreed to install, construct and/or maintain at the request and expense of Applicant, certain
facilities consisting of net generator output meter.
In consideration of the mutual promises herein, the parties agree as follows:
1. Installation of Utility-owned special facility shall at all times be and remain the property of Utility.
2. Service through these special facilities shall be limited to a maximum demand ( also known as: duty load) of not
more than 203 kV A for electric service. ·
3. Utility's performance hereunder is contingent upon: a) securing without cost to Utility, any necessary easements,
rights of way or highway permits necessary for the installation of said special facilities; and b) availability of the
material required to provide said special facilities.
4. This Contract may be assigned by Applicant only upon the assignee's written acceptance of said assignment, and
the approval of Utility as evidenced by written endorsement hereon; however, such approval shall not constitute
a release of Applicant's obligation hereunder unless expressly so provided in said endorsement.
5. All representations, statements, terms and stipulations, heretofore made and ·agreed by the parties with relation
to the above-mentioned special facilities, except as specifically set forth in this Contract, are superseded by the
provisions of this Contract, and no representation of any agents or employee shall be binding upon Utility except
as herein set forth.
6. Applicant agrees to be governed by the Utility's applicable rates and rules on file with the California Public
Utilities Commission, which rates and rules are made a part hereof by reference, a copy of which will be
furnished to Applicant upon request. This Contract shall at all times be subject to such changes or modifications
as said Commission may, from time to time, direct in the exercise of its jurisdiction.
Form 106-1202 (6/96)
·• (
7. Total Estimated Installed Cost of Requested Special Facility:
(a) 1,570.00
(
Of the total estimated installed cost, Utility and Applicant have mutually agreed upon:
$1,570.00 (b) as a one-time payment adjusted by the applicable factor as established in the Special Facilities
section of SDG&E's applicable electric Rule No.2, copy attached.
(c) Total Estimated Installed Cost (a) less one-time payment (b)
( d) amount in ( c) to be paid by Applicant through a $ _____ /month charge over a __
month amortization period at %) per month as established in the Special Facilities section of
SDG&E's applicable Electric Rule No. 2, copy attached.
( e) O&M to be paid by Applicant will be the product of L %) per month, as established in the
Special Facilities section ofSDG&E's applicable Electric Rule No. 2, which will result in a
payment by applicant of $ ____ _;/ month over a __ -month peripd.
8. If Applicant is a corporation, partnership, joint venture or a group of individuals, the subscriber hereto
represents that he has the authority to bind said corporation, partners, joint venturers or individuals, as the case
maybe.
IN WITNESS WHEREOF, the parties hereto have caused this Contract to be executed for and on behalf of each, by
the duly authorized agents, partners or corporate officers, as of the day and year first above written.
APPLICANT:
Carlsbad Municipal Water District
arlsbad CA 92008
SAN DIEGO GAS & ELECTRIC COMPANY,
acoq,onrtion~
By, ~ Individual-Utility)
By.__J;~~~'f::?::.==:=====-----'¼,c.1,p HlrVJP;? Date Executed: __ _.../._,f ..... ~----~""'il""u"'-"-'a ___ i,,,-:_>9'---
foL c.w.cit,, ~,tNw
Name: Conrad C. Hammann, Jr.
(Please Print or Type)
Title: Public Works Director
Date: July 1, 2013
Address:
1635 Faraday Avenue
Carlsbad, CA 92008
Telephone: (760) 602-2730
Social Security Number or
Tax I.D. Number ,,_95.,_-..,,.6=00"-4:..r.7.:.9""3 _______ _
Applicant is a corporation: Yes [ ] No [X]
Form 106-1202 (6/96)
..
~ns~· -,u IE
A ~ Sempra Energy" utility
GENERATING FACILITY INTERCONNECTION AGREEMENT
(CONTINUOUS EXPORT)
This Generating Facility Interconnection Agreement ("GFIA") is entered into by and between City of
Carlsbad ("Electricity Producer" or "EP ") and San Diego Gas & Electric Company ("SDG&E"). The
EP and SDG&E are sometimes also referred to in this GFIA jointly as "Parties" or individually as "Party."
