HomeMy WebLinkAbout2023-02-16; Village and Barrio Traffic Circles and Barrio Lighting Projects Update (District 1); Gomez, PazTo the members of the:
CITY COUNCIL
Date2/u.f1~ CA V CC ✓
CM_1~LocM (3)L
February 16, 2023
Council Memorandum
To:
From:
Honorable Mayor Blackburn and Members of the City Council
Paz Gomez, Deputy City Manager, Pub~orks
Geoff Patnoe, Assistant City Manager ~ Via:
{city of
Carlsbad
Memo ID# 2023019
Re: Village and Barrio Traffic Circles and Barrio Lighting Projects Update (District 1)
This memorandum provides an update to a previous Council Memorandum dated Oct. 13, 2022
(Attachment A) on the Village and Barrio Traffic Circles, Capital Improvement Program (CIP)
Project No. 4015, and the Barrio Lighting Project, CIP Project No. 4013.
Background
The Council Memorandum dated Oct. 13, 2022, provided background information on both
projects.
Discussion
Village and Barrio Traffic Circles Project
Staff have recei.ved approval of federal grant funding for this project, as well as the Barrio
Lighting project. The grant funding, which is under the Community Project
Funding/Congressionally Directed Spending (CPFCDS) program, will be overseen by the California
Department of Transportation (Caltrans). Staff submitted the draft CPFCDS application to
Caltrans Headquarters in January 2023. Once Caltrans approves the application, the next step is
to submit the Request for Authorization (RFA) and the Authorization to Proceed, also known as
an E-76, which will release the programmed funds for preliminary engineering.
Staff have submitted drafts of both documents to the Caltrans District Local Assistance Engineer
for their initial review. However, staff recently learned from Caltrans that the previously
programmed $600,000 of grant funding for the preliminary engineering phase cannot be used on
the Village and Barrio Traffic Circles and Barrio Lighting projects since the federal procurement
requirements for the consultant selection process were not followed. This is because the projects
were already in the design phase and the consultants had been selected before award of the
grant.
Staff will amend the Regional Transportation Improvement Program (RTIP), to reallocate the
$600,000 preliminary engineering funding to the construction phase for the projects. The next
timeframe for updates to the RTIP is February 2023, with the San Diego Association of
Governments (SAN DAG) Chief Executive Officer's approval expected by April 2023. Once
SAN DAG approves the RTIP amendment, staff will go through the process noted above to release
Public Works Branch
Transportation Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 442-339-2730 t
Council Memo -Village and Barrio Traffic Circles and Barrio Lighting Projects Update (District 1)
February 16, 2023
Page 2
funding for construction. Staff will initiate this process once the envirol]_mental process is
complete.
Staff are also working with Caltrans on the National Environmental Policy Act (NEPA) process to
obtain environmental clearance for both projects. NEPA clearance is required due to federal
funds being applied to the projects. Concurrent with the process to receive the funding, staff
submitted the Preliminary Environmental Study (PES) form to Caltrans. Caltrans reviewed and
approved the PES form. The approved PES requires additional environmental studies to be
completed for the projects. Staff have prepared agreements for two additional consultants to
complete these technical studies for NEPA.
Public Art for the Village and Barrio Traffic Circles Project
As stated in the Council Memorandum dated Oct. 13, 2022, Cultural Arts staff have adjusted the
timing for a release of a limited Call for Artists to align with the revised construction and funding
allocation timelines, which are expected to be available in March 2023. Meetings between Public
Works staff and Cultural Arts staff include an ongoing dialogue to review the infrastructure
requirements related to the traffic circle located at Pine Avenue and Harding Street. Once Public
Works staff have finalized the specific site parameters including the project timeline and site
schematics, which are essential elements within the limited Call to Artists, Cultural Arts staff will
initiate the public art process.
Barrio Lighting Project
Upon continued coordination with San Diego Gas & Electric (SDGE) for Phase 1, it was
determined that SDGE cannot service two streetlights proposed on Pine Avenue and on Tyler
Street due to SDGE's current overhead load capacity, despite SDGE's pdor approval for all
locations. Staff have coordinated with SDGE to instead install a new streetlight at the south
corner of Pine Avenue and Tyler Street. This results in 13 total new streetlights as part of Phase 1.
Currently, 12 of the 13 streetlights have been energized and are working. The remaining light at
the corner of Pine Avenue and Tyler Street is currently under construction with an estimated
completion date of April 2023.
Phase 2 of the Barrio Lighting Project, which is currently in the design phase, will provide
pedestrian lighting in the Barrio neighborhood. An illumination study on the existing light level
conditions was recently completed to evaluate lighting needs and appropriate locations for new
pedestrian lights. Based on preliminary layouts, an initial layout proposed a total of 170+
pedestrian lights could be placed throughout the Barrio area. This information has been recently
shared with SDGE to start their review and conflict-check of these lights to determine feasibility.
