HomeMy WebLinkAbout2024-02-08; Beach Access Repairs and Upgrades Project Update (District 1); Gomez, PazTo the members of the:
CITY COUNCIL
Da:~~ lZ~ CA ✓ CC ✓
CM ACM _L DCM (3}.L
Council Memorandum
February 8, 2024
To:
From:
Honorable Mayor Blackburn and Members of the City Council
Paz Gomez, Deputy City Manager, Publi~orks
Via: Geoff Patnoe, Assistant City Manager Cf::£.
Re: Beach Access Repairs and Upgrades Project Update (District 1)
{city of
Carlsbad
Memo ID# 2024010
This memorandum provides an update on the Beach Access Repairs and Upgrades Project,
Capital Improvement Program (CIP) Project No. 3896.
Background
The city is working on a project to make necessary repairs and upgrades to the stairs and ·
walkway on the west side of Carlsbad Boulevard between Pine Avenue and approximately
30 feet north of Tamarack Avenue. The project includes structural repairs and improvements to
the concrete sidewalks, retaining walls and beach access stairways located along Carlsbad
Boulevard. These existing features would be replaced with similar materials and designs except
for the walkway, which would be widened to better accommodate the large number of walkers,
runners, joggers and other users.
The sidewalks and stairways were built in the 1980s. The sidewalk between Pine Avenue and
Maple Avenue is elevated and cantilevered over the bluff. There are four stairways to the lower
sea wall within the project area. Repairs are needed due to deterioration of the sidewalk
structure, exposed and rusted steel reinforcements, cracked and broken concrete, and rusting of
stairway components.
Discussion
The repair project was originally considered a maintenance project, but the scope has expanded
into an improvement project to address the current engineering standards and building code
requirements and to account for increased demand for beach access.
Overall, the repairs and additional work for improved access, mobility and aesthetics include:
• Widening the upper sidewalk westward, with a further foot of cantilever over the bluffs
for more space to walk
• Removing the metal beam and timber post guardrail on the east side of the sidewalk to
gain a foot of additional sidewalk space (this guardrail is not required based on the
Public Works Branch
Transportation Department
1635 Faraday Avenue I Carlsbad, CA 92008 I 442-339-2730 t
Council Memo -Beach Access Repairs and Upgrades Project Update (District 1)
February 8, 2024
Page 2
American Association of State Highway and Transportation Officials (AASHTO) Roadside
Design Guide -see below)
• Replacing existing streetlights with light fixtures on double-masts (i.e., one east and one
west), to improve street and sidewalk lighting
• Extending the lower sidewalk's eastern retaining walls a short distance to help maintain
the slope at the base of the stairways
• Replacing four sets of stairs from the upper sidewalk to the lower seawall
• Replacing the upper sidewalk platforms
Safety along Carlsbad Boulevard
As the city implements the policies in the General Plan Mobility Element, approved by the City
Council in 2015, safety along Carlsbad Boulevard is a top priority. In the same area as the beach
access project, the following changes have been made or are planned:
• Improved crosswalks with curb extensions to shorten the walking distance, center
medians to provide a place for pedestrians to stop, if needed, and flashing lights to alert
drivers when pedestrians are present
• Creating buffered bike lanes
• Slowing down traffic through restriping lanes and installing curb extensions
These changes work together to promote safer behavior among all road users.
Guardrail considerations
While it may seem counterintuitive to remove a guardrail in an area where we are making safety
improvements, there are several reasons why this design is preferred:
• The AASHTO Roadside Design Guide, which is used by transportation planners to
determine recommended street designs and features based on several factors, including
location, traffic, speeds and visibility, does not require a guardrail
• The existing guardrail was installed in the 1980s when Carlsbad Boulevard served as
Pacific Coast Highway with high speeds, prior to construction of Interstate 5
• Removing the guardrail will provide another foot of space to the walkway, which is one of
the most heavily used walkways in the region
• Removing the guardrail will make this segment of Carlsbad Boulevard consistent with
other similar segments
Council Memo -Beach Access Repairs and Upgrades Project Update (Di_strict 1)
February 8, 2024
Page 3
) ~
Rendering of Carlsbad Boulevard without the guardrail, before striping to one lane with a larger
buffer, an approved project that will be implemented in 2024.