In consideration of the mutual promises and obligations stated in this GFIA and its attachments, the
Parties agree as follows:
1. SCOPE AND PURPOSE
This GFIA provides for EP to interconnect and operate a Generating Facility (described below) in
parallel with SDG&E's Distribution System to 1) deliver to SDG&E on a non-compensated basis
or 2) sell energy produced by such Generating Facility directly to SDG&E pursuant to RES-BCT.
2. SUMMARY AND DESCRIPTION OF EP's GENERATING FACILITY
2.1 A description of the Generating Facility, including a summary of its significant
components and a single-line diagram showing the general arrangement of how EP's
Generating Facility and loads are interconnected with SDG&E's Distribution System, is
attached to and made a part of this GFIA as Appendix A.
2.2 Generating Facility identification number: 15334 Assigned by SDG&E)
2.3 SDG&E's customer electric service account number: 9522964244 (Assigned by SDG&E)
2.4 Name and address used by SDG&E to locate the electric service account used to
interconnect the Generating Facility with SDG&E's Distribution System:
CITY OF CARLSBAD
5300 SUNNY CREEEK RD C
CARLSBAD, CA 92010
2.5 The Gross Nameplate Rating of the Generating Facility: ~kW
2.6 The Net Nameplate Rating of the Generating Facility: 149 kW
2.7 The expected annual energy production of the Generating Facility is: 832.812 kWh
2.8 For the purpose of securing the Competition Transition Charge ("CTC") exemption
available under Section 372 of the California Public Utilities ("PU") Code, EP hereby
declares that the Generating Facility does IEl does not C meet the requirements for
"Cogeneration" as such term is used in Section 216.6 of the PU Code.
2.9 The Generating Facility's expected date of Initial Operation is: 6/01/2014.
The expected date of Initial Operation shall be within two years of the date of this GFIA.
142-0545 (06/06)
3. DOCUMENTS INCLUDED; DEFINED TERMS
3.1 This GFIA includes the following exhibits that are specifically incorporated herein and
made a part of this GFIA by this reference:
Appendix A -Description of Generating Facility and Single-Line Diagram
Appendix B -Copy of SDG&E's Electric Rule 2 and Rule 21
Appendix C -Copy of interconnection facilities financing and operation agreement
3.2 When initially capitalized, whether in the singular or in the plural, the terms used herein
shall have the meanings assigned to them either in this GFIA or in Rule 21 of SDG&E's
tariffs.
4. TERM AND TERMINATION
4.1 This GFIA shall become effective as of the last date entered in Section 17, below. The
term of the GFIA shall continue in full force and effect until the earliest date that one of
the following events occurs:
(a} The Parties agree in writing to terminate the GFIA; or
(b) The ____ dated ___ terminates for any reason.
4.2 SDG&E may elect to terminate this GFIA for one or more of the following additional
reasons:
(a) A change in applicable rules, tariffs, and regulations, as approved or directed by the
CPUC, or a change in any local, state or federal law, statute or regulation, either of
which materially alters or otherwise affects SDG&E's ability or obligation to perform
SDG&E's duties under this GFIA; or,
(b) EP fails to take all corrective actions specified in SDG&E's Notice that EP's
Generating Facility is out of compliance with the terms of this GFIA within the time
frame set forth in such Notice; or,
(c} EP abandons the Generating Facility. SDG&E shall deem the Generating Facility to
be abandoned if SDG&E determines, in its sole opinion, the Generating Facility is
non-operational and EP does not provide a substantive response to SDG&E's Notice
of its intent to terminate this Agreement as a result of EP's apparent abandonment of
the Generating Facility affirming EP's intent and ability to continue to operate the
Generating Facility.
4.3 Any agreement attached to and incorporated into this GFIA shall terminate concurrently
with this GFIA unless the Parties have agreed otherwise in writing.
5. GENERATING FACILITY OPERATION AND CERTIFICATION REQUIREMENTS
5.1 EP is responsible for operating the Generating Facility in compliance with all of SDG&E's
tariffs, including but not limited to SDG&E's Rule 21, and any other regulations and laws
governing the Interconnection of the Generating Facility.
5.2 EP shall not deliver reactive power to SDG&E's Distribution System unless the Parties
have agreed otherwise in writing.