Next Steps
Village and Barrio Traffic Circles Project
As stated above, staff will continue coordination with Caltrans regarding NEPA and release of the
federal funding for construction. Staff will initiate completing the environmental technical
Council Memo -Village and Barrio Traffic Circles and Barrio Lighting Projects Update (District 1)
February 16, 2023
Page 3
studies once the additional consultants' agreements are executed. Staff anticipate it will take six
months to complete and receive NEPA clearance.
Once NEPA approval is obtained, staff will finalize the project design and request the City
Council's approval of the plans and specifications and authorization to advertise for construction
bids. As the design is being finalized, staff will start the process as noted above to release funding
that has been allocated for the construction portion of the process. This includes submitting
another application for the RFA and E-76 forms to unlock the $5 million of the grant funding
programmed for the construction phase of both projects. It will take approximately three to six
months to complete the release of funding process. Upon release of funding, the city plans to
award the construction contract and issue a notice to proceed, which is expected to be in May
2024.
Barrio Lighting Project
Construction is almost complete on the last remaining streetlight in Phase 1. Once the trenching
and electrical work is complete, staff will coordinate with SDGE to energize the streetlight
located at the corner of Pine Avenue and Tyler Street. The remaining streetlight is expected to be
energized by the end of February 2023.
For Phase 2, staff are curre_ntly working with SDGE to review and perform a conflict check of the
170+ proposed pedestrian light locations throughout the Barrio area. Staff also plan to
concurrently field check each location to optimize the layout based on any potential field
constraints. Once SDGE is complete with its conflict check, staff plan to progress the concept
level design to an engineering design phase to create finalized plans, specifications and contract
documents by late 2023.
Attachment: A. Council Memorandum dated Oct. 13, 2022
cc: Scott Chadwick, City Manager
Cindie McMahon, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Michael Calderwood, Fire Chief
Mickey Williams, Police Chief
Tom Frank, Transportation Director/City Engineer
David Graham, Chief Innovation Officer
Jason Haber,· Intergovernmental Affairs Director
Zach Korach, Finance Director
Jeff Murphy, Community Development Director
Vicki Quiram, Utilities Director
Kristina Ray, Communication & Engagement Director
Suzanne Smithson, Library & Cultural Arts Director
Gina Herrera, Deputy City Attorney
Council Memo -Village and Barrio Traffic Circles and Barrio Lighting Projects Update (District 1)
February 16, 2023
Page 4
Hossein Ajideh, Engineering Manager
Eric Lardy, City Planner
Richard Schultz, Cultural Arts Manager
Eric Zielke, Senior Engineer
Lauren Ferrell, Associate Engineer
To the members of the:
CITY COUNCIL
Date J!l.w_cA ✓cc ~
cM L_AcM ~CM(3)_d'
October 13, 2022
ATTACHMENT A
Council Memorandum
To: Honorable Mayor Hall and Members of the City Council
From: Paz Gomez, Deputy City Manager, Public Works
Via: Geoff Patnoe, Assistant City Manage
{city of
Carlsbad
Memo ID# 2022112
~e: Village and Barrio Traffic Circles and rrio Lighting Projects Update (District 1)
This memorandum provides an update to a previous Council Memorandum dated April 28, 2022,
on the Village and Barrio Traffic Circles, Capital Improvement Program (CIP) Project No. 4015,
and the Barrio Lighting, CIP Project No. 4013.
Background
The Council Memorandum dated April 28, 2022, provided background information on both
projects.
Discussion
Village and Barrio Traffic Circles Project
Staff are awaiting receipt of federal funding from the U.S. Department of Transportation's Local
Transportation Priorities Account and under the Highway Infrastructure Programs (HIP),
administered by the Federal Highway Administration (FHWA) for the traffic circles and street
lighting projects. U.S. Representative Mike Levin's office secured $5 million dollars for the
projects.
To ensure that all federal requirements are met, the FHWA will send the funds to the California
Department of Transportation (Caltrans), and Caltrans will ultimately administer the funding to
the city. At this tir:ne, Caltrans has not provided an estimate on when the funds will be available ·
to encumber and begin the construction phase including bidding the project. Staff continue to
contact both the FHWA and Caltrans representatives weekly to obtain updates on the approval
process for the authorization to advertise the project for construction bids.
Since the grant is federal funding, the projectwill likely require the National Environmental Policy
Act (NEPA) process to obtain environmental clearance. In preparation, staff are currently working
to get a consultant under contract to provide the NEPA services and coordinate approval with
Ca It rans as the lead agency. Staff anticipate starting the NEPA efforts upon receipt of the grant
funds. Additionally, staff will work to prepare a Notice of Exemption (NOE) to satisfy the
California Environmental Quality Act (CEQA) requirements.