Examples of other areas along Carlsbad Boulevard that do not have a guardrail
1---tif'_: -1---1-~l-1-• • •
• . .. . . ..
Council Memo -Beach Access Repairs and Upgrades Project Update (District 1)
February 8! 2024
Page 4
Beach access stairs at Tamarack
The project previously included work to the sidewalk around the Tamarack Beach restroom and
to the at-grade stairway near Tamarack Avenue. However, these improvements would only
replace the existing facilities in kind. Instead, these improvements will be included in the
upcoming Americans with Disabilities Act (ADA) Beach Access CIP project, which will incorporate
enhanced accessibility features into the design. This project will improve accessibility by
constructing a new ADA-compliant pedestrian ramp from the intersection of Carlsbad Boulevard
and Tamarack Avenue to the existing beachfront walkway along the seawall with connection to
the existing Tamarack Beach restroom facility.
State Parks right-of-way
The project's geographical limits are entirely within the State Parks' right-of-way as shown on the
location map provided as Attachment A. As a result, the city must comply with the state's design
standards and coordinate design reviews and approvals with State Parks. Additionally, city staff
have coordinated with State Parks staff to determine how to reimburse State Parks for its costs
associated with plan reviews and construction inspection services.
Staff completed the environmental clearance and regulatory permits through the Planning
Commission on July 19, 2023, including the local coastal development permit. The remaining
effort is completion of the final engineering design; staff have completed review of the 90%
design submittal. Staff obtained third-party peer reviews of the 90% design for structural and
constructability. The consultant team is addressing comments from the 90%-complete design
review, which include State Parks' comments, and preparing for the upcoming 100% design
submittal, which is due to the city in spring 2024.
Council Memo -Beach Access Repairs and Upgrades Project Updat e (District 1)
February 8, 2024
Page 5
Next Steps
The following timeline is provided:
2024 Final engineeri ng and State Parks coo rdination
• Continue to work on the final engineering design to prepare
the construction plans, specifications and cost estimates to
advertise the project for construction bids
• Continue coordination with the State Parks staff to receive
the necessary project approvals, including a right-of-entry
permit for construct ion
Late 2024-early 2025 Traffic Safety & Mobility Commission recommendation and
City Council approval
• Present final designs with a staff recommendation for the City
Council to approve the plans and specifications and authorize
advertisement for construction bids
Early to mid-2025 City Council approval
• Ret urn to the City Council with the lowest responsive and
responsible bidder to request award of the construction
contract
Fall 2025-Spring 2027 Construction
• Construction of the project has been phased over 15 months
to minimize the associated impacts along Carlsbad Boulevard
and Tamarack State Beach during the summer season from
Memorial Day through Labor Day
Attachment: A. Location Map
cc: Scott Chadwick, City Manager
Cindie McMahon, City Attorney
Gary Barberio, Deputy City Manager, Community Services
Laura Rocha, Deputy City Manager, Administrative Services
Michael Calderwood, Fire Chief
Mickey Williams, Police Chief
Allegra Frost, Senior Assistant City Attorney
Gina Herrera, Assistant City Attorney
Tom Frank, Transportation Director/City Engineer
Zach Korach, Finance Director
Kyle Lancaster, Parks & Recreation Director
Jeff Murphy, Community Development Director
Kristina Ray, Communication & Engagement Director
Hossein Ajideh, Engineering Manager
Ed Garbo, Risk Manager
Council Memo -Beach Access Repairs and Upgrades Project Update (District 1)
February 8, 2024
Page 6
John Kim, City Traffic Engineer
Eric Lardy, City Planner
Todd Reese, Parks Services Manager
Nathan Schmidt, Transportation Planning and Mobility Manager
Eric Zielke, Senior Engineer
Lauren Ferrell, Associate Engineer
LOCATIO N MAP
0
N
PROJECT ,
SITE
PROJECT NAME BEACH ACCESS REPAIRS AND UPGRADES
PROJECT
ACIFIC
GEAN
Created By: Sara Jadhav 4/5/2023 J:\SaraJadhav_Customers\LaurenFerre/1\Project\Beach Access Repairs\MXD\LocationMap3896.mxd
Attachment A
Copyrii:/_ht nearmap
CIP No.
3896 Attachment
A