5.3 The Generating Facility shall be operated with all of EP's Protective Functions in service
whenever the Generating Facility is operated in parallel with SDG&E's Distribution
System. Any deviation from these requirements may occur only when the Parties have
agreed to such deviations in writing.
2 142-0545 (06/06)
'.
6. INTERCONNECTION FACILITIES
6.1 EP and/or SDG&E, as appropriate, shall provide Interconnection Facilities that
adequately protect SDG&E's Distribution System, personnel, and other persons from
damage or injury, which may be caused by the operation of EP's Generating Facility.
6.2 EP shall be solely responsible for the costs, design, purchase, construction, operation,
and maintenance of the Interconnection Facilities that EP owns.
6.3 If the provisions of SDG&E's Rule 21, or any other tariff approved by the Commission,
require SDG&E to own and operate a portion of the Interconnection Facilities, EP and
SDG&E shall promptly execute an agreement that establishes and allocates
responsibility for the design, installation, operation, maintenance, and ownership of the
Interconnection Facilities.
7. LIMITATION OF LIABILITY/INDEMNITY
Each Party's liability to the other Party for any loss, cost, claim, injury, liability, or expense,
including reasonable attorney's fees, relating to or arising from any act or omission in its
performance of this agreement, shall be limited to the amount of direct damage actually incurred.
In no event shall either Party be liable to the other Party for any indirect, special, consequential,
or punitive damages of any kind whatsoever.
As between SDG&E and EP, EP shall be solely responsible for and EP shall indemnify, defend
and hold SDG&E , and its current and future parent company, subsidiaries, affiliates and their
respective directors, officers, shareholders, employees, agents, representatives, successors and
assigns harmless from and against any and all claims, actions, suits, proceedings, losses,
liabilities, penalties, fines, damages, cost or expenses including without limitation, reasonable
attorneys fees (including fees and disbursements of in-house and outside counsel) of any kind
whatsoever resulting from (a) injuries to or death of any and all individuals, including, without
limitation, members of the general public, or any employee, agent, independent contractor or
consultant or affiliate of either SDG&E or EP, arising out of or connected in any manner with EP's
performance of services, or (b) damage to and/or destruction of property of SDG&E or EP arising
out of or connected in any manner with EP's performance of services, or (c) third party claims of
any kind, whether based on negligence, strict liability, or otherwise, arising out of or connected in
any manner to EP's or any of its subcontractors acts or omissions in breach of this Agreement..
This indemnification obligation shall not apply to the extent that injuries, death, loss, damage or
destruction is caused by either the willful misconduct by SDG&E or SDG&E's sole negligence.
8. INSURANCE
8.1 In connection with EP's performance of its duties and obligations under this GFIA, EP
shall maintain, during the term of the GFIA, general liability insurance with a combined
single limit of not less than:
(a) Two million dollars ($2,000,000) for each occurrence if the Gross Nameplate Rating
of EP's Generating Facility is greater than one hundred (100) kW;
(b) One million dollars ($1,000,000) for each occurrence if the Gross Nameplate Rating
of EP's Generating Facility is greater than twenty (20) kW and less than or equal to
one hundred (100) kW; and
(c) Five hundred thousand dollars ($500,000) for each occurrence if the Gross
Nameplate Rating of EP's Generating Facility is twenty (20) kW or less.
(d) Two hundred thousand dollars ($200,000) for each occurrence if the Gross
Nameplate Rating of EP's Generating Facility is ten (1 O) kW or less and EP's
Generating Facility is connected to an account receiving residential service from
SDG&E.
Such general liability insurance shall include coverage for "Premises-Operations, Owners
and Contractors Protective, Products/Completed Operations Hazard, Explosion,
Collapse, Underground, Contractual Liability, and Broad Form Property Damage
including Completed Operations."
3 142-0545 (06/06)
'.
8.2 The general liability insurance required in Section 8.1 shall, by endorsement to the policy
or policies, (a) include SDG&E, its affiliates/parent companies and their respective
officers, directors, employees, agents, representatives, successors and assigns as an
additional insured; (b) contain a severability of interest clause or cross-liability clause;
(c) provide that SDG&E shall not by reason of its inclusion as an additional insured incur
liability to the insurance carrier for payment of premium for such insurance; and
(d) provide for thirty (30) calendar days' written notice to SDG&E prior to cancellation,
termination, alteration, or material change of such insurance.