If NEPA approval is required, the approval process using the grant funds may take between six
months to one year to complete the NEPA requirements and obtain environmental clearance,
Public Works Branch
Transportation Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 442-339-2730 t
Council Memo -Village and Barrio Traffic Circles and Barrio Lighting Projects Update (District 1)
October 13, 2022
Page 2
which could delay the project bid until early 2024. Staff will continue to work with the FHWA and
Caltrans staff to obtain clarification on whether.the NEPA process is required.
Public Art for the Village and Barrio Traffic Circles Project
Cultural Arts staff have adjusted the timing to release a limited Call for Artists to align to the
revised construction and funding allocation timeline. This process to select an artist for the public
art at the traffic circle in the intersection of Harding Street and Pine Avenue could begin in late
2022, pending confirmation of the grant funding time line.
Barrio Lighting Project
The previous design for the Barrio Lighting Project included installation of 14 streetlights at
various locations throughout the Barrio as part of Phase 1. Staff continue to coordinate with San
Diego Gas & Electric (SDG&E) on this project, and 11 of the 14 streetlights have been energized.
The three streetlights that have not yet been energized require additional work, including
trenching and electrical work. SDG&E is unable to provide service to two of the three remaining
lights located on Pine Avenue and Tyler Street due to SDG&E's current overhead load capacity.
As an alternative, staff are working with SDG&E to install a new streetlight at the south corner of
Pine Avenue and Tyler Street. The other remaining light to be energized is located at the end of
the cul-de-sac at Palm Avenue, east of Harding Street. Staff continue to work with SDG&E on this
effort and anticipate this work will be completed by early 2023.
Phase 2 of the Barrio Lighting Project, which is currently in the design phase, will provide
pedestrian lighting in the Barrio neighborhood to provide connectivity to the Village. A study to
evaluate the existing lighting levels in the Barrio area has been completed. Staff are using this
study's information to evaluate lighting needs and light pole locations. Design criteria for new
pedestrian-scale lighting locations in the Barrio area include existing overhead utility lines,
sidewalk spacing and availability, maintaining driveway access and sight distances, and
Americans with Disabilities Act (ADA) requirements.
Next Steps
Village and Barrio Traffic Circles Project
Once federal funding requirements are provided by Caltrans, staff will provide another project
update including a target schedule and recommendations for completing the project.
· Barrio Lighting Project
Staff will continue to coordinate with SDG&E to install and energize the remaining streetlights in
Phase 1. Staff expect that these lights will be energized by early 2023.
For Phase 2, staff are currently reviewing placement based on the results of the lighting study
and will incorporate feedback received through the public outreach efforts. Once completed,
staff will finalize the engineering design and coordinate with utility companies. Once federal
Council Memo -Village and Barrio Traffic Circles and Barrio Lighting Projects Update {District 1)
October 13, 2022
Page 3
funding requirements are provided by Caltrans, staff will provide another project update
including a target schedule and recommendations for completing the project.
Attachment: A. Council Memorandum dated April 28, 2022
cc: Scott Chadwick, City Manager
Cindie McMahon, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Michael Calderwood, Fire Chief
Mickey Williams, Police Chief
Robby Contreras, Assistant City Attorney
Tom Frank, Transportation Director/City Engineer
David Graham, Chief Innovation Officer
Jason Haber, Intergovernmental Affairs Director
Zach Korach, Finance Director
Jeff Murphy, Community Development Director
Vicki Quiram, Utilities Director
Kristina Ray, Communication & Engagement Director
Suzanne Smithson, Library & Cultural Arts Director
Hossein Ajideh, Engineering Manager
Eric Lardy, City Planner
Richard Schultz, Cultural Arts Manager
Scott Lyle, Senior Engineer
Lauren Ferrell, Associate Engineer
To the members of the: J;J:UNCIL
Date A~CC L
CM V ACM v DCM (3) t:__,
ATTACHMENT A
Council Memorandum
April 28, 2022
To: Honorable Mayor Hall and Members of the City Council
From: Paz Gomez, Deputy City Manager, Public Works
Via: Geoff Patnoe, Assistant City Manager @
{city of
Carlsbad
Memo ID #2022050
Re: Village and Barrio Traffic Circles and Barrio Lighting Projects Update (District 1)
This memorandum provides an update to a previous Council Memorandum dated
Jan.'6, 2022, on the Village and Barrio Traffic Circles, Capital Improvement Program (CIP)
Project No. 4015, and the Barrio Lighting, CIP Project No. 4013.
Background
The Council Memorandum dated Jan. 6, 2022, provided background information on both
projects.