8.3 If EP's Generating Facility is connected to an account receiving residential service from
SDG&E and the requirement of Section 8.2(a) prevents EP from obtaining the insurance
required in Section 8.1, then upon EP's written Notice to SDG&E in accordance with
Section 9.1 , the requirements of Section 8.2(a) shall be waived.
8.4 Evidence of the insurance required in Section 8.2 shall state that coverage provided is
primary and is not in excess to or contributing with any insurance or self-insurance
maintained by SDG&E.
8.5 EP shall furnish the required insurance certificates and endorsements to SDG&E prior to
Initial Operation of the Generating Facility. Thereafter, SDG&E shall have the right to
periodically inspect or obtain a copy of the original policy or policies of insurance.
8.6 If EP is self-insured with an established record of self-insurance, EP may comply with the
following in lieu of Sections 8.1 through 8.4:
(a) EP shall provide to SDG&E, at least thirty (30) calendar days prior to the date of
Initial Operation, evidence of an acceptable plan to self-insure to a level of
coverage equivalent to that required under Section 8.1.
(b) If EP ceases to self-insure to the level required hereunder, or if EP are unable to
provide continuing evidence of EP's ability to self-insure, EP agrees to
immediately obtain the coverage required under Section 8.1 .
8.7 All insurance certificates, statements of self insurance, endorsements, cancellations,
terminations, alterations, and material changes of such insurance shall be issued and
submitted to the following:
9. NOTICES
San Diego Gas & Electric Company
Attn: Customer Generation.
8316 Century Park Court, CP52F
San Diego, CA 92123
9.1 Any written notice, demand, or request required or authorized in connection with this
GFIA ("Notice") shall be deemed properly given if delivered in person or sent by first class
mail, postage prepaid, to the person specified below:
If to SDG&E: San Diego Gas & Electric Company
Attn: Customer Generation
lfto EP:
8316 Century Park Court, CP52F
San Diego, CA 92123
Phone: (619) 696 -2000
FAX: (619) 819-4448
Carlsbad Municipal Water District
Attn: Conrad "Skip" Hammann Jr.
1635 Faraday Avenue
Carlsbad, CA 92008
Phone: (760) 602-2751
FAX: (760) 602-8562
9.2 A Party may change its address for Notices at any time by providing the other Party
Notice of the change in accordance with Section 9.1.
4 142-0545 (06/06)
9.3 The Parties may also designate operating representatives to conduct the daily
communications, which may be necessary or convenient for the administration of this
GFIA. Such designations, including names, addresses, and phone numbers may be
communicated or revised by one Party's Notice to the other.
10. ISO DECLARED EMERGENCIES
EP shall comply with all ISO protocols, including but not limited to the following: if the ISO
declares a Stage 2 or Stage 3 System Emergency, as defined in the ISO Tariff and Protocols,
SDG&E may dispatch EP to operate the Generating Facility and EP shall make all commercially
reasonable efforts to comply with such request within the physical limitations of the Generating
Facility.
11. REVIEW OF RECORDS AND DATA
11.1 SDG&E shall have the right to review and obtain copies of EP's operations and
maintenance records, logs, or other information such as, unit availability, maintenance
outages, and circuit breaker operation requiring manual reset, relay targets and unusual
events pertaining to EP's Generating Facility or its Interconnection with SDG&E's
Distribution System.
11.2 EP authorizes SDG&E to release to the California Energy Commission (CEC) information
regarding EP's facility, including customer name, location, size, and operational
characteristics of the unit, as requested from time to time pursuant to the CE C's rules and
regulations.
12. ASSIGNMENT
EP shall not voluntarily assign its rights nor delegate its duties under this GFIA without SDG&E's
written consent. Any assignment or delegation EP makes without SDG&E's written consent shall
not be valid. SDG&E shall not unreasonably withhold its consent to EP's assignment of this
GFIA.
13. NON-WAIVER
None of the provisions of this GFIA shall be considered waived by a Party unless such waiver is
given in writing. The failure of a Party to insist in any one or more instances upon strict
performance of any of the provisions of this GFIA or to take advantage of any of its rights
hereunder shall not be construed as a waiver of any such provisions or the relinquishment of any
such rights for the future, but the same shall continue and remain in full force and effect.
14. GOVERNING LAW, JURISDICTION OF CPUC, INCLUSION OF SDG&E's TARIFFS AND
RULES
14.1 This GFIA shall be interpreted, governed, and construed under the laws of the State of
California as if executed and to be performed wholly within the State of California without
giving effect to choice of law provisions that might apply to the law of a different
jurisdiction.
14.2 This GFIA shall, at all times, be subject to such changes or modifications by the CPUC as
it may from time to time direct in the exercise of its jurisdiction.
14.3 The interconnection and services provided under this GFIA shall at all times be subject to
the terms and conditions set forth in the tariff schedules and rules applicable to the
electric service provided by SDG&E, which tariff schedules and rules are hereby
incorporated into this GFIA by this reference.
14.4 Notwithstanding any other provisions of this GFIA, SDG&E shall have the right to
unilaterally file with the CPUC, pursuant to the CPUC's rules and regulations, an
application for change in rates, charges, classification, service, tariff or rule or any
agreement relating thereto.
5 142-0545 (06/06)
15. AMENDMENT AND MODIFICATION
This GFIA can only be amended or modified in writing and signed by both Parties.
16. ENTIRE AGREEMENT
This GFIA, including any incorporated tariff schedules and rules, contains the entire agreement
and understanding between the Parties, their agents, and employees as to the subject matter of
this GFIA. Each party also represents that in entering into this GFIA, it has not relied on any
promise, inducement, representation, warranty, agreement or other statement not set forth in this
GFIA or in the incorporated tariff schedules and rules.
17. SIGNATURES
IN WITNESS WHEREOF, the Parties hereto have caused two originals of this GFIA to be
executed by their duly authorized representatives. This GFIA is effective as of the last date set
forth below.
CITY OF CARLSBAD SAN DIEGO GAS & ELECTRIC COMPANY
By: By: ~~ Name: Name: -Ken Parks
Title: Public Works Director Title: Manager, Customer Generation
U[>¼/ t4:: Date:
II lzo/4'5 Date:
•
6 142-0545 (06/06)
. .
APPENDIX A
DESCRIPTION OF GENERATING FACILITY
AND SINGLE-LINE DIAGRAM
(Supplied by EP)
The pressure control hydrolelectric generator (PCHF) would be connected to a 480-volt, 3-phase
distribution panelboard (DP-PCHF) located on the PCHF Turbine Building. In addition to the
pressure controlled hydrolelectric generator, DP _PCHF would also provide a connection to a
208/120-volt panelboard for lighting, receptacles, and any HVA loads in the PCHF Turbine
Building.
Power generated by the PCHF will be transmitted to the existing Maerkle Pump Station through an
underground connection between DP _PCHF, located in the PCHF Turbine Building, and a new
circuit breaker installed in the existing 480-volt motor control center at the pump station. The
underground connection will consist of two parallel runs of 480-volt conductors sized for the
minimized voltage drop and losses between the interconnection point and the PCHF. The
conductors will be installed in Schedule 40 PVC conduit in a sand-bedded duct bank.
A new circuit breaker installed in the existing motor control center.
7 142-0545 (06/06)
r---------------------------------------------------------------, L.. SWITCHBOARD PCHF, 400 AMPS, 480 VOLTS, 3 (0), 3 WIRE. 60 HZ. 65 KASC RMS
! ! !
3P ~ ~ 400AF I) TM 300!~ 9 0
I
400AF l) TM
300 AT 9 65KAIC
l TM 0;i6
NC. l TM ~" i) ~-~" .) ~-
~
-----_,_ -\ --------------0 -----3 -------
~ING MCC..1
KEYNOTES:
~
! ..
!!
..J ~ !
~ SPLICE NEW CONDUCTORS AT EXISTING PB-<>4 WITH "-1/ EXISTING CONDUCTORS FOR EXISTING MSB-2 POWER FEED.
0 PROVIDE NEW FEEDER BREAKER AS SHOWN ON DWG. E-03.
~ VISIBLE DISCONNECT SWITCH, BOL TSWITCH MODEL J366WOL "v" OR EQUAL. 0 NET GENERATION OUTPUT METERING PROVIDED BY SDG&E.