Discussion
Village and Barrio Traffic Circles Project
In April 2021, staff worked with U.S. Representative Mike Levin's office to submit a fiscal year
(FY) 2022 Community Projects Funding request for the Village and Barrio Traffic Circles and
Barrio Lighting Projects to be funded through the federal budgeting and appropriations process.
Staff were recently notified that Representative Levin secured $5 million dollars of federal
funding from the U.S. Department ofTransportation's Local Transportation Priorities Account
and under the Highway Infrastructure Programs (HIP) for the traffic circles and street lighting
projects after Congress passed the Consolidated Appropriations Act, 2022.
Under the HIP account, there are 309 line-item projects totaling approximately $847 million
administered by the Federal Highway Administration (FHWA). Before this funding becomes
available to the city, the FHWA and the California Department ofTransportation (Caltrans) must
complete several steps. First, all congressionally directed projects assigned to FHWA will flow
through Caltrans.
Second, to ensure that all federal requirements are met, FHWA will send the funds to Caltrans,
and Ca It rans will ultimately provide them to the city. Staff therefore does not know when the ·
city will receive these funds. In accordance with the federal requirements, the funds are
available for obligation until Sept. 30, 2025. Any funding not obligated by the end of the federal
FY 2025 will expire.
Public Works Branch
Transportation Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 442-339-2730 t
Council Memo -Village and Barrio Traffic Circles and Barrio Lighting Projects Update (District 1)
April 28, 2022
Page 2
Since the FHWA program is a reimbursement program, expenses incurred before the FHWA
project authorization date are not eligible for reimbursement. Based on this requirement, staff
plan to delay going to the City Council with a request to approve the plans, specifications and
contract documents and to authorize bidding for both projects until funds are ready to be
disbursed. This will avoid incurring ineligible project expenditures.
A city webpage is currently active to provide information to the public, available at the
following link: https://www.carlsbadca.gov/departments/public-works/traffic-circles.
Barrio Lighting Project
Attachment A discussed installation of 14 streetlights at various locations throughout the Barrio
as part of Phase 1 of the Barrio Lighting Project. Staff have coordinated with San Diego Gas &
Electric (SDG&E) to energize 11 of the 14 streetlights. The three streetlights that have not yet _
been energized will require additional work, including trenching and electrical work. Staff will
continue_working with SDG&E in this regard and -anticipate this work will be completed by fall
2022.
Phase 2 of the Barrio Lighting Project, which is currently in the design phase, will provide
pedestrian lighting in the Barrio neighborhood. Phase 2A will focus on one of the major
corridors in the Barrio, which includes Roosevelt Street, Madison Street, Harding Street and
Magnolia Avenue, and will provide connectivity to the Village. Staff will be evaluating lighting
· needs along each corridor before determining initial light pole spacing.
Staff also completed focused public outreach to solicit input from the community on corridor
preference and priority in early 2022. Staff are currently performing a lighting study that will
include recommendations for new pedestrian-scale lighting locations in the Barrio area. The
final design of Phase 2A will proceed upon completion of the lighting study and will incorporate
feedback received through the public outreach efforts.
Next Steps
Village and Barrio Traffic Circles Project
Staff plan to finalize the plans, specifications and contract documents in late 2022 and will
request City Council approval of these documents and authorization to bid after receipt of the
federal funding.
Cultural Arts staff have adjusted their timing to release the Call for Artists to align to the newly
established construction and funding allocation timeline. A process to select an artist for the
public art at the traffic circle in the intersection of Harding Street and Pine Avenue will begin in
fall 2022.
Barrio Lighting Project
Staff will continue to coordinate with SDG&E to energize the remaining three streetlights in
Phase 1. Staff expect that these lights will be energized by fall 2022.
Council Memo -Village and Barrio Traffic Circles and Barrio Lighting Projects Update (District 1)
April 28, 2022
Page 3
For Phase 2A, staff are currently performing a lighting study for the Barrio area. Once
completed, staff will finalize the engineering design and coordinate with utility companies. Staff
will then bring Phase 2A to the City Council for approval of plans, specifications and contract
documents and authorization to bid after receipt of the federal funding.
cc: Scott Chadwick, City Manager
. Celia Brewer, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Michael Calderwood, Fire Chief
Mickey Williams, Police Chief
Robby Contreras, Assistant City Attorney
Tom Frank, Transportation Director/City Engineer
David Graham, Chief Innovation Officer
Jason Haber, Intergovernmental Affairs Director
Zach Korach, Finance Director
Jeff Murphy, Community Development Director
Vicki Quiram, Utilities Director
Kristina Ray, Communication & Engagement Director
Suzanne Smithson, Library & Cultural Arts Director
Hossein Ajideh, Engineering Manager
Scott Lyle, Senior Engineer
Lauren Ferrell, Associate Engineer