A PROVIDE THE FOLLOWING MULTI-FUNCTION PROTECTIVE "v" RELAY BUT NOT LIMITED: (27/59) UNDER/OVER VOLTAGE, (32Rl REVERSE POWER (46) ClJRRENT BALANCE (47)
VOL rAGE SEQUENCE, (51Vl VOLTAGE RESTRAINED
OVERCURRENT (51Nl NEUlRAL OVERCURRENT; AND (81O/U)
OVER/UNDER FR'EQUENCY.
LOCATION: HYDROELECTRIC FACILITY
VOLTS: 208/ 120
PHASE & WIRE: 3PH 4W
INTERRUPT: 18KAIC
VC/F DESCRIPTION
I SUPPLY FAN ISF-101 l
~ ! ..
! ~
5 ! ..
! ~
~ .,,
VCP-101
~
0
! ..
![
0 ~ ..,_
!:!.
~ l¥ ..,
!----149~
480VAC
3PHASE
3W1RE
,83PF
NEMA: 4X
FEED: BOTTOM
MTG. SURFACE
BUS RATING: 100
MAIN: CB
MAIN RA TING 100 AF 60 AT
LOAD (VA} BKR
1176 20A-1P
HTG-101 !
HYDROELECTRIC
GENERATOR
PANEL L-PCHF
PH A WEIGHTED VA
PH B WEIGHTED VA
PH C WEIGHTED VA
EQUIP SIZING VA
PANELAMPS
CIR 0 CIR BKR
1 A 2 20A-1P
T-PCHF
l-PCHF
15KVA
3" 480V
208/120V
3-#10 (Ill), 1-#4 (N), & 1-#10 (G).
,·-, ! I
I I L_I
L2
3644
2678
3507
10932
30.3
LOADNA) DESCRIPTION
160 INDOOR LIGHTS
~
! ..
!!
~ .. .,,
I FIT-101 50 20A-1P 3 B 4 20A-1P 540 RECPECTACLES: INDOOR
RTU-1 1000 20A-1P 5 C 6 20A-1P 174 OUTDOOR LIGHT
I
2251.F l) TM :;p
200~T 9 65KAIC
:XISTING
NCC-MSB2
,._ 1666 7 A 8 20A-1P 180 RECPECTACLES:OUTDOOR
EXISTING LIGHTING PANEL •L2• 1666 -20A-3P 9 B 10 20A-1P 4 EMERGENCY LIGHT
1666 11 C 12 20A-1P SPARE
SPARE 20A-1P 13 A 14 20A-1P SPARE
SPARE 20A-1P 15 B 16 20A-1P SPARE
SPARE 20A-1P 17 C 18 20A-1P SPARE
4/17/2013
1/C/F
I
I
I
..
~
.. . '
APPENDIX B
RULES: "2" and "21"
(Provided by SDG&E)
(Note: SDG&E's tariffs are included for reference only and shall at all times be
subject to such changes or modifications by the Commission as the Commission
may, from time to time, direct in the exercise of its jurisdiction. A copy of Rule 2 has
not been provided. A copy may be obtained from SDG&E's website:
www.sdge.com)
8 142-0545 (06/06)
~os/' .,J lE
b
A ~ Sempra Energy utility"'
November 26, 2014
Conrad "Skip" Hammann, Jr.
Carlsbad Municipal Water District
1635 Faraday Avenue
Carlsbad, CA 92008
Ken Parks
Customer Generation Manager
San Diego Gas & Electric
8316 Century Park Court
CP52F
San Diego, CA 92123
Tel: (858) 636-5581
Fax: (619) 819-4448
Cell: (858) 583-9429
kparks@sempraut,lities_com
Re: Authorization to Operate: Hydroelectric Turbine 149 kW @5300 Sunny Creek Road C
in Carlsbad, CA -("Project") -ID 15334
Dear Conrad "Skip" Hammann, Jr.:
This letter is formal notification that SDG&E has completed all required reviews of the
Project pursuant to Rule 21. The reviews have concluded that the Project has met all of the
requirements to interconnect and operate in parallel with SDG&E's electric system effective
immediately. This authorization is applicable to the electrical interconnection segment of
your Projects only. Please do not hesitate to call me if you have any questions.
Sincere~
Ken Parks